Installation Guide DriLyner TL
Installation Guide DriLyner TL
i
DriLyner tl
Internal wall insulation
—— C
arry out checks to ensure there is no dampness It is important to carry out a detailed close
or condensation / mould growth issues which inspection to the internal wall surface to identify
would affect a lining system being installed any dampness issues and to ascertain whether the
—— C
heck to make sure all existing ventilation outlets property has a damp-proof course (DPC), this will
can be maintained through to the new lining be dependent on the age of the property. It is worth
system that is installed asking the homeowner if the property has had a
DPC injection treatment while they have been in the
—— E
nsure assessments are made regarding the work
property, or if it was identified through the property
carried out
survey when it was purchased. Where a DPC is
• W
ill not compromise Building Regulations in identified, the condition should be checked as well
relation to workmanship, materials, fire safety as the distance of the floor level to the position of
and ventilation the DPC.
• W
ill not compromise the functionality and / or
safety of existing services Carrying out a close inspection of the external of the
property should be carried out to check for leaking
gutters, downspouts, missing flashings, deteriorating
brickwork and / or mortar joints, as these are
common problems which can result in penetrating
dampness.
1
Introduction
The purpose of this guide is to define and show the installation process for DriLyner tl; this is one of the
British Gypsum BBA-certified internal wall insulation systems which can be used to improve the energy
efficiency measures within buildings and is used in relation to PAS 2030 for quality management purposes.
While the construction methods for each wall lining system will vary, there is generic information which is
deemed best practice irrespective of which system is installed; this covers minimising air leakage, reducing
thermal bridging, accommodating fixtures of cupboards, radiators, curtain track, etc.
Under Building Regulations, Part L 1B there is a requirement for upgrading existing properties to an
improved U value of 0.3 where the footprint of each room allows. Depending on which lining system
is installed, it is important to have a U-value and dew point calculation carried out to ensure the wall
construction and new lining system do not create risks of harmful condensation within the wall fabric
and that the new level of insulation is met.
Socket outlets
When socket outlets on the existing walls need to
be repositioned on the new stud lining, it is likely
that cables will need to be brought forward. Moving
cables in this manner is not classified as ‘notified
work’ according to Approved Document P, 2013
Design and installation of electrical installations, and
can be carried out by a suitably competent person.
2
Specific BBA Approved IWI System
The following details should be read in conjunction with the British Gypsum Site Book and White Book.
These documents can be found at british-gypsum.com/literature.
System overview
Gyproc boards
3
Gypframe metal components
Gyproc Sealant
Used as an adhesive and to reduce air
leakage as well as providing optimum
sound insulation.
Installation guidance
Step 1
Determine high spots on the wall and plumb position to the
ceiling and floor.
Step 2
Transfer this dimension to the room corners, add an allowance of
10mm plus the board thickness and strike continuous chalk lines on
the floor and ceiling.
4
Installation guidance (continued)
Step 3
Trowel apply a continuous fillet of Gyproc Dri-Wall Adhesive to the
perimeter of the wall, services and openings for optimum airtightness.
Trowel apply adhesive to form dabs 50mm to 75mm wide and about
250mm long.
Step 4
Position dabs of Gyproc DriWall Adhesive in three vertical rows to
receive the first board.
Step 5
Cut plasterboard to fit the floor to ceiling height.
Position the first board, reverse side against the dabs, with the
bottom edge resting on plasterboard packing strips as required.
5
Installation guidance (continued)
Step 6
Tap the board back firmly using a straight-edge until it aligns with
the ceiling and floor chalk lines.
Step 7
Gently lift using a footlifter until the board is tight against the ceiling.
Insert additional packing strips at the base to wedge the board in place
and remove the footlifter.
Apply dabs for the next plasterboard and continue the drylining with
boards lightly butted.
Services
The cavity between the linings and the background can be used to
incorporate services. This minimises the depth of chasing required in
the background.
Fixings
For medium and heavy fixtures, select fixing devices of sufficient length
to penetrate well into the masonry wall.
6
Installation guidance (continued)
Step 8
At internal angles cut board to fit and position the cut edge
to the angle.
At reveals and external angles, run the lining past the corner (and, when
installing Gyproc ThermaLine laminate, cut back the insulation backing
to form a rebate) so as to form a neat junction with the reveal board or
wall lining.
Where timber or MDF window cills are installed, ensure they are
adequately sealed prior to completing the boarding around the
window reveals. Where it is practicable and the depth of the cill
allows, fix a Gyproc ThermaLine board before installing the window
cill on top of this.
Step 9
Install British Gypsum Nailable Plugs to provide secondary
mechanical fixings. Insert two plugs per board, 15mm in from each
edge at mid-height.
Select plugs to give a nominal 25mm penetration into the solid wall
(excluding plaster thickness). Drill hole 5mm longer than the plug.
Drive in each plug until the head is slightly below the liner without
fracturing it.
7
DriLyner tl junction detailing
1 External wall and intermediate floor junction 5 External wall and internal partition junction for
2 External wall and ground floor junction optimum thermal insulation
8
DriLyner tl junction detailing (continued)
External wall and intermediate floor junction External wall and timber ground floor junction
Window reveal with insulation External wall and internal wall junction. The 400mm
return is applied to both sides of the internal wall
9
DriLyner tl junction detailing (continued)
Whilst we recommend 400mm returns on internal walls to reduce the risk of surface condensation and mould growth and to
minimise heat loss at the junction, this rule does not apply where the external wall linings abuts a separating wall when the
adjoining property is not being upgraded with the same improvement measures.
