Example Structural Calculation - Foundation2
Example Structural Calculation - Foundation2
55 Huntingdon Street
SUBJECT ADDRESS:
London
N1 1BX
COMMISSIONING
Goran Mickovski
CLIENT:
DATE OF WRITING:
August 2018
www.mintstructures.co.uk
TABLE OF CONTENTS
TABLE OF CONTENTS 2
1. OVERVIEW 3
2 DESK STUDY 5
3. BASEMENT CONSTRUCTION 9
6 CONCLUSION 18
7 REFERENCES 19
8 APPENDICES 20
3
1. OVERVIEW
Existing structure:
The subject property is a mid-terrace two-storey house; with brick external walls, assumed
traditional cut roof (tiled) and is located set back from the pavement behind a small
courtyard. A small garden is present to the rear.
The terrace that the subject property is a part of does not date from the same era as
Georgian/Victorian terraces surrounding it, having been constructed at a much later date
th
Summary of Proposed assumed to be around the mid-20 century.
Works
Proposed works:
1. Formation of a single storey basement & front lightwell under the ground floor
and rear garden at the above address.
Reinforced concrete (RC) basement walls to be formed in one phase enabling the full
required basement depth to be achieved.
Two rows of horizontal props will be required to all full height underpins spanning
across the whole site. Props should remain in place until the basement and any
Fundamental
Construction Areas ground floor slabs have been fully constructed and have sufficiently cured providing
permanent lateral restraint to the new RC retaining walls.
All underpins and retained earth requires temporary works and shuttering during
excavation and casting until slabs are cast.
www.mintstructures.co.uk
Position of site
(approx.)
Site Location
The content of this document should be read in conjunction with temporary works drawing
set TW1-TW2 and the permanent works structural engineer’s package along with any other
relevant drawings/ details.
The purpose of this package is to provide a method statement and suggested construction
sequence to enable the required elements of temporary works to be installed thus allowing
Buildings of the age of the property in question have often reached equilibrium with
their surroundings. The superstructure slowly deforms with time during its life to
accommodate any minor settlements and therefore some work is likely to have been
carried out in the past and additional repairs may be necessary as a result of the
proposed works.
General Comments Any modifications to the existing property should be investigated with local opening
up works to assess their potential impact on the proposed scheme.
The contractor is responsible for the design and correct installation of all temporary
works required to safely install the proposed basement and any other affiliated works.
The contractor is to ensure that all excavations, any new structure and any
neighbouring structures are adequately supported for the full duration of the works.
2 DESK STUDY
The 1:50000 Geological Survey of Great Britain (England and Wales) covering the area (Sheet 256,
‘North London’, Solid and Drift Edition) indicates the site is underlain by the London Clay
Formation close to a head propensity band.
Position of site
(approx.)
Geological
information
Head propensity (if present) is a stratum consisting of geologically recent head deposits.
The London Clay formation typically comprises clay, silt and sand with occasional
gypsum crystals and claystone at depth. At the site location the London Clay is likely to
be approximately 70-100m thick.
Deeper bedrock stratum is beyond the scope of this report.
A desk study of historic boreholes was carried out using the BGS archives, the results of which are
summarized below. See Appendix for records of boreholes.
It should also be noted that isolated pockets of perched groundwater may be present within
material of low permeability found at shallow depths (especially within bands of Made Ground).
It is recommended that prior to any construction, as a minimum, monitoring standpipes are
placed on site to measure groundwater levels over an extended period of 4-6 weeks. (It is also
recommended that the water levels at these monitoring points are periodically measured
immediately prior to, and during construction. This will help to ensure correct measures are taken
if water is likely to be encountered during excavation.)
At the time of writing, soil analysis results are not available with regard to chemical attack on
Chemical attack below ground concrete structures. Therefore we have assumed basic precautions based on
on buried previous experience. Within the London Clay layer there is a good chance segregations of gypsum
concrete
will be present which may attack buried concrete. As a result of this we would recommend that
buried concrete is designed in accordance with full Class DS-2 conditions.
