K2 Data Centre Daily Report - 2024.01.08
K2 Data Centre Daily Report - 2024.01.08
Table Legend:
Bondek
Area (m2):
2264/3002 (75%)
DAILY SITE PROGRESS REPORT
Bondek Installation (Upper Roof)
Table Legend:
Bondek
Area (m2):
847/1410 (80%)
DAILY SITE PROGRESS REPORT
Bondek Installation (Lower Roof)
Table Legend:
Bondek
Area (m2):
0/1592 (0%)
DAILY SITE PROGRESS REPORT
Ground Floor Slab Progress Layout
Table Legend:
Concreted
Zone 1
BRC laying
Concreted area (m2):
3002/3002 (100%)
Zone 2
SCHEDULE PLAN
16/12/23 22/12/23
Zone 3
Zone 4
DAILY SITE PROGRESS REPORT
First Floor Slab Progress Layout
Table Legend:
Concreted
BRC laying
Zone 1
Concreted area (m2):
827/3002 (28%)
Zone 2 SCHEDULE PLAN
21/12/23 08/01/24
Zone 3
Zone 4
DAILY SITE PROGRESS REPORT
Upper Roof Slab Progress Layout
Table Legend:
Concreted
BRC laying
Concreted area (m2):
956/1410 (68%)
Zone 2
DAILY SITE PROGRESS REPORT
Lower Roof Slab Progress Layout
Table Legend:
Concreted
BRC laying
Concreted area (m2):
Zone 3
0/1592 (0%)
SCHEDULE PLAN
25/12/23 10/01/24
Zone 4
DAILY SITE PROGRESS REPORT
Steel Structure Layout (Upper Roof Floor)
Table Legend:
Steel Column
I-Beam
Beam: 85/97 (88%)
Note:
12 members highlighted
(red) is to be installed after
overhead crane installed
DAILY SITE PROGRESS REPORT
Steel Structure Progress
PLAN VS PLAN VS
PLAN QTY ACTUAL QTY PLAN QTY ACTUAL QTY
DATE CUMULATIVE ACTUAL / DATE CUMULATIVE ACTUAL /
/NOS /NOS /NOS /NOS
NOS NOS
27/10/23 17 14 -3 -3 7/11/23 18 0 -53 -53
28/10/23 17 15 -20 -5 8/11/23 18 0 -71 -71
29/10/23 17 13 -22 -9 9/11/23 18 0 -89 -89
30/10/23 17 10 -26 -16 10/11/23 18 0 -107 -107
31/10/23 17 12 -33 -21 11/11/23 18 9 -125 -116
1/11/23 17 15 -38 -23 12/11/23 18 11 -134 -123
2/11/23 17 18 -40 -22 13/11/23 19 28 -142 -114
3/11/23 17 15 -39 -24 14/11/23 19 12 -133 -121
4/11/23 17 15 -41 -26 15/11/23 19 28 -140 -112
5/11/23 17 3 -43 -40 16/11/23 19 8 -131 -123
6/11/23 17 22 -57 -35 17/11/23 19 22 -142 -120
DAILY SITE PROGRESS REPORT
Steel Structure Progress
PLAN QTY ACTUAL QTY PLAN VS ACTUAL PLAN QTY ACTUAL QTY PLAN VS ACTUAL
DATE DATE
/VOL /VOL / VOL /VOL /VOL / VOL
17/10/23 0 0 0 30/10/23 14 0 -104
18/10/23 0 0 0 31/11/23 90 0 -194
19/10/23 0 0 0 1/11/23 0 0 -194
20/10/23 90 0 -90 2/11/23 20 90 -124
21/10/23 0 0 -90 3/11/23 30 0 -154
22/10/23 0 0 -90 4/11/23 0 90 -65
23/10/23 0 0 -90 5/11/23 30 0 -95
24/10/23 0 90 0 6/11/23 0 0 -95
25/10/23 30 0 -30 7/11/23 0 30 -64
26/10/23 0 0 -30 8/11/23 14 0 -78
27/10/23 0 0 -30 9/11/23 3 30 -51
28/10/23 0 0 -30 10/11/23 14 0 -65
29/10/23 90 30 -90 11/11/23 20 0 -85
DAILY SITE PROGRESS REPORT
