SCED - Micro Piling and Grouting Installation - Package 31

The document is a Gantt chart project schedule for a MICRO Piling and Grouting Installation package from January 15, 2024 to April 15, 2024. It includes activities for project mobilization, engineering documents submittal and approval, shop drawing submittal and approval, procurement, and execution of installation works including excavation, steel installation, pressure grouting, foundation lifting and connection. The project involves installation of micro piles for WWRO HP pumps and is scheduled to start on January 15, 2024 and be completed by April 15, 2024.

Uploaded by

01095902062ahmed
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
35 views

SCED - Micro Piling and Grouting Installation - Package 31

The document is a Gantt chart project schedule for a MICRO Piling and Grouting Installation package from January 15, 2024 to April 15, 2024. It includes activities for project mobilization, engineering documents submittal and approval, shop drawing submittal and approval, procurement, and execution of installation works including excavation, steel installation, pressure grouting, foundation lifting and connection. The project involves installation of micro piles for WWRO HP pumps and is scheduled to start on January 15, 2024 and be completed by April 15, 2024.

Uploaded by

01095902062ahmed
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

MICRO Piling and Grouting Installation - Package 31 24/12/2023

Activity ID Activity Name Original Start Finish Total Float 2024


Duration
Jan Feb Mar Apr May
M.P. Micro P
Piles BACK(31)
M.P..1 MILESTONE
MIL
A1000 Start Project 0 15-Jan-2024 0 Start Project, 15-Jan-2024
A1010 Finish Project 0 15-Apr-2024* 0 Finish Project,
A1180 Submit and Obtain Approval – All Project Documents 0 21-Jan-2024* 0 Submit and Obtain Approval – All Project Documents,
A1190 Datasheet and Procurement Activities 0 21-Jan-2024* 0 Datasheet and Procurement Activities,
A1200 Drawings (for Construction) AFC 0 28-Jan-2024* 0 Drawings (for Construction) AFC,
A1210 Commence Works on site 0 28-Jan-2024* 0 Commence Works on site, 28-Jan-2024*
A1220 Completion of Works for Package 31 0 08-Apr-2024* 0 Completion of Works for Package 31
A1230 Commissioning and Project Closeout 0 15-Apr-2024* 0 Commissioning and Project

M.P..4 Mobilization
Mob
A1020 mobilization 6 15-Jan-2024 21-Jan-2024 0 mobilization

M.P..2 Engineering
Eng
M.P..2.6 Project
Proj Documents
M.P..2.6.3 Documents Submittal
A1030 HSE Documents 3 15-Jan-2024 17-Jan-2024 0 HSE Documents
A1040 Quality Plan 3 15-Jan-2024 17-Jan-2024 0 Quality Plan
A1050 Material 3 15-Jan-2024 17-Jan-2024 0 Material
A1060 Methode of statement 3 15-Jan-2024 17-Jan-2024 0 Methode of statement
A1070 RSJ’s Project Schedule 3 15-Jan-2024 17-Jan-2024 0 RSJ’s Project Schedule
A1080 All Project Security Pass Applications 3 15-Jan-2024 17-Jan-2024 0 All Project Security Pass Applications
M.P..2.6.1 Documents Approval
A1090 HSE Documents 2 18-Jan-2024 20-Jan-2024 0 HSE Documents
A1100 Quality Plan 2 18-Jan-2024 20-Jan-2024 0 Quality Plan
A1110 Material 2 18-Jan-2024 20-Jan-2024 0 Material
A1120 Methode of statement 2 18-Jan-2024 20-Jan-2024 0 Methode of statement
A1130 RSJ’s Project Schedule 2 18-Jan-2024 20-Jan-2024 0 RSJ’s Project Schedule
A1140 All Project Security Pass Applications 2 18-Jan-2024 20-Jan-2024 0 All Project Security Pass Applications
M.P..2.2 Shop
Sho drawing Track
M.P..2.2.1 Shop Drawing Submittal
A1240 shop drawing submittal 7 15-Jan-2024 22-Jan-2024 0 shop drawing submittal
M.P..2.2.2 Shop Drawing Approval
A1250 shop drawing approval 4 23-Jan-2024 27-Jan-2024 0 shop drawing approval

M.P..3 Procurement
Proc
A1150 Datasheet and Procurement Activities 5 15-Jan-2024 20-Jan-2024 0 Datasheet and Procurement Activities
M.P..3.1 Shop
Sho Drawing Tracking
M.P..3.1.1 Shop Drawing Submittal
A1160 Shop Drawing Submittal 6 15-Jan-2024 21-Jan-2024 0 Shop Drawing Submittal
M.P..3.1.2 Shop Drawing Approval
A1170 Shop Drawing Approval 5 22-Jan-2024 27-Jan-2024 0 Shop Drawing Approval

M.P..5 Exec
Execution Work
M.P..5.1 A12 - WWRO HP PUMPS - 1 (A12-G-7012)
M.P..5.1.1 Installation MicroPiles
A1600 Excavation 3 28-Jan-2024 30-Jan-2024 1 Excavation
A1610 Steel Installation 2 31-Jan-2024 01-Feb-2024 1 Steel Installation
A1620 Supply and Installation of Pressure Grouted 2 03-Feb-2024 04-Feb-2024 1 Supply and Installation of Pressure Grouted
A1630 installation Steel Plate 1 05-Feb-2024 05-Feb-2024 1 installation Steel Plate
M.P..5.1.2 Foundation & Connect F/M
A1635 Lifting of Foundation 1 06-Feb-2024 06-Feb-2024 1 Lifting of Foundation