Hydrology and
drainage
Flood Risk
According to the EA flood map for planning, the site is situated in Flood Zone 1 meaning it is of
low risk from flooding, the extracted EA image below shows the proximity of the site to local
areas of likely flooding. The specific risks from flooding are then further analysed in the following
pages.
Fig.10 – Showing flood risk from local river flooding according to the EA (2018).
Very low risk means that each year this area has a chance of flooding of less than 0.1%. This
takes into account the effect of any flood defences in the area. These defences reduce but do not
completely stop the chance of flooding as they can be overtopped, or fail.
Fig.11 – Showing flood risk from surface water flooding according to the EA (2018).
Groundwater movement around this type of proposed structure is cited in the Camden Geological,
Hydrogeological and Hydrological Study which states that large excavations for subterranean
structures in London have to date not been seen to cause serious problems resulting from
damming groundwater. Therefore the proposed basement is not considered at risk of significantly
affecting the flow of water in the area local to the site.
The current sewerage system serving the property in its existing condition is assumed to have
sufficient capacity to manage any proposed foul water demands as little flow or volume change is
expected.
It should be noted that this is a pre-planning report and therefore specific drainage details are
not available at the time of writing. It can be safely assumed, however, that the drainage system
serving the new basement will utilize a pumped drainage arrangement, incorporating fail-safe
systems to minimize risks of flooding.
3. BASEMENT CONSTRUCTION
Basement walls
Basement walls are to be formed in reinforced concrete following the underpinning sequence shown (see fig 3). In the
permanent case the RC walls will support any load applied from the structure over as well as resisting the retaining
soil, surcharging & any water present behind them (see fig 2).
Heave protection
The removal of excavated soil to form the basement will significantly reduce the loading on the deep clay layer likely
present below the property creating the possibility of heave occurring. Therefore heave protection to the slab is
recommended to avoid cracking within the basement slab (see fig 4.)
Notes:
1. Unless otherwise instructed a 50mm thick blinding layer should be provided beneath all
reinforced concrete to provide a clean level surface and avoid pouring directly on to
Materials
ground/hard core.
2. High Alumina Cement (HAC) should not be used under any circumstances.
Concrete cover
All cover should adhere to minimum values specified by the Eurocodes (BS EN 1992-1-
1:2004).
It is recommended that: Concrete internal cover = 35mm
Concrete external cover = 50mm
Direct contact with ground = 75mm
A specialist designed waterproofing system will be required to give the correct level of
protection against the ingress of groundwater, the detailed design and specification of
measures of this type however are beyond the remit of this report. It is advised that a
Waterproofing
waterproofing specialist is contacted early on in the design process and that as a minimum
the final waterproofing system complies with BS8102:2009 - Code of practice for protection
of below ground structures against water from the ground.
2
Allowable GBP @ ground level = 100kN/m (Granular soil type TBC)
Allowable GBP @ formation level:
Ground Bearing
pressure Allow for enhancement of 25% to account for excavated soil mass;
When mass excavation is carried out a certain degree of upward movement results in the
base of the excavation. This occurs due to the unloading associated with the removal of
the excavated spoil the soil recovery is considered in two parts.
Heave which results from the “elastic rebound” of the soil and is often seen predominantly
during construction.
Ground movement
Swell which results from a change in pore water absorption as the formation level strata
adjusts to the new stress conditions.
The site is underlain by a London Clay Formation which has a propensity for high levels of
shrinkage and swelling in relation to variances in moisture content, this is detailed by the
NHBC Standards, Chapter 4.2 (2010).
The actual amount of upward movement will depend on a combination of factors and as a
result is difficult to accurately predict, however to protect against these movements, floor
slabs should be fully suspended and cast over heave protection.
Any foundations that are required to be cast at shallow depths, within the zone of
influence of trees as specified by the NHBC, should adhere to the guidance given in the
aforementioned chapter NHBC Standards 4.2.
