Basic Design Report RDA+Causeway
Basic Design Report RDA+Causeway
December 2006
GM
JR
06-226
PREFACE
In response to a request from the Government of Sri Lanka, the Government of Japan
decided to conduct a basic design study on the Project for Construction of New Mannar
Bridge and Improvement of Causeway in the Democratic Socialist Republic of Sri Lanka and
JICA sent to Sri Lanka a study team from June 14, 2006 to June 20, 2006 and from
The team held discussions with the officials concerned of the Government of Sri
Lanka, and conducted a field study at the study area. After the team returned to Japan,
further studies were made. Then, a mission was sent to Sri Lanka in order to discuss a draft
basic design, and as this result, the present report was finalized.
I hope that this report will contribute to the promotion of the project and to the
Government of Sri Lanka for their close cooperation extended to the teams.
December 2006
Masafumi Kuroki
Vice-President
Letter of Transmittal
We are pleased to submit to you the basic design study report on the project for
This study was conducted by the Joint Venture of Nippon Koei Co., Ltd. and Oriental
Consultants Co., Ltd, under a contract to JICA, during the period from June, 2006 to January,
2007. In conducting the study, we have examined the feasibility and rationale of the project
with due consideration to the present situation of Sri Lanka and formulated the most
appropriate basic design for the project under Japan’s grant aid scheme.
Finally, we hope that this report will contribute to further promotion of the project.
Hiroshi Fujisawa
Chief Consultant
Basic design study team on
the project for Construction of New Mannar Bridge
and Improvement of Causeway
in the Democratic Socialist Republic of Sri Lanka
Nippon Koei Co., Ltd.
and
Oriental Consultants Co., Ltd.
Summary
Summary
1. Outline of the Country
The Bridge and Causeway connecting the Mannar Island and the mainland were
constructed in the 1930s with an overall length of 121.2m and an overall width of 4.26m. The
38.0m long steel truss center span of the bridge was blasted and the wreckage of the steel
truss members still remains in the canal. It was re-built temporarily with a steel Bailey bridge.
Both end sections, consisting of 4-lane 10.4m long concrete bridges, were also damaged
severely due to the blasting. The use of the existing bridges is limited to 10-ton vehicles and
at present there are risks of accident and damage caused by heavy vehicles, thus hindering
smooth transportation and causing high transportation cost. Traffic safety is also not ensured
for pedestrians passing the bridges. The existing causeway of approximately 3.5km long in
total and 6.3m wide on average is retained by masonry walls. Its single-lane carriageway with
a width of about 3.5m is paved by DBST and the sidewalks on both sides are paved by laterite
soil. Heavy vehicles passing on the causeway must reduce speed and wait on the sidewalk for
coming vehicles from the opposite side. The retaining walls are inclined or collapsed due to
the wheel load of heavy vehicles. However, the bridge and causeway reconstruction
programme was not implemented because of financial constraints and the prevailing security
situation in the project area.
Following the result of the peace process, GOS requested the Government of Japan to
extend Japan’s Grant Aid for the construction of the new Manner Bridge and improvement of
the causeway. In response to the request, the Japan International Cooperation Agency (JICA)
dispatched a Preliminary Study Team to Sri Lanka in March 2006. The team held discussions
with officials of GOS to confirm the requests from GOS and conducted a field survey.
Through the preliminary study, the team basically confirmed the necessity of urgent
construction of the bridge and improvement of the causeway. Based on the preliminary study
result, JICA decided to conduct a Basic Design Study (the Study) on the Project for the
construction of the new Mannar Bridge and improvement of the causeway, and dispatched a
basic study team (the Study Team) to Sri Lanka in July 2006 to discuss the scope of the
project and conduct the site survey and collect necessary data for basic design.
S-1
3. Design Policy and Facility Plans of the Project Construction Period and
Estimated Project Cost
Items Facilities
Bridge Type 6 Spans Connection PC I-Girder
Total Length 157.1m
Width Total Width: 10.40m
Carriageway: 2 lanes (3.70m + 3.70m)
Foot way: 1.50m each side (included Handrail)
Abutment Pile Bent Type (Cast-in-place concrete pile) 2 places
Slope Protection: Stone Masonry
Pier Pile Bent Type (Cast-in-place concrete pile) 5 places
Pavement Cold Mixed Asphalt Pavement: 50mm (Carriageway)
Causeway Total Length Approach Road in Beginning side: 140m
and Approach Causeway: 3,140m
Roads Approach Road to Bridge: Mainland side: 155m
Mannar Island side: 158m
Width Total Width: 11.00m
Carriageway: 2 lanes (3.70m + 3.70m)
Shoulder: 1.80m each side
(including top of wall of 60cm)
Causeway: Widening toward Western side
Type of Slope West Side: New RC Concrete Reverse-T Wall and
Protection Gravity Retaining Wall Type including Soft
Ground Measurement (Displacement Method)
East Side: Repair of Masonry Wall and Reinforced with
Concrete Cover
Approach Road: Sod/Grass
Pavement DBST (Double Bituminous Surface Treatment): 20mm
S-2
4. Construction Period and Estimated Project Cost
The detailed design including tender process will take about 7 months. The
construction period will be about 29 months. The total cost of the Project to be borne by the
Japan’s Grant Aid is estimated at Japanese Yen 1.878 billion and that by GOS at Japanese Yen
19 million (Sri Lanka Rupee 17 million).
The areas directly benefited by the Project cover Mannar and Vavuniya districts,
where about 200,000 people accounting for about 1% of the total population of Sri Lanka.
The direct impacts and effects of the Project implementation are solving of traffic
bottlenecks, reduction of transportation cost, activation of regional development and
improvement of stability of the people’s livelihood. Furthermore, the Government Agent of
Mannar expects to improve the access to the road network of the mainland of Sri Lanka in
line with the Road Sector Master Plan (RSMP) in 2005. The road development programme is
based on the future traffic projections and on development activities decentralizing from
Colombo to the economic growth centers in Sri Lanka.
In addition to such many direct impacts and effects, the regional industries such as
agriculture and fisheries will be activated by the reconstruction of the Mannar Bridge and
Causeway which constitute a bottleneck for the transport of products to/from agriculture and
fishery facilities. The Project will improve the transportation system of Mannar Province,
enhancing the agriculture and fisheries sectors and creating opportunities for resettlement of
displaced persons into their original industries.
Upon completion of the Project the new Mannar Bridge and Causeway will play the
role of a life-line corridor for the people living in Mannar and, as a result, a number of
benefits discussed above will be realized and the livelihood of those people will be improved.
In this regard, it is worth implementing the Project by the Japan’s Grant Aid at an earliest
date.
S-3
Preface
Letter of Transmittal
Summary
Contents
Location Map/Perspective
List of Figures and Tables
Abbreviations
Contents
i
2-3-2 SPECIAL ITEMS OF THE PROJECT ................................................................2-41
2-4 PROJECT OPERATION PLAN .......................................................................................2-42
2-4-1 YEARLY MAINTENANCE................................................................................2-42
2-4-2 PERIODICAL MAINTENANCE........................................................................2-42
2-5 COST ESTIMATE ............................................................................................................2-43
2-5-1 TOTAL PROJECT COST ....................................................................................2-43
2-5-2 MAINTENANCE COST .....................................................................................2-44
CHAPTER 3 PROJECT EVALUATION AND RECOMMENDATIONS............................ 3-1
3-1 PROJECT EFFECTS ..........................................................................................................3-1
3-2 RCOMMENDATIONS.......................................................................................................3-2
APPENDICES
1. Member List of the Study Team
2. Study Schedule
3. List of Parties Concerned in the Recipient Country
4. Minutes of Discussions
5. Basic Design Drawings
ii
N
Mannar-island MANNAR-ISLAND
Tallady
A14 Vavuniya
Anuradhapura
Puttalam
Mannar Town
THE DEMOCRATIC
SOCIALIST REPUBLIC OF
SRI LANKA
JAPAN
Tallady A32
The Project for Construction of New Mannar Bridge and Improvement of Causeway Location Map
PERSPECTIVE VIEW OF NEW MANNAR BRIDGE AND CAUSEWAY
List of Figures
List of Tables
iii
Abbreviation
iv
CHAPTER 1
1-1
returned to Japan, further study and basic design were conducted and the draft final report was
prepared. Then JICA sent the Basic Design Explanation Team to Sri Lanka from November 12 to
November 18, 2006 and the Minutes of Discussion, which mainly covered the results of the basic
design and the recipient country’s obligations, was agreed by both sides.
