Specifications Notes
Specifications Notes
Part A : Specification
Defination:
Specifications describe the products, materials
and work required by a construction contract.
They do not include cost, quantity or drawn inform-
-ation, and so need to be read alongside other inform-
-ation such as quantities, schedules and drawings.
Purpose of Specification:
1. The cost of a unit quantity of work is governed
by its specification.
2. A work is carried out according to its specification
and the contractor is paid for the same. Any change
in specification changes the tendered rate.
3. The necessity of specification is to verify and
check the strength of materials for a work involved
in a project.
4. Specification is an essential contract document
and is required for Arbitration or court cases.
5. Specification is necessary to specify the equip-
-ments, tools and plants to be engaged for a work
and thus enables to procure them beforehand.
Principles of specifications:
Types of Specifications
The specifications are broadly divided into three categories as
1. General or brief specifications,
2. Detailed specifications, and
3. Standard specifications.
Standard specifications.
=> General specification gives the nature and class of work and
materials in general terms to be used in the various parts of
the work, from the foundation to the superstructure.
=> It is a short description of different parts of the work
specifying materials, proportions, qualities etc.
=> General specifications give general idea of the whole work or
structure and are useful for preparing the estimate.
=> These general specifications doe not form part of the
contract document.
=> They are used in the estimates by the person who
prepares the estimates.
Detailed Specifications :
=> The detailed specifications form a part of the contract
document.
=> The detailed specification of an item of work specifies the
qualities and quanitites of materials, the proportion of mortar,
whorkmanship, the method of preparation and execution and the
method of measurement.
=> The detailed specifications of different items of work are
prepared separately which describe what the work should be
and how they should be executed and constructed.
=> Detailed specifications are written to express the requirements
clearly in concise form avoiding repetition and ambiguity.
=> The detailed specifications are arranged as for as possible in
the same sequence or order as the work is carried out.
The following provisions are made in the detailed specification
a. General provisions
b. Technical provisions.
a. General provisions
=> These are also known as conditions of contract and they apply
to the work as a whole.
=> In this document, the conditions governing the contract are
written.
=> The following groups of conditions of contract are generally
accommodated under the general provisions.
3. Standard Specifications
1. Subject matter
=> The subject matter of specifications should relate to the
information required after the contract is given to a particular
contractor. The requirements which are to be enforced
should only be included in the specifications.
2. Grammar
=> All sentences of the specifications should comply with the rules
of grammar. The style and tense should remain the same
throughout.
3. Selection of works
=> While writing specifications, only suitable works with desired
meaning should be used. Unfamiliar works of works having more
than one meaning should never be used in the specifications.
4. Accuracy
=> The information given in the specifications should be complete
and correct, otherwise the contractor may claim for any extra
cost due to damage occurred to him by the misleading
information supplied by the specifications.
5. Practical limits and commercial sizes
=> The specifications should be framed keeping in view the
practical limitations of materials and workmanship and they
should not specify practical impossibilities. Also, the
specifications should specify use of commercial sizes and
patterns of the material.
6. Fairness
=> The specifications should be fair and they should not be
framed in such a way as to throw all the risks on the shoulders
of the contractor.
7. Brevity
=> The sentences of the specifications should be short, simple
and concise. This is essential as the main purpose of the
specifications is to give directions to the contractor and the
supervising staff in carrying out the construction work.
Dimensions
The excavation shall be done in accordance with dimensions of
trenches shown in the working drawings.
Shoring
The sides of the trenches should be vertical and the bottom of
the trenches should be flat. In the case of loose soils the sides
of the trenches should be shored with steel sheets.
Fencing
Suitable temporary fencing is to be provided around the site of
excavation to avoid any accidental fall into the trenches.
Lime
The lime used for the concrete shall be freshly burnt and slaked.
It should be free from clayey particles and ashes. Unslaked
stone particles should be removed by shifting.
Broken Bricks
The overburnt bricks and the pieces of well burnt bricks are to
be broken to sizes ranging from 20 mm to 40 mm and stacked
for easy measurement. The brick bats shall be free from dirt,
dust, rubbish, leaf etc.
Fine aggregate
Surki made from well burnt brick bats is to be used as fine
aggregate. It should pass through I.S. sieve no.48 and free from
dust and dirt.
Proportioning
Lime, surki and broken bricks are to be mixed in the proportion
of 1:2:5 by volume. The materials are to be measured loose
without shaking or ramming.
Mixing
The mixing shall be done only by mechanical mixer. The broken
bats are to be soaked in clean water for atleast 2 hours before
mixing. The materials are first mixed to get uniform distribution
and then water is gradually added. The mixing process is to be
continued till all the brick bats are coated with mortar uniformly
and a workable concrete is obtained.
