Function For Welding, NDT
Function For Welding, NDT
2009F
FUNCTIONAL
OFFSHORE Rev. No. 6
SPECIFICATION
DESIGN Discipline: QA/QC
FOR WELDING
SECTION Page 1 24
& NDT of
24 10/01/2005 6
PDD / PNN SKS JSS
PREPARED / TOTAL No. OF
REVIEWED BY APPROVED BY DATE REV. No.
REVISED BY PAGES
FORMAT No. Ref. PROCEDURE No. ISSUE No. REV. No. REV. DATE:
ODS/SOF/004A ODS/SOP/008 TO 015 01 01 15/10/2003
SPEC. No. 2009F
FUNCTIONAL
OFFSHORE
SPECIFICATION Rev. No. 6
DESIGN
FOR WELDING Discipline: QA/QC
SECTION
& NDT Page 2 of 24
1.0 SCOPE
This specification modifies and/or supplements the referenced codes that apply
to all piping, pressure vessels, structural and pipeline welding. These
requirements cover welding done at supplier’s fabrication plant, Contractor’s
Yard, or field installation, either onshore or offshore.
The following Codes shall be the minimum acceptable standards for welding and
inspection. The latest edition, addenda, and supplement available at the time of
bidding will be used. Any part of any other non-listed code referred to in these
listed codes as augmentation is to be considered applicable.
STRUCTURAL
AWS D 1.1
API RP 2A
API RP 2B
ASME Section V, VIII
ASTM E 92 and E 142
API RP 2X
ASME SEC IIC
SNT-TC-1A
ASME Sec.IX
ANSI B 31.3
ANSI B31.4
ANSI B31.8
ASME Sec. VIII
ASME Sec. V
ASME Sec. II Part C
NACE-MR-01-75 / ISO 15156
SNT-TC-1A
FORMAT No. Ref. PROCEDURE No. ISSUE No. REV. No. REV. DATE:
ODS/SOF/004B ODS/SOP/008 TO 015 01 01 15/10/2003
SPEC. No. 2009F
FUNCTIONAL
OFFSHORE
SPECIFICATION Rev. No. 6
DESIGN
FOR WELDING Discipline: QA/QC
SECTION
& NDT Page 3 of 24
PIPELINES
1. Low hydrogen electrodes shall be used for structural and piping welding.
6. Internal line up clamp shall be used for pipeline welding 6” and above.
7. For pipelines , low hydrogen electrodes with uphill technique shall be used
for all repairs, when external line up clamp is used, tie-in, special crossings
and fillet welds.
8. Welding shall be carried out as per approved WPS. For structural and
carbon steel piping, previously qualified WPS are acceptable subject to the
PQR’s have been qualified in the presence of reputed IIIrd party inspection
agency,
as mentioned in Contract. All certificates shall be submitted to company
for review & approval. For entire pipeline welding and for piping welding
involving Corrosion Resistant Alloys (CRA) including CS-NACE, Cu-Ni,
SS and DSS etc, previously qualified procedures are not acceptable. The
contractor shall qualify new procedures for entire pipeline welding and for
piping welding involving CRA materials.
FORMAT No. Ref. PROCEDURE No. ISSUE No. REV. No. REV. DATE:
ODS/SOF/004B ODS/SOP/008 TO 015 01 01 15/10/2003
SPEC. No. 2009F
FUNCTIONAL
OFFSHORE
SPECIFICATION Rev. No. 6
DESIGN
FOR WELDING Discipline: QA/QC
SECTION
& NDT Page 4 of 24
PIPING: CS
a) Crude oil
b) Jet fuel
c) Fuel gas / instrument gas
d) Process gas
e) Production flow lines ( well fluid)
f) Injection water
g) Hydrocarbon (process)
h) Water ( in case of 90/10 Cu-Ni)
FORMAT No. Ref. PROCEDURE No. ISSUE No. REV. No. REV. DATE:
ODS/SOF/004B ODS/SOP/008 TO 015 01 01 15/10/2003
SPEC. No. 2009F
FUNCTIONAL
OFFSHORE
SPECIFICATION Rev. No. 6
DESIGN
FOR WELDING Discipline: QA/QC
SECTION
& NDT Page 5 of 24
9.3 For fillet welds and brazed joints where carrying out radiography is not
possible , magnetic particle test or dye penetrant test shall be carried out .