1-2
CHAPTER 2
2-1
GOS requested the Government of Japan to extend Japan’s Grant Aid for the
construction of the New Mannar Bridge and improvement of the Causeway which are
finally outlined in the basic design as follows:
- Construction of a new 157.1m long, 10.4m width bridge, with 6 PC I-Girder spans, 2
carriageways and foot walks on both sides.
- Improvement of the 3.14km long, 11.0m wide causeway, with 2 carriageways and foot
walks on both sides.
- Construction and improvement of 0.45m long, 11.0m wide approach roads, with 2
carriageways and foot walks on both sides.
The New Mannar Bridge has been planned to be constructed on the western side
of the existing bridge where existing important buildings and facilities that may be subject
to environmental impact of the Project are very few on the bridge alignment, and the
concrete bridge type has been selected to ensure durability against damage by salty water.
(3) Bridge Design and Construction Planning in Consideration of Dry and Rainy
Seasons
According to the results of site survey conducted from June and August 2006, the
construction works in the sea can be carried out in the dry condition. To minimize the
2-2
construction cost, the construction works below the high water level shall be completed
during the dry season.
(4) Measure against Settlement
As the sea bed is a soft ground, settlement will occur under the embankment. The
existing causeway and the widening section are in different conditions of soil
consolidation, resulting in a gap between them due to settlement. Taking this condition into
consideration, the displacement method (soft ground is excavated and replaced with good
embankment material) has been applied as a counter-measure against settlement
considering the reliability of this method, and the construction period and cost.
(5) Adopted Standards
The Geometric Design Standard of Road 1998 has been applied for geometric
design of roads and bridges. The Bridge Design Manual, RDA, 1997 which refers to BS
5400 Part 2, has been applied for bridge design. The Japanese Industrial Standard (JIS) has
been applied for expansion joints and rubber bearing shoes.
(6) Planning of Bridge and Causeway in Consideration of Future Maintenance
The bridge has been designed in consideration of minimum and easy maintenance.
Bridge drains, expansion joints and shoes have been designed considering easy cleaning
and durability. Concrete design strength, which should be durable against salty water, has
been determined and designed for quality of cement, aggregate and sand and their design
mix proportion.
2-3
Table 2-1 Record of Tidal Levels
2-4
2-2-1-3 Policy on Socio-Economic Condition
(1) Peace and Reconstruction Process
The project site is located in the government control area near the borderline
between the government control area and LTTE control area. Approximately 65% of the
population in the area is Tamils. The capital of Mannar prefecture is in the Mannar Island
and the new Mannar Bridge and causeway play a major role not only for passenger
transportation but also freight transportation. GOS expects to activate the regional
development and improve the stability of people’s livelihood near the borderline by
implementing the construction of the new Mannar Bridge and causeway. This project is
expected to accelerate the peace and reconstruction processes.
(2) Harmony with Local Society
For smooth implementation of the Project, the following factors are taken into
consideration:
- As the project site is located at the entrance of the capital of Mannar prefecture, the
design and implementation plan of the new Mannar Bridge and causeway will be
conducted considering the surrounding environment;
- The construction methods shall provide job opportunities to local people because there
are not sufficient jobs for people staying around the project site;
- Materials such as stone and sand that can be procured around the project site shall be
used to the maximum extent;
- The construction facilities such as construction yards and temporary roads shall be
planned with a view of re-using those facilities for residents’ relaxation after
completion of the Project.
2-5
2-2-1-4 Policy on Construction and Procurement
(1) Working Condition
Most people in Mannar are Tamils and Moors. Common labour can be recruited
relatively easily from Mannar but special technique is required for the implementation of
the Project. Engineers and special technicians required for the Project are available in
Colombo but they have no intention to work in Mannar due to many opportunities to work
for highway projects in the south and security problems in the north. Therefore, expatriates
from surrounding countries should be employed for the construction of cast-in-place
concrete piles and erection of PC girders. The employers shall conform to the Sri Lankan
Labor Law (enacted in 2004).
(2) Procurement of Machines and Materials
1) Cement
According to the hearing survey from manufacturers, two cement factories are
operating in the west and south regions of Sri Lanka. Cement is now in great demand due
to the current execution of projects for the restoration of Tsunami disaster. Normal
Portland cement manufactured in India and South Africa can be procured in Sri Lanka.
There are seven cement suppliers in Colombo. Ten ready mixed concrete suppliers with
batching plants are operating in Sri Lanka, but only in Colombo and the southern area.
Therefore, the batching plant should be procured in Colombo and installed at this site.
2) Reinforcing Bars/Steel Materials
Reinforcing bars and steel members will be procured from Singapore but PC
strand and anchors, which are not produced in Singapore, and tensioning jacks will be
imported from Japan.
(3) Sand, Stones and Borrow Materials
Sand will be procured from private suppliers at Kalar. The sand price is fluctuating
due to transportation cost and security control of the Army. Concrete and pavement
aggregate and stones for retaining walls and slope protection will be procured from the
suppliers operating a crushing plant at Madukanda or Mihintale. Borrow material for
embankment will be procured from the borrow pit in government land at Madhu.
(4) Bridge Accessories
According to the procurement survey at the local site, bearings and expansion
joints are not produced in Sri Lanka; therefore, they will be procured from Japan.
(5) Construction Machines
Construction equipment for road work can be rented in Sri Lanka. However, truck
cranes with over 80ton lifting capacity, all casing bored pile machine, and erection girder
for PC concrete girders and portal crane cannot be procured in Sri Lanka and Singapore.
They will be procured from Japan. Crushing plant will not be provided at the site so all
materials produced from stones will be procured from local suppliers.
2-6
2-2-1-5 Procurement of Local Contractors
Local contractors in Sri Lanka have experience in the construction of PC bridges
but they are not interested in working in Mannar. Subcontractors for cast-in-place concrete
pile and PC girder erection may be mobilized from Japan.
2-7
Ministry of Highways Road Development Authority
Legal Division
Works Division
2-8
(2) Maintenance Organization
As shown in Figure 2-2, RDA, which is responsible for the maintenance of roads
and bridges under the Board of Directors, has 9 provincial and 24 regional offices and is
operating with the maintenance budget. RDA Mannar Office is responsible for the
maintenance of the new Mannar Bridge and causeway and contracts with private repair
agencies for routine maintenance works. RC&DC (Road Construction & Development
Corporation) undertakes directly periodical maintenance and rehabilitation works under
contract with RDA. However, in order to ensure that periodical maintenance requiring
technical knowledge such as bridge repair and replacement of expansion joints can be
conducted appropriately, the following measures will be taken:
- The bridge and causeway will be so designed as to minimize and facilitate maintenance
works after their construction.
- Maintenance engineers in RDA will learn the inspection and maintenance management
systems for the new bridge and causeway through a training programme in Japan
during the construction stage.