The reason for not applying a 400mm return on a separating wall where the adjoining property is not being upgraded is
the increased risk of surface condensation and mould growth which could occur on the adjoining property. Where a row of
terraced properties are being renovated with the same internal wall insulation measure, this would allow the 400mm returns to
be applied on both sides of the separating wall to external wall junction. A quick way to summarise and remember if the detail
measure applies is both sides or no sides.
10
Understanding specific issues regarding detailing
Example detail
The detail opposite shows the additional insulation
within the floor void. It is important to note that
where the flooring does not get a seal against the
external plaster or brickwork, you need to ensure External wall and intermediate floor junction
that the perimeter of the floor has an effective seal
with Gyproc Sealant or Gyproc DriWall Adhesive.
11
Understanding specific issues regarding detailing (continued)
12
Understanding specific issues regarding detailing (continued)
To ensure that upgrading of external walls is as effective as The wall surface can be finished with Thistle finish plasters
possible, it is very important to prevent air leakage through or alternatively Gyproc jointing materials. When skirtings
the structure, or at least keep it to an absolute minimum. are applied, it is good practice to apply a seal along the
face side of the skirting where it abuts the flooring.
Air leakage can occur between the interior and exterior,
as well as between different elements of the building
envelope. Tools required to carry out the DriLyner Installation
—— Tape measure —— Straight-edge
Air leakage through the masonry wall occurs through
cracks, gaps where there is poor adhesion between the —— Spirit Level —— Hand saw
mortar and the masonry units, or diffusion through the —— Mastic gun —— Hawk
masonry units themselves. Where the plaster has been —— Chalk line —— Trowel
removed and air leakage through the wall is thought to
—— Hammer —— Hammer drill
be excessive, it should be tackled before the IWI system is
installed by applying a parging coat to the inner surface of
the wall.
The above list of tools is not exhaustive and additional tools
As the insulation component of the system is in intimate may be required dependent on the requirements of the
contact with the plasterboard, air movement behind the work being carried out.
system should not occur. However, to prevent unwanted
air leakage all junctions with other elements should be well - It is important to note that British Gypsum have four
sealed with particular attention being paid to the joints systems which are BBA approved. These systems are different
between the IWI system and the window frames. in construction techniques and in order to become a Registered
Installer for each system, attendance is required on each course; on
In addition, Gyproc Sealant should be used to seal electric site assessment is linked to each system specific course.
Fixing guidance
Fixings for use with Gyproc plasterboards and ThermaLine board range
There is a wide variety of fixing devices suitable for securing fixtures and fittings to internal wall lining systems. Generally,
the choice of individual fixing devices will depend on the loading requirements. This section gives recommendations on
the selection of generic devices and proprietary fixings.
The table below gives example fixing devices and typical applications using Gyproc ThermaLine boards to meet the
specific load criteria. The guidance given is primarily concerned with fixtures at the time of installation. Subsequent
installation is less easy, especially for heavier fixtures that will often require considerable care, if the lining is not to be
locally deflected.
PD10 plastic cavity fixing into Gyproc ThermaLine super or Gyproc ThermaLine pir 6kg (43kg)
1 Safe Working Load (SWL) - a safety factor of four (steel fixings) and seven (plastic fixings) has been used.
For technical assistance on above fixings, please contact the fixings manufacturer. The suitability of the fixing must be confirmed by the building designer /
fixing manufacturer. Reference can also be made to the Construction Fixing Association (CFA) guidance note ‘Fixing
For Plasterboard’, which is currently under review by the CFA and can be accessed at www.fixingscfa.co.uk
When specifying a fixing to / through Gyproc ThermaLine laminates, please give consideration to the thickness and compressibility of the insulation to
ensure that the fixing used is fit for purpose.
13
Saint-Gobain Technical Academy
Our courses are designed to increase knowledge on the products and systems we offer, the regulations and
market requirements that drive demand as well as providing practical guidance on installing our systems.
Saint-Gobain Technical Academy training courses are run by fully qualified instructors at Kirkby Thore near
Penrith, East Leake near Nottingham, Erith in Kent and Clevedon near Bristol.
Clevedon
Unit 1, The Courtyard
Barnes Ground, Kenn,
Clevedon, North Somerset
BS21 6TB
East Leake
East Leake, Loughborough,
Leicestershire, LE12 6HX
Erith
Church Manorway, Erith,
Kent, DA8 1DE
Flitwick
Enterprise Way, Flitwick,
Bedford, MK45 5BY
Kirkby Thore
Kirkby Thorem Nr. Penrith,
Cumbria, CA10 1XU
For further details on courses, locations and dates, please contact the Saint-Gobain Technical Academy
on 0844 561 8810 or visit the British Gypsum website: british-gypsum.com
14
FSC
Technical enquiries
British Gypsum
Technical Advice Centre
East Leake
Loughborough
Leicestershire
LE12 6HX
british-gypsum.com
British Gypsum
@britishgypsum
Head Office, East Leake,
Loughborough,
Leicestershire, LE12 6HX www.linkedin.com/company/british-gypsum
Tel: 0115 945 1000