Mass excavations associated with the construction of basements increase potential that a
development will cause ground movement in the local area if the construction processes
are not managed correctly. However these movements can be mitigated with experienced
and proper design processes adhering to the relevant codes of practice. The design of both
the temporary works and permanent works must be carried out by a suitably qualified, and
crucially, experienced team of engineers, architects, designers and other specialists working
closely to ensure that as far as is practically possible the proposed scheme has any possible
weaknesses, where movements may occur, designed out.
The appended calculation shows that we currently assess the CIRIA C580 Damage Category
to be 2 (Slight).
A monitoring plan should be set out at the design stage, however an indicative suggested
plan is included in the next section (this is not for any on-site purposes and all monitoring
must be carried out by a specialist company to their own method statements).
The resistance of the existing and surrounding buildings is defined in BS 4866:2010 in
Annex B and the subject and neighbouring buildings fall in Group 1 in clause B.4.1
(traditionally built) - “Generally, this group is of heavy unframed construction and has a
very high damping coefficient due, for example, to soft lime mortar or plaster”.
The foundations for the subject and neighbouring buildings are assumed to fall into Class
C in clause B.5.3 (Strip footing).
The soil type from drift maps and historical boreholes is London clay, therefore according
clause B6 the soil is classified as type e – “soft cohesive soils (clays)”.
Resistance to vibration
According to table B.1 the subject and neighbouring buildings can be classed as Category 6
which indicates a medium to high resistance to vibration.
According to Table B.2 the resistance to vibration can be categorised as class 10, which
indicates a medium to high level resistance to vibration which require minor protective
measures against vibration. The method of construction detailed with the construction
method statement, coupled with the the contractors own method statements for Noise,
Dust and Vibration mitigation will protect the neighbouring buildings from the effects of
vibration during construction.
The proposed works are subject to the Party Wall etc. Act 1996 and it is therefore advised
that the client starts the process/instructs a surveyor as early as possible to ensure that the
necessary party wall awards are in place before work commences.
Party Walls
(For further advice on the party wall process please contact the MiNT Structures party wall
department.)
4 SUGGESTED STRUCTURAL MONITORING PLAN
A ‘traffic light’ system should be adopted with the use of Green, Amber and Red trigger
levels as follows;
GREEN (0-5mm) – Activities OK to proceed.
AMBER (5-10mm) – Increase the monitoring frequently (minimum twice weekly),
review of structural scheme and start implementing contingency
measures if trends indicate the Red trigger may shortly be
reached. [Showing recorded values are close to maximum
projected settlement (say max. 80% of predicted settlement)]
RED (>10mm) - Implement measures to secure site, cease movements and stop
all construction works. [Showing recorded values are at, or above
tolerable levels, exceeding serviceability limit states.]
TRIGGER VALUES
Where maximum movements are recorded exceeding Amber/Red trigger values these
should immediately be reported to the design team along with a description of all recent
on- site activities. A review of the results should be undertaken and readings re-checked to
confirm their accuracy, the design team should not assess the movement focussing solely
on the affected areas but also review the site as a whole, checking for non-proximate
contributory factors. Appropriate repair specifications and reviews of working practices
should be specified and implemented to minimise risk of progressive settlement.
NOTE: The trigger levels suggested within this document are indicative only. Final
movement levels must adhere to Local Authority guidelines and these should be obtained
before confirmation of final trigger values.
Precise locations for levelling targets should be prescribed by the monitoring specialist
however the following guideline is suggested;
As stated in the BRE digest 386 – Monitoring building and ground movement by precise
levelling - a minimum of 8-12 target locations should be installed around the whole site to
TARGET LOCATIONS
provide Northing, Eastings and Level measurements to an accuracy of ±0.3mm (It is
recommended that targets are installed at each storey height). Consideration should also
be given to the provision of monitoring locations on neighbouring structures (provisions of
this type TBC by monitoring specialist and relevant party wall representative).
