ACCROPODEII Design Guidelines
ACCROPODEII Design Guidelines
PRELIMINARY DESIGN
GUIDELINES
1
Version V03 – Published in February 2023
2
Contents
1. Presentation………………………………………………………………………………………………………………………………………4
2. Glossary…………………………………………………………………………………………………………………………………………….5
3. Standard values - ACCROPODETM II unit…………………………………………………………………………………………….6
4. Unit Shape and characteristics………………………………………………………………………………………………………….7
5. Typical cross-section of a breakwater with a single-layer armour facing……………………………………………8
6. Summary of the preliminary design………………………………………………………..............................................9
7. Data required………………………………………………………………………………………………………………………………….10
8. Preliminary sizing of the unit…………………………………………………………………………………………………………..11
9. Underlayer………………………………………………………………………………………………………………………………………16
10. Design guide table…………………………………………………………………………………………………………………………..18
11. Toe mound……………………………………………………………………………………………………………………………………..19
12. Crest of the structure………………………………………………………………………………………………………………………24
13. Steps……………………………………………………………………………………………………………………………………………….25
14. Roundhead……………………………………………………………………………………………………………………………………..26
15. Inner slope………………………………………………………………………………………………………………………………………27
16. Transitions………………………………………………………………………………………………………………………………………28
17. Quantity estimate…………………………………………………………………………………………………………………………..29
18. Physical scale modelling………………………………………………………………………………………………………………….30
19. Technical assistance………………………………………………………………………………………………………………………..33
20. Calculator………………………………………………………………………………………………………………………………………..37
21. Terms and conditions of use……………………………………………………………………………………………………………38
3
1. Presentation
The design guidelines
This document is intended for designers of
maritime structures who wish to use the
ACCROPODE™ II technique for protecting rubble-
mound breakwaters. These guidelines provide the
key information required to perform the
preliminary design of ACCROPODE™ II armour
facings in accordance with the basic principles of
the technique developed by SOGREAH (now
ARTELIA) over more than 40 years.
Reliability through
experience
CLI is the leader in breakwater protection
technology using so-called “single-layer” systems.
It has taken part in more than 380 projects in many
countries involving ACCROPODE™, ECOPODE™,
ACCROBERM™ and CORE-LOC™ units in a wide
variety of conditions. It has acquired more than 70
years of experience in the construction of concrete
armour facings for maritime breakwaters, starting
with the TETRAPODE unit in 1953. 1981 saw the
invention of the first single-layer unit, named the
ACCROPODETM, which became the industry
benchmark as the years went by. ACCROPODE TM
units have been used in sizes ranging from 0.7m3 in
areas with moderate waves to 28m3 to protect
structures in Japan against the very strong waves
of the Pacific Ocean. The ACCROPODE™ technique
is far more than a mere concrete unit; it is a
complete procedure guaranteeing that the
characteristics developed by its inventor are
achieved in full on the projects where it is applied.
CLI’s specialist team provides technical assistance
at all stages of the project. This assistance is
intended for parties such as Owners, Engineers,
physical scale modelling laboratories and, more
particularly, construction contractors. To complete
the package, CLI provides a compliance certificate
issuing procedure enabling all parties to ensure
that the breakwater is built in accordance with the
ACCROPODE™ technology.
