SCED - Micro Piling and Grouting Installation - Package 31
SCED - Micro Piling and Grouting Installation - Package 31
M.P..4 Mobilization
Mob
A1020 mobilization 6 15-Jan-2024 21-Jan-2024 0 mobilization
M.P..2 Engineering
Eng
M.P..2.6 Project
Proj Documents
M.P..2.6.3 Documents Submittal
A1030 HSE Documents 3 15-Jan-2024 17-Jan-2024 0 HSE Documents
A1040 Quality Plan 3 15-Jan-2024 17-Jan-2024 0 Quality Plan
A1050 Material 3 15-Jan-2024 17-Jan-2024 0 Material
A1060 Methode of statement 3 15-Jan-2024 17-Jan-2024 0 Methode of statement
A1070 RSJ’s Project Schedule 3 15-Jan-2024 17-Jan-2024 0 RSJ’s Project Schedule
A1080 All Project Security Pass Applications 3 15-Jan-2024 17-Jan-2024 0 All Project Security Pass Applications
M.P..2.6.1 Documents Approval
A1090 HSE Documents 2 18-Jan-2024 20-Jan-2024 0 HSE Documents
A1100 Quality Plan 2 18-Jan-2024 20-Jan-2024 0 Quality Plan
A1110 Material 2 18-Jan-2024 20-Jan-2024 0 Material
A1120 Methode of statement 2 18-Jan-2024 20-Jan-2024 0 Methode of statement
A1130 RSJ’s Project Schedule 2 18-Jan-2024 20-Jan-2024 0 RSJ’s Project Schedule
A1140 All Project Security Pass Applications 2 18-Jan-2024 20-Jan-2024 0 All Project Security Pass Applications
M.P..2.2 Shop
Sho drawing Track
M.P..2.2.1 Shop Drawing Submittal
A1240 shop drawing submittal 7 15-Jan-2024 22-Jan-2024 0 shop drawing submittal
M.P..2.2.2 Shop Drawing Approval
A1250 shop drawing approval 4 23-Jan-2024 27-Jan-2024 0 shop drawing approval
M.P..3 Procurement
Proc
A1150 Datasheet and Procurement Activities 5 15-Jan-2024 20-Jan-2024 0 Datasheet and Procurement Activities
M.P..3.1 Shop
Sho Drawing Tracking
M.P..3.1.1 Shop Drawing Submittal
A1160 Shop Drawing Submittal 6 15-Jan-2024 21-Jan-2024 0 Shop Drawing Submittal
M.P..3.1.2 Shop Drawing Approval
A1170 Shop Drawing Approval 5 22-Jan-2024 27-Jan-2024 0 Shop Drawing Approval
M.P..5 Exec
Execution Work
M.P..5.1 A12 - WWRO HP PUMPS - 1 (A12-G-7012)
M.P..5.1.1 Installation MicroPiles
A1600 Excavation 3 28-Jan-2024 30-Jan-2024 1 Excavation
A1610 Steel Installation 2 31-Jan-2024 01-Feb-2024 1 Steel Installation
A1620 Supply and Installation of Pressure Grouted 2 03-Feb-2024 04-Feb-2024 1 Supply and Installation of Pressure Grouted
A1630 installation Steel Plate 1 05-Feb-2024 05-Feb-2024 1 installation Steel Plate
M.P..5.1.2 Foundation & Connect F/M
A1635 Lifting of Foundation 1 06-Feb-2024 06-Feb-2024 1 Lifting of Foundation
Actual Level of Effort Remaining Work Milestone Page 1 of 2 TASK filter: All Activities
Actual Work Critical Remaining Work © Oracle Corporation
MICRO Piling and Grouting Installation - Package 31 24/12/2023
M.P..7 Commissioning
Com and Project Closeout
A1580 Asbuilt Drawings 2 08-Apr-2024 09-Apr-2024 0 Asbuilt Drawings
A1590 Testing & Handing Off 4 10-Apr-2024 14-Apr-2024 0 Testing & Handing Off
Actual Level of Effort Remaining Work Milestone Page 2 of 2 TASK filter: All Activities
Actual Work Critical Remaining Work © Oracle Corporation