• PRIOR TO COMMENCEMENT OF CONSTRUCTION MONITORING READINGS SHOULD BE
CARRIED OUT ONCE TO ESTABLISH A SET OF CONTROL VALUES.
Note: Final monitoring intervals and levels of pre- & post-construction readings must be
confirmed by the specialist monitoring contractor.
5. SUGGESTED METHOD STATEMENTS
1. BASEMENT UNDERPINNING
1.2. Hand excavate pins in sections not exceeding 1.0m following numbered sequence provided in temporary
works drawing package. (Typical number sequence shall be 1, 3, 5, 2, 4) under no circumstances are
adjacent pins to be opened during construction.
1.3. During excavations ensure vertical faces are shored at all times using 18mm ply, timber wailing pieces
and horizontal strutting. The exposed face of the excavation should be lined with ‘Hardie Backer 500’
cement board trench sheeting or similar permanent sacrificial shuttering with de-bonding membrane
installed to the inside face of trench sheets prior to concreting.
1.4. Reinforcement should be placed in position in preparation for casting the underpinning base, starter bars
should be provided to enable a connection between the base and the vertical stem to be formed.
1.5. Local authority building control officer or appointed inspector to inspect and pass reinforcement prior to
concreting base section.
1.6. Pour concrete base and kicker sections to structural engineer’s details. Use vibrating pokers to ensure full
compaction of concrete and removal of trapped air pockets within forms.
1.7. Once base has sufficiently cured (min 24 hours) place reinforcement to vertical stem including horizontal
dowel link bars to neighbouring pins (horizontal dowels to structural engineers specification).
1.8. Formwork to be secured with heavy timbers and “Leada Acrow” or similar trench props supported off of
the central earth mass to retain the concrete during pouring. Leave 75mm clearance between top of
concrete pour and underside of existing foundation.
1.9. Pour concrete stem section to structural engineer’s details, use vibrating pokers to ensure full compaction
of concrete within forms.
1.10. Allow 48 hours curing time between concrete pour and installation of dry pack. Clean underside of
existing foundation using wire brush or similar in preparation for installation of dry pack.
1.11. Use 1:3 dry pack well rammed into position between head of pin and underside of existing foundation
(Dry pack to be installed after each individual pin has been cured see point 2.1 regarding corbel removal.)
1.12. Strike formwork following lapsing of sufficient curing period (normally approximately 7 days)
1.13. Underpinning is to continue according to sequence specified in temporary works drawing package
following previously described method.
1.14. Central earth mass is to be retained to enable local shoring of pins and trenches as underpinning
progresses.
1.15. Following completion of all underpinning the central soil mass can be excavated in stages to allow
installation of high level lateral “Mabey Mass 50” or similar engineer approved props in accordance with
propping plan (Drwg TW1).
1.16. The remaining central soil mass can now be removed and a second row of lateral props can be installed
rd
to restrain the lower 3 of the pins.
1.17. Excavate for reinforced concrete basement slab ensuring lateral propping remains in place at all times.
1.18. Compact base of slab excavation and place reinforcing bars to structural engineer’s specification.
1.19. Cast basement slab to structural engineer’s details using vibrating pokers to ensure full coverage of
concrete and removal of trapped air pockets.
1.20. Once basement slab has sufficiently cured (min 14 days) the remaining propping can be removed.
Upon completion of underpinning and sufficient curing of dry packing has been allowed, the existing brick corbel
foundation projection can be removed using hand tools to leave the wall over flush with the face of the RC
underpinning. Care should be taken when removing the corbel to avoid causing undue damage. Where brickwork
is in poor condition it should be carefully made good in small increments.
3. STEPPING OF BASEMENT FLOOR LEVELS
The below sequence specifies a suggested method of slab installation where steps in the basement floor level are
required. Construction details should be specified in, and installed in accordance with, the structural engineer’s
package.