4
Figure 1: ACCROPODETM II units in Kuwait
2. Glossary
Symbol Description
Unit
5
3. Standard values – ACCROPODETM II unit
Saturated unit weight – single-layer armour unit 𝛾𝑠𝑎𝑡 = 19 𝑘𝑁/𝑚3 [cf. note 2]
Note 1 – Source: Eurotop Manual Table 6.2 (values for a slope of 1:1.5)
Note 2 - Indicative values estimated by ARTELIA in order to model ACCROPODE™ II unit layers as “ground” elements
6
4. Unit shape and characteristics
Zc
harmour
Design
HS
hb – water depth
above the toe
h - water depth at
mound
Crown wall Crest/berm Core Underlayer Artificial armour facing Scour apron Toe mound Natural bed Bed slope in front of the structure
8
6. Summary of the preliminary design
Site conditions
• Waves
• Water levels
• Bathymetry
PHYSICAL
SCALE ③ DESIGN OF THE ARMOUR FACING
MODEL
TESTS
Underlayer
Adaptation to the armour unit and the site conditions
Toe mound
Choice of type of toe mound and stability check
Crest
Definition of crest type. Consideration of construction aspects
9
7. Data required
The information below is required for the preliminary design of the armour facing:
• Precise bathymetry in the vicinity of the structure;
• Reference wave;
• Water level: tide variations, influence of storms, levels induced by climate change;
• Wave breaking conditions;
• Minimum concrete density at the site;
• Sea water density;
• Rockfill density;
• Armour crest level zc;
• Foundation level of the first unit at the armour toe zP;
• Lifetime of the structure;
• Return period of design-critical events.
N.B.:
In the context of a preliminary design, the
Figure 5: Hydraulic shovel and lattice boom crawler crane during ACCROPODE TM II unit placing
wave to be used is H1/3. This corresponds to
the “significant wave height, the average of
the highest third of the waves, based on
time domain analysis”, for the Hudson and
Van der Meer formulae. The locations of
wave points are selected by the structure
designer depending on the site conditions.
10
10
8. Preliminary sizing of the unit
③ Factors
Right - Figure 6: Diagram explaining the influencing unit
preliminary unit sizing process size
11
11
Stability coefficient
ACCROPODETM II with breaking wave ACCROPODETM II without breaking wave ACCROPODETM II with breaking wave ACCROPODETM II without breaking wave
12
Figure 10: photograph of ACCROPODETM unit
placing using a crane mounted on a barge
Hudson formula
The size of the ACCROPODE™ II units is calculated
using the Hudson formula, with a hydraulic
𝑯𝑺 𝟑
stability coefficient that varies as indicated in the 𝑽=
previous section. 𝑲𝑫 ∆𝟑 𝒄𝒐𝒕𝒂𝒏 𝜶
Where
V ACCROPODE™ unit volume m3
HS Significant wave height (H 1/3) m
Δ Concrete relative density (𝜌𝑐 − 𝜌𝑤 )/𝜌𝑤 kg/m3
ρc Concrete density kg/m3
ρw Sea water density kg/m3
KD Hydraulic stability coefficient [-]
cotan α Cotangent of the slope angle (see notes below) [-]
Notes
Generally speaking, slopes of 4:3 or 3:2 may The usual concrete density values range
be used. In the Hudson formula, it is between 2,300 kg/m3 and 2,500 kg/m3.
preferable to use a slope of 4:3 (cotan(α) = Outside this range, the hydraulic response
1.33). Gentler slopes lead to lower friction and may differ from that of a standard armour
interlocking forces, which are detrimental to facing.
unit stability.
13
Factors influencing unit stability
Other factors must be considered in fine-tuning the preliminary design obtained using the Hudson
formula. Table 3 below indicates the influential parameters that are encountered most frequently.
There may be others specific to the individual work site.
Structure in the wave breaking Frequent waves close to the It is suggested to reduce the stability
zone design wave. Fatigue effect. coefficient by 20%.
Note
1
According to [1] CIRIA-CUR-CETMEF Rock When several factors among those listed in
Manual, The use of rock in hydraulic table 3 are combined, they must be
engineering – 2009, section 5.2.2.1, a low- addressed with a conservative approach to
crested structure has a crest level above or be on the safe side. Less is known about
below the still sea water level. combined effects, and they are difficult to
control. In this case, the lowest stability
coefficient KD value must be selected and
then reassessed with an increased safety
factor left to the discretion of the structure
designer. It is advisable to increase the size
of the units. Physical scale model testing
remains strongly recommended in all cases.
14
Number of rows on the slope
15
9. Underlayer
Layout
Single-layer armour units are placed on an
underlayer with specific properties. To guarantee a
suitable base for the armour units, the rockfill
forming the underlayer must be laid so as to:
Table 5 summarises the geometrical information on the rockfill to be used to build the underlayer.
