0% found this document useful (0 votes)
476 views8 pages

Element - 111 - 579-Bill of Quantity For Constructing Main House of Mosque

This document provides a bill of quantities for constructing the main house of a mosque. It includes 8 sections (A-H) that list materials, units, quantities, rates, and amounts for items like preliminary works, substructure, superstructure, roof structure, doors/windows, electrical installation, plumbing installation, and finishing works. The total estimated cost is over 30 million Rwandan francs.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
476 views8 pages

Element - 111 - 579-Bill of Quantity For Constructing Main House of Mosque

This document provides a bill of quantities for constructing the main house of a mosque. It includes 8 sections (A-H) that list materials, units, quantities, rates, and amounts for items like preliminary works, substructure, superstructure, roof structure, doors/windows, electrical installation, plumbing installation, and finishing works. The total estimated cost is over 30 million Rwandan francs.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 8

BILL OF QUANTITY FOR CONSTRUCTING MAIN HOUSE OF MOSQUE

ITEM DESCRIPTION UNIT QTY RATE AMOUNT


A Preliminary works
1 Site installation including site hoarding, site lighting,
temporary washrooms and sign board Item 1 200,000 200,000
2
General Leveling of the whole plot, excavation and
take away all excavated soil away from the site
regardless to the offloading place. Item 1 250,000 250,000
3 Setting out the building Item 1 100,000 100,000
S/Total 550,000

B SUBSTRUCTURE
1 Excavate for strip foundation 400mm wide and to a depth
n.e 1.5m. m³ 52 1,500 78,000
2 Excavate for pad foundation of 400 x 400mm in size but
not exceeding 1.00m deep m³ 20.5 1,500 30,750
3 200 x 200mm thick reinforced concrete beam of mixing
ratio 350kg/m³ with bars of 12mm diam. + Wooden
formwork of first choice, including fixing and supply,
sectioning, bending and fixing the bars. m³ 1.4 200,000 280,000
4 50mm thick blinding concrete layer for strip and pad
foundation of mixing ratio 250kg/m³ m³ 2.8 15,000 42,000
5 200*200mm Reinforced concrete column footing of
mixing ratio 350kg/m³ with bars of 12mm diam. +
wooden formwork of first choice, including fixing and
supply, sectioning, bending and fixing the bars. m³ 2.8 200,000 560,000
6 200 x 200mm thick reinforced concrete ground beam of
mixing ratio 350kg/m³ with bars of 12mm diam. +
Wooden formwork of first choice, including fixing and
supply, sectioning, bending and fixing the bars. m³ 1.6 200,000 320,000
7 400mm thick approved rubble stone foundation walling
bedded and jointed with cement sand mortar of mixing
ratio 300kg/m³ m³ 4.2 60,000 252,000
8 Backfilling and compaction around the foundation +
surface compaction inside the hall m³ 10.3 5,000 51,500
9 150mm thickness hard core filling of good quality + 1m
around the building m² 10.9 2,500 27,250
10 50mm thick plain insitu concrete layer ( anti-termite) of
mixing ratio 250kg/m³ m² 4.8 10,000 48,000
11 50mm thick surface blinding of mixing ratio 300kg/m³ m² 3.9 12,500 48,750
S/Total 1,738,250

C SUPERSTRUCTURE
1 200mm thick cement block walls jointed with cement
sand mortar of mixing ratio 300kg/m³ m³ 42.60 60,000 2,556,000
2 500mm thick retaining walls jointed with cement sand
mortar of mixing ratio 300kg/m³ m³ 30.1 60,000 1,806,000
3 200 x 200mm thick reinforced concrete columns of
mixing ratio 350kg/m³ with bars of 12mm diam. +
Wooden formwork of first choice, including fixing and
supply, sectioning, bending and fixing the bars. m³ 1.50 350,000 525,000
4 200 x 200mm thick reinforced concrete lintel of mixing
ratio 350kg/m³ with bars of 12mm diam. + Wooden
formwork of first choice, including fixing and supply,
sectioning, bending and fixing the bars. m³ 0.9 350,000 315,000
S/Total 5,202,000