Chairman
General Manager
Northern
Sabaragamuwa
North Western
Southern
Western
Eastern
Eastern
Central
Uva
Technical Officer Technical Officer Technical Officer (2) Clerk (2) Drivers (2)
Work Supervisor Work Supervisor Work Supervisor (3) Office Aide (1)
Labors (75)
2-9
2-2-1-7 Policy on the Grade of Facilities and Equipment
(1) Design Standards
Sri Lankan design standards and manual are applied for the design of bridge and
causeway to determine the suitable and economic scale of facilities for the Japan Grant Aid
Project. But expansion joints, rubber shoes will be procured from Japan considering the
lower quality of local products and the severe site conditions suffering damage by salty
water.
(2) Policy on Reconstruction of Bridges and Causeway
The Mannar Bridge was blasted in 1990 and is now in a severely dilapidated
condition presenting a risk of collapse due to the traffic of heavy vehicles. The new bridge
construction policy is that a temporary bridge will be provided for the transportation of
equipment and materials for bridge works, and the existing bridge will be used only for the
general traffic. Most bridge works including foundations will be executed on the
temporary bridge.
On the other hand, the existing causeway structure is still relatively sound but its
width is narrow and deteriorated in some section. The causeway widening policy is that
part of the existing causeway will be used as a detour road with a single traffic way for
both construction vehicles and general traffic during the construction and then will be
incorporated into the new causeway which has been widened toward the western side.
The reconstruction of the bridge and causeway is designed with a view of
providing sufficient safety against the past maximum high tide level and an appropriate
navigation clearance (20m wide and 4m height). Considering the site conditions such as
scouring, waves and canal erosion, both abutments will be moved back from the existing
location.
The abutment and slope protections are designed to be flexible to alleviate the
critical damage due to waves by following the deformation of seabed and bank slope.
Therefore, periodical maintenance shall be conducted to protect the bridge and causeway
structures, and subsidiary structures.
(3) Consideration of Traffic Safety
The Mannar Bridge is located at the entrance of Mannar city where a provincial
capital and administrative, educational and business center exist. It is predicable that the
number of pedestrians and bicycles passing on the bridge will increase after its
construction. Therefore, safety facilities should be provided for pedestrians to ensure their
safety and sidewalks for pedestrians should be considered in the bridge design.
2-10
temporary bridge. In parallel with the foundation and substructure works, PC girders will
be cast at the fabrication yard. PC girders will be pulled out by winches from the
fabrication yard to the erection site behind the abutments and then erected by means of
erection girder. The construction period of the new bridge including the temporary bridge
is approximately 21 months. Shortly after the completion of the bridge, RDA shall
demolish the steel truss bridge that fell in the sea to ensure safe navigation of fishing boats
during the construction period.
Considering the above conditions, the construction of the Project will commence
in October, 2007 with the mobilization in the end of the rainy season and both bridge and
causeway works will be carried out at the beginning of the dry season. The total
construction period is estimated to be 29 months.
2-11
2) Bridge Design Conditions
Table 2-3 Bridge Design Conditions
Items Design Condition Notes
Navigation Clearance Height:4.0m, Width:20.0m refer to 2.3.2
Live Load HA Load, B Load:30 Unit BS5400 Part 2, 1978
Wind Load 60 miles/hr. RDA Bridge Design Manual
Temperature 33.8~2.9℃ RDA Bridge Design Manual
Design
Loads P=Impact (ton)
RDA Bridge Design Manual
Impact P=0.1 x W x V W=Weight of Ship (9ton)
and Site Conditions
V=Speed of Ship (20m/sec)
Seismic Load Zero RDA Bridge Design Manual
PC I-Girder 50N/mm2
Cross Beam 50N/mm2
RC Slab 40N/mm2
Design Strength of Concrete Concrete in the Air 40N/mm2 RDA Bridge Design Manual
Cast-in-place Concrete Pile
50N/mm2
and Pile Bent
Leveling Concrete 25N/mm2
PC I-Girder 40mm
Cross Beam 40mm
RC Slab 50mm
Concrete Coverage Concrete in the Air 50mm RDA Bridge Design Manual
Cast-in-place Concrete Pile
55mm
and Pile Bent
Leveling Concrete -
10 400
1 500 3 700 3 700 1 500
300 1 200
Foot Walk Carriageway Cold-mix Asphalt
Hand Rail Cycle Lane Concrete
1.5%
2.5% 2.5%
2-12
2) Causeway Width Structure
The cross section of causeway is as shown in Figure 2-4 based on the same
classifications as the bridge. The minimum width of structure is as follows:
- Carriageway = 7.4m (3.7m x 2 lanes)
- Foot walk/cycle = 1.8m (Foot walk/cycle = 1.2m and top of retaining wall)
According to the RDA Geometric Design Standard of Roads, 1998, the width of
foot walk is 1.8m in minimum but it is maintained to be the same (1.2m) as that of the
bridge and a space of 0.6m on the top of the retaining wall is used for the installation of
guard stones in the section of the causeway for minimizing the construction cost. The
width of the causeway is 11.0m in total. On the top of the retaining wall, guard stones will
be provided for traffic safety.
11 000
WEST EAST
1 800 3 700 3 700 >1 800
600 1 200 1 200 >600
Shoulder Carriageway DBST
Existing Causeway
11 000
WEST EAST
1 800 3 700 3 700 1 800
600 1 200 1 200 600
Shoulder Carriageway DBST
Armoured Rock Guard Rail
3.0% 3.0%
0.5ton, t=0.5m
1:1.5 Sodding
1:2
Geotextile
Existing Causeway
Shelter Layer
Gravel t=0.15m
2-13
2-2-2-2 Facility Plan
(1) Bridge Center Line
To select the location of the reconstructed bridge, the following three alternatives
have been taken into consideration:
Route- A : 20m on the western side of the existing bridge
2-14
Table 2-4 Alternative Plans of Bridge Center Line
Route Evaluation
• Big radius can be provided at the end junction, so traffic can move to the
junction smoothly.
20m to the • Easy access to police office is provided. Movement of gasoline stand and
west of demolish of 2 abandoned houses have already been agreed with the
A
existing Government Agents concerned.
bridge • RDA has studied this route and concluded that it is economical and
acceptable.
Good
• Road alignment is almost same as the existing road and bridge, so the impact
on the existing facilities is minimized.
Same • Construction of the new bridge is carried out only after a detour bridge is
alignment as constructed and the existing bridge and wreckage of steel truss bridge are
B removed, so the construction period is longer and the cost is higher compared
existing
bridge with other alternatives.
• Construction of a temporary bridge for construction works is also required, so
it is not economical. Fair
• Only small radius can be aligned at the end of junction, so the road alignment
is out of design criteria.
20m to the
• The water supply pipe on the eastern side of the existing road is affected by
east of
C the bridge construction.
existing
• A detour road is required for the existing road to the fort.
bridge
• Military check point and police facilities are affected by the
Bad
alignment.
Fisheries Market
Mangrove
Fisheries Port
Abandoned House
QS
ARoute Check Point Abandoned House
Army
B Route
Court
Mannar Bridge
Concret Basin
C Route Gate
2-15
(2) Bridge and Causeway Plan
The new Mannar Bridge and causeway are designed as shown below.
1) Newly Constructed Bridges
The existing bridge has a total length of 121.2m, a 38.0m long center span and 4
10.4m long spans on both sides. As the existing bridge was constructed with a relatively
short length, local scouring occurred around the abutments. It is considered that the
hydraulic condition of the canal will be unchanged, although the existing bridge will be
demolished after the construction of the new bridge. In the design of the new bridge, both
abutments are set back from the existing abutments to minimize the risks of local scouring
and waves caused by the southwestern wind in the monsoon season.
The navigation clearance of 4.0m height and 20.0m width has been agreed with
the agencies concerned. Based on this clearance, the minimum length of the center span is
over 22.0m. The use of prestressed concrete girder type for the bridge is reasonable and
economical considering its durability against salty breezes at the seashore.
