Le 2007
Le 2007
H.T. Le and S. Santoso are with the Department of Electrical and Computer
Engineering, The University of Texas, Austin, TX 78712.
treated as a combination, making the solution comprehensive. Case study 1: Voltage Stability analysis of the wind farm
Therefore, in our research, we develop a systematic ESS- impacts on the 6-bus power system
based solution Case study 2: Determination of maximum-possible wind
power penetration level(s)
for improving wind power integration in connection with the Case study 3: Application of an energy storage system for
grid voltage stability. improving wind power integration
Case study 1 aims at identifying and quantifying the wind
II. APPROACH, OBJECTIVES AND IMPLEMENTATION OUTLINES farm impacts on system voltage stability. The results help
clarify and justify the need for installing an ESS. Case study 2
A. General approach determines how much wind power could be integrated to
As mentioned above, our ESS-based solution is developed maintain an acceptable voltage stability condition for the
and evaluated while taking into account the voltage stability system. The information obtained in the first two case studies
characteristics of the power system of interest. We start with is used to determine the size and develop ESS charge-
evaluation of the grid stability condition under the impacts of discharge scheme. Finally, the operation and the
a large wind farm and determination of acceptable wind effectiveness of the ESS are investigated in Case study 3.
power penetration levels for the system. The information
obtained is used in the design and operation of the ESS. III. STUDY ENVIRONMENT AND GENERAL CONDITIONS
Finally, the ESS operation and effectiveness are evaluated
with respect to the amount of integrated wind power and the A. Description of the 6-bus power system
system voltage stability. In this way, the solution comprises The 6-bus power system (Fig. 1) is a strong network with
three steps: (i) Quantification of wind farm impacts on grid two generators which supply power to the loads through three
voltage stability, (ii) Determination of acceptable wind power 138-kV lines. The total line length is 125 km and total load is
penetration levels, and (iii) Using ESS to facilitate wind 203.7 MW and 82.1 MVAR (219.6 MVA). The total
power integration. generation capacity is 270 MVA. The difference between the
Both static and dynamic voltage stability analyses will be total generation and total load (i.e. the spinning reserve) is
used for the solution development. The analyses are initially 18.7%. Generator Swing1 represents a stiff supply grid with
carried out on a small 6-bus power system, then on a realistic the sending end voltage (V1) maintained at 1.0∠00 pu. The
transmission system. In this paper, we present the operational real power output of generator Gen6 is 43 MW
development and evaluation of the three-step solution by and the reactive power limits are ±25 MVAR. The operational
static voltage stability analyses of the small power system. In voltage at Bus 6 is set to be 1.0 pu. No transformer taps are
the next research phases, the solution is refined using steady- set to raise the secondary-side voltages. The system major
state (or static) and dynamic analyses of the real-world load (Load 3) is connected to the main power source (i.e.
transmission system. The 6-bus system is custom-designed Swing1) via a short and strong line (Line 23) which has small
based on the real-world transmission system in such a way so impedance. Load 4 is located near Gen6 which feeds it. Load
that its major properties are analogous to those of the real- 5 is connected at Bus 5 and is fed through a relatively-weak
world system. Therefore, despite its modest size, the 6-bus and long line. This line has significantly higher impedance
system is also realistic and can be used to provide insights to with the length more than twice that of Line 23 and Line 34
actual conditions. The main advantage of using this simple combined. When there is no wind farm or ESS operational,
system is that the system voltage stability characteristics can the system is in normal operation condition with the voltage
be determined analytically (i.e. using by-hand solutions). profile within +/-5% limits (i.e. within the range of
B. Objectives 95%÷105% of the nominal values). This condition is used as
the base case (called Base case 1) for comparison purposes.
The objectives of this paper’s study are:
When the wind farm and/or ESS are concerned, they are
(i) To evaluate voltage stability impacts of a large wind
connected at Bus 5.
farm (140 MW) on the 6-bus power system. The
system real power loss is used as additional
information of the wind farm impacts.