Actual Level of Effort Remaining Work Milestone Page 1 of 2 TASK filter: All Activities
Actual Work Critical Remaining Work © Oracle Corporation
MICRO Piling and Grouting Installation - Package 31 24/12/2023

Activity ID Activity Name Original Start Finish Total Float 2024


Duration
Jan Feb Mar Apr May
A1640 Connection (Dowel Bars) 1 07-Feb-2024 07-Feb-2024 1 Connection (Dowel Bars)
A1650 Steel fixing for Slab 1 08-Feb-2024 08-Feb-2024 1 Steel fixing for Slab
A1655 Concrete Pouring 1 10-Feb-2024 10-Feb-2024 1 Concrete Pouring
M.P..5.2 A12 - WWRO HP PUMPS - 2 (A12-G-0012)
M.P..5.2.1 Installation MicroPiles
A1740 Excavation 3 11-Feb-2024 13-Feb-2024 1 Excavation
A1750 Steel Installation 2 14-Feb-2024 15-Feb-2024 1 Steel Installation
A1760 Supply and Installation of Pressure Grouted 2 17-Feb-2024 18-Feb-2024 1 Supply and Installation of Pressure Grouted
A1770 installation Steel Plate 1 19-Feb-2024 19-Feb-2024 1 installation Steel Plate
M.P..5.2.2 Foundation & Connect F/M
A1555 Lifting Foundation 1 20-Feb-2024 20-Feb-2024 1 Lifting Foundation
A1660 Connection (Dowel Bars) 1 21-Feb-2024 21-Feb-2024 1 Connection (Dowel Bars)
A1670 Steel fixing for Slab 1 22-Feb-2024 22-Feb-2024 1 Steel fixing for Slab
A1900 Concrete Pouring 1 24-Feb-2024 24-Feb-2024 1 Concrete Pouring
M.P..5.3 A12 - WWRO HP PUMPS - 3 (A12-G-8012)
M.P..5.3.1 Installation MicroPiles
A1780 Excavation 3 25-Feb-2024 27-Feb-2024 1 Excavation
A1790 Steel Installation 2 28-Feb-2024 29-Feb-2024 1 Steel Installation
A1800 Supply and Installation of Pressure Grouted 2 29-Feb-2024 03-Mar-2024 1 Supply and Installation of Pressure Grouted
A1810 installation Steel Plate 1 03-Mar-2024 04-Mar-2024 1 installation Steel Plate
M.P..5.3.2 Foundation & Connect F/M
A1675 Lifting Foundation 1 04-Mar-2024 05-Mar-2024 1 Lifting Foundation
A1680 Connection (Dowel Bars) 1 05-Mar-2024 06-Mar-2024 1 Connection (Dowel Bars)
A1690 Steel fixing for Slab 1 06-Mar-2024 07-Mar-2024 1 Steel fixing for Slab
A1910 Concrete Pouring 1 07-Mar-2024 09-Mar-2024 1 Concrete Pouring
M.P..5.4 A12 - PIPING SKID - 1 (A12-G-7012/0012/8012)
M.P..5.4.1 Installation MicroPiles
A1820 Excavation 3 09-Mar-2024 12-Mar-2024 1 Excavation
A1830 Steel Installation 2 12-Mar-2024 14-Mar-2024 1 Steel Installation
A1840 Supply and Installation of Pressure Grouted 2 14-Mar-2024 17-Mar-2024 1 Supply and Installation of Pressure Grouted
A1850 installation Steel Plate 1 17-Mar-2024 18-Mar-2024 1 installation Steel Plate
M.P..5.4.2 Foundation & Connect F/M
A1695 Lifting Foundation 1 18-Mar-2024 19-Mar-2024 1 Lifting Foundation
A1700 Connection (Dowel Bars) 1 19-Mar-2024 20-Mar-2024 1 Connection (Dowel Bars)
A1710 Steel fixing for Slab 1 20-Mar-2024 21-Mar-2024 1 Steel fixing for Slab
A1920 Concrete Pouring 1 21-Mar-2024 23-Mar-2024 1 Concrete Pouring
M.P..5.5 A12 - (RO SWWW-WW PUMP AREA)
M.P..5.5.1 Installation MicroPiles
A1860 Excavation 3 23-Mar-2024 26-Mar-2024 1 Excavation
A1870 Steel Installation 2 26-Mar-2024 28-Mar-2024 1 Steel Installation
A1880 Supply and Installation of Pressure Grouted 2 28-Mar-2024 31-Mar-2024 1 Supply and Installation of Pressure Grouted
A1890 installation Steel Plate 1 31-Mar-2024 01-Apr-2024 1 installation Steel Plate
M.P..5.5.2 Foundation & Connect F/M
A1715 Lifting Foundation 1 01-Apr-2024 02-Apr-2024 1 Lifting Foundation
A1720 Connection (Dowel Bars) 1 02-Apr-2024 03-Apr-2024 1 Connection (Dowel Bars)
A1730 Steel fixing for Slab 1 03-Apr-2024 04-Apr-2024 1 Steel fixing for Slab
A1930 Concrete Pouring 1 04-Apr-2024 06-Apr-2024 1 Concrete Pouring

M.P..7 Commissioning
Com and Project Closeout
A1580 Asbuilt Drawings 2 08-Apr-2024 09-Apr-2024 0 Asbuilt Drawings
A1590 Testing & Handing Off 4 10-Apr-2024 14-Apr-2024 0 Testing & Handing Off

Actual Level of Effort Remaining Work Milestone Page 2 of 2 TASK filter: All Activities