On the center line of the new bridge (20m on the western side from the existing
bridge), both abutments will be constructed in sea water and therefore affected by waves.
Slop protection and revetment should be strong enough to withstand waves but low
construction cost and easy maintenance should be ensured.
Based on the above conditions, three alternatives have been evaluated in the
following aspects i) Structural aspect; ii) Cost/constructability; and iii) Maintenance as
shown in Table 2-5. Alternative-B (bridge length: 157.1m, girder length: 26.0m, 6 spans of
continuous PC I-Girders) has been selected as the most appropriate from the following
viewpoints:
- In the case of span length of 25.1m for Alternative-A and 26.1m for Alternative-B, the
difference of bridge cost is negligible because girders have the same height and the
same erection equipment is used for their erection. On the other hand, Alternative-A
requires large abutments to set the footing under the sea bed and it is necessary to
provide strong revetment and slope protection leading to uneconomical design:
- In Alternative-C, the number of spans can be reduced by providing longer girders of
30m. But for 30m spans, the PC T-Girder type should be applied, which results in an
increase in the construction cost. Alternative-C would also require large foundation,
substructure and girders and therefore large equipment should be used.
- For Alternative-B it has been planned to construct abutments on a wide mound so as
not to be affected by waves. The filled mound will be protected by stone riprap and
revetment, which can be easily maintained by RDA Mannar Office.
2-16
Table 2-5 Alternative plans of span Arrangement
Profile Evaluation
Alternative -A, Bridge Length 151.6m, (girder Length 2.05m), 6-spans Connection PC-I Girder + Wet Masonry Protection Structural Point ( Erosion)
To shorten bridge length,
Bridge Length 151 100 (Span [email protected]+25.100) protection with wet masonry
Main Land Mannar
(Slope 1:1)to protect erosion
Existing Bridge
is provided.
○
Navigation Navigation
Clearance Clearance
Economic and Construction
H.H.W.L.+0.600 M.S.L.
H4.00 x W20.00 H4.00 x W20.00 Scale of abutments, slope
protection and foundation
and costs are bigger than
Alternative-B, although
○
Navigation Navigation
Clearance Clearance Economic and Construction
H4.00 x W20.00 H4.00 x W20.00 Scale of abutments, slope
protection and foundation
are smaller than Alternative-
A, and cost is lowest among
Sodding Stone Riprap them ◎
Scoring/Erosion Evaluation
In maintenance of scoring
and ersion are easy. ◎
Alternative-C Brige Length 158.40m (Girder Length 31.5m), 5-Span, Connection PC T-Girder + Stone Riprap Structural Point ( Erosion)
Both abutments are set back
Bridge Length 158 400 (Span Length 31.650+3@31,700+31.650) on mound filled and
protected by stone riprap to
make easy mentenance.
◎
Navigation
Clearance Economic and Construction
H4.00 x W20.00 Scale of abutments, slope
protection and foundation
are smaller than Alternative-
A, and cost is lowest among
them ○
Evaluation
Constructability and cost are
inferior among 3 alternatives ○
2) Widening of Causeway
Causeway widening should be planned to incorporate the existing causeway to
minimize the construction cost. The causeway widening alternatives are i) Widening to the
western side, ii) Widening to the eastern side; and iii) Widening on both sides. Based on
the result of site survey, the alternative of widening to the western side utilizing the eastern
retaining wall has been considered the most appropriate from the following viewpoints:
- The western retaining wall is damaged more seriously than the eastern retaining wall;
- The alignment of the existing eastern retaining wall is relatively straight, therefore
modification of the road alignment is limited;
- In the case of widening on both sides, the construction cost increases because it
requires the construction of new retaining walls on both sides and a traffic detour road;
- As the centerline of the new bridge is shifted 20m to the west, connection of the bridge
alignment with the alignment of the westward widened causeway is smooth; and
- As an existing water supply pipe is laid under the eastern shoulder, the eastern retaining
wall should be maintained to enable future inspection and repair of this water supply
pipe.
A basic plan of the causeway widening to the western side is shown in Figure 2-6.
11 000
WEST EAST
1 800 3 700 3 700 >1 800
600 1 200 1 200 >600
Shoulder Carriageway DBST
Existing Causeway
Replacement Soil
Figure 2-6 Basic Plan for Causeway Widening to the Western Side
2-18
b) PC T-Girder
The economical span length of T-shaped PC girder is 25m to 40m. The designed
span length of 26.1m is also acceptable but not so economical. On the other hand, the
construction period is shortened because no concrete slabs are required. Considering the
same condition as PC I-Girders as mentioned in item a) above, the girder erection method
is applied for PC T-Girders. However, the weight of a PC T-Girder is approximately 80
tons, so larger fabrication yard and erection facilities are required. PC T-Girders are
connected to each other on the piers to make a continuous structure. In such a way,
expansion joints on the piers and maintenance are not required.
c) Steel I-Girder
The economical span length of steel I-Girders is 25m to 45m. Steel I-Girders are
manufactured only in a neighboring country (Thailand) and have to be transported by ships
and trucks to the construction site in Sri Lanka. The transportation cost is very high. As
steel girders can be fabricated in parallel with the construction of foundation and
substructure, the construction period can be minimized. However, steel girders are subject
to corrosion and deterioration due to sea water, so the maintenance cost including painting
is higher.
d) Overall Evaluation
The use of steel I-Girders is not viable from the economical and maintenance
viewpoints. In comparison between PC I-Girders and PC T-Girders, the PC T-Girder type
would be more preferable in view of its shorter construction period. The critical path in the
construction schedule is on the causeway construction but not on the bridge construction.
In conclusion, the PC T-Girder is superior to other alternatives in the structural,
constructability, economical and maintenance aspects.
2) Pier and Foundation Type
The sea water depth at the location of piers is 5~6m. A relatively hard clay layer is
found at 10 to 20m from the ground surface but the sand stone layer deeper than 20m is
considered as the bearing layer for bridge piles. Based on such conditions, four alternative
types, i.e. i) Wall type pier + Spread footing, ii) Circular column pier + Cast-in-place
concrete pile, iii) Caisson foundation pier, and iv) Pile bent foundation pier have been
considered.
a) Wall Type Pier + Spread Footing
The wall type pier type does not obstruct the water current and is strong against
collision by ship. However, cofferdams made of steel sheet piles are required for execution
of deep seabed excavation. Spread foundation on relatively hard clay is not acceptable for
pier foundation considering the consolidating settlement of clay and local scouring. Spread
foundation requires low construction cost but high maintenance cost. In the comprehensive
cost comparison, the spread foundation type is not economical.
b) Circular Column Pier + Pile Foundation (Cast-in-place Concrete Pile)
The circular column pier type obstructs the water current but has good appearance.
Considering the deep scouring depth, the pile foundation type is applied for the circular
column pier. For this type, it is also necessary to provide cofferdams as same as mentioned
in item a) above for construction of pile caps and cast-in-place concrete piles, which leads
to cost increase. The construction period of this type is the longest among the four
alternatives.