(ii) To determine maximum-possible penetration level(s) of
wind power for the 6-bus system
(iii) To investigate the possibility of using an energy storage
system to increase wind power integration into the 6-
bus system
Fig. 1. Schematic diagram of the 6-bus power system with a wind farm
C. Implementation outlines
Power system data
Three case studies are carried out to meet the three
Generator Swing1: 220 MVA, 18 kV, R= 0.0008713 Ω, Xd = 2 pu
objectives, specifically Generator Gen6: 50 MVA, 18 kV, R= 0.000052 Ω, Xd = 2 pu
3
Transformer TRF12: 300 MVA, 18 kV/138 kV, GY-GY, R= 0.154%, X=6.0304% output levels. For identification purpose, each of this power
Transformer TRF46: 55 MVA, 18 kV/138 kV, GY-GY, R= 0.3%, X= 10.05%
Line 23: 15 km, R=0.0409132 Ω/km, X=0.375125 Ω/km, B=4.43 microS/km level is associated with a condition called a “case”. For
Line 34: 25 km, R=0.0409132 Ω/km, X=0.375125 Ω/km, B=4.43 microS/km example, in Case 1, the wind farm outputs 5 MW, in Case 28
Line 45: 85 km, R= 0.135343 Ω/km, X= 0.483124 Ω/km, B= 3.425 microS/km
Load 3: 153.5 + j63.9 MVA, PF= 0.923 lagging
the wind farm outputs 140 MW and so on. Note that, apart
Load 4: 41.3 + j15.5 MVA, PF = 0.936 lagging from WF output level, each case has other properties such as
Load 5: 8.9 + j2.7 MVA, PF = 0.957 lagging
Wind farm: 140 MW, PF=1.0
power loss and voltage stability characteristics. Base case 1 is
used for comparison purposes.
B. Modeling of wind farm and ESS
Power loss profile
This study is concerned primarily with static voltage
The system total real power losses (or P losses) for Base
stability analyses. To serve the analyses, the wind farm and
case 1 (i.e. the network without the wind farm) and the cases
ESS are modeled as negative loads with appropriate power
with the wind farm operational are shown in Fig. 2. The wind
profiles. This means that the wind farm is operated at or very
farm first helps reduce the total P losses at its lower power
close to the unity power factor. Today, this is a requirement
production but increases the losses at higher output levels.
(i.e. grid code) and/or a common practice [21-24].
14
C. Simulation package
P loss = 12.703 MW
Power system simulation package named Neplan is used in 12
this study. This simulations package is capable of performing
static and dynamic stability analyses. Matlab is used where 10
measured from the point on the V-Q curve of interest where Fig. 2. System real power losses under various wind power generation.
∂V / ∂Q = 0 to the zero-Q line (see Fig. 3 for illustration of Q-
Compared to Base case 1, the loss reduction is achieved
reserve margin for Case 28). The Q-reserve margin chosen to
for the wind farm production range from 5 to 30 MW. The
represent the reactive power condition of the system is the
highest loss reduction is 15.8%, obtained when the wind farm
margin calculated at the weakest bus. To determine the
outputs 15 MW. Visibly, the main reason for the loss
weakest bus, a V-Q sensitivity simulation is performed on the
reduction is that the wind farm supplies power to the local
6-bus system under the condition of Base case 1. Bus 5
load (8.9 MW for Load 5), leading to the smaller power flow
exhibits the largest V-Q sensitivity, indicating that it is most
from Swing1 (see Fig. 1 for the 6-bus system component
sensitive to any changes in reactive power (either injection or
layout). With the wind farm operational, most or all feeding
absorption) in the system. Therefore, it is chosen as the
power to Load 5 does not have to go through Line 45, which
indicator of the system reactive power reserve status. For this
is a long line with high impedance (i.e. higher loss).
6-bus system, there are four eigenvalues in total. They are
However, when the wind farm power production becomes
calculated following V-Q modal analysis and are used in
high, the losses rise dramatically, up to 830.6% (12.703 MW).
parallel with the Q-reserve margin to judge the system
The obvious reason is that the wind power now goes in the
stability condition.
reverse direction to the system major load (Load 3) through
the high-loss Line 45. The power flow over Line 34 also
IV. CASE STUDY RESULTS
becomes stronger, causing additional losses on the same line.
