Project Plan Template SAP Business ONE

The document outlines the project plan for implementing a new Shama Cooking Oil ERP system over 90 days. It involves several key phases: project preparation, planning and analysis of the current and desired future systems, development of a business blueprint, realization including system setup and testing, end user training, uploading of opening balances, go-live, and final project closure activities. The project will implement a new SAP B1 system to support Shama's business processes including procurement, production, sales, inventory, finance and other operations.

Uploaded by

Ahmed Khan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
178 views

Project Plan Template SAP Business ONE

The document outlines the project plan for implementing a new Shama Cooking Oil ERP system over 90 days. It involves several key phases: project preparation, planning and analysis of the current and desired future systems, development of a business blueprint, realization including system setup and testing, end user training, uploading of opening balances, go-live, and final project closure activities. The project will implement a new SAP B1 system to support Shama's business processes including procurement, production, sales, inventory, finance and other operations.

Uploaded by

Ahmed Khan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

Project Plan

ID Task Name Duration Start Finish


1 1 Shama Cooking Oil 90 days Tue 1/9/24 Mon 5/13/24
2 1.1 Project Preparation 2 days Tue 1/9/24 Wed 1/10/24
3 1.1.1 Finalization/Submission of Project Charter & Project Plan 1 day Tue 1/9/24 Tue 1/9/24
4 1.1.2 Submission of Basic Info File & Master Data Readiness 1 day Wed 1/10/24 Wed 1/10/24
5 1.2 Project Planning & Business Blueprint 42 days Thu 1/11/24 Fri 3/8/24
6 1.2.1 Master Data / Setup Data Finalization 2 days Thu 1/11/24 Fri 1/12/24
7 1.2.1.1 Handing over of Master Data to Abacus 1 day Thu 1/11/24 Thu 1/11/24
8 1.2.1.2 Receiving of Basic Info. File from Shama and Finalization 1 day Fri 1/12/24 Fri 1/12/24

