Mars Manual-210608
Mars Manual-210608
700KW-1250KW
STATIONARY LOAD BANK
Last Revision Date: June 8, 2021
For the most up-to-date information for this product and others,
please contact Simplex, Inc. at (800) 637-8603 or
visit us on the web at http://www.simplexdirect.com.
Table of Contents
1 Warnings and Cautions......................................................... 1
Safety information symbols 1
Cautions 1
2 Nameplates and Placards...................................................... 5
3 Description and Specification............................................... 9
Overview of Use 9
Control System 9
Cooling System 9
Load System 9
Safety 9
4 Unpacking............................................................................11
Included Components 11
Primary Inspection 11
5 Installation...........................................................................13
Load Bank Placement 13
Installation Procedure 15
Remote HMI installation 16
Load Dump installation 17
Current Transformer installation 18
MODBUS installation 20
Heater installation 21
BMS/BAS Installation 22
6 Setup.....................................................................................23
General Settings 23
Automatic Mode 23
7 Operating Instructions........................................................25
Pre-operation checks 25
Setting up the test 25
Testing operation 26
Metering (if equipped) 26
Shutdown and cooling 26
8 Automatic Mode ..................................................................27
Overview 27
Setting Up Automatic Mode 28
Entering Automatic Mode 28
9 Maintenance/Troubleshooting...........................................29
General maintenance 29
Each Operation 29
Every 6 Months 29
Troubleshooting 30
10 Alarms and Warnings...........................................................31
Alarms 31
Warnings 31
!
This Fire warning symbol points out potential fire
hazards.
! Its fumes are toxic, and the liquid can deteriorate wiring
insulation. Keep the extinguisher properly charged and be
familiar with its use. If there are any questions pertaining to
fire extinguishers, please consult the local fire department.
• The illustrations in this manual are examples only and may
differ from your load bank.
• Load Bank warranty is void if incorrectly cooled.
(800) 637-8603
www.simplexdirect.com
PN 24055502
Safety The Mars is protected by sensors to ensure that the load bank
is sufficiently cooled and that the exhaust does not exceed a safe
Description and Specification — 9
temperature, which could damage the load bank or present a
safety hazard to the operator. When a failure occurs, the safety
system immediately removes the load to protect the equipment
from permanent damage.
Table 1 Current draw at specified resolutions (in kilowatts)
These measurements are based on ideal numbers. They do not take into account
control power draw, power cable resistance, voltage droop, etc.
1. Load bank
2. Controller (remote or local)
3. Manual
4. Drawing package
Optional equipment
1. Additional controllers
2. Exhaust hood
3. Current transformers
4. Other optional equipment
Primary Before installing your Mars, inspect the shipping crate and
Inspection load bank. Physical or electrical problems could arise from
handling and vibration. Never apply power to a load bank before
performing this procedure. The following five-point inspection
is recommended before installation and as part of a 6-month
maintenance schedule or when the load bank is relocated:
If any 1. If the crate shows any signs of damage, examine the load
problems bank in the corresponding areas for signs of initial problems.
are observed 2. Check the entire outside of the cabinet for any visual damage,
during which could cause internal electrical or mechanical problems
Primary due to reduced clearance.
Inspection, 3. Open the control panel door and inspect all relays and
call Simplex control modules. Make sure all components are secure in
24 hours a their bases and safety bails are in place. Spot-check electrical
day at connections for tightness. If any loose connections are found,
800-637-8603 inspect and tighten all remaining connections.
4. Examine all accessible internal electrical components such
as fuses, contactors, and relays. Check lugged wires at these
components.
5. Check the load element chamber for foreign objects, broken
ceramic insulators, and mechanical damage.
Unpacking — 11
5 INSTALLATION
Load Bank Normally equipped, Mars Figure 1 Air Flow
Placement load banks are intended
for outdoor installation. A
forced air system, which
discharges out of the top
of the unit, cools the load
elements (See Figure 1 Air
Flow.) Load banks require
large quantities of air
Improperly circulation, so it is essential
installing to install the unit in an
this unit may area that provides adequate
result in airflow. Before conducting
damage or load tests, a review of site
destruction conditions by trained
of the personnel is recommended.
load bank,
The load bank requires at
adjacent
least 20 feet of vertical clearance; 6 feet of clearance on the front,
equipment,
left, and right; and 1.5 feet of clearance in the rear (see “Figure 2
and the
Clearance requirements” on page 14).
building
housing the The load bank should be placed in a secure area accessible by
unit. trained personnel only.