2-19
c) Caisson Foundation Pier
The caisson foundation pier was applied for the existing Mannar Bridge. Its
diameter is normally about 3m in Sri Lanka. To minimize the construction cost of caisson
foundation, construction of filled cofferdams is required for working areas in the sea. The
filling for cofferdams in the deep sea canal is not acceptable for environment reason. If
filled cofferdams are not provided, mechanical excavation for large diameter piles is very
costly because it needs large size equipment and it is also difficult to procure such
equipment and casing pipes.
d) Pile Bent Foundation Pier
The pile bent diameter is the same as that of the column of substructure, therefore
so both works can be proceeded in continuity. It is not necessary to provide cofferdams for
construction of pile-bents, therefore the construction period and cost are drastically
minimized. The diameter of pile bents is only 1.2m which presents no obstruction to
navigation but they may be damaged by ship collision. The pile bent concrete should be
protected with steel pipe used for concrete placing of pile bents. The pile bent pier is a
structure with heavy load on the top of pier, so the horizontal displacement at the bearing
shoes tends to be large. To solve this problem, the following measures are adopted;
- Simple PC I-Girders will be connected continuously on the pier, so as to prevent them
from falling even when the displacement becomes large; and
- The diameter of the pile bents will be over 1,200mm in order to secure high stiffness of
bridge piers.
e) Overall Evaluation
In case those piers are constructed in the sea canal, construction conditions such as
current, tide, and waves are complicated and may lead to construction problems. All pile
bent foundation works are executed by means of construction equipment and machines on
the temporary bridge, therefore the construction period and cost can be minimized. In the
area considered not being subject to seismic force, the horizontal load is relatively small
and the vertical load due to the reaction force from the superstructure is steadily supported
by long pile bents penetrated into the sand rock layer. Therefore, the pile bent pier type is
the most appropriate from the structural and economical viewpoints as shown in Table 2-7.
3) Abutment and Foundation Type
Abutments are constructed in the shallow sea. The depth of sea water becomes
deeper near the canal but erosion of the canal slope is not observed. The abutment on the
Mannar Island side may be affected by waves. Based on such conditions, two alternative
types, i.e. i) Reversed T-type abutment, and ii) Pile bent abutment have been considered.
a) Reversed T-type Abutment
Abutments of this type are structurally stable because their footing is constructed
under the seabed. On the other hand, as the abutment is subject to horizontal loadings due
to a large earth pressure. The scale of the abutment will be larger and the number of piles
be increased. Although the total bridge length can be shortened, both abutments should be
protected with strong concrete slope protection and this leads to cost increase. If such
consolidated concrete slope protection is damaged due to waves, their maintenance and
repair by the RDA Mannar Office are difficult and limited.
b) Pile Bent Abutment
In this type, small abutments supported by pile bents are constructed on a filled
mound around the abutments at a level not affected by waves. The slope of the mound is
protected by stone riprap and revetment, so the slope maintenance is simple and can be
2-20
easily conducted by the RDA Mannar Office. In the case of small earth pressure, the
abutment size may be smaller and the number of piles may be decreased. Although the
total bridge length will be longer resulting in an increase in the cost of superstructure, the
total construction cost decreases because the costs of foundation, substructure, slope
protection and revetment are lower.
c) Overall Evaluation
The pile bent abutment type is the most appropriate from the structural,
economical and maintenance viewpoints as shown in Table 2-8.
2-21
Table 2-6 Comparative Study for Bridge Superstructure
Plan
- Post-tension PC I shaped girder is applied for the - Post-tension PC girder is applied for the span of - Steel I shaped girder is applied for the span of
Structural span of 20~30m. 25~40m. 25~45m.
Condition - Height of the girder will be higher than I-girder, so - Steel will be seriously affected by the sea water
◎ elevation will raise. ◎ △
2-22
- Post-tension PC girder is fabricated and stressed in - Post-tension PC girder is fabricated and stressed in - Steel girders are procured from the third countries and
the construction site near the bridge and then erected the construction site near the bridge and then erected transport ship and trailer through Colombo, so the
Construction by erection girder or two heavy track cranes (80- by erection girder or two heavy track cranes (more transport cost is relatively high.
Condition - 100ton). than 100ton).
Erection girder or track cranes can be hired in - Erection equipment shall be large due to heavy weight
Singapore. ◎ of girder. ○ △
Procurement - Bridge site condition is limited, so erected by erection - Condition is same as the I-girder. But girder is heavier - Two track cranes of around 40~50ton lifting capacity
of Material girder is recommended for safety. than I-girder, heavy equipment should be used for are required for erection.
and Erection ◎ erection. ○ ○
- Maintenance of bridge is not necessary exception of - Maintenance of bridge is not necessary exception of - It is required to inspect and maintenance periodically
Maintenance cleaning of drain, expansion joint, bearing and cleaning of drain, expansion joint, bearing and for the painting.
incidentals. ○ incidentals. ○ △
- PC post tension I-girder of 25~30m is economical - Concrete bridge is reasonable to use natural resources - Steel material and fabrication cost of steel girder is
Economical and light of weight, so erection equipment will be mainly. extremely high compared with concrete girder mainly
Aspects minimize than T-girder - Equipment shall be larger than the construction of I- consists of local product material
- Erection girder can be hired in Singapore. girder.
◎ ○ △
Overall Most reasonable bridge type The steel girder use is not reasonable for high cost and
Evaluation ◎ ○ main material imported from third countries. △
◎ : Very Good ○ : Good △: Poor
Table 2-7 Comparative study for Bridge Superstructure
Alternative-A Alternative-B Alternative-C Alternative-D
Description Wall with Spread Foundation Column with Cast-in-situ Pile Beam with Cylinder Caisson Pile Bent
/Pre-fabricated Concrete Pile
1) Depth of water level is high (5~6m depth to seabed) 2) Seabed layer is sediment sand
Ground/Constructi 3) Basement layer is sand rock and depth from seabed is around 20m 4) Temporary jetty is required any foundation type to choose due to construction way to construction yard
on Condition at M annar Island, foundation work in the deep water and navigational clearance for fisheries' boats
View of Cross
Section
2-23
Hydrology - M inimize the affected structure area - Opening width is reduced due to a - Opening width is reduced due to bold - M inimize the affected structure area in
Characteristics in the water course ◎ bold column in the water course △ columns of caisson in the water course △ the water course ○
- Spread footing is located below water - Pile cap with more than 4 cast-in- - Traditional method of RC cylinder - Pilling work be done from temp.
level, huge cofferdam is necessary to place piles reach to the sand rock caisson of dia. 2.5~3.0m in Sri Lanka platform extended from the jetty with
install in the seabed so the layer. Construction of caisson is necessary rotary power drilling machine
construction period is extended. - or more than 6 pre-fabricated concrete - to build costly sand bank higher level transferred from the third country.
Construction
piles. than the water level. - Permanent steel tubular pipe is required
Ability
- Pile cap is located below water level, Depth of caisson in the coarse sand concreting in the water and protection
sheet pile cofferdam is necessary to layer must be deep due to avoid from the impact by the fisheries' boat
install so the construction period is - settling Piling work is faster than any other
△ extended. △ ○ - foundation. ◎
- M aintenance of seabed scoured - M aintenance of seabed scoured - M aintenance of seabed scoured - M aintenance of seabed scoured around
M aintenance around wall is necessary periodically. around column and pile cap is around caissons is necessary piles is necessary periodically.
○ necessary periodically ○ periodically ○ ○
- Construction costs are showing a - Construction costs are showing a - Construction costs are showing a - Less of the temporary structure is most
Economical
tendency to rise due to installation of tendency to rise due to installation of tendency to rise due to long economical method of the foundation
Aspects
cofferdam of steel sheet piles. △ both of cofferdam and jetty. △ construction period △ ◎
- Due to installation of cofferdam, cost Due to installation of cofferdam, cost Due to installation for casted concrete It is a suitable pier type aiming at cost
Overall Evaluation up and construction period is up and construction period is step by step, construction period is down
extended. △ extended. △ extended. ○ ◎
◎ : Very Good ○ : Good △: Poor
Table 2-8 Comparative Study for Abutment Substructure/Foundation
Alternative-A Alternative-B
Description
Inverted T-type Abutment Pile Bent Abutment
View of Cross
Section
- As Pile cap is installed below sea bed, abutment is not affected by local scoring due - As Pile cap is installed on the mound not to affect sea. The mound is filled widely
to waves. and protected by stone riprap.
2-24
Structural Futures - As large earth pressure forces to the abutment, the number of piles showing a - As light earth pressure forces to the abutment, the number of piles showing a
tendency to increase. tendency to reduce.
- The type of abutment is strongly resistance to horizontal force (earthquake). - The type of abutment is flexibly resistance to horizontal force (earthquake).
- As Pile cap is installed below sea bed, cofferdam is necessary to construct the piles - Construction of piles is easy to undertake on the ground above water level.
Construction and abutment. - Volume of excavation and concrete of abutment become small, so that the
Ability/Period - Volume of excavation and concrete of abutment become large, so that the construction period shortens.
construction period extends long. △ ○
- Concrete or wet masonry protection is applied against scoring and waves. - Slope protection around the mound is necessary to inspect periodically, but
- These protection is difficult to repair and maintain in case of defect for RDA maintenance is easy with simple repair of stone placing.
Maintenance
Mannar office Construction costs are showing a tendency to increase because - Construction costs are showing a tendency to reduce because excavation, number
abutment is large and . ○ of piles and concrete volume of abutments are relatively small. ○
- Construction costs are showing a tendency to increase because abutment is large - Construction costs are showing a tendency to reduce because excavation, number
Economical and coffer-dam for protection of the slope. of piles and concrete volume of abutments are relatively small.
Aspects - This type of abutment is not suitable for this project to minimize construction cost - This type of abutment is suitable for this project to achieve the cost reduction and
and maintenance in future although it is reliable △ easy maintenance after construction. ◎
This type of abutment is not suitable for this project to minimize construction cost This type of abutment is suitable for this project to achieve the cost reduction and
Overall Evaluation
and maintenance in future although it is reliable for scoring. △ easy maintenance after construction. ◎
◎ : Very Good ○ : Good △: Poor
(4) Structure of Causeway
The causeway structure is of embankment type with slope protection and retaining
wall type composed of vertical filling. Protection of this embankment type is the same as
for the approach roads (refer to Figure 2-5) such as wet or dry masonry and stone riprap.
The vertical filling is protected by reversed T-type or gravity type retaining wall. Both
types have advantages and disadvantages but the same type as the existing retaining walls
(vertical filling type) has been selected because the existing eastern retaining wall will be
used as the new eastern wall of the widened causeway after being reinforced. Based on the
1~2 year probability inundation on the existing causeway, the inundation level is estimated
at MSL+1.2m and the proposed height of the improved causeway is set up at MSL+1.4m
providing an allowance of 20cm which is the thickness of the base course.
1) Type of Retaining Wall
There is no record of large scale repair of the causeway since the Netherlands
constructed it in 1918. The RDA Mannar Office is repairing the retaining walls damaged
by heavy traffic applying RDA’s standards. The Study Team judged that the type of
retaining wall constructed by the Netherlands is suitable for the site conditions in Mannar
in both technical and economical aspects. However, the Study Team inspected and studied
the damaged retaining walls and found the causes of damage. Based on the Team’s
findings, the new retaining wall has been classified by four types for each height, and
designed referring to the RDA Bridge Design Manual, 1997 and BS5400 Part 2, 1978.
a) Retaining wall under 1.0m (Type-A), 1.0~3.5m (Type-B and Type-C)
The retaining walls of Type-A, Type-B and Type-C, which are a gravity type with
a wet masonry as shown in Figure 2-7, are stable against earth pressure and are economical.
These retaining walls have been adopted in the design in consideration of the RDA
standard retaining wall. The front of retaining walls is covered with reinforced concrete
(15cm thick) to prevent damage to the surface of wet masonry.
b) Retaining Wall over 3.5m (Type-D)
The retaining wall of Type-D, which is a reversed T-type concrete wall as shown
in Figure 2-7, has been selected for a height of over 3.5m. Placing of pre-cast blocks may
be applied for the reversed T-type concrete wall but it is costly due to the use of heavy
concrete blocks. Cast-in-place concrete in the dry condition at the site is more economical
considering the construction schedule with work concentration in the dry season.
2000
2500
3500
2-25
2) Culverts
The causeway has 2 stone arch culverts and 6 pipe culverts connecting the lagoon
(tidal land) on both sides. To maintain the existing ecological system, the culverts will be
rehabilitated. They have been designed with the same existing features. The type, size,
state of damage of culverts and their rehabilitation method are shown in Table 2-9.
Table 2-9 Existing Conditions and Rehabilitation Method of the Culverts
Stone Arch Culverts 2xφ2.1xH1.2m Some key stones are moved Extension of culvert and repair at top
2
at top of arch with RC concrete
3 Pipe Culverts 12xφ0.90m Relatively good condition Extension of pipe culverts
Stone Arch Culvert 2xφ1.6xH0.85m Relatively good condition Extension of culvert and repair at top
4
with RC concrete
Pipe Culverts 4xφ0.60m Deteriorated and clogged Removal of old pipes and installation
5
pipes of new pipes in same number and size
Pipe Culverts 4xφ0.60m Deteriorated and clogged Removal of old pipes and installation
6
pipes of new pipes in same number and size
Pipe Culverts 4xφ0.60m Deteriorated and clogged Removal of old pipes and installation
7
pipes of new pipes in same number and size
Pipe Culverts 4xφ0.60m Clogged pipes Removal of old pipes and installation
8
of new pipes in same number and size
3) Settlement Measure
From the results of the centerline survey on the causeway, it was found that
settlement occurred along the causeway. As a very soft layer of 2~3m thick is deposited on
the seabed of the lagoon, necessary measures dealing with settlement should be taken for
the widening area before embankment. The considered measures against settlement
include i) Pre-loading Method, ii) Displacement Method, iii) Drain Method, and iv)
Concrete Slab Method, as described below:
a) Pre-loading Method
The pre-loading method is a standard and economical method for settlement but it
takes long time to consolidate and complete the settlement on soft ground. This method is
not applicable in the limited construction period and space which leads to ineffective
surcharge and compaction. It is also uneconomical because the surcharged material is not
re-used for the other construction.
b) Displacement Method
The displacement method that consists in excavating and replacing the soft ground
with good embankment material is a reliable measure against settlement. However,
construction of cofferdams with steel sheet piles is required for excavation of soft ground,
resulting in cost increase. To minimize the cost, coffering works should be carried out
during the low tide in the dry season to provide small scale cofferdams. The displacement
method presents no problem even within a limited construction period because
consolidation period is not concerned.
c) Sand Drain Method
Prior to applying the pre-loading method, drain pipes are excavated and filled with
sand to accelerate consolidation of soft ground. The sand drain method can reduce the
construction period in comparison with the pre-loading method but still cause a little
2-26
problem with regard to the construction period due to the import and inland transportation
of sand drain machines, and low working efficiency in the limited place.
d) RC Concrete Slab Method
The RC slab method is suitable for structural and economical aspects because the
existing retaining wall and new retaining wall are used for slab pedestals. However, repair
and maintenance of damaged RC slabs is difficult for the RDA Mannar Office. Slab
pedestals are not durable against settlement.
e) Overall Evaluation
The construction of the widened causeway consists of application of
counter-measures for settlement, embankment of retaining walls and pavement in a
continuous sequence on the critical path. Considering the construction period of 29 months,
the displacement method and RC concrete slab method are deemed appropriate. However,
the displacement method is reliable against settlement and is economical in view of cost
reduction by concentrating coffering works during the low tide in the dry season. The
overall evaluation of the settlement measures is summarized in Table 2-10.