The nominal limits (NLL and NUL) of natural rockfill for the underlayer must be between 7% [NLL] and 14%
[NUL] of the armour unit mass (see Ref [1] section 5.2.2.3). However, a tolerance may be applied to optimise
the number of rockfill categories required for a given project. (see Table 6)
The grading must not be too narrow (as this leads to difficulties during construction) or too wide (as this
reduces filter porosity and poses a potential risk of segregation). To ensure an evenly distributed grading, the
following relation should preferably be used: 2 ≤ NUL/NLL ≤ 3 (see Ref [1] section 5.5.5.3 and Ref [2]). The
rockfill must have angular shapes and a large number of broken faces.
16
Figure 14: Photograph of an underlayer
17
The Design Guide Table for ACCROPODE™ II and ECOPODE™ provides information on
the characteristics of the units, concrete consumption, density, etc. This table is given
10. Design Guide Table below and can be consulted on CLI’s website [https//www.concretelayer.com]. It is
advisable to refer to the version available on the website, as this contains the most
recent updates.
1919
Types of toe mound
ACCROPODE™ TOE MOUND
The ACCROPODE™ toe mound is the basic
solution to ensure good stability in the
majority of cases. It is the most widely used,
because it is the easiest to construct. It
consists of a row of armour units placed on a
scour apron and reinforced by a double layer
of rockfill so as to guarantee the stability of
the first unit. The thickness of the rockfill must
not exceed that of the single-layer armour
units. The thickness of the toe mound should
not normally be less than two-thirds of the
unit height.
Opposite:
Figure 17: ACCROPODE™II toe mound
Figure 18: Type I embedded toe mound - loose soil and rock
Figure 19: Type II embedded toe mound - rock
Figure 20: Rockfill toe mound in V-shaped trench
20
ACCROBERM™ I AND II
TOE UNITS Below:
Figure 21: 3D view - ACCROBERMTM I placement
Figure 22: ACCROBERM™ I unit in toe position
To provide a more reliable and more Figure 23: 3D view - ACCROBERMTM II placement
economical solution, two types of toe unit Figure 24: ACCROBERM™ II unit in toe berm position
have been developed. Both of these solutions
must be used in the specific conditions
describe below.
yNACCROBERM™ I
a o
This unit replaces the first row of
u y II units and does away with the
ACCROPODE™
double layer a of rockfill that serves as a toe
us berm in a standard toe mound. Therefore it
c-ch
difficulties of stabilising the rockfill in
conventional toe mounds.
oeu
This unit is particularly suitable when the bed
slopes opposite the structure are between 0
ch
and 5%. For a steeper bed slope, this unit may
not be sufficient to stabilise the toe. In this
e
case an embedded toe mound will be
required.
The weight of the unit is the same as that of Dv
the ACCROPODE™ II unit that it supports. The 4 Dv
4
So 3
grid is also determined according to that of the usS
-coou
So
u 3
e
ACCROPODETM II armour units is adapted in
S
Noyau
ou
ACCROBERM™ II
y
hc e
aThis unit is used in an eco-design approach. It
coo
N is u
positioned as a reinforcing “toe berm” as a
uus
A
o
substitute for rockfill. The centre of this ring-
ocheu
shaped unit is filled with rockfill of a specific
y
Dv
c-ch
uousc-
a development stages.
their habitats and
4
It substantially reduces the footprint of the
u a new ecosystem. The
oeu
-sSco
v
units find a suitable substrate on which to
ch
4
used with this unit. 4
So 3
The size of the ACCROBERM™ II units is usS
-coou
usc-c
Noyau
determined according to the armour unit grid. hoeu Dv
21
Noyau 4
General approach
to toe mound
depth
22
22
Toe mound stability
3
𝐻𝑠
𝑊50 = ( ) 𝜌𝑟
(2 + 6.2 (ℎ/ℎ𝑏 )2.7 ) 𝑁𝑜𝑑 0.15 ∆
23
12. Crest of the structure
The type, level and width of the breakwater crest are generally defined by the following parameters:
• Overtopping rate, in accordance with the design criteria and, in particular, the purpose of the structure
• Whether or not the crest of the structure must be made accessible
• Constructional aspects enabling the project costs to be optimised.
Generally speaking the following minimum values are adopted for the width of a berm made of artificial
armour units:
These principles ensure that the units are sufficiently interlocked with each other and with the crown wall.
Below this limit, it is still feasible to place the units but implementation becomes more difficult. On the
other hand, only having a single row of units on the crest against a crown wall is strongly discouraged. There
is a risk that this single row will not be blocked correctly between the slope and the wall. Special attention
must be paid to low-crested breakwaters (crest level less than a height H s from the design maximum sea
water level), because armour units placed on a horizontal surface are less able to interlock with each other.
It is hence recommended to increase the unit weight of the units and to conduct physical scale model tests
in order to determine their stability (Ref [1] section 5.2.2.4). Moreover, with a view to maintaining the
future structure and its armour facing, provision for an access road is recommended. If an access road
cannot be built to carry out maintenance on the structure, this work can potentially be done from the sea.
3 Dn 3 Dn
Figure 27: Example of a crest with a crown wall Figure 28: Example of a completely covered crest
24
13. Steps
Left, opposite:
Figure 29 & Figure 30:
Photographs of the reinforced
concrete access steps
25
14. Roundhead
Left, opposite:
Figure 31: 3D view of a
roundhead
Figure 32: Photograph of the
roundhead on the project to
extend the Port of Constanta in
Romania
26
15. Inner slope
The main parameters for designing the armour facing of the breakwater inner slope are defined by:
There is no specific formula for sizing the single-layer armour facing on the inner side of the breakwater.
The Hudson formula can be used for an initial approach if waves penetrate inside the harbour, but its
limits will soon become apparent. Given the effects listed above, a physical scale modelling approach is
preferable. Special attention must be paid during these tests to the toe mound on the inner side and to
the consequences of overtopping.
Laboratory physical scale models will be required to determine the stability of this inner slope.
Below - Figure 33: Photograph of a breakwater with ACCROPODETM II units in Aberdeen (Scotland)
27
27
27
16. Transitions
Transitions between different unit sizes/types or with rockfill are specific points that require special attention,
because they result in a grid loss in the armour facing which must be considered as a critical point.
First of all, positioning these transitions in places that are critical in terms of wave action (roundhead and bends)
is strongly discouraged. Physical model tests can help to locate the wave concentration zones, in order to avoid
position transitions elsewhere.
A transition between units must be made along a line at an angle of 45° over the slope height. The larger units
must be placed below the smaller ones. Whenever possible, the difference in unit volumes must not exceed 30%
in order to avoid differences in armour thickness. When the differences in armour thickness are small (less than
H/6), it is preferable to align the sections of the underlayer. When the differences exceed H/6, it is preferable to
consult CLI.
Whenever possible, a transition between units should also be followed by a change in underlayer size. It is also
possible to make transitions between two-layer and single-layer units. It is preferable to align the outer armour
facings to avoid step-like effects between the units.
45°
Figure 34: Transition between two different ACCROPODETM II unit sizes Figure 35: Close-up of the transition in Figure 34
28
17. Quantity estimate
Stages
The conventional method for
performing the quantity estimate
consists in using a graph-based
solution.
③ Number of ACCROPODE™ II
units
Number of ACCROPODE™ II units
= Theoretical surface area x N
Where N, number of units/m²
④ Concrete volume
Concrete volume = theoretical
surface area x concrete
consumption in m3/m² (cf. Design
Guide Table - table 6).
Right - Figure 36: Positioning the
neutral fibre graphically N.B.: For the Dv of each size, it is advisable to contact CLI in order to obtain the exact value
29
18. Physical scale modelling
30
Unit stability on a
physical scale model
31
USUAL DAMAGE CRITERIA USED WITH PHYSICAL SCALE MODELS
For a 120% overload of the design wave conditions (120% Hs), the damage criterion is:
Below - Figure 39: Photograph of a model breakwater with ACCROPODE TM II units during laboratory testing
32
The technical assistance provided by CLI in
relation to the sub-licence agreement for
TENDERING PHASE
During the tendering phases, CLI experts
are also available to answer any questions
regarding the technique, in the strictest
confidence.
33
Assistance during the
construction phase
AT THE START OF THE WORKS
In the context of the sub-licence agreement, CLI
supplies the specifications required by the
contractor in charge of the construction works.
The services provided include:
• Provision of the Technical Information Document,
drawing together the specifications and the
experience acquired through the 380 projects
completed worldwide.
• Supply of a list of experienced ACCROPODE™
II formwork manufacturers, or of available
second-hand formwork;
• Supply of unit shape definition drawings and
simplified formwork drawings;
• Review of and advice regarding the methods for
fabricating and placing ACCROPODE™ II units;
• Assistance with setting up a quality monitoring
system.
COMPLIANCE CERTIFICATE
On request, following the feasibility study and at
the very start of the works, CLI can set up a
“Compliance Certificate” procedure to confirm
that the ACCROPODE™ II armour facing is
constructed in accordance with the specifications
and best practice.
34
Inspection and
maintenance of the
structures
CLI assists project owners by providing the Figure 43: 3D point cloud of an ACCROPODE™ armour facing
appropriate documentation and proposing
comprehensive armour facing
inspection/assessment services performed
by its experts and specialists. These
inspections are based on the
implementation of 3D numerical models
with centimetre accuracy that detect all
movements irrespective of the underwater
visibility conditions. In most cases the
intervention of divers is not required.
35
CLI’s Project in the world
Key
Years
1981 – 1988
1989 – 1994
1995 – 1999
2000 – 2005
2006 – 2011
2012 – 2017
36
120. Calculator
A tool for estimating unit size is
available on the CLI website:
www.concretelayer.com/fr/calculateur
37
21. Terms and conditions of use
Intellectual property
and rights of use
ACCROPODE™, ECOPODE™ and
ACCROBERM™ are registered trademarks
and protected internationally by Artelia.
CORE-LOC™ is a registered trademark
protected internationally the USCOE. The
use of any of the technologies stated
above requires the prior signature of a
sub-licence agreement with CLI.
Warnings relating to
this document
This document is intended for specialised
readers who have a solid grounding in the
dimensional design of rubble-mound
breakwaters and maritime hydraulic
structures.
The dimensional design of armour facings
is a complex process. This document does
not claim in any way to constitute the
complete source of data or information
required to design an armour facing.
Users must refer to best practice and the
applicable standards in designing their
structure. The aim of this document is to
provide general information and the
initial conditions for the preliminary
design of breakwaters with an
ACCROPODE™ II single-layer armour
facing. This document is not a design
handbook and it does not take into
consideration all the aspects of designing
a breakwater; it only covers the main
information relating to or influencing the
armour facing. The structure designer
remains responsible for the design of the
structure in its entirety. It is vital to
confirm the structure design with the aid
of 2D and 3D physical scale models. CLI or
Artelia will not be held liable under any
circumstances for direct or consequential
damage resulting from use of the content
of this document.
A number of online resources to be used
in parallel with and as a complement to
this document are available on the
www.concretelayer.com website.
38
References Contacts
[1] CIRIA-CUR-CETMEF The Rock Manual: The CONCRETE LAYER INNOVATIONS
use of rock in hydraulic engineering – 2009
6, rue de Lorraine
[2] Standard EN 13383 Armourstone 38130 ECHIROLLES – France
[3] Hydralab III Guidelines for physical model Tel.: +33(0) 476 044 774
testing of breakwaters. Rubble mound Fax: +33(0) 476 044 775
breakwaters NA3.1-2 August 2007
Website: www.concretelayer.com
Email: [email protected]
39
39
ACCROPODETM II
ACCROPODETM I
CORE-LOCTM
ECOPODETM
ACCROBERM TM I
ACCROBERM TM II
40
41