The extent of inspection shall remain same as for radiography.
9.4 All the lines which are stress relieved or have design pressure more than 50
Kg/ cm2 shall be radiographed for 50% of weld joints even if not required
as per 9.1 to 9.3.
a) The internal weld protrusion on ‘ pigged lines “ shall not exceed 1.6
mm ( 1/16 Inch)
9.7 Those field welded joints, which can not be leak tested due to unavoidable
reason shall always be 100% radio graphed.
FORMAT No. Ref. PROCEDURE No. ISSUE No. REV. No. REV. DATE:
ODS/SOF/004B ODS/SOP/008 TO 015 01 01 15/10/2003
SPEC. No. 2009F
FUNCTIONAL
OFFSHORE
SPECIFICATION Rev. No. 6
DESIGN
FOR WELDING Discipline: QA/QC
SECTION
& NDT Page 6 of 24
12. NDT Personnel : All NDT personnel shall be currently qualified under
ASNT Level II (as per SNT-TC-1A) or client approved equivalent
certification scheme (like PCN, CSWIP) for the category of non-
destructive examination being undertaken.
14. Welding shall not be performed when the ambient temperature is lower
than zero degree C, when surfaces are wet or exposed to rain, snow or high
wind velocities, when welders are exposed to inclement conditions, or
when conditions prevent required inspections.
15. Only welding equipment that is in good working condition and that is
properly grounded shall be used. All welding machines shall be calibrated
prior to commencement of fabrication and calibration certificates shall be
available for audits. Certification shall be valid for 6 month periods, or as
per manufacturer’s recommendation.
FORMAT No. Ref. PROCEDURE No. ISSUE No. REV. No. REV. DATE:
ODS/SOF/004B ODS/SOP/008 TO 015 01 01 15/10/2003
SPEC. No. 2009F
FUNCTIONAL
OFFSHORE
SPECIFICATION Rev. No. 6
DESIGN
FOR WELDING Discipline: QA/QC
SECTION
& NDT Page 7 of 24
17. Arc strikes should be made in weld groove. Arc strikes on the surface of
base metal shall be removed by grinding, including any hardened zone
beneath the strike. Any such repair shall be visually and magnetic particle
inspected.
1. Material subjected for CTOD Testing shall be tested and shall meet
or exceed CTOD value of 0.35mm.
3. WPS subjected for CTOD testing shall be tested and shall meet or
exceed CTOD value of 0.20 mm.
2. The deposited filler metal shall match the chemistry, corrosion resistance
(if required) and minimum physical properties of the parent metal when
similar metals are welded.
FORMAT No. Ref. PROCEDURE No. ISSUE No. REV. No. REV. DATE:
ODS/SOF/004B ODS/SOP/008 TO 015 01 01 15/10/2003
SPEC. No. 2009F
FUNCTIONAL
OFFSHORE
SPECIFICATION Rev. No. 6
DESIGN
FOR WELDING Discipline: QA/QC
SECTION
& NDT Page 8 of 24
8. Pipes of dissimilar materials shall not be welded to each other but shall be
flanged unless otherwise approved.
9. Compressor and turbine piping, including lube and seal oil piping, and
other piping requiring special cleaning as shown in the drawings provided
by the supplier shall have the root pass deposited by the gas tungsten arc
process. The backside of the root pass shall be purged with inert gas.
10. If the bore of the pipe is different from the bore of fittings or flanges, to
which it is welded, by more than 3mm (total bore diameter), the thicker
member shall be bored, taper bored or ground smooth to match the
specified bore. Figure 328.4.3 of ASME B 31.3 will governs the geometry
of all taper boring and beveling.
11. Coupling or other weld-on type branch connection shall be located at least
80 mm away from any weld joint.
