National Electric Code (NEC) 120-Percent Rule
National Electric Code (NEC) 120-Percent Rule
As a licensed and bonded electrical contractor, the City and County permitting departments hold us to
very high standards. One of those standards is to adhere to strict electrical safety guidelines that are
published as part of the NEC. One particular rule makes certain that the meter enclosure installed on
your home is capable of handling the maximum amount of utility and solar + storage power to your
home at the same time. Adding a solar photovoltaic system to your home is like adding a second utility
connection on the opposite side of the meter. We must now consider the rating of the meter equipment
located between these two power sources, more specifically the bus bar rating. This is commonly
referred to as the NEC 120% rule.
When it comes to designing a solar PV or battery energy storage system for any residential property, the
120% rule is used to determine the limit of how much new power generation the site’s electrical
infrastructure can safely handle.
Yes, maybe the roof may be able to support several kilowatts of solar PV and you have enough wall
space to install a large capacity battery, but can the existing electrical infrastructure handle all of that
extra power? This is where you will hear whispers of the 120% rule. Well, what does that even mean?
This rule is meant to calculate how many amps can be back-fed through the customer side of the meter
within a measure of safety. In this instance, you have to consider that not only is the solar PV and/or
battery energy storage system supplying power to the home but the grid is also present and able to
supply additional power to the home from the utility side of the meter. With multiple sources feeding
power from opposite ends, what prevents the electrical equipment in the middle of the two from
becoming overloaded and possibly becoming a fire hazard? Prior to the installation of the solar PV and/
or battery energy storage system, all of the power is supplied from a single source through the home’s
main breaker.
Main Breaker
Main Breaker
Load
Load Breakers
Breakers
Busbar
Unfortunately, this additional 40 amps is not sufficient for many solar PV or battery energy storage
systems. A typical PV+Battery installation could require upwards of 60 - 80 amps.
NEC code mandates that “The sum of the ampere ratings of overcurrent devices in circuits supplying
power to a busbar or conductor shall not exceed the rating of the busbar or conductor”. Further, it goes
on to allow as much as 120% of a busbar’s rating to be exceeded. This is where the calculation comes
in to play.
(Busbar Rating (A) x 1.2) - Main Breaker Rating (A) = Max (PV + Battery) (A)
Let’s start with an example. We have a 200 Amp bus rating for our service panel. In it, we have a 200
Amp main breaker.
In this example, the maximum output of our PV system can be 40A. This would satisfy the busbar rating
without an issue. However, in many instances there is a need or desire to have a much larger system, so
what then?
If we exceed the rating of the busbar without regard to the 120% rule, we are creating a scenario where
we are feeding a panel board with too much energy and have nothing in place to prevent the sum of the
loads in that panel from drawing more current than the busbar can handle.
What do we do in this case? Above all else, we need to have a PV system that is safe and installed to
code. What can we do to remedy this and still retain the system size we have targeted?
One solution is to feed the existing main breaker power into a new “sub-panel” that has a higher busbar
safety rating. This solution may require additional boxes the side of your home, but it may be a very cost
effective solution compared to others.
Another solution may be to downsize the main breaker in your existing service panel. So in our case
above we could remove the 200A main breaker and replace it with a 175A main breaker to allow us to
install up to 65A of PV. This approach is effective when taking careful consideration of all the existing
loads in the home. There could be a potential for these loads to draw close to or more than the amp
rating of that 175A breaker.
Alternative solutions could include upgrades to your existing electrical service equipment or possibly a
reduction in your overall PV system size to meet the 120% rule guidelines.