Because the unit generates a lot of heat, never operate near
sprinkler systems.
Operating the load bank in a confined space will recycle hot
exhaust air through the cooling system, which can cause severe
damage.
The load bank may compete with nearby generators for
cooling air.
Installation — 13
Figure 2 Clearance requirements
14 — Installation
Installation 1. To bring in the source’s Figure 3 Ground Bus
Procedure power cables, pull holes
in the Conduit Opening,
located in the bottom of
the load bank’s control
panel enclosure (see
Mars load Figure 5 Conduit
banks feature Opening).
a power 2. Confirm the test source is
outlet in the properly grounded.
control panel 3. Ground the load bank
for your use. by connecting the
This outlet is Grounding Bus to an earth
limited to 2 ground or grounding rod. Figure 4 Main Load Bus
amps. See Figure 3 Ground Bus
4. Connect the source’s
power output to the load
bank via the Main Load
Bus with appropriately
sized cables (see Figure 4
Main Load Bus).
Installation — 15
Remote HMI If your HMI is installed Figure 6 HMI TBH
installation directly on the load bank,
skip to the next section.
16 — Installation
Load Dump If the Load Dump Figure 9
installation feature is desired, remove Load Dump Jumper
the factory-installed
jumper at TB-R 1–2 and
connect customer-supplied
Load Dump contacts to
TB-R 1–2 (See Figure 9
Load Dump Jumper). To
dump the load, open the
customer-supplied contact.
To enable load, close the
customer-supplied contact.
Installation — 17
Current If your load bank is Figure 10
Transformer equipped with Metering, Current Transformers
installation Automatic Mode or
Regenerative Mode options,
you will have to install
current transformers on
your power cable.
18 — Installation
Figure 13
Current
Transformer
placement for
Metering
Figure 14
Current
Transformer
placement for
Auto/Regen.
Mode
The first current transformer must be installed on Phase A, and the second must be
installed on Phase C.
Installation — 19
MODBUS The Mars load bank Figure 15 TB-COM
installation supports the Modbus
protocol, implemented
either as RS485 or TCP/
IP (which is an optional
upgrade).
To implement Modbus
control and monitoring,
connect the load bank to
your facility’s systems as
follows:
For RS485:
Figure 16 Modbus Serial
1. Connect the RS485+ line Converter
to TB-COM 1
2. Connect the RS485- line
to TB-COM 2
3. Connect the wire
shielding to TB-COM
Terminal 3
20 — Installation
Heater Mars load banks are Figure 17 TB-SH
installation equipped with space heaters
for cold weather operation
and to prevent condensation,
which can damage the
unit. The heaters require
a dedicated power source
independent of control
power at all times to prevent
startup failure due to cold
environments.
To run power to the
heaters:
1. Run a 120V, 15A, 1-phase power cable into the control panel.
2. Connect the Line leg of the power cable to SH-1
3. Connect the Neutral leg of the power cable to SH-2
4. Connect the Ground leg of the power cable to SH-3
The heaters are set at 50 degrees Fahrenheit. If a different
temperature is required, adjust the red thermostat on the front
of the heater.
Installation — 21
BMS/BAS The Polaris provides a Figure 18 TBR
Installation set of Remote Signal Dry
Contacts, which allow you to
integrate the load bank into
your Building Management
System (BMS) or Building
Automation System (BAS)
The dry contacts provide an
alarm message, letting you
know if the load bank has
failed.
To enable BMS/BAS
functionality, wire three
cables to TBR 5-7. Continuity between TBR 5 and TBR 6 indicate
normal load bank operation, and continuity between TBR 5 and
TBR 7 indicate load bank failure.
