This inspection and test plan outlines the inspection process for the installation, testing, and commissioning of fire pumps. It lists 4 key activities: 1) documentation approval, 2) material inspection, 3) installation inspection, and 4) testing and commissioning. For each activity, it identifies the frequency of inspection, the applicable specifications and criteria, and the inspection roles and responsibilities of the contractor and consultant. Upon completion, both the contractor and consultant must sign-off to approve the inspection and test plan.

Uploaded by

Amie GTuned
Copyright
© © All Rights Reserved
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
262 views

ITP For Installation Testing Commissioning of Fire Pump

This inspection and test plan outlines the inspection process for the installation, testing, and commissioning of fire pumps. It lists 4 key activities: 1) documentation approval, 2) material inspection, 3) installation inspection, and 4) testing and commissioning. For each activity, it identifies the frequency of inspection, the applicable specifications and criteria, and the inspection roles and responsibilities of the contractor and consultant. Upon completion, both the contractor and consultant must sign-off to approve the inspection and test plan.

Uploaded by

Amie GTuned
Copyright
© © All Rights Reserved
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
You are on page 1/ 1

INSPECTION & TEST PLAN

REF. NO.

VANTAGE KUL14 REV. NO. 00


DATE :
PAGE : 1 OF 1

ACTIVITY: INSTALLATION, TESTTING & COMMISSIONING OF FIRE PUMPS

AREA/LOCATION:

ITP approved by CONTRACTOR's QA/QC: ITP approved by consultant:


Signature: Signature:
Date: Date:
INSPECTION LEVEL
SERIAL NO. DESCRIPTION FREQUENCY SPECIFICATION/CRITERIA VERIFICATION RECORD
ITL CONTRACTOR consultant

1 DOCUMENTATION

Once (Approval prior


1.1 Material Approval
to start of activity)
Specifications. -- H H

1.2 Shop Drawing Approval Each Shop Drawing Specifications and submittals. -- H H

Once (Approval prior


1.3 Method Statement Approval
to start of activity)
Specifications and submittals. -- H H

2 MATERIAL INSPECTION

2.1 Check the Material as per approved submittal. Each Delivery Specifications and submittals. -- H H

3 INSTALLATION INSPECTION

Area Wise or As
Check the installation as per approved drawing. Check the physical
3.1
Installation of equipment.
instructed by Specifications and submittals. -- H H
consultant.

As instructed by
4 TESTING & COMMISSIONING
consultant.
Specifications and submittals. -- H W H W

LEGEND: H: HOLD W: WITNESS S: SURVEILLANCE R: REVIEW