12. When socket weld fittings or valves are used, pipe shall be spaced
approximately 1/16 inch to avoid “bottoming” which could result in
excessive welds stress.
13. The inside of the brazed fitting and outside of the tube shall be cleaned
with sand Paper. Flux paste to be evenly applied to the joint.
14. Reinforcing pads shall be added only after external and internal visual
inspection the attachment. Reinforcing pads shall be provided with ¼”
tapped weep hole. Weep holes should be plugged after welding of pads is
over.
15. Exposed machined and threaded surfaces shall be protected from oxidation
during heat treatment.
16. Flange bolt holes shall straddle the established horizontal and vertical
centerlines of the pipe except where connection to equipment dictates
otherwise.
17. Cleaning of the piping after fabrication and heat treatment shall be
performed externally and internally to remove all loose scale, weld spatter,
sand and other foreign materials.
FORMAT No. Ref. PROCEDURE No. ISSUE No. REV. No. REV. DATE:
ODS/SOF/004B ODS/SOP/008 TO 015 01 01 15/10/2003
SPEC. No. 2009F
FUNCTIONAL
OFFSHORE
SPECIFICATION Rev. No. 6
DESIGN
FOR WELDING Discipline: QA/QC
SECTION
& NDT Page 9 of 24
18. Welding shall not be done when quality of completed weld would be
impaired by prevailing weather conditions, air borne moisture, blowing
sand or high winds. Windshields may be used when practical.
19. All welders working on the project shall wear identification cards made at
contractor’s cost which shall contains photograph, welders name, welder
no. Procedure qualified and Company’s/Engineer’s representative’s
signature.
20. Welder shall be supplied with tempil stick – thermal crayons or pendox
gauges so that welders and inspector can check and control the temperature
of weldment.
21. No weld shall be coated, painted, hydrotested before it has been
inspected and accepted.
1. Where field welds are designated, the prefabricated pipe shall be cut
off 150 mm longer than the dimensions shown on the pipe fabrication
drawings to allow for modification then precise fit-up in place.
3. The location of field welds, where not indicated on the drawings, will
be the responsibility of the Contractor.
FORMAT No. Ref. PROCEDURE No. ISSUE No. REV. No. REV. DATE:
ODS/SOF/004B ODS/SOP/008 TO 015 01 01 15/10/2003
SPEC. No. 2009F
FUNCTIONAL
OFFSHORE
SPECIFICATION Rev. No. 6
DESIGN
FOR WELDING Discipline: QA/QC
SECTION
& NDT Page 10 of 24
4. For each welding process, the welding procedures shall specify all
equipment settings. The Contractor’s Welding Supervisor shall check
daily and record machine settings for each weld procedure used
during welding activities. This record shall be available for audit by
the Company representative.
FORMAT No. Ref. PROCEDURE No. ISSUE No. REV. No. REV. DATE:
ODS/SOF/004B ODS/SOP/008 TO 015 01 01 15/10/2003
SPEC. No. 2009F
FUNCTIONAL
OFFSHORE
SPECIFICATION Rev. No. 6
DESIGN
FOR WELDING Discipline: QA/QC
SECTION
& NDT Page 11 of 24
6. The Contractor shall be responsible for all costs, including labor and
laboratory testing, associated with welder qualification tests and
retests.
7. The Company may request a retest of any welder at any time and
from time to time during the work. If a welder fails to qualify, then at
the discretion of the company representative, all non-installed welds
completed by that welder shall be examined by additional
radiographic tests, over and above that which would normally be
required or specified in the drawings for that pipe work and the same
shall be charged to the Contractor’s account.
27. REPAIRS:
FORMAT No. Ref. PROCEDURE No. ISSUE No. REV. No. REV. DATE:
ODS/SOF/004B ODS/SOP/008 TO 015 01 01 15/10/2003
SPEC. No. 2009F
FUNCTIONAL
OFFSHORE
SPECIFICATION Rev. No. 6
DESIGN
FOR WELDING Discipline: QA/QC
SECTION
& NDT Page 12 of 24
5. Internal weld metal projecting into the pipe on weld neck orifice
flanges shall be removed and ground smooth with the pipe.