A. Case study 1: Analysis of the wind farm voltage stability Evaluation of system voltage stability condition
impacts on the 6-bus power system We now evaluate the system voltage stability condition by
This case study aims at identifying and quantifying the comparing the system reactive reserve margins for four
wind farm impacts on system voltage stability. The results selected cases (i.e. four power output levels) with that of Base
would help clarify and justify the need for mitigation case 1 (69.36 MVAR). Fig. 3 shows that the system has more
measures (i.e. using an ESS). Q-reserve (71.64 MVAR) when the wind farm power
Setting: The 140-MW wind farm (WF) is connected at Bus production is relatively low, such as in Case 6 (WF P=30
5 (Fig. 1). Its power output is gradually increased from 5 MW MW). However, the wind farm quickly exhausts the system
to 140 MW in 5-MW increments. This results in 28 power reactive reserve as more and more of its power is pushed into
4
the system. The Q-reserve margins for Case 20, 24, and 28 are power losses and two voltage-stability criteria, namely, system
56.19 MVAR, 47.24 MVAR, and 36.54 MVAR respectively. reactive reserve margins and eigenvalues.
The Q-reserve for Case 28 is reduced by 47.4% compared to This finding is an interesting one. To date, wind farm high
that of the base case. This means that the system voltage demand for reactive power is often considered as the main
stability condition significantly deteriorates as the wind farm factor that affects the stability condition of power networks.
output becomes high. The V-Q curves are also narrower, This case study reveals that, even with full reactive
indicating that the system is more vulnerable to voltage compensation, a strong (or excessive) reverse power flow
instability. from the wind farm could also worsen the system stability
condition (by exhausting the network reactive power reserve
120
and increasing power losses).
100
80
B. Case Study 2: Determination of maximum-possible wind
Base case 1
power penetration levels
Reactive power, MVAR
60
Case 28
Case study 2 determines how much wind power should or
40 Q-reserve margin
Case 24 for Case 28 could be integrated while maintaining an acceptable voltage
20
stability condition for the system. The results are used
0 together with the results of Case study 1 in operating the ESS
-20 in Case study 3.
-40 Setting: The wind farm is connected at Bus 5 (Fig. 1). Its
-60 Case 6
power production is gradually increased from 5 MW in 5-MW
-80 Case 20 increments until the system power flow calculation fails to
40 50 60 70 80 90 100 110 120
converge (i.e. the system is close to voltage-collapse and V-Q
Bus voltage, % curve calculation cannot be performed). This means that the
wind farm output is allowed to exceed its original rating (i.e.
Fig. 3. Selected V-Q curves calculated at Bus 5
140 MW). The amount of integrated wind power (i.e.
Note: Case 6: WF P = 30 MW; Case 20: WF P=120 MW penetration level) is determined with respect to different
Case 24: WF P=140 MW; Case 28: WF P=140 MW
voltage stability conditions (i.e. limits) which are represented
TABLE I by the system Q-reserve margins and four smallest
SYSTEM EIGENVALUES FOR FOUR SELECTED CASES eigenvalues. Base case 1 is used for comparison purposes.
Note that, since the system is at peak load and peak
Base case 1 Case 6 Case 20 Case 24 Case 28
WF=0 MW WF=30 MW WF=70 MW WF=100 MW WF=140 MW generation in the base case, this is a lowest voltage stability
3.0513 3.1001 2.9092 2.1708 1.9541 condition without the wind farm (i.e. a conservative situation
13.6490 13.7142 13.5613 11.0932 10.8662 for voltage stability evaluation).
45.5067 45.6042 45.2777 42.8893 42.4347
104.6754 104.7861 104.4714 104.0193 103.5058 Results
The main results obtained for this case study are shown in
Table I shows the system eigenvalues for the above four Fig. 4 and Table II. Fig. 4 illustrates the amount of wind
selected cases. For the 6-bus system, there are four power that can be integrated into the 6-bus system versus the
eigenvalues for a system condition (i.e. Base case 1, Case 6, respective reactive reserve margin. Table II contains the
and so on). The system eigenvalues for the selected cases system eigenvalues for the conditions (i.e. different wind
confirm the findings using the V-Q curves. The eigenvalues power injection levels, or cases) illustrated in Fig. 4. It also
are improved (i.e. larger) for Case 6 where the V-Q curve shows how the eigenvalues change compared to those of Base
indicates better Q-reserve margin, meaning that the system is case 1.
more voltage-stable. All the eigenvalues for Case 20 through
Case 28 are worse than the corresponding values of Base case 200 190
160
140
respective V-Q curves. 140
120
120 110
100
Discussion for Case Study 1 100
60
its power production is relatively comparable with the local
40
load. It helps reduce real power losses and improve the
20
voltage stability condition. However, as the wind farm power 0
becomes high compared to the local power consumption, the 66.00 56.19 51.94 47.24 36.54 24.21 13.95 2.88
Q-reserve margins, MVAR
strong reverse power flow increases the losses and lowers the
system stability. This judgment is based on the system real Fig. 4. Amount of integrated wind power versus Q-reserve margin
5
The wind power injection levels shown in Fig. 4 and Table power penetration level for the 6-bus system is around 190
II correspond to the numbered cases, as following: Case 14 MW. Other lower penetration levels may also be defined in
(70 MW), Case 20 (100 MW), Case 22 (110 MW), Case 24 observance of the respective voltage stability limits, but the
(120 MW), Case 28 (140 MW), Case 32 (160 MW), Case 35 three identified penetration levels correspond to three most
(175 MW), Case 38 (190 MW). The eigenvalues for Case 20 important voltage stability conditions of the 6-bus system.
are not shown in Table II due to space limitation.