5.1. Once underpinning is complete excavate central dumpling in stages down to formation level of higher
level slab installing propping as excavation progresses.
5.2. Place reinforcement for upper slab to structural engineer’s specification and drive starter bars for step at
slab edge ready for connection with step wall section and lower slab (see fig 5).
5.3. Once slab has had sufficient curing time (min 48 hours), excavate down to lower slab formation level.
5.4. Place reinforcement for lower slab and RC step to structural engineer’s specification.
5.5. Cast lower slab and step wall section and allow adequate curing time (48hours) before removing any slab
formwork. (Horizontal propping of walls across site to remain in place for min 14 days until slab has had
sufficient curing time).
The method described below is a typical generic steel beam/frame installation; full requirements for shoring of
superstructure should be assessed on site at the start of the project through opening up and inspection of
existing structure
Prior to any underpinning or steel work installation the contractor may also carry out the following works:
Provide bracing to openings including doors and windows with timber constructed frames.
Where frames are to be installed and supported at basement level, pin sections supporting columns/beams
should be excavated and cast first prior to any steel installation being carried out.
Connection details, splices and base plates to be installed in accordance with structural engineer’s specification.
Installation Method
6.1. First install securely diagonally braced “Leada Acrow” propping placed either side of the wall requiring
support, props should be sited on paving slabs bearing on well consolidated ground throughout.
6.2. Install 152x152x30UC needle beams at high level spanning between the Acrow dead shoring to provide
support to the brickwork over and enable removal of masonry panel below.
6.3. Once needling/propping is positioned and tightened brickwork below can be carefully removed by hand.
6.4. Where permanent steel framework is specified members needed to transfer loads in to RC pins should be
installed in accordance with structural engineer’s details to provide a bearing for the high level beam.
6.5. Where bearings are specified cut slots into walls to accept padstone or bearing plates as specified by
structural engineer (allowing 48 hours to cure where padstone are cast).
6.6. Insert permanent steel beam either fixed to columns or seated 100mm into walls at each end on bearings.
6.7. Dry packing should be placed between the top flange and the underside of the wall over allowing 48 hours
to cure. (Where beam is seated on bearings dry pack should also be placed 75mm above and below the
beam well rammed into position and any defective brickwork around beam ends should be removed and
made good using class B engineering bricks and 1:3 mortar once dry pack has cured.)
6.8. Following the provision of full support to the wall above, (and bracing has been securely fitted if frame
installation is being carried out) any temporary works in relation to its support can be removed.
6.9. Any voids in the brickwork where needles had been positioned should now be repaired by bricking up.
6.10. Once adequate support has been provided by the permanent works structure underpinning can proceed as
specified in fig.3.
7.2. The vertical faces of the sump chamber should be supported with a pre-made shutter positioned in the
area excavated for the sump. The sump shutter should be constructed from 18mm thick plywood sheets
with drilled vertical faces to provide a porous surface allowing ground water to flow through.
7.3. Ground water will now flow into the excavated sump to be extracted using a suitable Semi Trash
dewatering pump and appropriate diameter discharge hose.
7.4. Discharge from the sump should be directed to the nearest manhole and a drain filter should be fitted to
avoid any large debris being deposited into the sewer.
7.5. After completion of the excavation and preparation for the concrete pour has been carried out ensure the
sump area is fully dewatered before removing pump and pouring concrete.
7.6. The process above should then be repeated for each excavation where ground water is found.
6 CONCLUSION
The result of this preliminary pre-planning report is that the proposed basement can be
completed successfully without undue impact on its surroundings provided it is constructed
in adherence to statutory guidelines, designed by a suitably experienced and qualified
CONCLUSION design team. It should be noted that the above conclusion is based on the information
available at the time of writing and is not based on site specific geotechnical analysis.
The proposed development is unlikely to significantly increase flood risk at the site and its
surrounding area.