6. For all welds requiring PWHT, the specified inspection and NDT
shall be performed after completion of PWHT process but not before
the welds have cooled to ambient temperature. NDT prior to PWHT,
performed in addition to mandatory NDT following PWHT, shall be
at the discretion of the Contractor. However, where defects requiring
repair are located by this inspection, it shall be brought to the notice
of Company.
8. After final heat treatment, the Contractor shall identify the piping as
having received PWHT. The method of identification shall be
recorded on the as-built isometric and P&ID together with the other
recorded information.
FORMAT No. Ref. PROCEDURE No. ISSUE No. REV. No. REV. DATE:
ODS/SOF/004B ODS/SOP/008 TO 015 01 01 15/10/2003
SPEC. No. 2009F
FUNCTIONAL
OFFSHORE
SPECIFICATION Rev. No. 6
DESIGN
FOR WELDING Discipline: QA/QC
SECTION
& NDT Page 13 of 24
Radiographic Examination:
FORMAT No. Ref. PROCEDURE No. ISSUE No. REV. No. REV. DATE:
ODS/SOF/004B ODS/SOP/008 TO 015 01 01 15/10/2003
SPEC. No. 2009F
FUNCTIONAL
OFFSHORE
SPECIFICATION Rev. No. 6
DESIGN
FOR WELDING Discipline: QA/QC
SECTION
& NDT Page 14 of 24
Ultrasonic Examination:
1. Chill rings and backing strips can provide improved root beads on single
sides welds. Their use, however is prohibited as they may cause fatigue
crack initiation.
3. PRE-HEAT REQUIREMENT
4. INTER-PASS TEMPERATURE
5. WELDING PROCESS
Only gas metal arc ( GMAW), gas tungsten arc (GTAW), automatic
submerged arc (SAW), manual shielded metal arc (SMAW), or flux cored
FORMAT No. Ref. PROCEDURE No. ISSUE No. REV. No. REV. DATE:
ODS/SOF/004B ODS/SOP/008 TO 015 01 01 15/10/2003
SPEC. No. 2009F
FUNCTIONAL
OFFSHORE
SPECIFICATION Rev. No. 6
DESIGN
FOR WELDING Discipline: QA/QC
SECTION
& NDT Page 15 of 24
arc (FCAW) welding process shall be used. Other welding processes shall
not be used.
a) GMAW welding shall not be exposed to air drafts greater than 8 Km/h.
d) GMAW-S may be used for the root pass only in combination with SAW
welding, and for the root pass in non-critical joint applications.
e) Spray transfer mode of metal deposition for GMAW is limited to the flat
position.
f) Weld areas shall be blasted or ground to white metal prior to welding when
GMAW or GMAW-S is used.
a) FCAW welding with external gas shielding shall not be exposed to air
drafts greater than 8 Km/h.
c) Self – shielded flux core shall not be used as root or fill pass beneath other
processes.
WPS QUALIFICATION
All structural welding shall be done in accordance with AWS D1.1. Draft
WPS shall be agreed with client prior to the commencement of procedure
qualification testing.
FORMAT No. Ref. PROCEDURE No. ISSUE No. REV. No. REV. DATE:
ODS/SOF/004B ODS/SOP/008 TO 015 01 01 15/10/2003
SPEC. No. 2009F
FUNCTIONAL
OFFSHORE
SPECIFICATION Rev. No. 6
DESIGN
FOR WELDING Discipline: QA/QC
SECTION
& NDT Page 16 of 24
- Hardness Testing
- Impact Testing
- CTOD Testing
CTOD testing may be used to justify an increase in the maximum thickness
of material that can be welded without the application of PWHT as defined
elsewhere in this Spec. CTOD testing shall be carried out as per BS 7448.
