CH 4. Project Costing and Valuation
CH 4. Project Costing and Valuation
1
5. Project cost estimation
Project cost estimation is the process of valuing on monetary expression,
including the cost of all possible entrants necessary for the planning,
implementing and monitoring stages of the proposed project under
consideration.
If the available financial capacity is smaller than the estimated cost, it is
important to redefine the scope of the work by either changing the
specification or size of the work.
The possible entrants of project cost are:
Preliminary investigation (project appraisal costs)
design and supervision (consultancy cost )
construction works (contractor’s cost )
land owning cost
monitoring costs
Cost due to construction is the focus of this chapter
Cost includes:
Example: Material Break Down for 1m3 C-25 concrete (1:2:3 mix)
Purposes of Estimation and factors affecting cost estimation
This is the most reliable and accurate type of estimate. The quantities of items are
carefully prepared from the drawings and the total cost worked out from up to
date market rates. Detailed estimate is accompanied by a detailed report,
detailed specification for the execution of the work, and detailed drawings, etc.
3. Revised Estimate
It is a detailed estimate prepared afresh when the original detailed estimate is beyond
an acceptable range. It should be accompanied by all the papers as in the case
of the detailed estimate and also should include the comparative statements of
variations in each item of works.
4. Supplementary Estimate
When additional works are there, a fresh detailed estimate is prepared to supplement
the original work.
Rate Analysis
Rate Analysis is the process of fixing cost per unit of measurement for the
different item of works. Cost due to construction (contractor’s cost) is given
special attention here.
Total cost per unit of work (TC) may be grouped into two components;
2. Indirect cost.
The direct cost (DC) includes cost due to material, cost due to labor, cost due to
equipment, whereas
Overhead costs are expenses for general office facility, rents, taxes, electrical
light, water, and other miscellaneous items.