0% found this document useful (0 votes)
29 views5 pages

Selga, Aldrin Jhon Bsit

1) The document contains information about a project including activities, durations, and predecessor relationships. 2) The critical path of the project is activities A, B, C, F, G, H. 3) It will take 31 weeks to complete the project.

Uploaded by

Aljon Selga
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
29 views5 pages

Selga, Aldrin Jhon Bsit

1) The document contains information about a project including activities, durations, and predecessor relationships. 2) The critical path of the project is activities A, B, C, F, G, H. 3) It will take 31 weeks to complete the project.

Uploaded by

Aljon Selga
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 5

Selga, Aldrin Jhon

BSIT

X Y XY X² (ƩY)(ƩX²) - (ƩX)(XY) (585)(21145) - (325)(38135) 12369825 -


68 132 8976 4624 N(ƩX²) - (ƩX)² 5(21145) - (325)² 105725 -
64 108 6912 4096
62 102 6324 3844 N(ƩXY) - (ƩX)(ƩY) 5(38135) - (325)(585) 190675 -
65 115 7475 4225 N(ƩX²) - (ƩX)² 5(21145) - (325)² 105725 -
66 128 8448 4356
325 585 38135 21145

X
Y X 69
68
132 68 67
108 64 66
102 62 65
64
115 65 63
128 66 62
61
60
59
100 105 110 115 120 125 130 135
12393875 -24050
105625 100 -240.5

190125 550
105625 100 5.5
Selga, Aldrin Jhon
BSIT

Activity Immediate Predecessor Time


A - 4
B A 9
C A, B 7
D A 4
E B 3
F C, D 6
G D, F 3
H E, F, G 2

Activity ES EF LS LF Slack Critical Path


A 0 4 0 4 0 0 YES
B 4 13 4 13 0 0 YES
C 13 20 13 20 0 0 YES
D 4 8 16 20 12 12 NO
E 13 16 26 29 13 13 NO
F 20 26 20 26 0 0 YES
G 26 29 26 29 0 0 YES
H 29 31 29 31 0 0 YES

A. Construct the Network Diagram


B. What is the Critical Path A,B,C,F,G,H
C. How many weeks will it take to complete the Project? 31 Weeks
D. How much Slack Time does Activity E have? 13
E. Construct the GANTT Chart
Selga, Aldrin Jhon
BSIT

B 4 13 E 13 16
9 4 13 3 26 29

A 0 4 C 13 20
4 0 4 7 13 20 H 29 31
2 29 31
D 4 8 F 20 26
4 16 20 6 20 26

G 26 29
3 26 29
Selga, Aldrin Jhon
BSIT

Activity 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
A
B
C
D
E
F
G
H