Introduction To Dams
Introduction To Dams
(1-2)
Syllabus Topic:Different terms Related to Dams
Syllabus Topic:Introduction
(New Syllabus w.e.f academic year 22-23) (P8-70) aTech-Neo Publications...A SACHIN SHAH.Venture
Dams and Hydraulic Structure (SPPU-Sem 8-Civil) (Introduction to Dams)..Page no. (1-4)
Uses of Coffer Dam Various dams are classified based on the materials used
for their construction.
(i) Coffer dams are temporarily constructed for the
Following are the various types of dams based on
construction of projects like, bridge piers and materials.
abutments, dams or locks, etc.
() Concrete dam
(iü) It provides safe environment to work.
Material used for such dam is concrete.
(iüi) Material of coffer dam can be typically reused on
other construction project. Note: Gravity dams, arch dams and butters dams are
classified as concrete dams.
(iv) Steel sheet piles can be easily installed and
removed. (iü) Masonry dam
(üü) Debris dams Materials used for such dam are stone rubbles, bricks
etc.
These type of dams are being constructed to avoid the
flow of debris such as sand, gravel, drift wood along (iii) Timber dam
with rain water in the river and such way water
Material used for such dam is wood.
becomes relatively clear and clean after passing over
the debris dam. (iv) Steel dam
These type of dams is relatively having of low height. (v) Earth dam
the water of
It is specially constructed so as to divert Material used for such dam is clay or earth.
the river into an off-taking canal or conduit.
(vi) Rock fill dam
(v) Detention dams
constructed in case of Material used for such danm is rock fill.
These type of dams are being control the floods.
excessive flood and thus such dams (vii) Composite dam
Classification of dams based on
Material Material used for such dam is rock fill and earth
2.
Classification of dams fill.
under
based on material Earth dam as well as rock fill dam comes
the type of embankment dam.
(i) Concrete dam Concret dam
1. Concrete gravity dam Concrete dam are basically classified into two types :
1. Concrete gravity dam
dam
2. Concrete buttress Concrete gravity dam is a rigid type of dam in which
the external forces like water pressure, wave pressure,
(ü) Masonry dam
silt pressure, uplift pressure are resisted by the weight
(iiü) Timber dam of the dam itself.
All major and important gravity dams are constructed
in concrete. Concrete gravity dam can be straight 0r
(iv) Steel dam
curved in plan.
(v) Earth
2. Concrete buttress dam
(vi) Rock fill o
This type of dam consists of a number of piers
into a
(vii) Composite darm buttress dividing the space to be dammed
number of spans.
based on material
Fig. C1.3: Types of dams
SHAHVenture
22-23) (P8-70) Tech-Neo Publications...A SACHIN
(New Syllabus w.e.f academic year
Dams and Hydraulic Structure (SPPU-Sem 8-Civil)
(Introduction to Dams).Page no. (1-5)
Panels are constructed of horizontal arches or flat slabs
Types of dams based on Structural action
So as to hold up and retain the water
between
buttresses. These type of dam are classified into various types
based on the structural action.
ODefinition : If panels consists of concrete arches, then
it is called as multiple arches buttress damn and it Types of dams based on
structural action
panels consists of flat slab, then it is called as deck
type buttress dan. () Gravity dams
3. Classification of dams based on
Action
Hydraulic (ii) Earth dams
(New Sylabus w.e.f academic year 22-23) (P8-70) Tech-Neo Publications.A SACHIN SHAH Venture
(Introduction to Dams)....Page no. (1-6)
Dams and Hydraulic Structure (SPPU-Sem 8-Civil)
does not
(v) Steel dam (ii) Steel dams are lighter and therefore it
absorb the shocks from vibrations of spilling
O Definition : The dam which consist of a steel water.
framework with a steel skin plate on its upstream face
is called as steel dam. (ii) Life of steel dam is less than concrete dams.
which is
(iv) It has to be anchored at foundation
Such dam are classified into the types : difficult.
(a) Cantilever type steel dam Earth and Rockfill dams
3.
(b) Direct strutted steel dam
Merits of earth and rockfill dams
a 1.2.1 Merits and Demerits of Various These dams can be constructed over any type of
Types of Dams available foundations.
than other
(ii) These dams are generally economical
Ua. what are the advantages and disadvantages of types.
(SPPU - April 14., 4 Marks) rapidly and
dams ? (iii) These dams can be constructed more
| UQ. State and explain the advantages of R.C.C. Dams. with unskilled labour.
(SPPU - April 15, 4 Marks)
3(iv) These dams can be constructed with
available materials.
locally
22-23) (P8-70)
(New Syllabus w.e.f academic year La Tech-Neo Publication..A SACHIN SHAH Venture
Dams and Hydraulic Structure (SPPU-Sem 8-Civil)
(Introduction to Dams)....Page no. (1-7)
Syllabus Topic : Selection of Site for Dam than shallow reservoir. It reduces the cost of land
acquisition and evaporation losses.
1.3 SELECTION OF SITE FOR DAM 11. Dam site should fulfil the various purposes like
irigation, drinking water, water for industry etc.
UQ. Briefly explain six factors considered for selecting a 12. Dam site should be easily accessible throughout the
site for dam. (SPPU - May 17 (In Sem.J. 6 Marks) year.
