Diamer Basha Dam Project Contract Mw-1: Dam Part (Civil Works) and Tangir Hydropower Works

This weekly report provides progress updates for critical activities on the Diamer Basha Dam Project for the period of December 25th to 31st, 2023. River diversion works such as the guide wall and diversion canal excavation are lagging behind schedule due to delays in equipment and material delivery as well as security issues. Excavation of the diversion canal upstream section is 76.7% complete while the middle section is 88.7% done, with work slowed by insufficient resources. The downstream section makes little progress at 38% due to space constraints. Rebah diversion tunnel excavation and concrete lining are fully completed while contact and consolidation grouting activities are on schedule.

Uploaded by

Nauman Liaqat
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
127 views3 pages

Diamer Basha Dam Project Contract Mw-1: Dam Part (Civil Works) and Tangir Hydropower Works

This weekly report provides progress updates for critical activities on the Diamer Basha Dam Project for the period of December 25th to 31st, 2023. River diversion works such as the guide wall and diversion canal excavation are lagging behind schedule due to delays in equipment and material delivery as well as security issues. Excavation of the diversion canal upstream section is 76.7% complete while the middle section is 88.7% done, with work slowed by insufficient resources. The downstream section makes little progress at 38% due to space constraints. Rebah diversion tunnel excavation and concrete lining are fully completed while contact and consolidation grouting activities are on schedule.

Uploaded by

Nauman Liaqat
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 3

Ref: MW1-DBDC-004-371 Jan 03, 2024

General Manager/Project Director Chief Executive Officer


Diamer Basha Development Company, Liaison Office, Diamer Basha Development
Diamer Basha Dam Project Office, Company.
Chilas. 708 - WAPDA House, Lahore.
Telephone: +92-5812-920209 Telephone: +92-42-99201572
Facsimile: +92-42-99201059

DIAMER BASHA DAM PROJECT


CONTRACT MW-1: DAM PART (CIVIL WORKS) AND TANGIR HYDROPOWER WORKS

Subject: Weekly Monitoring of Critical Activities of Ongoing Projects by Member


(Water) WAPDA 25-Dec-2023 to 31-Dec-2023

Dear Sir,

Please find enclosed herewith duly filled Pro-forma for weekly monitoring of critical activities
for the week starting from 25-Dec-2023 to 31-Dec-2023.
Yours Sincerely,

Sakir Cengiz
Project Manager / Engineer’s Representative
Diamer Basha Consultants Group (DBCG)

Encl: As stated above

Copy to: CE (Construction), DBDC Office, Chilas

49-H, Gulberg-III, Lahore, Pakistan. Tel: +92-42-35846601-02, +92-42-35846619


Email: [email protected], [email protected]
Page 1 of 1
Project Name: Diamer Basha Dam Project

Weekly Report For Critical Activities 25 Dec 2023 To 31 Dec 2023


Accumulative Progress Up to Reporting
Commencement Date Finish Date
Week

Sr # Critical Activities Revised Plan Remarks/Reasons of Delay Bottlenecks


Anticipated/
BL Planned Actual/Anticipated BL Planned Planned (as per Modified Actual
Revised
Diversion Scheme)

01 River Diversion and Care of Water


1. Timely delivery of Hydro-mechnical
Contractor is presently performing drilling for
Gates and Allied Parts including related
secant piles and curtain grouting works.
Guide Wall 23-Jun-22 31-Jan-23 08-Mar-23 24-Dec-23 100.00% 100.00% 78.00% accessories / systems.
Contractor has been advised to expedite
2. Immediate deployment of new
concreting progress on Guide Wall.
percussion drills for U/S and D/S
cofferdams
Diversion Canal
3. Resource deployments for ongoing
grouting activities for temporary and
Contractor's progress is lagging behind due permanent works.
DC U/S Excavation (U/S of CH230,Section 1 ) 14-Sep-21 28-Oct-21 A 08-May-23 01-May-24 100.0% 97.6% 76.7% to less deployment of equipment and 4. Security Arrangements for Critical
manpower. Work fronts.
5. Timely completion of pending /
Pace of work is very slow due to less balance works for river diversion.
DC Middle Excavation (CH230-CH640,Section 2) 09-Oct-21 04-Apr-21 A 28-Oct-22 19-Dec-23 100.0% 100.0% 88.7% 6. Resolution of security / land
resource deployment.
acquisition issues at various work fronts
including main dam sites
No progress during reporting period due to
DC D/S Excavation (D/S of CH640,Section 3) 19-Jun-21 29-Oct-21 A 08-May-22 28-Nov-23 100.0% 100.0% 38.0% congested space at D/S Area, Contractor is
working at DT#1 Outlet Slope areas.