Discussion for Case study 2
The selected three voltage stability techniques (i.e. V-Q
TABLE II curve, V-Q sensitivity and V-Q modal analysis) can be used
SYSTEM EIGENVALUES FOR DIFFERENT WIND POWER INJECTION LEVELS effectively to determine different penetration levels of wind
power for a power network.
System eigenvalues, MVAR/% For the 6-bus system, three most important penetration
Base levels are identified. Penetration level 1 is 70 MW of wind
case 1 Case 14 Case 22 Case 24 Case 28 Case 32 Case 35 Case 38
1 2 3 4 5 6 7 8
power, or 34.36 % of the system demand. At this penetration
3.0513 3.0427 2.2553 2.1708 1.9541 1.6439 1.2952 0.6330 level, the static voltage stability condition of the original
13.6490 13.6790 11.1799 11.0932 10.8662 10.5378 10.1725 9.5072 system is maintained. At Penetration level 2 (110 MW, or
45.5067 45.5123 43.0661 42.8893 42.4347 41.7903 41.0862 39.8321 54%), the system stability condition is reduced by around
104.675 104.703 104.22 104.019 103.506 102.784 102.004 100.636
25%, but its normal operation is still possible. Penetration
Change in system eigenvalues compared to Base case 1, %
level 3 (MW, or 93.27%) corresponds to a lowest stability
Base
case 1 Case 14 Case 22 Case 24 Case 28 Case 32 Case 35 Case 38 condition of the system. Beyond this limit, the system enters
9 10 11 12 13 14 15 16 voltage-unstable region that could lead to voltage collapse.
0.00 -0.28 -26.09 -28.86 -35.96 -46.12 -57.55 -79.25 The knowledge of these limits (i.e. penetration levels) is
0.00 0.22 -18.09 -18.73 -20.39 -22.79 -25.47 -30.35
useful since they indicate the boundaries for the system safe
0.00 0.01 -5.36 -5.75 -6.75 -8.17 -9.71 -12.47
0.00 0.03 -0.44 -0.63 -1.12 -1.81 -2.55 -3.86
operation. As shown in Case study 3, the limits help
Note: For Column 10-16, plus sign (+) = increase and minus (−) = decrease
determine a reference point for efficient operation of the
energy storage system.
The analysis of all the obtained results reveals three major
C. Case Study 3: Application of an energy storage system for
wind power penetration levels with respect to three critical
improving wind power integration
voltage stability limits for the 6-bus system, as following.
Penetration level 1: 70 MW of wind power, or 34.36 % of In this case study, the operation and the effectiveness of
the system demand (based on the total real power demand of the ESS are investigated.
203.7 MW). The voltage stability condition (i.e. Case 14) is Setting: The wind farm is connected to Bus 5 (Fig. 1). Its
essentially the same as that of the original system (i.e. Base power production for 8 hours is shown in Fig. 5 and Column 2
case 1). The Q-reserve margin is 66 MVAR (Fig. 4), which is of Table III. An energy storage system (ESS), modeled as a
less than that of Base case 1 (69.36 MVAR) by just 4.85%. negative load, is connected at the same bus as the wind farm.
The system eigenvalues are close to those of Base case 1 The storage system is controlled to store and release wind
(Column 1, 2 and 10, Table II). energy according to the schemes developed in Table III where
Penetration level 2: 110 MW, or 54% of the system Column 3 is the charge and Column 4 is the discharge
demand. The voltage stability limit is reduced by around 25% scheme. Base case 1 is used for comparison purposes.