D ROOF STRUCTURE
1 60 x 60mm metallic tube trusses including any other
accessories with anti-termite layer Lm 625 2,200 1,375,000
2 Ditto 40 x 40mm wooden purlins including any other
accessories wit anti-termite layer Lm 302 1,700 513,400
3 Supply and fix prepaint CIS 28BG with all necessary
accessories ( Dark red) m² 169 12,500 2,112,500
4 Prepaint CIS Ridges of 28 BG ( Dark red) Lm 15.6 5,500 85,800
5 Prepare and apply one coat of undercoat and three coats
of gloss paint on metallic gutters m² 20.9 2,500 52,250
6 Supply and fix a 110mm PVC down pipes with all
accessories Lm 23.3 2,500 58,250
S/total 4,197,200

E DOORS AND WINDOWS ( All with one way vision


glass)
1 240*240cm double leaf metallic door with glassy mullion
and all other accessories pcs 5 120,000 600,000
2 170*190cm Metallic glazed window with other
accessories pcs 10 60,000 600,000
3
Prepare and apply one coat of undercoat and three coats
of gloss paint on metallic casement windows and doors
m² 52.9 2,500 132,250
S/total 1,332,250

F ELECTRICAL INSTALLATION
1 Plate switch one gang one way pcs 16 3,000 48,000
2 13A socket outlet pcs 14 3,500 49,000
3 Electric wire for switching & lighting outlet points of
2mm with PVC insulator Lm 557 600 334,200
4 Electric wire for socket outlet points of 2.5mm with PVC
insulator Lm 428 750 321,000
5 ceiling lamp with 3 single fluorescent fitting pcs 15 2,000 30,000
6 wall spot light fitting pcs 17 15,000 255,000
7 Main earth at adaptable box by 25mm PVC copper
electrode in manhole complete with all accessories Item 2 35,000 70,000
8 Allow a provisional of Rwandan Francs to cover the cost
of other accessories like Mk boxes, junction boxes,
saddles, plastic conduits etc. including a sum to liaise
with connection to the main power box Item 1 500,000 500,000
S/total 1,607,200

G PLUMBING INSTALLATION
1 supply and installation of water Evacuation pipes of PVC
of 110 Lm 55.9 1,700 95,030
2 60*60cm manhole with a concrete cover pcs 14 30,000 420,000
3 Supply and fix rain water harvesting tank of 10m³ with all
accessories (support made of stone masonry+ tank) pcs 4 1,000,000 4,000,000
4 supply and fix china vitreous clay hand wash with all
accessories pcs 7 60,000 420,000
5 Toilet paper roll holder pcs 7 10,000 70,000
6 supply and fix china vitreous clay toilet with all
accessories pcs 7 100,000 700,000
7 supply and fix mirror with all accessories pcs 7 25,000 175,000
8 Construction, supply and fix tabs for bacis hygienic
preparation with all accessories pcs 2 350,000 700,000
9 1,5m diam. Soak pit and to a depth not exceeding 15m
with a concrete cover + air vent pipe pcs 1 200,000 200,000
10 Construction, supply and fix all necessary accessories for
septic tank pcs 1 1,500,000 1,500,000
11
Allow a provisional of Rwandan Francs to cover the cost
of other accessories like nipples, union, T, conduits etc.
including a sum to liaise connection to the main pipe
Item 1 250,000 250,000
S/total 8,530,030

H FINISHING WORKS
1 Steel float finish of 30mm thick plaster on brick walls +
columns + beam with cement sand mortar of mixing ratio
300kg/m³. m² 1124.3 3,000 3,372,900
2 A 7cm wide concrete splash apron finished with cement
screed of mixing ratio 300kg/m³. m² 112.9 10,000 1,129,000
3 400 x 400 x 6mm white glazed granite non slip floor tiles
bedded and jointed with clear adhesive on prepared
backings m² 222 25,000 5,545,000
4
Prepare and apply one coat of undercoat and three coats
of weather guard paint on plastered walls externally
m² 356.5 3,000 1,069,500
5 Jointing stone retaining walls with cement sand mortar of
mixing ratio 300kg/m³. m² 210.5 2,500 526,250
6 Metallic round handrail of 4cm in diam. With rails of
2cm Lm 59.8 25,000 1,495,000
7 wooden ceilings with modern board m² 221.8 17,500 3,881,500
8 Prepare and apply one coat of undercoat and three coats
of silky vinyl on plastered walls internally + columns +
lintel/ beam m² 258.1 3,000 774,300
9 Prepare and apply one coat of gloss paint finish on
metallic handrails m² 80.5 2,500 201,250
S/total 17,994,700
GRAND TOTAL 41,151,630

EXTERNAL HOUSES INCLUDING


TOILETTES AND CLASS ROOMS

A. GROUND FLOOR
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
A Preliminary works
1 Setting out the building Item 1 80,000 80,000
S/Total 80,000

B SUBSTRUCTURE
1 Excavate for strip foundation 400mm wide and to a
depth n.e 1.5m. m³ 50.5 2,000 101,000
2 50mm thick blinding concrete layer for strip
foundation of mixing ratio 250kg/m³ m³ 14.9 10,000 149,000
3 400mm thick approved rubble stone foundation walling
bedded and jointed with cement sand mortar of mixing
ratio 300kg/m³ m³ 20.4 60,000 1,224,000
4 Backfilling and compaction around the foundation +
surface compaction inside the rooms m³ 21.4 1,500 32,100
5 150mm thickness hard core filling of good quality + 1m
around the building m² 8.9 2,000 17,800
6 50mm thick plain insitu concrete layer ( anti-termite) of
mixing ratio 250kg/m³ m² 7.5 10,000 75,000
7 50mm thick surface blinding of mixing ratio 300kg/m³ m² 7.8 15,000 117,000
8 Hessian bituminous felt damp proof course m² 15.6 1,500 23,400
S/Total 1,739,300

C SUPERSTRUCTURE
1 200mm thick block cement walls jointed with cement
sand mortar of mixing ratio 300kg/m³ m³ 24.3 60,000 1,458,000
2 200 x 200mm thick reinforced concrete LINTEL of
mixing ratio 350kg/m³ with bars of 12mm diam. +
Wooden formwork of first choice, including fixing and
supply, sectioning, bending and fixing the bars. m³ 1.9 200,000 380,000
S/Total 1,838,000

D DOORS AND WINDOWS


1 90*240cm Metallic glazed door with all other
accessories pcs 5 60,000 300,000
2 190*170cm Metallic glazed window with other
accessories pcs 6 40,000 240,000
3 90*210cm Single leaf wooden door with mullion and
metallic frame + all other accessories pcs 7 25,000 175,000
4
Prepare and apply one coat of undercoat and three coats
of gloss paint on metallic casement windows and doors
m² 23.2 3,000 69,600
5 Prepare and apply two coats of clear vanish on
hardwood timber doors (on both sides) m² 21.2 2,500 53,000
S/total 837,600

B ROOF STRUCTURE
1 60 x 40mm wooden trusses including any other
accessories with anti-termite layer Lm 112.9 2,800 316,120
2 Ditto 40 x 40mm wooden purlins including any other
accessories wit anti-termite layer Lm 60.2 1,700 102,340
3 Supply and fix prepaint CIS 28BG with all necessary
accessories ( Light blue) m² 31.2 12,000 374,400
4 Metallic gutters including any other accessories with
anti-rust layer Lm 5.6 6,000 33,600
5 Metallic fascia board including any other accessories
with anti-rust layer Lm 6 4,500 27,000
6 Prepare and apply one coat of undercoat and three coats
of gloss paint on metallic gutters m² 7.8 2,500 19,500
7 Supply and fix a 110mm PVC down pipes with all
accessories Lm 5.9 2,500 14,750
S/total 887,710

E ELECTRICAL INSTALLATION
1 Plate switch one gang one way pcs 15 3,000 45,000
2 Socket outlet pcs 15 3,000 45,000
3 Electric wire for switching & lighting outlet points of
2mm with PVC insulator Lm 128.2 1,000 128,200
4 single ordinary lamp pcs 19 2,000 38,000
S/total 256,200

F PLUMBING INSTALLATION
1 Supply and installation of water supply PPR pipes in
toilets, urinal and hand washing basins. Lm 109.8 2,000 219,600
2 supply and installation of Evacuation and ventilation
pipes of PVC of 110 Lm 59.7 1,700 101,490
3 supply and installation of Evacuation and ventilation
pipes of PVC of 75 Lm 48.2 1,500 72,300
S/total 393,390