Laying compacting
The concrete shall be laid to the required thickness, not more
than 200 mm and a time, and compacted by ramming with
rammers weighing 4.5 to 55 kg.
Curing
The lime concrete, so laid, is to be kept wet for atleast 7 days.
Stone
The stone shall be obtained from the approved queries. It shall
be sound, free from cracks and decay and shall have a specific
gravity of not less than 2.5.
Mortar
Cement mortar 1:6 to be used.
Method of Laying
The stones are to be laid on broadest face which gives better
opportunity to fill the spaces between stones by the mortar.
The stones are laid layer by layer with sufficient mortar in
between them for better binding. The outer face of the
basement should be vertical and the joints are to be staggered.
There shall be no gap, between the stones, unfilled by mortar.
Curing
The masonry should be kept in we condition by sprinkling water
thrice daily for atleast 7 days after construction.
Base Course
The basic course shall be of 25 mm thick cement concrete of a
1:2:4 mix using 12 mm size granite stone chips as coarse aggregate
and sand as fine aggregate. The top of flooring concrete or R.C.C.
slab shall be cleaned well and applied with cement slurry of
2 kg/m2 before placing the chips concrete. The base course is to
be compacted, leveled and smoothed by wooden floats.
Mosaic Tiles
Precast tiles of 200 mm x 200 mm x 20 mm size are to be used.
They shall be manufactured under hydraulic pressure of not less
than 14 N/mm2 and given the first grinding with machine before
laying. The proportion of cement to sand in the backing of the
tiles shall not be leaner than 1:3 by weight. The marble chips
shall be hard, dense sound and homogeneous in texture.
Laying of Tiles
The bedding for the tiles shall be with cement mortar 1:3. The
average thickness of the bedding mortar shall be 20 mm and the
thickness at any place shall be not less than 10 mm. Cement
bedding shall be spread, tamped and corrected to proper levels
and allowed to harden before the tiles are set.
Neat cement slurry of honey like consistency shall be spread
over the bedding at the rate of 4.4 kg/m2. Tiles shall be washed
clean and shall be fixed in this grout one after another, each tile
being gently tapped with a wooden mallet till is properly bedded
and in level with the adjoining tiles. The joints shall be kept as
thin as possible not exceeding 1.5 mm and in straight lines.
Materials
Portland cement of initial setting time not less than 30 minutes
and medium size clean sand free from organic matters and salts
are to be sued for making mortar. The water to be used shall be
clean and potable.
Mixing Mortar
The sand and cement shall be first mixed dry in the required
proportion thoroughly to get a uniform colour. The required
amount of water shall be added slowly and gradually
and the mortar mixed wet to give a uniform paste.
Application of Mortar
The surface to be plastered shall be cleaned and wetted with
water before the mortar is applied. Plastering shall be started
from the top and proceeded towards the bottom. The plastered
surface shall be made level and flush with wooden straight edges
and rubbed thoroughly with wooden floats to ensure smooth and
even surface.
Curing
Plastered surface shall be kept wet by sprinkling water for atleast
7 days.
6. Detailed specification for distempering
The distemper shall be of the approved colour and quality.
Water shall be added as prescribed by the manufacture, stirred
well often during use, to maintain uniform colour and consistency.
The plastered surface of the wall is scraped and cleaned
with wire brushes and rubbed smooth with sand papers. Distemper
shall not be applied in wet weather. It shall be applied with good
brushes, first horizontally and then immediately crossed off
vertically which together shall constitute one coat.
The second coat will be also applied in the same manner
after the first coat has dried. The finished surface shall be even
and uniform and shall show no brush marks.
A. C. Sheets
The sheets shall be approved quality, free from cracks and
damages. Semi corrugated sheets of 1100 mm width and 1750 mm
length are to be used. The thickness of the sheets shall not be
less than 6 mm.
Purlins
Angle purlins of required size shall be used at spacing not
exceeding 1.4m.
Laying of Sheets
The sheets should be laid starting from the eaves, with the
smooth side facing upwards and with a minimum of 150 mm lap
at the ends. The over hang of the sheets shall not exceed 300 mm.
Pitch
The slope of the roof shall be not flatter than 1 vertical to 5
horizontal and not steeper than 1 vertical 1 horizontal.
Fixing
The sheets shall be fixed to the purlins from the top of
corrugation by 8 mm dia G.I. hooks and nuts. The holes shall be
drilled and not punched. Each hook shall have a bitumen washer
and metal washer placed over the sheet before the nut is
screwed.
Ridges and Hips
Ridges and hips shall be of the same brand of the sheets and have
the same patern of corrugations. They shall be free from cracks
and damages. The ridge capping shall be screwed to the ridge
purlins by same type of bolts used for fixing the sheets.