Program For Combined Foundation Design With Piles
Program For Combined Foundation Design With Piles
163 171 103 107 109 117 139 151 159 167
C3-1 C3-9 A2-3 A3-3 B1-1 B1-9 C1-1 C2-5 C2-13 C3-5
1.4 0.81 0.95 0.81 1.26 1.26 1.26 1.26 0.95 1.4
1.14 0.76 1.6 1 0.9 1.14
1.6 1
1 1 1 1
1.6 0.96 1.6 1.6
175
C3-13
0.81
0.76
1
1. GENERAL
3. MATERIAL SPECIFICATIONS
3.1 Strength
Reinforcement bar yield strength 420 MPa
Concrete compressive strength at 28 days (Cylinder) 25 MPa
Anchor bolts : fy(bolt) 250 MPa
4. FOUNDATION DETAIL
4.2 Elevation
Top of pedestal 100.30 m
Top of Foundation 98.70 m
Unit 100.00 m
Ground water level (dw) 98.00 m
Pedestal-1(T-1504)
Name Loading Type Vert. Load Horizontal Load Moment Load
kN Hx (kN) Hz (kN) Mz (kN-m) Mx (kN-m)
A Empty/Dry 70.0 0.0 0.0 0.0 0.0
B Operating 250.0 0.0 0.0 0.0 0.0
C Full of Water 287.0 0.0 0.0 0.0 0.0
D Earthquake 0.0 60.0 60.0 616.0 616.0
E Wind 0.0 35.0 35.0 253.0 253.0
Pedestal-2(T-1502&T-1503)
Name Loading Type Vert. Load Horizontal Load Moment Load
kN Hx (kN) Hz (kN) Mz (kN-m) Mx (kN-m)
A Empty/Dry 247.0 0.0 0.0 0.0 0.0
B Operating 714.0 0.0 0.0 0.0 0.0
C Full of Water 997.0 0.0 0.0 0.0 0.0
D Earthquake 0.0 150.0 150.0 2920.0 2920.0
E Wind 0.0 115.0 115.0 1640.0 1640.0
X
h3 PEDESTAL # 2
h2 PEDESTAL # 1 Y
h1
Wx
Px
2 1
bz
Wz Pz
Z C.W = +ve
4 3 C.C.W = -ve
X
b2
7.1 Footing
Thickness of Foundation h1 0.800 m
Height of Foundation (GL-TOF) Hf 1.300 m
Depth of Foundation (GL-BOF) df 2.100 m
7.2 Pedestals
Height of Padestals h3 1.600 m
Soil Cover h2 1.300 m
Pedestal-1 Pedestal-2
Pedestal in X-dir Px 1.700 m 2.800 m
Pedestal in Z-dir Pz 1.700 m 2.800 m
Area of Padestal 2.39 m² 6.49 m²
Area (Padestal + d) 4.72 m² 10.07 m²
Weight of Padestal 91.9 KN 249.3 KN
7.3 Piles
Dimension of Pile Dp 0.800 m
Length of Pile Lp 15.000 m
Area of Pile 0.50 m²
Area (Pile + d) 1.74 m²
7.4 Saddles
No of Saddles 2
C/C Distance between Saddles b2 4.500 m
Centroidal Dist. Of Pedestal # 1 2.525 m
Centroidal Dist. Of Pedestal # 2 1.975 m
No of Piles 4
Piles in X-dir 2
Piles in Z-dir 2
Pile to edge spacing 0.5
Pile to Pile distance in X-dir bx 4.750 m
Pile to Pile distance in Z-dir bz 2.500 m
8. STABILITY CHECK
Wd V Total Vert. Hx Mz
kN kN kN kN kN-m
1 A2-1 1289.0419 317.0 1606.0 150.0 1941.9
2 A3-1 1160.1377 285.3 1445.4 149.1 2588.4
3 B-1 1289.0419 1601.0 2890.0 0.0 -1555.5
4 B-7 1289.0419 1601.0 2890.0 90.0 -203.7
5 C1-1 1289.0419 1281.0 2570.0 0.0 -1090.0
6 C2-1 1289.0419 1281.0 2570.0 150.0 1163.0
7 C3-1 1289.0419 1281.0 2570.0 149.1 1778.4
8 C3-9 1160.1377 1152.9 2313.0 149.1 1887.4
Wd V Total Vert. Hz Mx
kN kN kN kN kN-m
1 A2-3 1289.0419 317.0 1606.0 150.0 2253.0
2 A3-3 1160.1377 285.3 1445.4 149.1 2868.4
3 B-1 1289.0419 1601.0 2890.0 0.0 0.0
4 B-9 1289.0419 1601.0 2890.0 90.0 1351.8
5 C1-1 1289.0419 1281.0 2570.0 0.0 0.0
6 C2-5 1289.0419 1281.0 2570.0 150.0 2253.0
7 C3-5 1289.0419 1281.0 2570.0 149.1 2868.4
8 C3-13 1160.1377 1152.9 2313.0 149.1 2868.4
H / n (n = no of piles)
Shear Capacity of
Longitudinal Transverse Pile (kN)
A2-1 37.5 280 OK !