Each set of CTOD tests shall comprise a minimum of three valid
specimens. CTOD testing is required on full penetration test welds
representing the maximum thickness of materials that are to be welded by
any single process or combination of processes. Separate tests are required
to qualify single and double sided preparation. The steel selected for
performance of the test programme shall have minimum Carbon
Equivalent not less than 0.02 of the maximum CE value to be used on the
FORMAT No. Ref. PROCEDURE No. ISSUE No. REV. No. REV. DATE:
ODS/SOF/004B ODS/SOP/008 TO 015 01 01 15/10/2003
SPEC. No. 2009F
FUNCTIONAL
OFFSHORE
SPECIFICATION Rev. No. 6
DESIGN
FOR WELDING Discipline: QA/QC
SECTION
& NDT Page 17 of 24
project. All test plates shall be welded using heat inputs representative of
the highest to be used during production welding.
For each test the least values of δc, δu or δm shall be greater than or equal
to 0.20mm when tested at 0oC unless specified otherwise in the relevant
drawings.
- Heat Input
Charpy qualification of weld deposit and HAZ is valid only for welding
procedures with heat inputs maintained with in ±25% of the tested weld.
This may require more stringent tolerance on travel, speed, voltage and
amperage.
Fracture Mechanics Tests and assessment (CTOD, as per BS 7448) may be used
to obviate the requirement for PWHT (as per b & c), if approval in writing is
given by the Company. In this case CTOD test shall be carried out during the
WPS qualification.
FORMAT No. Ref. PROCEDURE No. ISSUE No. REV. No. REV. DATE:
ODS/SOF/004B ODS/SOP/008 TO 015 01 01 15/10/2003
SPEC. No. 2009F
FUNCTIONAL
OFFSHORE
SPECIFICATION Rev. No. 6
DESIGN
FOR WELDING Discipline: QA/QC
SECTION
& NDT Page 18 of 24
All PWHT shall be performed in accordance with AWS D1.1 and the welding
procedure qualification.
d) For all welds requiring PWHT, the specified inspection and NDT shall be
performed after completion of PWHT process but not before the welds
have cooled to ambient temperature. NDT prior to PWHT, performed in
addition to mandatory NDT following PWHT, shall be at the discretion of
the Contractor. However, where defects requiring repair are located by this
inspection, it shall be brought to the notice of Company.
e) The contractor shall submit a heat treatment procedure for approval by the
Company. This procedure shall define heat and cooling rate, holding time
at temperature and details of temperature measurement and control
methods.
NDT of FCAW welds shall require a minimum of 24 hrs waiting period to allow
for potential delayed cracking.
Removal of Defects
FORMAT No. Ref. PROCEDURE No. ISSUE No. REV. No. REV. DATE:
ODS/SOF/004B ODS/SOP/008 TO 015 01 01 15/10/2003
SPEC. No. 2009F
FUNCTIONAL
OFFSHORE
SPECIFICATION Rev. No. 6
DESIGN
FOR WELDING Discipline: QA/QC
SECTION
& NDT Page 19 of 24
Gouging
All low fatigue joints shall be inspected for acceptance to required profile and
toe grinding shall be performed, if required.
Weld through primers to be used during fabrication are subject to the approval
by the Company and shall be included in the weld procedure qualification.
During Weld Procedure Qualification, the thickness of weld through primer shall
be measured. Any increase in thickness of primer in production shall necessitate
re-qualification of the affected WPS.
Quality Control Procedures for welding operations shall include the following -
FORMAT No. Ref. PROCEDURE No. ISSUE No. REV. No. REV. DATE:
ODS/SOF/004B ODS/SOP/008 TO 015 01 01 15/10/2003
SPEC. No. 2009F
FUNCTIONAL
OFFSHORE
SPECIFICATION Rev. No. 6
DESIGN
FOR WELDING Discipline: QA/QC
SECTION
& NDT Page 20 of 24
positive means of identification of the electrodes held in the drying ovens, the
drying cycle, temperature and time held, shall be established.
6.2 Flux
The flux conditioning procedure shall detail methods of assuring dryness before
use, recovery of flux after use, screening of foreign materials and flux, and the
storage of flux to prevent contamination.
c) SAW flux, not fused in welding, may be recycled, but shall be free from
fused flux, mill scale, dirt and other foreign matter.
FORMAT No. Ref. PROCEDURE No. ISSUE No. REV. No. REV. DATE:
ODS/SOF/004B ODS/SOP/008 TO 015 01 01 15/10/2003
SPEC. No. 2009F
FUNCTIONAL
OFFSHORE
SPECIFICATION Rev. No. 6
DESIGN
FOR WELDING Discipline: QA/QC
SECTION
& NDT Page 21 of 24
a) All welding materials shall be stored in a clean dry area until used, as
described in AWS D1.1.
b) Wet or damaged electrodes, contaminated flux and rusted filler wire shall
be rejected and removed from the fabrication site.
c) Welding wire and SAW flux shall be stored in a dry location at a minimum
temperature of 21ºC.
The welder and weld area shall be provided with protection during periods of
inclement weather and/or excessive wind conditions. The procedures shall
include means of protecting electrodes, wires, fluxes, etc.
Suitable windshields must be provided when the wind velocity exceeds 32 km/h
or 8 km/h in case of GMAW and gas shields FCAW.
8.0 DOCUMENTATION
The CONTRACTOR shall establish and maintain procedures for identifying full
details of welding, welding procedures, records of inspection, non destructive
testing and compliance with the Specification for each welded joint and repair in
the completed works. The following documents shall also be generated:
1.NDT Plan
2.NDT Drawings
3.Certification Package for each NDT drawing.
The weld number shall be marked against all welds on the works. The weld
number shall be in accordance with a scheme of numbers shown on the shop
drawings. Welds shall mark their welds with their identifying number.
FORMAT No. Ref. PROCEDURE No. ISSUE No. REV. No. REV. DATE:
ODS/SOF/004B ODS/SOP/008 TO 015 01 01 15/10/2003
SPEC. No. 2009F
FUNCTIONAL
OFFSHORE
SPECIFICATION Rev. No. 6
DESIGN
FOR WELDING Discipline: QA/QC
SECTION
& NDT Page 22 of 24
FORMAT No. Ref. PROCEDURE No. ISSUE No. REV. No. REV. DATE:
ODS/SOF/004B ODS/SOP/008 TO 015 01 01 15/10/2003
SPEC. No. 2009F
FUNCTIONAL
OFFSHORE
SPECIFICATION Rev. No. 6
DESIGN
FOR WELDING Discipline: QA/QC
SECTION
& NDT Page 23 of 24
APPENDIX-A
HARDNESS TESTING
3. The hardness surveys shall be prepared and tested in accordance with ASTM E
92, Standard Test Method for Vickers Hardness (Hv) of Metallic Materials,
using an applied load of 10 kgf.
4. Indentations shall be made along all of the transverses shown for each type of
weld tested, approximately 1 mm below the surface of the base metal. In the
weld metal, a minimum of three equally spaced indentations along the traverse
shall be made. In the heat-affected zone, the indentations shall start as close to
the fusion line as practicable. A minimum of three readings shall be taken at
each weld toe. One additional reading shall be taken at least 20 mm from the
fusion line at each traverse to represent unaffected base metal.
5. The maximum hardness value obtained from any indentation shall not exceed
350 Hv. If any single value exceeds 350 Hv and a retest adjacent to the failed
test also produces one or more values exceeding 350 Hv, the procedure
qualification test has failed these requirements and a new test weld shall be made
with some planned modifications of essential variables or techniques (change
heat input, increase preheat, later bead sequence, etc.) and retest.
FORMAT No. Ref. PROCEDURE No. ISSUE No. REV. No. REV. DATE:
ODS/SOF/004B ODS/SOP/008 TO 015 01 01 15/10/2003
SPEC. No. 2009F
FUNCTIONAL
OFFSHORE
SPECIFICATION Rev. No. 6
DESIGN
FOR WELDING Discipline: QA/QC
SECTION
& NDT Page 24 of 24
Fig.1
FORMAT No. Ref. PROCEDURE No. ISSUE No. REV. No. REV. DATE:
ODS/SOF/004B ODS/SOP/008 TO 015 01 01 15/10/2003