GQ. What factors govern selection of type of dam ? 13 The natural environment all around the dam site should
not be disturbed drastically and it should be clean and
Following are the various factors governing the hygienic.
selection of site for a dam:
1.
14. The dam site should be selected in such way that it
Suitability of type of foundation available at reasonable should have minimal cost of construction and
depth at the selected site of the proposed dam.
subsequent maintenance.
There should be suitable type of foundation 15. Dam site should be selected in such way that should
available at reasonable depth.
provide maximum benefit to the society after the
If required, the existing foundation condition can completion of dam.
be improved by suitable methods like grouting, 16. Dam site should be selected so as to have minimum
guniting etc. , rate of siltation which ensure the maximum life of the
In short, good foundation should be available at reservoir.
resonable depth.
2. The river gorge should be narrow at the selected dam 1.3.1 R.C.C Dam
site in order to obtain minimum length of the dam so
that cost of the construction will be minimal because UQ. Explain the concept of construction of R.C.C. Dams.
construction cost of dam varies directly with its length. (SPPU - May 15, 4 Marks)
Thus the river gorge should be narrow at the
selected dam site. When there is topography consisting of U-shaped
valley with very little overburden, then R.C.C gravity
3. ISite for dam should be located in a narrow valley. dam is mostly recommended.
4. The dam site should have sufficient and suitable space
R.C.C dam is a solid structure made of concrete and
available for spillway of sufficient capacity so as to steel reinforcement and constructed across the river so
pass the excess floods safe.ly over the spillway from ws as to develop the reservoir on its upstream side.
to d/s side.
5 The dam site should be located on high ground so as to R.C.C dam are strong, durable and having the
reduce the dam costs and also to facilitate easy maximum reservoir capacity. Dead load of dam is
distributed in such way that the entire section resists
drainage of the area. the pressure of water on the upstream side.
6. The dam site should have impervious bed or
R.C.Cdam can sustain the various types of loads like :
impervious strata so as to prevent seepage of water and
sides in order to reduce erosion. ) weight of the dam
7 Materials for the construction of dam should be locally () water pressure on upstream side
available so as to reduce transportation cost of (iü) wave pressure
material. (iv) uplift pressure
The dam site should be easily accessible from nearby (V) pore pressure
road or rail line for easy transportation of labour, (vi) silt pressure
technical staff and materials. (vii) wind pressure and
9 The dam site should have less (viü) earthquake pressure or seismic load.
submergence of the
valuable land and property on the upstream site. It Initial cost of construction of R.C.C dam is high but
reduces the cost of acquisition of such land. long term cost is minimum.
Submergence area should not more than 10%. The Fig. 1.3.1 shows the section of R.C.C dam
10. The quantity of water stored in the reservoir should be subjected to various types of loads or pressures.
maximum and hence deep reservoir is preferred rather
(New Sylabus w.e.f academic year 22-23) (P8-70) Tech-Neo Publications...A SACHIN SHAH Venture
(Introduction to Dams)....Page no.(1-8)
Dams and Hydraulic Structure (SPPU-Sem 8-0Civil)
Axis of dam
Impact of waves
MWL
FRL
|D Reinforced cement concrete
Inertia force
H= Hydraulic
of water due to
height Centre of gravity (G)
earthquake
Hydrostatic
pressure on
u/s side
TWL
W
-Self weight
Toe
Uplift force
Slit pressure Hydrostatic
pressure of
Heel
fail water
Uplift pressure diagram on d/s force
Base width
22-23) (P8-70)
(New Syllabus w.e.f academic year Tech-Neo Publications..A SACHIN SHAH Venture
Dams and Hydraulic Structure (SPPU-Sem 8-Civil)
(Introduction to Dams)...Page no. (1-9)
2. Selection of masonry dam 5. Selection of buttress dam
For selection of masonry gravity dam, sufficient or When there is a wide valleys having very good sound
adequate quantity of good quality of stone should be rock which resisting the higher contact stresses, then
available near the site. construction of buttress dam is more suitable to gravity
dam.
Thus, availability of good quality stone should be Volume of concrete saved in such case can be 40 to
nearby the site in case of masonry dam. 60%.
3. Selection of concrete dam 6.
Selection of embankment type of dam or
Earthen dam
Large quantity of cement, coarse aggregate and fine
aggregate and steel will have to be transported to the When there is soil foundation having low contact
site for a concrete gravity dam.
stresses, then embankment type of dam or earth fill
dam is most suitable.
It increases the transportation cost. Hence concrete Earth fill dam or earthen dam can be constructed on
gravity dam is selected for large dam. See Fig. 1.4.1 for any type of foundation.
better understanding. To construct the earth filldam, large quantities of earth
Ushaped valley with material ranging from impervious to pervious is
very litte overburden required and it should be available locally.
Impervious earth material is required to construct the
core and hearting portion.
Pervious earth material is required to construct the
Overburden casing. See Fig. 1.4.3 for better understanding,
Sound rock Very wide valley with deep overburden
(New Sylabus w.e.f academic year 22-23) (P8-70) Tech-Neo Publications...A SACHIN SHAH Venture
Dams and Hydraulic Structure (SPPU-Sem 8-Civil) (Introduction to Dams).Page no. (1-10)
Composite dam
Overburden having
varying depth