G FINISHING WORKS
1 Steel float finish of 30mm thick plaster on block +
columns + beam with cement sand mortar of mixing
ratio 300kg/m³. m² 78.5 3,000 235,500
2 A 7cm wide concrete splash apron finished with cement
screed of mixing ratio 300kg/m³. m² 40.3 10,000 403,000
3 300 x 300 x 6mm white glazed ceramic non slip floor
tiles bedded and jointed with clear adhesive on prepared
backings in washing rooms m² 35.2 18,000 633,600
4 Prepare and apply one coat of undercoat and three coats
of emulsion paint on plastered walls internally m² 89.7 2,500 224,250
S/total 1,496,350
GRAND TOTAL OF EXTERNAL
HOUSES 6,640,840

FENCE & EXTERNAL WORKS (LAND


SCAPING, GARDEN, PISTE , DRAINAGE
AND EXTERNAL LIGHTING)

A. LANDSCAPING

A DESIGNATION UNITY QTE RATE AMOUNT


1 Garden plantations, pasyparum in all the spaces
non constructed, with trees plantations m² 60.3 2,500 150,750
2 Construction of walk ways in prefabricated
pavers which are able to resist the loading for
heavy cars m² 42.5 18,500 786,250
3 Construction of storm water drainage , constructed
in stones masonry with finishing of mortar
concrete m3 1.2 70,000 84,000
4 Supply and fixing kerbs of 60cm in concrete for the
parking painted black and white ml 25.3 8,000 202,400
6
Excavate, Supply culvert to carry the rain water
collected from the drainage system to the big water
drainage near the road ml 2.6 25,000 65,000
S/TOTAL 1,288,400

B FENCE
Item Description Unit Qty Rate Amount

I EXCAVATION WOKS
1 Excavation for foundation m3 35.9 2,500 89,750
S/TOTAL 89,750

MASONRY AND CONCRETE WORKS


1 Blinding concrete m3 0.8 60,000 48,000
2 Foundation in stones m3 12.2 60,000 732,000
3 roofing m² 45.2 1,000 45,200
200 x 200mm thick reinforced concrete columns of
mixing ratio 350kg/m³ with bars of 12mm diam. +
Wooden formwork of first choice, including fixing and
4 supply, sectioning, bending and fixing the bars. m³ 2.8 250,000 700,000
200mm thick brick cutie walls jointed with cement
sand mortar of mixing ratio 300kg/m³ m³ 5.6 60,000 336,000
5 60x40x2mm Hollow post to support wire mesh lm 81.5 3,500 285,250
6 20x20x2mm vertical wires lm 45.3 1,000 45,300
7 30x30x2mm rails lm 42.1 2,500 105,250
Prepare and apply one coat of undercoat and three
8 coats of gloss paint wire gratings m² 39.6 2,500 99,000
3
9 cover in cement on top of foundation m 3.7 15,000 55,500
10 rejoining for foundation and walls m² 63.2 15,000 948,000
Metallic gates made of hollow tubes with all
11 accessories 5.50x3m pcs 3.0 250,000 750,000
Supply and install public light fixed on the concrete
columns of the fence ( including elec. Wires to the
12 power supplier) pcs 12.0 15,000 180,000
S/TOTAL 4,329,500

TOTAL 5,617,900

FIRE DETECTION SYSTEM

Item Description Unit Qty Rate Amount

Fire detection and fire Alarm.

1 Manual call point /Break glass. pcs 12 18,000 216,000


2 Electronic sounder with an outlet of 90dB
at 1meter pcs 4 65,000 260,000
3 Allow for detector and Sounders wiring
with 1.0mm Twin fire resistant cable. Item 1 825,000 825,000
4 Supply and fix portable powder
extinguisher (9kg) pcs 12 90,000 1,080,000
5 Installation of lightning protection of at
least 60m radius of protection Item 1 2,500,000 2,500,000

Total 4,881,000

B O Q OF PROPOSED CONSTRUCTION
OF MOSQUE IN RUBAVU DISTRICT
GRAND SUMMARY

Item Amount in FRW

1 MULTPURPOSE HALL 41,151,630


2 FENCE & EXTERNAL WORKS (LAND
SCAPING, GARDEN, PARKING, PISTE , 5,617,900
DRAINAGE AND EXTERNAL LIGHTING)
3 EXTERNAL TOILET 6,640,840
4 FIRE DETECTION SYSTEM 4,881,000
GENERAL TOTAL 58,291,370

We say the total amount of: fifty eight million two hundred ninety one thousand and three hundred
seventy Rwanda Francs.

You might also like