compared to that of the original system (i.e. Base case 1). The Assumptions: (a) It is assumed that the 6-bus system
figure of 25% is based on the fact that the system Q-reserve demand (i.e. total load) and the matching generation stay at
margin for Case 22 (51.94 MVAR, Fig. 4) is reduced by their peaks (i.e. the condition in Base case 1) for the
25.12% and the system smallest eigenvalue is decreased by considered 8 hours. This is a conservative scenario for voltage
26.09% (Column 11, Table II). However, the system normal stability evaluation since the system stability is at a lowest
operation is still possible with the voltage profile within +/- level under the peak-load condition. (b) For each hour of
5% limits. There is no line or generator overload. consideration, the wind farm power output is unchanged. In
Penetration level 3: 190 MW, or 93.27% of the system practice, a wind farm power output changes every minute or
demand. The system reactive reserve is almost exhausted even every second. In this case study, hourly-averaged wind
(2.88 MVAR, Fig. 4) and the eigenvalues are reduced by up to power production is considered. (c) Wind power forecast is
79.25% compared to those of Base case 1 (Column 16, Table 100-percent correct i.e. the power production for any hour is
II). A penetration level higher than this causes the system to predicted with 100-percent accuracy. In practice, wind power
become voltage-unstable and can lead to voltage collapse. forecast inaccuracy may range from 15% to 50%. In the next
Simulation shows that, when the wind farm power is increased research phases, the accuracy of less than 100% will be
to 194 MW, the system power flow fails to converge. considered. (d) The ESS capacity is sufficiently large to store
Calculation of V-Q curve is impossible because V-Q all wind energy as desired. For each hour of consideration, the
sensitivity is too large. This means that the maximum wind ESS charging rate is fast enough to store all surplus energy
6
during that 1-hour period. power to the system at all times. Certainly, if the wind farm
power production is low, an output of less than 60 MW is
Selection of charge-discharge reference point for ESS
acceptable since the amount does not affect the voltage
The reference point is essential for the ESS operation since
stability condition of the original system.
it indicates when the ESS is to start to store wind power or to
release it. In case a control system for the ESS is modeled Calculation of power charge-discharge profiles for ESS
explicitly (likely in dynamic simulation), this point would be a Given the wind farm 8-hour power profile and the
reference point for the control system. reference point of 60 MW, it is possible to calculate the
It is not straightforward to set this reference point. If it is amount of wind power that should be stored in the ESS and
too low and the wind farm power output is high, a large the amount that the ESS should release during each hour. The
amount of wind power would have to be diverted into the result is shown in Table III. Column 3 shows the amount of
ESS. This means that the ESS size would have to be very wind power to be stored in the ESS for every hour while
large (i.e. higher ESS capital cost). In addition, less wind Column 4 indicates the hourly power that the ESS should
power is channeled into the power system in this situation. If discharge. Column 5 shows the cumulative power in the ESS
the reference is too high, the system stability may be affected i.e. the energy available in the ESS during each hour. The
because of the excessive wind power flow. In [16, 17] the combined hourly power output from the wind farm and the
wind power plant power output of 0.9 pu is the control storage system is calculated and shown in Column 6.
objective. In [19] the real power reference is chosen to be the
TABLE III
wind farm average real power. This study uses a grid-based
CALCULATION OF POWER CHARGE-DISCHARGE PROFILE FOR ESS
approach. It selects the reference point based on the overall Cumulative Combined
voltage stability status of the power network. The core idea is Time WF Power ESS energy in output of
that the reference is chosen so as to meet two criteria Interval, power, to ESS, output, ESS, WF & ESS,
hour MW MW MW MWh MW
simultaneously: (i) to maintain the network voltage stability
1 2 3 4 5 6
and (ii) to channel a maximum-possible amount of wind
1 75 15 0 15 60
power into the system. 2 105 45 0 60 60
3 70 10 0 70 60
120 4 15 0 45 25 60
110
105 5 110 50 0 75 60
100 6 45 0 15 60 60
Wind farm power, MW
7 25 0 35 25 60
80 75
70 8 35 0 25 0 60
60 60 60 60 60 60 60 60
60
45 The wind farm power profile and the calculated charge-
40 35 discharge profile for the ESS are based on the above
25
15
simplified conditions (i.e. the assumptions). They are
20
sufficient for this pilot investigation of the ESS-based solution
0 viability and effectiveness. In the next studies, more realistic
1 2 3 4 5 6 7 8 conditions will be considered, such as different wind farm
Time interval, hour
power output profiles, ESS charging rate, and/or size.
Fig. 5. Uncontrolled WF output and target power profile for 8 hours
Results
Note: Fig. 5 shows the uncontrolled 140-MW wind farm power The main simulation results are plotted in Fig. 6 and Fig. 7.
production for 8 hours (i.e. without the ESS) and the desired power Without the ESS, the results show that the system voltage
profile (i.e. with the ESS). The set of dark-filled bars is the wind farm
power profile and the set of stripe-bars is the target power profile. stability condition varies dramatically as the wind farm power
production goes up and down. At times the system Q-reserve
The results of Case study 1 and Case study 2 (Section A margin is improved by around 3% while at other times the
and B) show that channeling around 70 MW of wind power margin drops by up to 25.13% (Fig. 6, Time interval 5). The
(i.e. 34.36 % of the system demand, or Penetration level 1) system eigenvalues confirm this situation. The smallest
into the 6-bus system could maintain the original stability eigenvalue is reduced by up to 26.09% (Fig. 7, Time interval
condition (i.e. Base case 1). Therefore, to be more 5) as the wind farm outputs up to 110 MW into the system.
conservative, the reference point of 60 MW is chosen for the Operation of the 6-bus system under this condition is clearly
ESS. For example, if the wind farm outputs 75 MW, 60 MW undesirable since the stability condition is deteriorated
is allowed to go freely into the grid and 15 MW is diverted to significantly every time the wind power flow becomes high
the ESS for storing. In the opposite situation, if the wind farm (e.g. 105 MW at Time interval 2, 110 MW at Time interval 5).
outputs less than 60 MW, say 50 MW, the ESS releases 10 With the ESS operational, a steady wind power flow of 60
MW (provided the power is available in the storage) to the MW is maintained for the entire 8-hour period. The system
system. The final goal is to ensure around 60 MW of wind reactive reserve margin stays close to that of Base case 1 with
7
a slight decrease of 1.54% (Fig. 6). On the other hand, the voltage stability condition slightly. One more advantage of the
system eigenvalues are improved (Fig. 7). This means that the ESS is that it increases the system spinning reserve, thanks to
ESS helps increase the voltage stability limit for the 6-bus the energy available in the storage at certain times. For
system. All the wind power produced by the wind farm is instance, at the 5th hour, the stored energy (i.e. not yet
integrated into the system. released) in the ESS is 75 MWh (Column 5, Table 4.7). This
For the 8-hour period, the ESS releases a total amount of means that, during this hour, the original system spinning
120 MW of wind power (sum of Column 4, Table III). reserve (50.4 MVA, or 18.7%) becomes 125.4 MVA, or
Without the ESS, either this amount of wind power has to be 46.4%. Larger spinning reserve implies better voltage stability
thrown away, or be integrated into the system at the cost of since the system has more power to support voltage and
lowering stability. The maximum amount of energy that the frequency during the time interval.
ESS has to carry is 75 MWh (during the 5th hour, Column 5, By using static analyses, some useful additional
Table III). This means that the ESS would need to be sized at information is also obtained. It includes the total energy
around 75 MWh to meet the storage requirement for the 8 released by the ESS during the 8-hour period and the
hours of interest. This could be an economic size given the maximum energy that the ESS is to carry during an hour-time.
ESS total energy release of 120-MW during the same period. This information may be used to determine an appropriate
The wind farm capacity is 140 MW, so the ESS size is about size for the ESS and in ESS economic analyses.
half of the wind farm rating.
V. CONCLUSION
10
In this paper, a three-step solution using an energy storage
5 Base case 1
system for improving wind power integration is developed. Its
effectiveness is evaluated on a small 6-bus non-radial power
Change in Q-reserve margin, %
0
system that hosts a large 140-MW wind farm. The goal is to
-5
With ESS
integrate a maximum-possible amount of wind power into the
system without compromising the system voltage stability.
-10
The results obtained from the three case studies show that
-15 goal has been achieved and the solution is effective. The
Without ESS
-20
solution will be refined using static and dynamic analyses of a
realistic transmission system and the results will be reported
-25
in the future.
-30
1 2 3 4 5 6 7 8
Time interval, hour VI. REFERENCES
Fig. 6. Change in Q-reserve margin with and without ESS
[1] GWEC, "GWEC Global Wind 2005 Report," Global Wind Energy
10 Council, http://www.gwec.net/fileadmin/documents/Publications/GWEC-
Global_Wind_05_Report_low_res_01.pdf, current 25 Sept 2005.
5 With ESS [2] AWEA, "Wind power outlook 2006," American Wind Energy
Association, http://www.awea.org/pubs/documents/Outlook_2006.pdf,
Change in smallest eigenvalue, %
VII.