22 — Installation
6 SETUP
The Mars load bank offers Figure 19 Setup Screen
a number of configuration
Mars load options through its setup
banks feature screens. You can access the
a power setup screens by pressing “F4
outlet in the - Setup” or the F4 function
control panel key.
for your use.
This outlet is At the main setup screen,
limited to 2 you are presented with four
amps. options:
1. General Settings
2. Automatic Mode Settings
3. Test Mode (Intended only for Simplex engineers)
4. Factory Setup (Intended only for Simplex engineers)
Testing To begin testing, press the “Master Load” button. This will
operation activate the load bank and begin applying the load displayed
in the upper right area of the screen. To quickly decrease or
increase the load, press the “-” and “+” buttons.
Shutdown and When the test is complete, press the Master Load button then
cooling the Control Power button to remove the load from the test source.
The load bank’s fan will continue running for the duration of the
cooldown delay (see page 23 for more information).
26 — Operating Instructions
8 AUTOMATIC MODE
Figure 27 Setup Screen
The Mars load bank can
be equipped with an optional
automatic mode, which will
extend your generator’s life
by protecting it against wet-
stacking and reverse current.
10%
10%
Entering When your load bank is configured, return to the main screen
Automatic by pressing the “Back” button. From the Main screen, press the
Mode “F2 - Auto” button or the F2 function key to enter the Automatic
Mode screen (See Figure 30 Automatic Mode Running.)
On the Automatic Mode screen, press the “Auto Mode”
switch. Once this mode is enabled, the load bank will monitor
your generator and step the load up or down as necessary.
Once configured and enabled, your load bank can remain in
Automatic Mode indefinitely.
28 — Automatic Mode
9 MAINTENANCE/TROUBLESHOOTING
General The load bank has been designed to require minimum
maintenance maintenance. All components have been chosen for a long,
reliable life. Two basic intervals of maintenance are required:
each operation and every 6 months.
Each • Check the air intake screens and louvers, fan and cooling
Operation chamber, and exhaust openings for any obstructions or
foreign objects.
• Check fan blades for stress fractures.
• Check the exhaust vent for obstructions
Remove all • Check the load branches for blown fuses or opened load
power from resistors.
the load bank
before To check the fuses or load resistors, operate the load bank
servicing the from a balanced 3-phase source and check the three line
unit. currents. The three current readings should be essentially the
same. If a sizable difference is noted, one or more load fuses or
load resistors may have malfunctioned.
Maintenance/Troubleshooting — 29
Trouble Although Mars load banks are designed with trouble-free
shooting operation in mind, some problems can arise. Please consult the
following table for solutions to the most common issues before
contacting a Simplex service representative.
Table 2 Troubleshooting
Problem Solution
Load bank Ensure load bank is wired to source correctly
wired to
Check for and replace any blown fuses
source but
won’t turn on Tighten any loose relays, contactors, lugged wires, etc.
30 — Maintenance/Troubleshooting
10 ALARMS AND WARNINGS
Mars load banks are protected by four types of sensors.
Alarms The Mars load bank’s HMI features five status areas:
Warnings The Mars features one warning: Intake Temp High. When
this warning is triggered, the Intake Temp status area will turn
yellow.
Mars load banks do not dump load when a warning is
triggered, but the problem should be investigated as soon as
possible.