A3-1 37.3 280 OK !
B-1 0.0 210 OK !
B-7 22.5 280 OK !
C1-1 0.0 210 OK !
C2-1 37.5 280 OK !
C3-1 37.3 280 OK !
C3-9 37.3 280 OK !
A2-3 37.5 280 OK !
A3-3 37.3 280 OK !
B-1 0.0 210 OK !
B-9 22.5 280 OK !
C1-1 0.0 210 OK !
C2-5 37.5 280 OK !
C3-5 37.3 280 OK !
C3-13 37.3 280 OK !
9. DESIGN OF REINFORCEMENT
Wd V Total Vert. Hx Mz
kN kN kN kN kN-m
1 A2-1 1224.5898 301.2 1525.7 240.0 3309.3
2 A3-1 1044.124 256.8 1300.9 210.0 3788.0
3 B1-1 1624.1928 2453.8 4078.0 0.0 -2383.0
4 B1-7 1624.1928 1683.4 3307.6 144.0 526.5
5 C1-1 1624.1928 1941.8 3566.0 0.0 -1638.2
6 C2-1 1624.1928 1363.4 2987.6 240.0 2433.9
7 C2-9 1224.5898 1168.8 2393.3 240.0 2608.3
8 C3-1 1804.6587 1542.8 3347.4 210.0 2716.5
9 C3-9 1044.124 989.4 2033.5 210.0 3196.1
Wd V Total Vert. Hz Mx
kN kN kN kN kN-m
1 A2-3 1224.5898 301.2 1525.7 240.0 3604.8
2 A3-3 1044.124 256.8 1300.9 210.0 4040.0
3 B1-1 1624.1928 2453.8 4078.0 0.0 0.0
4 B1-9 1624.1928 1683.4 3307.6 144.0 2162.9
5 C1-1 1624.1928 1941.8 3566.0 0.0 0.0
6 C2-5 1624.1928 1363.4 2987.6 240.0 3604.8
7 C2-13 1224.5898 1168.8 2393.3 240.0 3604.8
8 C3-5 1804.6587 1542.8 3347.4 210.0 4040.0
9 C3-13 1044.124 989.4 2033.5 210.0 4040.0
Transverse Direction
Bottom Rebar 34 bars T 25 @ 200 mm
Top Rebar 34 bars T 25 @ 200 mm
PEDESTAL # 1 PEDESTAL # 2
Vu 663.179 KN 2220.51 KN
bo 6.902 m 10.082 m
Vn1 = (1+2/ß)√fc' b0d /6 11863 kN 17329 kN
Vn2 = (αsd/bo+2)√fc' b0d /12 9863 kN 11685 kN
Vn3 = √fc' b0d /3 7909 kN 11553 kN
Vc = min(Vn1, Vn2, Vn3) 7909 kN 11553 kN
11 PADESTAL DESIGN
PADESTAL # 1 PADESTAL # 2
Rebar Size 20 mm 25 mm
Sectional Area 314 mm² 491 mm²
Nu 131.1 KN 402.0 KN
Mu 1120.0 KN-m 3280 KN-m
r = h/H 0.93 0.96
Nu / Ag 0.05 0.06
Mu / Ag . H 0.28 0.18
p 0.004 0.003
Act 5630.4 mm² 6955.2 mm²
Rebar nos 18 15
As on both sides 10053 mm² 12763 mm²
Vu 663.2 KN 2220.51 KN
Ag 2.39 m² 6.49 m²
d 1625 mm 2720 mm
Rebar Size 10 mm 10 mm
Rebar pitch 150 mm 150 mm
Sectional Area 79 mm² 79 mm²
Rebar nos 11 12
11.4 Rebar Arrangement for Padestal
Padestal # 1:
Padestal # 2: