Pekerjaan : Install bekisting precast slab Pekerjaan : Install bekisting precast balok
Pekerjaan : Uji kuat tekan beton precast umur 7 hari Pekerjaan : Uji kuat tekan beton precast umur 7 hari
LAPORAN HARIAN
SUPERVISI PROYEK PEMBANGUNAN JETTY PT. INDONESIA
Project / (Proyek)
PLANTATION SYNERGY Day of / (Hari Ke -) 138
Location / (Lokasi) SANGKULIRANG, KAB. KUTAI TIMUR, KALIMANTAN TIMUR Time Left / (Sisa Waktu) 227 days / (hari)
Owner / (Pemilik) PT. PERINDUSTRIAN SAWIT SYNERGY Month / (Bulan) March / (Maret )
Consultant / (Konsultan) PT. ATRYA TEKNIKA KONSULINDO Day / (Hari) Mon Tue Wed Thu Fri Sat Sun
Contractor / (Kontraktor) PT. BUDI BAKTI PRIMA (Senin) (Selasa) (Rabu) (Kamis) (Jumat) (Sabtu) (Minggu)
Duration / (Masa Pelaksanaan) 365 days / (hari) Date / (Tanggal) 1
SUMMARY OF CONTRACTOR SITE WORK / (KEGIATAN KONTRAKTOR DI LOKASI PEKERJAAN) WEATHER CONDITION / (KONDISI CUACA)
CHECK / CHECK / TIME / Heavy High
LIST OF WORK / (DAFTAR PEKERJAAN) LIST OF WORK / (DAFTAR PEKERJAAN) Clear High Wave
(Cek) (Cek) (Jam) Rain Tide
I. GENERAL V. BERTH D 08 - 09 0 0
1 Mobilization & Demobilization - A. MOORING DOLPHIN 1 09 - 10 0 0
2 Engineering/Documentation/As Built Dwgs/Survey/Material Test √ 1 Piling Works - 10 - 11 0 0
3 Lighting and Safety - 2 Reinforce Concrete K.430 (In Situ) - 12 - 13 mid break / (istirahat)
4 Temporary Facilities √ 3 Steel Work - 13 - 14 0 0
5 APD/HSE √ 4 Appurtenance - 14 - 15 0 0
6 PDA Test - B. BREASTING DOLPHIN 1,2,3 15 - 16 1 0
II. CAUSEWAY 1 Piling Works - 16 - 17 1 0
1 Revetment, Batu - 2 Reinforce Concrete K.430 (In Situ) - Total
2.00 - - -
III. BERTH B 3 Steel Work - Time
A. MOORING DOLPHIN 1,2 - 4 Appurtenance - Loss
1 Piling Works - C. CATWALK Time
2 Reinforce Concrete K.430 (In Situ) - 1 Piling Works - % Loss
3 Steel Work - 2 Reinforce Concrete K.430 (In Situ) - Time
4 Appurtenance - 3 Catwalk Structure -
MAN POWER - LABOUR / (Tenaga Kerja)
B. BREASTING DOLPHIN 1,2,3 VI TRESTLE 360m x (7.5m- 11.5m)
1 Piling Works - 1 Piling Works -
Position / (Posisi) Amount / (Jumlah)
2 Reinforce Concrete K.430 (In Situ) - 2 Reinforce Concrete K.430 (In Situ) -
3 Steel Work - 3 Reinforce Concrete K.430 (Precast) A. Main Contractor
4 Appurtenance - 4 P/T Girder L = 20m - 1. Project Manager 1 Org
C. CATWALK 5 Trestle Protector - 2. Site Manager 1 Org
1 Piling Works - 6 Other Work - 3. Site Engineer 2 Org
2 Reinforce Concrete K.430 (In Situ) - VII Berth E (171 m x 26 m) 4. Quality Control 1 Org
3 Catwalk Structure - A. PLATFORM - 5. HSE Manager 1 Org
IV. BERTH C 72.500 x 20.00 m 1 Piling Works - 6. HSE Officer 1 Org
A. PLATFORM 2 Reinforce Concrete K.430 (In Situ) - 7. Supervisor 3 Org
1 Piling Works - 3 Reinforce Concrete K.430 (Precast) - 8. Surveyor 4 Org
2 Reinforce Concrete K.430 (In Situ) - 4 Steel Work - 9. Ass. Quality Control 1 Org
3 Reinforce Concrete K.430 (Precast) - 5 Appurtenance - 10. Ass. Surveyor 2 Org
4 Appurtenance - B. MOORING DOLPHIN 11. Logistik 2 Org
B. MOORING DOLPHIN (MD.1 & MD.2) 1 Piling Works - 12. Safety Officer 2 Org
1 Piling Works - 2 Reinforce Concrete K.430 (In Situ) - 13. Operator B.Plant 1 Org
2 Reinforce Concrete K.430 (In Situ) - 3 Steel Work - 14. Operator Exca 2 Org
3 Appurtenance - 4 Appurtenance - 15. Driver 4 Org
4 Steel Work - C. CATWALK - 16. Welder 8 Org
1 Piling Works - 17. Asst Batching Plant 2 Org
2 Reinforce Concrete K.430 (In Situ) - 18. Admin 1 Org
3 Catwalk Structure - 19. Accounting/ Finance 2 Org
DESCRIPTION OF ACTIVITIES / (Uraian Kegiatan) 20. Electrical 1 org
21. Mekanik inspeksi 1 org
21. Alken 1 org
1. Test beton umur 7 hari 22. Daily worker 9 org
2. Inspeksi pra pengecoran precast slab ( PS1 24, PS3 = 3) 23. Helper 5 org
3. Install bekisting precast 24. Security 4 org
4. Pabrikasi tulangan precast balok Sub Total 62 org
B. Sub Contractor
1. Civil Foreman 2 org
2. Civil Worker 18 org
3. Piling Crew 15 org
Sub Total 35 org
Total Amount /
97 org
(Total Jumlah )
MATERIAL USED / (Material Yang Dipakai)
LIST OF EQUIPMENT / (Daftar Peralatan)
1. Excavator 2 Unit
2. Crane pancang 2 Unit
3. Crane servis cap.55 T 1 Unit
4. Crane servis cap. 50 T 1 Unit
5. Crane servis cap. 70 T 2 Unit
NON-CONFORMANCE SITE WORKS / (PEKERJAAN YANG TIDAK SESUAI) 6. Crane servis cap. 80 T 2 Unit
Description / Cause of Non-Conformance Work / Corrective Action Taken 7. Dump truk 2 Unit
(Deskripsi) (Penyebab dari pekerjaan yang tidak sesuai) (Tindakan Koreksi yang diambil) 8. Truk mixer 2 Unit
Semua pekerjaan sudah diperiksa dan sesuai 9. Wheel loader 2 Unit
10. Tug boat dan barge 3 set
11. Genset 5 Unit
12. Travo las 5 Unit
13. Bar bender 2 Unit
14. Bar cutter 1 Unit
15. Molen cor 1 Unit
16. Pompa air 1 Unit
Hujan deras, kegiatan diluar ruangan terbatas