Procedure For Welding
Procedure For Welding
Production welding
ACPL
Procedure
For
Production Welding
1 Scope
This document shall be followed for the fabrication of all types of weld joints and repairs
of the weld of Steel Pipeline network for distribution of natural gas network.
ASME Sec. II, Part - C Specification for welding Electrodes and Filler Materials
3 Procedural Step
3.2 Execution
The root gap shall be accurately checked and shall conform to the qualified welding
procedure. The use of pipe clamp either internal or external is selected considering
requirements of pigging of pipeline in future However, in some case (tie in welds,
flanges, fittings, diameter of pipe 10” etc.) where it is impossible to use internal clamps,
an external line up clamp may be used.
Approved welding procedure Specification shall be used for production.
Certified electrodes shall only be used for the welding. Electrode selection shall be done
as per approved WPS.
Welding Procedure Qualification and Welder’s Qualification Records shall be verified by
GGL / TPIA before starting the welding. No welder shall be permitted to work without the
possession of Welder identity card.
Welding of various materials under this specification shall be carried out using Shielded
Metal Arc Welding Process (SMAW) with the approval of the Engineer – in – charge/TPIA.
From the ground and support skids shall be minimum two per pipe, the skid shall have
rubber sheet / sand / soft soil / saw dust bags placed over them to avoid damage to the
pipe coating. Prior to the line up, pipes shall be checked with cleaning / gauging pig to
ensure freedom internal dent or debris.
Seam orientation of welded pipe shall be selected to ensure that at the circumferential
welds, the longitudinal welds shall be staggered in the top 90 o of the pipeline, or 250 mm
whichever is the lesser. A longitudinal joint shall pass an appurtenance of a structural
element at a minimum distance of 50 mm.
For pipe of the same nominal wall thickness the circumferential offset shall not exceed 1.6
mm. No hot dressing shall be permitted. When different wall thickness are involved, the
thickness of thicker pipe shall be tapered to a minimum 1:4 by grinding or any other
means approved at site. Alignment and fit- up shall be checked before welding.
Any branch connection, sleeve, etc. shall be positioned at least 150 mm from any other
adjacent weld.
The welds for fittings shall be so located that the toe of the weld shall not come within 50
mm of any other adjacent weld.
When welding pipes of different pipe grade (as directed by Engineer-in-charge/TPIA.)
A special transition piece shall be used. This shall have a minimum of 1:4 taper. The welds
shall be subject to both ultrasonic and radiographic inspection.
Before commencement of welding works Aneri Construction shall submit Electrode Batch
Certificates to the GGL/TPIA for all electrodes prior to deployment on the project.
3.2.3 Preheating
As per qualified WPS
Preheating shall extend to at least 50 mm on both sides of the weld area.
Preheating temperature shall be maintained over the whole length of the joint during
welding. The CONTRACTOR to check the temperature shall provide temperature
indicating crayons or other temperature indicating devices.
Upon re-starting of any suspended welding operating (after depositing weld metal of at
least 50% of pipe thickness) and depending on the material, wall thickness and welding
process, a pre-heating of at least. 100 degree C shall be carried out.
3.2.4 Welding
The welding process to be employed is given in the welding specification any deviation
shall be through the written consent of GGL/TPIA agency. The root gap shall be accurately
checked and shall be as per qualified WPS.
When an external line up clamp is used, all spaces between bars or at least 60% of the
first pass shall be welded before the clamp is released and the pipe remaining adequately
supported on each side of the joint.
Aneri Construction shall inform GGL/TPIA, if any section of pipeline containing incomplete
welds falls from the skid.
The root pass of butt joints shall be executed properly so as to achieve full penetration
with complete fusion of the root edges.
Welding shall not be interrupted during a pass and shall be completed as early as possible.
Any kind of movement of components, shocks, vibrations, bumping and stresses are
prohibited while welding is in progress.
Once the deposit of first pass has been started, it must be completed as rapidly as possible
in accordance with the WPS, all interruptions to the welding cycle shall be kept to a
minimum.
The welding speed shall be within the parameters as that established in the qualified
welding procedure.
3.2.4.1 Cleaning:
Removing the flux, craters, welding irregularities, slag etc. shall be by means of a power
brush/ power grinding.
All finished welds shall be visually inspected for parallel and axial alignment of the work,
reinforcement, concavity, shrinkage, cracks, undercuts, dimensions of weld porosity and
other surface imperfections noted shall be rectified, to the satisfaction of the contract
specification
3.2.5 NDT:
100% NDT of the total Main line welding joints and all Tie-in and Fittings joints, Valve
joints shall be carried out. and the results to be recorded in the approved format.
4 Welding Repairs:
Welds, which do not comply with the standards of acceptability, shall be repaired or the
joint cut out and re-welded.
A Separate welding procedure with welders’ qualification (as per API1104 and GGL/TPIA
approved) shall be required to be produces before taking repairing jobs.
Repair will be done with SMAW process by a single welder as per the WPS.
With respect of radiography or other NDT method, repair location will be marked on the
weld to reference points on film with tracing paper.
4.1 Method of Repair
Partial Repair: Each layer will be thoroughly checked for this type of discontinuity
predicted NDT reports. Smooth grinding will be done to make “V” groove and clean all
surfaces. This is limited to 30% of weld length only.
Through Repair: Grinding will be done up to root and root opening will be done by chisel,
hacksaw blade. The entire repair portion will be ground smoothly to “V” groove, to attain
root of sufficient gap as per WPS. Minimum repair length to be 100 mm as measured over
recap length. Limiting the root repair to only 20% of weld length.
The welded joint to be repair in the preheated to the extent of 50mm on either side of
weld using Propane hand held torch up to 1000 C.
4.2 Welding:
After identifying the defects, grinding shall be done to remove the defects. Care shall be
taken to ensure that no grinding marks on pipe surface anywhere. DPT examination shall
be done to ensure the removal of defect. Root sealing or single pass repair deposit shall
not be permitted. Internal root defects shall be ground thoroughly and welded with a
minimum of two passes as per qualified procedure. The edge preparation shall be smooth
free form burrs, cuts and other surface irregularities. The root gap shall be made carefully
The welded area shall be thoroughly cleaned. Repairs opening the root shall be carried
out in the presence of the GGL/TPIA. All repairs shall be carried out during the day after
initial radiography of as early possible
The reports of the all repairs shall be maintained by the Aneri Construction and shall be
submitted to the GGL/TPIA
Each pass will be thoroughly cleaned using Power brush / Grinder
The repair shall be subjected, as a minimum requirement to the same testing and
inspection requirements as the original weld. The entire joint shall be re-radiographed. A
100% ultrasonic test shall be done at the repaired area externally. Any repaired area that
is wide, irregular or rough shall be rejected and a full cut out shall be done.
Only one attempt at repair of any region is permitted and no re repairs will be acceptable.
5 Documentation
Inspection Report
Inspection Test Plan