7 REFERENCES
1) Codes / Regulations
II) UK National Annex for Eurocode : Basis of structural design (NS BS EN 1990:2002)
VI) UK National Annex for Eurocode 2 : Design of concrete structures (NA BS EN 1991-1-1:2004)
VIII) UK National Annex for Eurocode 3 : Design of steel structures (NA BS EN 1993-1-1:2005)
2) Books / Manuals
I) Concrete Basements: Guidance on the design and construction of in-situ concrete basement structures – R. S.
III) Manual for the design of steelwork building structures to Eurocode 3 (October 2010) – IStructE.
th
IV) Reynolds’s reinforced concrete designer’s handbook 11 Edition - C. E. Reynolds et al.
rd
V) Standard Method of Detailing Structural Concrete 3 Edition (June 2006) – IStructE.
8 APPENDICES
Created with PTC Mathcad Express. See www.mathcad.com for more information.
Job: 55 huntingdon Street, N1 1BX
Made By: LS Job No.: M18241
Date: Aug 2018
Horizontal
δih
Decrease in movement with distance (per m): Δh ≔ ― = 0.333 ――
lih
Vertical
δiv
Decrease in movement with distance (per m): Δv ≔ ― = 0.333 ――
liv
Created with PTC Mathcad Express. See www.mathcad.com for more information.
Job: 55 huntingdon Street, N1 1BX
Made By: LS Job No.: M18241
Date: Aug 2018
Horizontal
Vertical
Created with PTC Mathcad Express. See www.mathcad.com for more information.
Job: 55 huntingdon Street, N1 1BX
Made By: LS Job No.: M18241
Date: Aug 2018
Limiting tensile strain for very slight damage (Cat. 1): εlim1 ≔ 0.075%
Limiting tensile strain for slight damage (Cat. 2): εlim2 ≔ 0.15%
Created with PTC Mathcad Express. See www.mathcad.com for more information.
Job: 55 Huntingdon St, N1 Job No.: 18241
Made By: LS Revision: -
Date: Aug 2018 Page no:
-3
Concrete [normal reinforced] - (unit load) : ≔ 24 ⋅
-3
Soil [Firm clays / Dense Gravel] - (unit load) : ≔ 18 ⋅
-3
Water - (Bulk density) : ≔ 9.81 ⋅
-2
Characteristic tensile strength of reinforcement: ≔ 500 ⋅
-2
Characteristic compressive cube strength of concrete : ≔ 35 ⋅
Base: ≔ 75
Soil characteristics:
Angle of friction -
Granular Soils - [BS8002, 2.2.4 - = 30 + A + B
A & B taken as 0, worst case]
≔ 30
-2
Granular soil types taken as - ≔ 0.1 ⋅
[Taken from Geotechdata.info, for inorganic clay of high plasticity (London clay) - 15-25kN/m²]
Created with PTC Mathcad Express. See www.mathcad.com for more information.
Job: 55 Huntingdon St, N1 Job No.: 18241
Made By: LS Revision: -
Date: Aug 2018 Page no:
Earth Pressure:
The calculation below for the coefficient of earth pressure is designed to take in to
account both 'active' and 'at rest' pressure influences. The value taken accounts for the
stem not being infinitely stiff but also in the permanent case resisting lateral pressure with
little deflection. Therefore an intermediate median value between Ka and Ko is used.
(An additional value for any inclination of the ground level is allowed for with the
addition of the angle beta.)
1
―
2
⎛ 2 2⎞
cos (( )) - ⎝((cos (( )))) - ((cos (( )))) ⎠
≔ ――――――――――― 1
= 0.48
―
2
⎛ 2 2⎞
cos (( )) + ⎝((cos (( )))) - ((cos (( )))) ⎠
Meadian coefficient:
⎛ - ⎞
≔ + ⎜―――⎟ = 0.59
⎝ 2 ⎠
1
―
2
⎛ 2 2⎞
cos (( )) + ⎝((cos (( )))) - ((cos (( )))) ⎠
≔ ――――――――――― 1
= 2.07
―
2
⎛ 2 2⎞
cos (( )) - ⎝((cos (( )))) - ((cos (( )))) ⎠
Created with PTC Mathcad Express. See www.mathcad.com for more information.