2-27
Table 2-10 Comparative Table for Measure of Settlement on the Causeway
Alternative-A Alternative-B Alternative-C Alternative-D
Description
Pre-loading Displacement Drain RC Concrete Slab
Table 2-10
盛土 盛土
Plan
置き換え土 ドレーン
although cost is low procedure because no need to wait for consolidation time to provide sand along causeway.
Execution Period consolidation. drains, it is still not enough
△ ◎ ○ ○
Short pre-loading time and limited Displacement (2-3m) with selected soil Settlement can be minimized due to There is a risk on cracks on RC slab
loading height are ineffective for checking bearing strata is effective. drains to shorten consolidation time. due to the settlement of new retaining
Effectiveness
consolidation. Settlement is expecting wall
Settlement
in future.
△ ◎ ○ △
It is a popular method with the lowest Cost is relatively higher than other Cost is relatively higher than other RC Concrete Slab is the most expensive
cost plans due to cofferdam. But, execution plans due to cofferdam. But, execution in the alternatives. Maintenance cost is
Cost is concentrated in dry season to is concentrated in dry season to relatively high.
minimize cost. minimize cost.
◎ ○ △ △
Although it is the lowest cost, it is It is the most reliable method for Settlement can be minimized but Risk of cracks on slab due to
expecting to the decline of retaining measure of settlement. Cost can be execution time is longer than settlement and its difficulty of
Overall wall and cracks on pavement with short reduced to concentrate on coffering displacement method. maintenance are not acceptable.
Evaluation pre-loading. works in dry season.
△ ◎ ○ △
◎ : Very Good ○ : Good △: Poor
(5) Structure of Pavement
Asphalt pavement is more popular than concrete pavement for road construction in
Sri Lanka. Except a part of the main road, double bituminous surface treatment (DBST)
will be applied for the road surface as stipulated in RDA Pavement Manual. There is no
asphalt plant operating in the northern area and road repair is done by penetration
macadam. In view of such a situation in the northern area, DBST has been selected for
surface pavement considering extensive accomplishments by this method in Sri Lanka, its
economical and easy application and the experience of the RDA Mannar Office in the
maintenance of this kind of pavement.
1) Standard of Pavement
The pavement of causeway and approach road has been designed with a CBR
value determined from the geotechnical survey results. The new pavement on the widened
section of the causeway and the raising and overlay on the existing pavement have been
designed on the basis on the Guide to the Structural Design of Roads under Sri Lankan
Condition. The design life of pavement has been determined to be 10 years considering the
future traffic volume stated the above Guide.
2) Cumulative Number of Standard Axles
The cumulative number of standard axles that will traverse the road in the course
of its design life is estimated with the factors such as daily traffic volume, rate of traffic
growth by vehicle type, equivalent standard axle (ESA), as shown in Table 2-11. The
applied rates of traffic growth by vehicle type are the average rates stipulated in RDA
Guideline (A Guide to the Structural Design of Loads under Sri Lankan Condition, April
1999). According the RDA Guideline, the cumulative number of standard axles (3.66 x
106) is classified as T5.
Cumulative
Traffic Growth
Daily Traffic Equivalent Number of
Vehicle Type Rate by Vehicle
Volume Standard Axle Standard Axles
Type (%)
(x 106 )
Heavy Vehicle 446 5.5 1.88 2.13
Medium Vehicle 368 5.5 1.17 1.10
Light Vehicle 944 3.5 0.01 0.01
Long Bus 486 4.0 0.30 0.34
Mini Bus 371 4.0 0.09 0.08
Total 2,615 3.66
2-29
Traffic classe T5 Traffic classe T5 Traffic classe T5
(Subgrade strength (Subgrade strength (Subgrade strength
classe S3) classe S4) classe S5(a))
SD 20
DBST SD 20
DBST
225 225
DGAB DBST 20
225 225
DGAB SD
325 325mm
SSB1 250 250 DGAB
250 250
SSB1 SSB1
150 150
To Mannar Island
To Mannar Island To Mannar Island
6.3m 6.3m
9.2m 9.2m
Rotary Junction T-shaped Junction
To Vavuniya To Vavuniya
2-30
(7) Traffic Safety Facilities and Ancillary Facilities
1) Pre-cast Concrete Hand railing
Pre-cast concrete handrails consisting of posts and railings will be provided on the
bridge for protection of pedestrians from falling. Handrails have been designed applying
RDA standards.
2) Kerb Stones
Kerb stones will be provided on the bridge for preventing vehicles from running
onto the foot walk that is a special device used by RDA. Kerb stones are made of pre-cast
concrete according to RDA standards.
3) Guardrails
As the height of embankment behind abutments is approximately 6.0m, steel
guardrails with steel posts embedded in ground will be provided for protection of
pedestrians from falling. Guardrails will be installed on the embankment sections higher
than 2.0m on both sides of the approach road.
4) Guard Stones
Guard stones will be provided on the causeway for preventing vehicles from
falling into the lagoon. Concrete guard stones of the same type as that installed on the
existing causeway will be placed on the top of retaining walls at 2.5m intervals.
5) Expansion Joints
Expansion joints designed according to RDA standards are of simple steel
fabrication used for small bridges and are not good for long bridges like the Mannar
Bridge and not suitable for use at the seashore. It is necessary to use imported expansion
joints suitable for long bridges and durable against salty water. Therefore, the expansion
joints to be used for the Mannar Bridge will be imported from Japan and fabricated
according to the Japanese quality standards.
6) Bridge Drainage
The average annual rainfall at the bridge site is not high at about 980mm, therefore
it is not necessary to provide drain pits, which are difficult to clean and remove debris for
maintenance. Only drain pipes designed according to RDA standards will be provided.
7) Illumination on Bridge
Illumination will be provided only for the bridge section to ensure safety for
passing ships under it. The illumination on bridge has been designed according to RDA
standards and AASHTO standard. Electric power required for the illumination will be
supplied from the low voltage power line near the gasoline station in the Mannar Island.
2-31
Table 2-12 Mannar Bridge and Approach Road
Item Mannar Bridge Approach Road
The approach road will be
Improvement Method The bridge will be reconstructed.
reconstructed.
Class of Road Class-A, Local, Plain Class-A, Local, Plain
70 km/hr
Design Speed 70 Km/hr
Near Junction:60km/hr
Cross Section Carriageway: 3.7m x 2= 7.4m Carriageway: 3.7m x 2= 7.4m
Shoulder (Foot walk): 1.5 (1.2)m x 2 Shoulder (Foot walk): 1.8 (1.2)m x 2
Total width: 10.4m Total width: 11.0m
Total Length of Bridge Junction at beginning point: 140 m
157.1 m
and Approach Road Bridge on Mannar Island side: 158m
Bridge on Mainland side: 155 m
Span (Girder Length) 6 spans (26.2m) -
Type of Structure Concrete Bridge Approach to abutment with
embankment
Superstructure PC precast I-Girder (30 girders)
Substructure 5 Bridge piers: pile bent
2 Bridge abutments: pile bent
Foundation Cast-in-place concrete pile (φ1.2m):
627m
Pavement Asphalt concrete pavement Min. 50mm Carriageway: DBST: 20mm
(Cold mixed type) Shoulder: DBST: 20mm
Falling Protection Pre-cast concrete hand railing : 310m Steel guardrail: 160m
Slope Protection Stone riprap: 720m3 Sodding
Illumination Facilities Bridge section: 157.1m(H=10m), one side -
2-32
2-2-3 BASIC DESIGN DRAWINGS
The basic design drawings are provided in Appendix-1
2-33
(3) Permission to Labour, Materials and Equipment in site
To minimize and smooth the security control during the construction at the
junction of the beginning point on the mainland side and beside of the Mannar bridge, the
following measures shall be taken:
- ID cards will be issued by the Army in Mannar to and carried by all staffs working in
the site;
- Japan ODA logo marks will be stuck on all equipment operating in the site to
distinguish between the general and construction vehicles.
