Method Statement For Valve Replacement at Jalan Berkat
Method Statement For Valve Replacement at Jalan Berkat
DOC-KS AMAN-M-018-MS-0
METHOD STATEMENT FOR VALVE REPLACEMENT AT
Revision 0
JALAN BERKAT
Date 10/10/2023
Table of Contents
3.1 Preliminaries
4.1.1 Materials
4.1.3 Manpower
5.1 Safety
5.2 Environment
1.0 Purpose
This method statement generally described the procedures and scope of works to
carry out and complete the valve replacement at Jalan Berkat.
All works shall comply with the requirement of Local Authorities. The contractor shall
execute the works in strict conformity with the approved plans and shall arrange for
the necessary formalities to be complied with.
Doc. No. DOC-KS AMAN-M-018-MS-0
METHOD STATEMENT FOR VALVE REPLACEMENT AT
Revision 0
JALAN BERKAT
Date 10/10/2023
3.1 Preliminaries
i. All the signboard and safety equipment shall be ready and comply with
the requirement of the authorities and approved by clients.
ii. Flagman provided on site shall be incharged to control traffic flow and
signboards to be used during physical work on site.
4.1.1 Material
ITEM DESCRIPTION
1. 1 nos MS pipe 100mm cut to suit site
2. 1 nos 100mm Sluice valve
3. 1nos 100mm Flange adaptor
4. Bolt and Nut
5. EPDM Gasket
6. Ring Flanges
4.1.3 Manpower
Item Description No. Of Personnel
1 Supervisor 1
2 Skilled Worker 2
3. General Worker 2
4. Flagman 2
Doc. No. DOC-KS AMAN-M-018-MS-0
METHOD STATEMENT FOR VALVE REPLACEMENT AT
Revision 0
JALAN BERKAT
Date 10/10/2023
i. Ensure excavation and fabrication of pipeworks has been prepared early before the
replacement work.
ii. Close the water sources at existing pipe by authoritiy (Air Selangor Petaling Region).
iii. After the water sources completely closed, the scour valve need to open to dewatering
the water inside the pipe assist by plant operation.
v. Dismantle the existing valve together with the short piece by untightening the bolt nut
at the joint, then remove/lifting the valve to temporary area.
vi. Install the new DN100 sluice valve complete with short piece, gasket, bolt nut and
flange adaptor to the existing pipeline.
vii. After complete the new valve installation, the water sources can be open for supply
and recovery.
5.1 Safety
i. Safety tool box meeting shall be conducted before start work to remind
workers about concerning the safety.
ii. All workers shall provide with proper Personal Protective Equipement (PPE)
and shall be worn every time they are entering the site.
iii. Permit to work (PTW) shall valid for working on site.
iv. Safety Supervisor shall ensure that the activity shall carry out in a safe
manner.
v. Proper and adequate provision of temporary signage’s and barricade at
working area.
Doc. No. DOC-KS AMAN-M-018-MS-0
METHOD STATEMENT FOR VALVE REPLACEMENT AT
Revision 0
JALAN BERKAT
Date 10/10/2023
5.2 Environment
new 200mm DI
new 200mm DI
Doc. No. DOC-KS AMAN-M-018-MS-0
METHOD STATEMENT FOR VALVE REPLACEMENT AT
Revision 0
JALAN BERKAT
Date 10/10/2023
Jalan Berkat
pipe 150mm
Existing DI
New DI pipe 200mm
Berkat 5
Lorong
150 x150mm tee with
2nos Dresser joint Existing AC pipe 100mm
150mm
PROJECT PROPONENT :
PENGURUSAN AIR SELANGOR SDN. BHD. GHAZALI & ASSOCIATES SDN BHD KNH TECHNOLOGY SDN. BHD.