C3A - Monthy Report - Swing Studio DG006 30 DEC
C3A - Monthy Report - Swing Studio DG006 30 DEC
Monthly
Report
Page No.
5.0
1.0 Projected work for coming month
Progress Charts Engineering Works
………………………
……………………… 14
04
6.0
2.0 Contractor Recourses
Procurements logs ………………………
……………………… 16
06
7.0 Project cash flow & S-curve & ……………………… 18
3.0 Contractor Recourses
variation log ……………………… 09
4.0
8.0 QA/QC SummaryWORKS
ENGINEERING ……………………… 11
20
5.0
9.0 Environment Health & Safety
Progress Photos ……………………… 14
22
The Project comprises the carrying out and completion of the Swing Studios building including the
Pocket substation forming part of the project known as DG006 PROPOSED SWING STUDIOS
BUILDING, EMIRATES GOLF COURSE in the Emirate of Dubai.
• Main Building
Service YARD, RECEPTION CORRIDOR SWING STUDIO -Number 5 OFFIC, TOILET
(MAN-WOMEN) STORE, CONTROL ROOM ,CLUB REPAIR ROOM, ELECTRICAL
ROOM
• Pocket Substation
2. Project Update:
(Data are measured up to end of the month and respecting the endorsement to the Contract)
Item Status
3. Budget Update:
(Data are measured up to end of the month and respecting the endorsement to the Contract, refer
to the attached V.O. log for further details)
4. Fact List:
5. NOCs Status
SITE WORKS
7.2 75%
- CONCRETE WORKS
7.3 89%
- MASONRY WORKS
7.4 87%
A. Time
Planned Actual
37% 19.72%
Total NCRs : 5
Pending NCRs : 2
Ncr status
1-Long lead item for civil & Mep to need corrective actions to meet milestones.
2- client instruction to finish external works at the end of December and remove
portacabins and temporary fence.
1. Progress Update:
Please refer to the attached Progress Update of the Approved Program Rev03
Please refer to look ahead the attached 1 month of the Approved Program Rev03
Project Director AC 1
Project Manager AC 1
Planning engineer AC 1
Construction 1
AC
Engineer
1
Site Engineer AC
QS Engineer AC 1
QA/QC Engineer AC 1
Electrical Engineer AC 1
Mechanical Engineer AC 1
Safety Officer AC 1
General Foreman AC 2
Procurement AC 2
Document Controller AC 2
Draughtsman AC 2
Secretary AC 1
Office Coordinator AC 1
Office Boy AC 1
Security AC 1
PRE-QULIIFICATION STATUS
MATERIAL STATUS