Job: 55 Huntingdon St, N1 Job No.: 18241
Made By: LS Revision: -
Date: Aug 2018 Page no:
Underpinning Conditions:
NOTES / ASSUMPTIONS:
1. The Basement slab is 300mm thick and will be screeded for domestic use.
2. The basement walls are supporting the building over supported on the substrata
beneath.
3. Soil type is taken as London Clay (BGS Sheet 256) to be confirmed by specialist
site investigations.
4. Water - Allow for 9.81kN/m² at ground level.
5. Passive pressures generated due soil present in front of base are ignored due to
excavations for slab installation.
6. The following design does not check against rotational side failure, it is assumed
pins will be fully propped/shored to contractor's designs at all times.
7. The following design does not include deflection checks as these are assumed to
be negligible.
8. The calculation does not include SLS checks for either cracking or shrinkage.
9. The calculation does not allow for the effect of ground water seepage beneath
the wall.
10.In the absence of geotechnical data GBP is taken as 125kN/m^2 allowing for
100kN/m^2 @ ground level + 10kN/m^2 enhancement at formation level (this is
conservative estimate but cannot be increased without a full SI report)
Created with PTC Mathcad Express. See www.mathcad.com for more information.
Job: 55 Huntingdon St, N1 Job No.: 18241
Made By: LS Revision: -
Date: Aug 2018 Page no:
CONDITION A
Wall Details:
Wall Height - ≔ 3.7
Soil Height - ≔
Vertical Loads:
NOTE: All line loads are assumed to be acting centrally on wall stem.
-1
Permenant line load on wall (say) - ≔ 75 ⋅
-1
Imposed line load on wall (say) - ≔ 15 ⋅
-1
Total line load on wall - ≔ + = 90 ⋅
Created with PTC Mathcad Express. See www.mathcad.com for more information.
Job: 55 Huntingdon St, N1 Job No.: 18241
Made By: LS Revision: -
Date: Aug 2018 Page no:
Horizontal forces:
-2
≔ ⋅ ⋅ = 39.3 ⋅
-2
Surcharge magnitude - ≔ 5.0 ⋅
≔ ⋅ ⋅ ⋅ 1.0 = 10.92
⎛ ⎞ ⎛ ⎞
≔⎜ ⋅ ――⎟+⎜ ⋅ ――⎟ = 109.87 ⋅
⎝ 3 ⎠ ⎝ 2 ⎠
⎛ ⎛ ⎛ ⎞⎞⎞ ⎛ ⎞ ⎛ ⎛ ⎞⎞
≔ ⎜⎛⎝ ⎞⎠ ⋅ ⎜ - - ⎜―― ⎟⎟⎟ + ⎜ ⋅ ―⎟ + ⎜ ⋅ ⎜ - ――⎟⎟ = 230.94 ⋅
⎝ ⎝ ⎝ 2 ⎠⎠⎠ ⎝ 2⎠ ⎝ ⎝ 2 ⎠⎠
Mres
Check: ―― > γot ; = 2.1 = “SO OK”
Mot
-2
Base adhesion: = “Clay” ∴ = 20 ⋅ [See deisgn data]
∴ ≔ ⎛⎝ ⋅ tan (( ))⎞⎠ + ⎛⎝ ⋅ 2⎞
⎠ = 136.31
≔ + = 83.62
Fresist
Check: ――> γslide ; = 1.63 = “SO OK”
Fslide
Created with PTC Mathcad Express. See www.mathcad.com for more information.
Job: 55 Huntingdon St, N1 Job No.: 18241
Made By: LS Revision: -
Date: Aug 2018 Page no:
-2
= 125 ⋅ = “Clay”
B
Check within middle 3rd: e<― = “SO OK”
6
Max/ Min pressures:
-2
Pressure @ heel: = 34.91 ⋅
-2
Pressure @ toe: = 111.79 ⋅
-1
= 34.52 ⋅
Horizontal forces:
≔ 0.5 ⋅ ⋅ = 56.1
≔ ⋅ ⋅ ⋅ 1.0 = 9.59
⎛⎝1.0 ⋅ ⎞⎠
2
fig.2 - Retaining wall diagram.
≔ ⋅ ――――― ⋅ 1.0 = 51.81
2 [Water table taken at full height of wall]
Design moment at base of wall, M
⎛⎛ ⎞ ⎛ ⎞ ⎛ ⎞⎞
≔ 1.5 ⋅ ⎜⎜ ⋅ ――⎟ + ⎜ ⋅ ――⎟ + ⎜ ⋅ ――⎟⎟ = 198.72 ⋅
⎝⎝ 3 ⎠ ⎝ 2 ⎠ ⎝ 3 ⎠⎠
Created with PTC Mathcad Express. See www.mathcad.com for more information.
Job: 55 Huntingdon St, N1 Job No.: 18241
Made By: LS Revision: -
Date: Aug 2018 Page no:
≔ - - ―= 240
2
Ultimate moment of resistance, Mu
2
≔ 0.156 ⋅ ⋅ ⋅ = 314.5 ⋅
2
≔ ―――――― = 1834.91 [in per meter i.e. mm²/m]
0.95 ⋅ ⋅ ((0.95 ⋅ ))
2
= 2094.4 [mm²/m]
Created with PTC Mathcad Express. See www.mathcad.com for more information.
Job: 55 Huntingdon St, N1 Job No.: 18241
Made By: LS Revision: -
Date: Aug 2018 Page no:
-2 -2
Heel: ≔ 1.6 ⋅ = 55.85 ⋅ Pressure @ toe: ≔ 1.6 ⋅ = 178.87 ⋅
-2
Maximum varying bearing pressure : ≔ - = 89.18 ⋅
Design moment at internal face of wall (Base self weight omitted conservatively)
2
≔ ――――――= 951.89 [in per meter i.e. mm²/m]
0.95 ⋅ ⋅ ⎛⎝0.95 ⋅ ⎞⎠
2
= 1005.3 [mm²/m]
So use - min. H16 bars @ 200 centres (1005 mm²/m) in btm of base
Created with PTC Mathcad Express. See www.mathcad.com for more information.
Job: 55 Huntingdon St, N1 Job No.: 18241
Made By: LS Revision: -
Date: Aug 2018 Page no:
2
≔ 0.002 ⋅ ⋅ = 700 (half in each face so divide by 2 to get FF req.)
2
≔ ⋅ 0.5 = 350 [mm²/m]
2
= 565.5
So use - H12 bars @ 200 centres in far face bars to prevent excessive cracking
2
≔ max ⎛⎝0.001 ⋅ ⋅ , 25% ⋅ ⎞⎠ = 350 [mm²/m]
2
= 392.7 [mm²/m]
END OF CALCULATION
Created with PTC Mathcad Express. See www.mathcad.com for more information.
Job: 55 Huntingdon St, N1 Job No.: 18241
Made By: LS Revision: -
Date: Aug 2018 Page no:
Reinforcement summary
Created with PTC Mathcad Express. See www.mathcad.com for more information.
Hamdan House, 2nd fl.,
760 High Road, London, N12 9QH.
T: 020 8446 4650
E: [email protected]
W: www.mintstructures.co.uk
Hamdan House, 2nd fl.,
760 High Road, London, N12 9QH.
T: 020 8446 4650
E: [email protected]
W: www.mintstructures.co.uk
0 1 2 3 4 5m
PROJECT
DRAWING
NUMBER Rev
Scale
PROJECT
DRAWING
NUMBER Rev
Scale