2-34
aggregate, sand, water and cement, low W/C, air contained calibration of concrete plant,
regulation on transportation and placing of concrete should be given utmost attention.
2-35
2-2-4-4 Consultant Supervision
(1) Supervision
The engineering services for construction supervision will begin with the
acceptance of the construction contract and the issuance of a Notice to Proceed (N/P) to
the Contractor.
The Consultant shall perform his duties in accordance with the criteria and
standards applicable to the construction works and shall exercise the powers vested in him
as the Engineer under the Contract to supervise the field works by the Contractor.
The Consultant within his capacity as the Engineer shall directly report to RDA
and JICA Colombo about the field activities and shall issue field memos or letters to the
Contractor regarding various matters, including progress, quality, safety and payment for
the works under the Project. After one year from the completion of the construction, the
Consultant will conduct the final inspection for defects reliability as the final task of the
Consultant.
(2) Implementation Organization
A Resident Engineer will basically stay at the construction site and conduct both
construction supervision and project management. The necessary specialists for each stage
are as follows:
- Team Leader : Coordination and liaison for all the project activities to ensure
smooth progress and management in all technical aspects
- Bridge Engineer : Technical and quality control of bridge works
- Road Engineer : Technical and quality control of causeway and approach road
2-36
Table 2-15 Quality Control Tests Plan
Item Test Method Frequency
Liquid Limit, Liner Shrinkage
(< Sieve No.4)
Sieve Gradation
Crushed Mixed Material Each site/Crushing plant
Abrasion Loss
Rock
Aggregate Density
Maximum Dry Density
Paving Field Density (Compaction) Daily
Prime Coat Quality Certificate
and Material Bitumen
Tack Coat Applied Volume/Weight Every 500m2
Quality Certificate & Chemical
Bitumen Every material
Analysis
Material Sieve Gradation Every mixing
Aggregate Water Absorption
Every material
Abrasion Loss
Marshall Stability
Marshall Flows
Cold Mix
Air Voids
Asphalt
Mix Requirement Voids in Material Aggregate Every mixing
Indirect Tensile Strength
Immersion (Strength) Index
Bitumen Content
Temperature in Mixing Each site
Compaction Temperature in Compaction Each site
Sampling (Marshall Test) Each site
Quality Guarantee, Chemical &
Cement Every material
Physical Analysis
Water Chemical Analysis Every material
Admixture Quality Guarantee, Chemical Analysis Every material
Bulk Specific Gravity Dry
Fine
Material Sieve Gradation, Finesse Modulus Every material
Aggregate
Clay and Friable Particles
Concrete Bulk Specific Gravity Dry
Coarse Flakiness Index
Every material
Aggregate Sieve Gradation
Sodium Sulfate Soundness
Mixing Test Calibration of Batching Plant Before starting concrete works
Slump Daily
Pouring
Concrete Temperature before Pouring Daily
Strength Compressive Strength at 7 & 28 days Daily or every 50m3
Re-bar/PC
Material Quality Certificate Each lot
strand
Calibration of Hydraulic Jacks and Before starting prestressing
Prestressing Equipment
PC Stressing Pump works
Control of Prestressing Graph of Prestressing Control Each stressing
Mixing Test Calibration of Mixer Before grouting works
Grouting Pouring Consistency, Temperature
Every mixing
Strength Compressive Strength at 7 & 28 days
2-37
2-2-4-6 Procurement Plan
Bridge construction materials such as steel, reinforcing bar, PC cable, etc. cannot
be procured inside Sri Lanka, but are available in Singapore. However, PC cable and its
anchors including tensioning jack, rubber bearings and expansion joints will be imported
from Japan to ensure good quality and durability against saline water. Construction
equipment such as PC girder erection machine (erection girder method) and all casing
bored pile machine is not available in Sri Lanka and Singapore, so this equipment will be
procured from Japan.
There is no a concrete plant in Mannar but it is available in Colombo. To control
the quality of concrete effectively, concrete plants will be procured from Colombo and
installed inside the camp yard.
Aggregates and stones will be purchased from the suppliers having crushing plants
located at Madukanda and Mihintale. Principal construction materials can be procured as
shown in Table 2-16 and. Table 2-17.
Third
Materials Sri Lanka Japan Reason Import Route
Country
Portland Cement ○
Aggregate/Sand ○
Reinforcing Bar ○
Steel/Sheet Pile ○
PC Strand and No production in Sri Marine
○
Anchorage Lanka transportation
Admixture ○
Wood/Plywood ○ -
Bituminous Material ○ -
Fuel (Diesel and -
○
Gasoline)
Rubber Bearing No production in Sri Marine
○
Shoes Lanka transportation
Expansion Joint ditto ditto
○
(Rubber)
Plaque Plate ○ ditto ditto
2-38
Table 2-17 Indicative Procurement of Construction Equipment
Third
Items Procurement Sri Lanka Japan Route of Transport
Country
Inland transport from
Bulldozer lease ○ - -
Colombo
Backhoe lease ○ - - ditto
Dump Truck lease ○ - - ditto
Truck Crane lease ○ - - ditto
Motor Grader lease ○ - - ditto
Road Roller lease ○ ditto
Tire Roller lease ○ ditto
Asphalt Distributor lease ○ - - ditto
Concrete Plant lease ○ ditto
Agitator Truck lease ○ ditto
Vibration Hammer lease ○ ditto
Breaker with Crawler Crane lease ○ ditto
All Casing Bored Pile Sea transport from Japan
lease ○
Machine to Colombo
Casing Pipe φ1200mm lease ○ ditto
Hammer Grab lease ○ ditto
Gantry Crane lease ○ ditto
PC Tendon/Jack and Pump lease ○ ditto
Erection Girder lease ○ ditto
4-wheel Drive Vehicle lease ○ ditto
2-39
Table 2-18 Tentative Implementation Schedule
Month 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29
(Site Survey)
(Detailed Design 4 months)
(Works in Japan)
Detailed Design
(Works in Japan)
(Tendering 3 months)
(Contract of Contractor)
(Mobilization)
(Construction Period 29 months)
(Foundation/Substructure)
(Fabrication of PC Girder)
(Bridge Accessories)
(Finish Work)
2-40
2-3 OBLIGATIONS OF THE RECIPIENT COUNTRY
- Relocation of the gasoline stand and 2 abandoned houses affected by the works:By the
End of August 2007;
- Provision and clearance for the main camp yard and temporary construction yards at
both bridge sides:By September 2007;
- Relocation of a water supply pipe affected by the works at the site during construction;
- Relocation of telephone lines affected by the works at the site during construction;
- Provision and clearance for the main camp yard:By September 2007.
- Provision of the soil disposal and construction waste areas:By September 2009.
- Issue ID cards to all staffs and security stickers on all vehicles and equipment : By
November 2007
- Assignment of security policemen on full time basis at the camp yard and the
construction yards:From October 2007 to February 2010.
2-41
2-4 PROJECT OPERATION PLAN
- Repair of revetment around abutments and retaining walls after cyclone (at every two
years)
- Overlay of surface layer of bridges, causeway and approach roads at every 5 years
- Repair of bearing shoes and expansion joints at every 10 years
2-42
2-5 COST ESTIMATE
2-43
(3) Condition of Cost Estimate
- Estimate Time 2006 : Average rate of 6 months before the end of July
- Exchange Rate : 1.0 Rs = 0.0098 US$ (= 1.1443 Yen)
: 1.0 US$ = 116.77 Yen
- Construction Period : 29 months
The Project will be implemented under the Japan’s Grant Aid scheme. The above
project costs would be revised by the Japanese Government before issuing the Exchange of
Notes (E/N).
2-44