9 1.2.2 ASIS Analysis 16 days Mon 1/15/24 Mon 2/5/24


10 1.2.2.1 Purchase Process Local ASIS Analysis 1 day Mon 1/15/24 Mon 1/15/24
11 1.2.2.2 Purchase Process Import ASIS Analysis 2 days Tue 1/16/24 Wed 1/17/24
12 1.2.2.3 Inventory & Store Process ASIS Analysis 1 day Wed 1/17/24 Wed 1/17/24
13 1.2.2.4 Sales Process ASIS Analysis 2 days Thu 1/18/24 Fri 1/19/24
14 1.2.2.5 Production Process ASIS Analysis 7 days Fri 1/19/24 Mon 1/29/24
15 1.2.2.6 Accounts/ Finance ASIS Process Analysis 1 day Tue 1/30/24 Tue 1/30/24
16 1.2.2.7 Payroll ASIS Process Analysis 1 day Wed 1/31/24 Wed 1/31/24
17 1.2.2.8 Banking and Budgeting ASIS Process Analysis 1 day Thu 2/1/24 Thu 2/1/24
18 1.2.2.9 Fixed Assets Process Analysis & Reporting Requirement 1 day Mon 2/5/24 Mon 2/5/24
19 1.2.3 To Be 16 days Tue 2/6/24 Tue 2/27/24
20 1.2.3.1 Purchase Process Analysis & Reporting Requirement 1 day Tue 2/6/24 Tue 2/6/24
21 1.2.3.2 Inventory and Store Management Process & Reporting 1 day Wed 2/7/24 Wed 2/7/24
Requirement
22 1.2.3.3 Production Process Analysis & Reporting Requirement 7 days Thu 2/8/24 Fri 2/16/24
23 1.2.3.4 Sales Process Analysis & Reporting Requirement 1 day Mon 2/19/24 Mon 2/19/24
24 1.2.3.5 Account / Finance Process Analysis & Reporting 3 days Tue 2/20/24 Thu 2/22/24
Requirement
25 1.2.3.6 Payroll Process Analysis and Reporting Requirements 1 day Fri 2/23/24 Fri 2/23/24
26 1.2.3.7 Fixed Assets Process Analysis & Reporting Requirement 2 days Mon 2/26/24 Tue 2/27/24
27 1.2.4 Business Blueprint Finalization 8 days Wed 2/28/24 Fri 3/8/24
28 1.2.4.1 Compilation and Finalization of Business Blueprint 2 days Wed 2/28/24 Thu 2/29/24
29 1.2.4.2 SAP Installation 1 day Fri 3/1/24 Fri 3/1/24
30 1.2.4.3 Business Blueprint internal review by AC and Submission to 1 day Mon 3/4/24 Mon 3/4/24
SHAMA
31 1.2.4.4 Internal Review of Business Blueprint by SHAMA 1 day Tue 3/5/24 Tue 3/5/24
32 1.2.4.5 Workshop on BBP 1 day Wed 3/6/24 Wed 3/6/24
33 1.2.4.6 Changes in Business Blueprint & Final 1 day Thu 3/7/24 Thu 3/7/24
34 1.2.4.7 Business Blueprint Sign-off 1 day Fri 3/8/24 Fri 3/8/24
35 1.3 Project Realization 15 days Mon 3/11/24 Fri 3/29/24
36 1.3.1 SAP Solution Readiness 10 days Mon 3/11/24 Fri 3/22/24
37 1.3.1.1 System Initialization SAP B1 2 days Mon 3/11/24 Tue 3/12/24
38 1.3.1.2 System Configuration SAP B1 4 days Wed 3/13/24 Mon 3/18/24
39 1.3.1.3 Customization & Testing 2 days Tue 3/19/24 Wed 3/20/24
40 1.3.1.4 Print Layout Designing 2 days Thu 3/21/24 Fri 3/22/24
41 1.3.2 User's Acceptance Test 5 days Mon 3/25/24 Fri 3/29/24
42 1.3.2.1 User's Acceptance Testing 5 days Mon 3/25/24 Fri 3/29/24
43 1.3.2.2 User's Acceptance Sign-Off 0 days Fri 3/29/24 Fri 3/29/24
44 1.4 Final Preparation 17 days Mon 4/1/24 Tue 4/23/24
45 1.4.1 End User Trainings & Hands-On 11 days Mon 4/1/24 Mon 4/15/24
46 1.4.1.1 Training & Hands on - Master Data Management and 2 days Mon 4/1/24 Tue 4/2/24
Administration
47 1.4.1.2 Training & Hands on - Procure to Pay 1 day Wed 4/3/24 Wed 4/3/24
48 1.4.1.3 Production 2 days Thu 4/4/24 Fri 4/5/24
49 1.4.1.4 Training & Hands on - Sales & Services 1 day Mon 4/8/24 Mon 4/8/24
50 1.4.1.5 Training & Hands on - Inventory & Warehouse Management 1 day Tue 4/9/24 Tue 4/9/24

51 1.4.1.6 Training & Hands on - Financials (Payable, Receivables, 2 days Wed 4/10/24 Thu 4/11/24
Banking, & FA)
52 1.4.1.7 Changes as Identified during Training & Hands on 1 day Fri 4/12/24 Fri 4/12/24

Page 1
Project Plan
ID Task Name Duration Start Finish
53 1.4.1.8 Trainings Feedback & Sign-Offs 1 day Mon 4/15/24 Mon 4/15/24
54 1.4.2 Opening Balances Uploading & System Readiness Final Checkup 6 days Tue 4/16/24 Tue 4/23/24

55 1.4.2.1 Cut Off Date for Opening Balances (Stock, Customers, 2 days Tue 4/16/24 Wed 4/17/24
Vendors & GL)
56 1.4.2.2 Collection & Uploading of Stock Opening Balances 2 days Thu 4/18/24 Fri 4/19/24
57 1.4.2.3 Opening Balances Validation & Pre-Go Live Check List 2 days Mon 4/22/24 Tue 4/23/24
58 1.5 Go-Live and Support 15 days Tue 4/23/24 Mon 5/13/24
59 1.5.1 Post Go-Live Support 13 days Tue 4/23/24 Thu 5/9/24
60 1.5.2 Final Project Closure Meeting & Support Handover 2 days Fri 5/10/24 Mon 5/13/24