02 RB-Diversion and Flushing Tunnel


RB Diversion Tunnels 2

Excavation (Heading) 100.0% 100.0%


14-Jul-21 12-Jul-21 A 02-Jul-22 28-Jan-23 A 100.0%
Excavation (Benching) 100.0% 100.0%

Concrete Lining 14-Jan-22 17-May-22 A 24-Oct-22 28-Oct-23 A 100.0% 100.0% 100.0%

Contact Grouting 19-Sep-22 28-Jul-23 15-Oct-22 28-Nov-23 A 100.0% 100.0% 100.0%

Consolidation Grouting 19-Sep-22 28-Jul-23 15-Oct-22 28-Nov-23 A 100.0% 100.0% 100.0%


Accumulative Progress Up to Reporting
Commencement Date Finish Date
Week

Sr # Critical Activities Revised Plan Remarks/Reasons of Delay Bottlenecks


Anticipated/
BL Planned Actual/Anticipated BL Planned Planned (as per Modified Actual
Revised
Diversion Scheme)

RB Intake Structure

DT Intake Excavation 19-Mar-21 05-Mar-21 A 23-Sep-22 28-Jan-23 A 100.0% 100.0% 100.0%

Contractor's progress is gradually improving,


Concrete-DT No. 2 Intake 20-Mar-22 21-Dec-22 17-Sep-22 18-Aug-23 100.0% 100.0% 80.0% Contractor has been advised to catch up the
progress at site to avoid any further delays.

No progress during reporting period,


Installation Work 28-Jun-23 31-Aug-23 100.0% 100.0% 65.0% Installation of Gates & 2nd stage Embedded
Parts upto 971 Elv. completed

RB Outlet Structure

Excavation 01-Mar-21 15-Mar-21 A 06-Sep-21 28-Jan-23 A 100.0% 100.0% 100.0%

No progress during reporting period, work


Concrete-DT No. 2 Outlet 24-Feb-22 02-Apr-23 08-Oct-22 30-Aug-23 100.0% 100.0% 73.0% impacted due to Contractor's poor site
planning.

No progress during reporting period,


Installation Work 21-Jun-23 31-Aug-23 100.0% 100.0% 59.0% Installation of Gates & 2nd stage Embedded
Parts is in progress

U/S Coffer Dam 18-Nov-22 18-Oct-22 A 29-Apr-23 16-Apr-24 100.0% 66.7% 59.0% Drilling works for Phase-II are in progress

Drilling at remaining portion of Phase-I is in


D/s Coffer Dam 18-Nov-22 02-Nov-22 A 29-Apr-23 16-Apr-24 100.0% 79.8% 66.8%
progress.
03 Dam

Earth and Rock Works

Slow progress due to non-deployment of


Left Bank (LB5#-15#,Section 1) 24-Mar-21 24-May-21 A 01-Aug-23 29-Jul-24 100.0% 71.8% 30.2%
required resources and limited workfronts.

Dam Pit (16#-21#,Section 2) 11-Mar-23 12-Mar-24 11-Aug-23 31-Dec-24


100.0% 33.4% 39.8% No progress during reporting period.
Dam Pit (22#-24#,Section 3) 02-Apr-22 01-May-21 A 05-Jul-23 25-Jul-24

No progress during reporting period due to


re-profiling area of Dam Right Abutment due
Right Bank (RB 25#-36#,Section 4) 19-Mar-21 20-Mar-21 A 02-Aug-22 03-Jan-24 100.0% 99.9% 56.6%
to Contractor's poor site planning and
execution.