0% found this document useful (0 votes)
6 views

Book 1

1. The document is a daily report summarizing work progress for the construction of a jetty by PT. Indonesia Plantation Synergy. 2. On day 138, work included installing formwork for precast concrete slabs and beams, inspecting formwork prior to pouring concrete, and concrete strength testing of precast elements at 7 days. 3. The report lists ongoing and planned work for various components of the jetty including berths, dolphins, trestles, and provides a status update against the project schedule and resources used.

Uploaded by

IJ IW
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
6 views

Book 1

1. The document is a daily report summarizing work progress for the construction of a jetty by PT. Indonesia Plantation Synergy. 2. On day 138, work included installing formwork for precast concrete slabs and beams, inspecting formwork prior to pouring concrete, and concrete strength testing of precast elements at 7 days. 3. The report lists ongoing and planned work for various components of the jetty including berths, dolphins, trestles, and provides a status update against the project schedule and resources used.

Uploaded by

IJ IW
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 3

DOKUMENTASI

SUPERVISI PROYEK PEMBANGUNAN JETTY PT. INDONESIA PLANTATION


Bulan ke : 6
SYNERGY
Periode : 01 Maret - 31 Februari PT ATRYA TEKNIKA KONSULINDO
Lokasi : Sangkulirang - Kutai Timur - Kalimantan Timur ENGINEERING CONSULTANT
Tanggal : 1 Maret 2021

Pekerjaan : Install bekisting precast slab Pekerjaan : Install bekisting precast balok

Pekerjaan : Inspeksi pra pengecoran Pekerjaan : Pabrikasi tulangan balok precast

Pekerjaan : Uji kuat tekan beton precast umur 7 hari Pekerjaan : Uji kuat tekan beton precast umur 7 hari
LAPORAN HARIAN
SUPERVISI PROYEK PEMBANGUNAN JETTY PT. INDONESIA
Project / (Proyek)
PLANTATION SYNERGY Day of / (Hari Ke -) 138
Location / (Lokasi) SANGKULIRANG, KAB. KUTAI TIMUR, KALIMANTAN TIMUR Time Left / (Sisa Waktu) 227 days / (hari)
Owner / (Pemilik) PT. PERINDUSTRIAN SAWIT SYNERGY Month / (Bulan) March / (Maret )
Consultant / (Konsultan) PT. ATRYA TEKNIKA KONSULINDO Day / (Hari) Mon Tue Wed Thu Fri Sat Sun
Contractor / (Kontraktor) PT. BUDI BAKTI PRIMA (Senin) (Selasa) (Rabu) (Kamis) (Jumat) (Sabtu) (Minggu)
Duration / (Masa Pelaksanaan) 365 days / (hari) Date / (Tanggal) 1
SUMMARY OF CONTRACTOR SITE WORK / (KEGIATAN KONTRAKTOR DI LOKASI PEKERJAAN) WEATHER CONDITION / (KONDISI CUACA)
CHECK / CHECK / TIME / Heavy High
LIST OF WORK / (DAFTAR PEKERJAAN) LIST OF WORK / (DAFTAR PEKERJAAN) Clear High Wave
(Cek) (Cek) (Jam) Rain Tide
I. GENERAL V. BERTH D 08 - 09 0 0
1 Mobilization & Demobilization - A. MOORING DOLPHIN 1 09 - 10 0 0
2 Engineering/Documentation/As Built Dwgs/Survey/Material Test √ 1 Piling Works - 10 - 11 0 0
3 Lighting and Safety - 2 Reinforce Concrete K.430 (In Situ) - 12 - 13 mid break / (istirahat)
4 Temporary Facilities √ 3 Steel Work - 13 - 14 0 0
5 APD/HSE √ 4 Appurtenance - 14 - 15 0 0
6 PDA Test - B. BREASTING DOLPHIN 1,2,3 15 - 16 1 0
II. CAUSEWAY 1 Piling Works - 16 - 17 1 0
1 Revetment, Batu - 2 Reinforce Concrete K.430 (In Situ) - Total
2.00 - - -
III. BERTH B 3 Steel Work - Time
A. MOORING DOLPHIN 1,2 - 4 Appurtenance - Loss
1 Piling Works - C. CATWALK Time
2 Reinforce Concrete K.430 (In Situ) - 1 Piling Works - % Loss
3 Steel Work - 2 Reinforce Concrete K.430 (In Situ) - Time
4 Appurtenance - 3 Catwalk Structure -
MAN POWER - LABOUR / (Tenaga Kerja)
B. BREASTING DOLPHIN 1,2,3 VI TRESTLE 360m x (7.5m- 11.5m)
1 Piling Works - 1 Piling Works -
Position / (Posisi) Amount / (Jumlah)
2 Reinforce Concrete K.430 (In Situ) - 2 Reinforce Concrete K.430 (In Situ) -
3 Steel Work - 3 Reinforce Concrete K.430 (Precast) A. Main Contractor
4 Appurtenance - 4 P/T Girder L = 20m - 1. Project Manager 1 Org
C. CATWALK 5 Trestle Protector - 2. Site Manager 1 Org
1 Piling Works - 6 Other Work - 3. Site Engineer 2 Org
2 Reinforce Concrete K.430 (In Situ) - VII Berth E (171 m x 26 m) 4. Quality Control 1 Org
3 Catwalk Structure - A. PLATFORM - 5. HSE Manager 1 Org
IV. BERTH C 72.500 x 20.00 m 1 Piling Works - 6. HSE Officer 1 Org
A. PLATFORM 2 Reinforce Concrete K.430 (In Situ) - 7. Supervisor 3 Org
1 Piling Works - 3 Reinforce Concrete K.430 (Precast) - 8. Surveyor 4 Org
2 Reinforce Concrete K.430 (In Situ) - 4 Steel Work - 9. Ass. Quality Control 1 Org
3 Reinforce Concrete K.430 (Precast) - 5 Appurtenance - 10. Ass. Surveyor 2 Org
4 Appurtenance - B. MOORING DOLPHIN 11. Logistik 2 Org
B. MOORING DOLPHIN (MD.1 & MD.2) 1 Piling Works - 12. Safety Officer 2 Org
1 Piling Works - 2 Reinforce Concrete K.430 (In Situ) - 13. Operator B.Plant 1 Org
2 Reinforce Concrete K.430 (In Situ) - 3 Steel Work - 14. Operator Exca 2 Org
3 Appurtenance - 4 Appurtenance - 15. Driver 4 Org
4 Steel Work - C. CATWALK - 16. Welder 8 Org
1 Piling Works - 17. Asst Batching Plant 2 Org
2 Reinforce Concrete K.430 (In Situ) - 18. Admin 1 Org
3 Catwalk Structure - 19. Accounting/ Finance 2 Org
DESCRIPTION OF ACTIVITIES / (Uraian Kegiatan) 20. Electrical 1 org
21. Mekanik inspeksi 1 org
21. Alken 1 org
1. Test beton umur 7 hari 22. Daily worker 9 org
2. Inspeksi pra pengecoran precast slab ( PS1 24, PS3 = 3) 23. Helper 5 org
3. Install bekisting precast 24. Security 4 org
4. Pabrikasi tulangan precast balok Sub Total 62 org
B. Sub Contractor
1. Civil Foreman 2 org
2. Civil Worker 18 org
3. Piling Crew 15 org
Sub Total 35 org
Total Amount /
97 org
(Total Jumlah )
MATERIAL USED / (Material Yang Dipakai)
LIST OF EQUIPMENT / (Daftar Peralatan)