Intake Temp
Ensure load bank has
Insufficient airflow access to sufficient
cool air intake
Load Dump
Load dump jumper Replace load dump
fell out of TB-LD 1-2 jumper
Option D - Automation/
Metering page 34
Option E - Communication
(TCP/IP Data Logging)
page 35
PLC
page 36
Control Relays
page 38
Parts listings - 33
Table 4 Option D - Automation/Metering
Terminal Block, 4
TB-M 1 25678547
Connections, Black
Terminal Block, 4
TB-M 2 25678546
Connections, Red
Terminal Block, 4
TB-M 3 25678557
Connections, Blue
Terminal Block, 4
TB-M 4, 6 25678536
Connections, Grey
Terminal Block, 4
TB-M 5, 7 25678537
Connections, Green
Digital Metering
DMP1 24345050
Package, RS232
34 - Parts listings
Table 5 Option B - Communication (TCP/IP Data Logging)
Modular Controller
CM1 and Protocol 24955043
Converter
Ethernet Switch, 5
NS1 24955074
Port, Unmanaged
Parts listings - 35
Table 6 PLC Component list
4PT Thermocouple
EX2 24955023
Input Module
DC Power Supply,
DC1 25457900
60W, 24VDC
RS232/RS485
CM2 24953500
Converter, RJ12 Port
Terminal Block,
Spring Type,
TB-COM1-6 25678532
20A, 600Vac, 2
Connections, Grey
36 - Parts listings
Parts listings - 37
Table 7 Control Relays
38 - Parts listings
2A
Parts listings - 39
Table 8 Terminal Blocks
40 - Parts listings
Parts listings - 41
Table 9 Option 010 - Space Heaters
Terminal Block, 2
TB-SH 1-3 25678532
Connections, Grey
Enclosure Heater,
HTR1 120Vac, 550W w/ 25309211
Thermostat
42 - Parts listings
Phase A
page 45
Phase B
page 46
Phase C
page 47
Load
control
Subpanel terminal
blocks
page 48
Parts listings - 43
Table 10 Center Subpanel
Contactor, 40A
RC 1-6 13011040
Resistive
Contactor, 65A
RC5-15 13011065
Resistive
Contactor, 40A
FMC1 13011040
Resistive
Transformer, 300VA,
T1 25457650
480/240:240/120Vac
44 - Parts listings
Table 11 Phase A Detail
Parts listings - 45
Table 12 Phase B Detail
46 - Parts listings
Table 13 Phase C Detail
Parts listings - 47
Table 14 Load Control Terminal Blocks
Terminal Block, 4
TB-L 1 25678547
Connections, Black
Terminal Block, 4
TB-L 2 25678546
Connections, Red
Terminal Block, 4
TB-L 3 25678557
Connections, Blue
Terminal Block, 2
TB-L 4-19 25678532
Connections, Grey
48 - Parts listings
Appendix B — MODBUS CONTROLS
Table 15 Modbus Controls (Read/Write)
Function
Name Type Address
Code
Activate Coil 01 16586
Fan
Apply Load Coil 01 16704
Modbus controls - 49
Table 16 Modbus Indications (Read only)
Function
Name Type Address Notes
Code
Fan Failure
Coil 01 16485
Alarm
Load Dump
Coil 01 16486
Activated
Floating
Applied Load 03 29077
Point
Regulate Mode
Coil 01 16705 (a)
Active
Regenerative
Sensing Mode Coil 01 16706 (b)
Active
Floating
Vab 03 28673 (c)
Point
Floating
Vbc 03 28675 (c)
Point
Floating
Vac 03 28677 (c)
Point
50 - Modbus controls
Table 15 Modbus Indications (Cont.)
Function
Name Type Address Notes
Code
Va Floating
03 28679 (c)
Point
Modbus controls - 51
Modbus 1. Ensure that “Regulate Mode Active” (16705) and
Control “Regenerative Sensing Mode Active” (16706) are OFF,
Directions indicating that the load bank is ready for Modbus Control
2. Turn “Activate Fan” (16586) ON to energize the cooling fan
3. Verify fan is running by checking that “Fan Running” (8193
is ON
4. Write the desired amount of KW to apply to “KW To Apply”
(28911)
5. Turn “Apply Load” (16704) ON to energize the desired
amount of load
6. Verify applied load by reading value at “Applied Load” 29077.
The load bank will apply as much load as possible to reach the
“KW To Apply” value, without exceeding it.
7. Monitor other values as desired.
8. Turn “Apply Load” off to de-energize the load
9. Turn “Activate Fan” OFF to stop the cooling fan. Load bank
will continue to operate cooling fan for Cooldown Time set
on HMI.
10.Cooldown mode has ended and cooling fan has stopped
when “Fan Running” is OFF
11.Cooldown mode can be stopped by writing ON then OFF to
“Cancel Cooldown” (16487)
52 - Modbus controls
Contact Simplex
for all your Load Bank and Fuel Supply needs.
Simplex, Inc.
5300 Rising Moon Road
Springfield, IL 62711
800-637-8603
www.simplexdirect.com