Blast wall Progress
PLAN QTY ACTUAL QTY PLAN VS ACTUAL PLAN QTY ACTUAL QTY PLAN VS ACTUAL
DATE DATE
/VOL /VOL / VOL /VOL /VOL / VOL
12/11/23 11 0 -96 25/11/23 23 0 -420
13/11/23 20 0 -116 26/11/23 20 0 -440
14/11/23 0 0 -116 27/11/23 0 0 -440
15/11/23 110 0 -226 28/11/23 40 0 -480
16/11/23 0 0 -226 29/11/23 30 90 -420
17/11/23 0 0 -226 30/11/23 0 0 -420
18/11/23 3 0 -229 1/12/23 93 0 -513
19/11/23 0 0 -229 2/12/23 0 0 -513
20/11/23 33 0 -262 3/12/23 3 0 -516
21/11/23 11 0 -273 4/12/23 26 0 -542
22/11/23 3 0 -276 5/12/23 3 0 -545
23/11/23 11 0 -287 6/12/23 39 0 -584
24/11/23 110 0 -397 7/12/23 40 0 -624
DAILY SITE PROGRESS REPORT
Blast wall Progress
PLAN QTY ACTUAL QTY PLAN VS ACTUAL PLAN QTY ACTUAL QTY PLAN VS ACTUAL
DATE DATE
/VOL /VOL / VOL /VOL /VOL / VOL
8/12/23 11 0 -635 21/12/23 26 0 -808
9/12/23 20 0 -655 22/12/23 0 0 -808
10/12/23 0 0 -655 23/12/23 0 0 -808
11/12/23 124 0 -779 24/12/23 51 0 -859
12/12/23 0 0 -779 25/12/23 0 0 -859
13/12/23 3 0 -782 26/12/23 0 0 -859
14/12/23 23 0 -805 27/12/23 23 120 -762
15/12/23 3 0 -808 28/12/23 0 0 -762
16/12/23 30 0 -838 29/12/23 90 0 -852
17/12/23 11 0 -849 30/12/23 12 90 -751
18/12/23 3 0 -852 31/12/23 3 0 -754
19/12/23 0 90 -762 1/1/24 0 0 -754
20/12/23 20 0 -782 2/1/24 20 30 -744
DAILY SITE PROGRESS REPORT
Blast wall Progress
PLAN QTY ACTUAL QTY PLAN VS ACTUAL PLAN QTY ACTUAL QTY PLAN VS ACTUAL
DATE DATE
/VOL /VOL / VOL /VOL /VOL / VOL
3/1/24 44 0 -788 16/1/24 9
4/1/24 0 0 -788 17/1/24 0
5/1/24 0 30 -758 18/1/24 3
6/1/24 29 0 -816 19/1/24 20
7/1/24 0 0 -816 20/1/24 0
8/1/24 17 0 -833 21/1/24 11
9/1/24 20 22/1/24 0
10/1/24 0 23/1/24 0
11/1/24 20 24/1/24 20
12/1/24 0 25/1/24 3
13/1/24 3 26/1/24 0
14/1/24 0 27/1/24 0
15/1/24 3 28/1/24 0
DAILY SITE PROGRESS REPORT
Blast wall Progress
PLAN QTY ACTUAL QTY PLAN VS ACTUAL PLAN QTY ACTUAL QTY PLAN VS ACTUAL
DATE DATE
/VOL /VOL / VOL /VOL /VOL / VOL
29/1/24 0 6/2/24 20
30/1/24 0 7/2/24 0
31/1/24 3 8/2/24 0
1/2/24 0 9/2/24 0
2/2/24 0 10/2/24 0
3/2/24 9 11/2/24 0
4/2/24 0 12/2/24 3
5/2/24 0
TOTAL: -1,784m3 810m3 -974m3
DAILY SITE PROGRESS REPORT
Brick Wall Progress
Progress:
Cable trench
BW 1-1 BW 2-1 installation:
(147m/326m)
45.09%
BW 1-2 BW 2-2
BW 1-3 BW 2-3
BW 1-4 BW 2-4
DAILY SITE PROGRESS REPORT
Copper Tape Installation (Ground Floor Layout)
TABLE LEGEND:
Copper tape installed
DAILY SITE PROGRESS REPORT
Copper Tape Installation (First Floor Layout)
TABLE LEGEND:
Copper tape installed
DAILY SITE PROGRESS REPORT
Daily Planning (09/01/2024)
4
Bird View 1
Bird View 2
Bird View 3
Bird View 4
• PROGRESS PHOTO