TYPE / (Jenis) AMOUNT / (Jumlah)

1. Excavator 2 Unit
2. Crane pancang 2 Unit
3. Crane servis cap.55 T 1 Unit
4. Crane servis cap. 50 T 1 Unit
5. Crane servis cap. 70 T 2 Unit
NON-CONFORMANCE SITE WORKS / (PEKERJAAN YANG TIDAK SESUAI) 6. Crane servis cap. 80 T 2 Unit
Description / Cause of Non-Conformance Work / Corrective Action Taken 7. Dump truk 2 Unit
(Deskripsi) (Penyebab dari pekerjaan yang tidak sesuai) (Tindakan Koreksi yang diambil) 8. Truk mixer 2 Unit
Semua pekerjaan sudah diperiksa dan sesuai 9. Wheel loader 2 Unit
10. Tug boat dan barge 3 set
11. Genset 5 Unit
12. Travo las 5 Unit
13. Bar bender 2 Unit
14. Bar cutter 1 Unit
15. Molen cor 1 Unit
16. Pompa air 1 Unit
Hujan deras, kegiatan diluar ruangan terbatas

Disetujui, Diperiksa , Dibuat,


Report to be made for each working day of inspector, and signed /submitted to
Engineer before end of the next working day, and please take Photo during your
Supervision Activity /
(laporan ini harus dibuat
setiap hari kerja oleh Inspector dan ditandatangani kemudian di serahkan kepada
Engineer paling lambat1 hari setelah laporan ini dibuat, dan mohon untuk mengambil
foto pada saat melakukan aktivitas pengawasan). Sumarsono Leonardo Mallangi Wiji Purniawan
setiap hari kerja oleh Inspector dan ditandatangani kemudian di serahkan kepada
Engineer paling lambat1 hari setelah laporan ini dibuat, dan mohon untuk mengambil
foto pada saat melakukan aktivitas pengawasan).
PT.PSS Site Engineer Inspector

You might also like