Onshore Pipeline Construction
Onshore Pipeline Construction
OVERVIEW - 1
O
Planningg for new capacity
p y must begin
g far in advance of
transporting the first barrel of oil or refined petroleum product,
or the first cubic foot of natural gas.
Regardless
dl off the
h length
l h off the
h pipeline,
i li the
h construction
i
process must be carefully planned to ensure the safety and
integrity of the new pipeline, and then executed to meet
construction
t ti schedules
h d l and d seasonall weather
th conditions.
diti
S eps
Steps
Route Selection
Regulatory Processes
Design
g
Site Preparation
Pipe
p Stringing
g g
Trenching
Bending
Welding
Coating
Lowering and Backfilling
Testing
S Restoration
Site
Route
ou e Selection
Se e o - 1
Pipeline construction requires a great deal of planning, consultation and
preparation.
Following
g the decision to move ahead with a project,
p j the company
p y
must assess alternative routes for the pipeline, and select a final
proposed route.
Route
ou e Selection
Se e o - 2
The general public and government agencies along the proposed route
are also
l consulted,
l d individually
d d ll andd through
h h public
bl notices andd public
bl
meetings.
Effects on buildings
buildings, fences
fences, crops
crops, water supplies
supplies, soil
soil,
vegetation, wildlife, air quality, noise, safety, landowner
interests, and more, are taken into consideration. FERC also
considers whether a pipeline can be placed near or within an
existing pipeline, power line, or highway or railroad right-of-
way.
Regulatory
egu a o y Process
o ess - 2
If a determination is made that the p
project
j will make no
significant environmental impact, the project usually moves
forward quickly.
Design
es g - 2
Pipe sections are fabricated in steel rolling
mills and inspected to assure they meet
government and industryy safetyy standards.
g
Generally between 40 and 80 feet in length,
they are designed specifically for their
i t d d location
intended l ti in
i the
th pipeline.
i li
Site
S e Preparation
epa a o - 2
The crew also prepares a working surface for the additional
construction equipment that
h willll follow.
f ll
Trenching
e g
After stringing the pipe sections in place, a trench is dug along the rights-of-way
alongside
l id the
th pipe
i sections.
ti Topsoil
T il is
i often
ft removed d from
f the
th workk area andd
stockpiled separately to be used in site restoration. Mechanical equipment such
as wheel trenchers or backhoes is used to dig the pipe trench. Occasionally, rock
drilling and blasting is required to break rock in a controlled manner. The
material
i l that
h isi excavated d during
d i trenchinghi operations
i is
i temporarily
il stockpiled
k il d
on the non-working side of the trench. This material will be used again in the
backfill operation.
The trenches are dug deep enough to allow for an adequate amount of cover
when the pipe is buried. Federal regulations require that transmission pipelines
be buried at least 30 inches below the surface in rural areas and deeper in more
populated areas.
areas In addition,
addition the pipeline must be buried deeper in some
locations, such as at road crossings and crossings of bodies of water, and may
be less in other locations such as when it is installed in consolidated rock. The
depth of burial of the line must be in accordance with Federal pipeline safety
regulations.
regulations
Bending
e d g-1
A bending machine is used in the field to
make slight bends in individual sections of the
pipe
i tot accountt ffor changes
h iin the
th pipeline
i li
route and to conform to the topography.
Bending
e d g-2
All bending is performed in strict accordance
with prescribed standards to ensure integrity
off th
the b
bend.
d
Often bend configurations
g must be
determined ahead of time. They are then pre-
engineered and prefabricated in a special
shop and then brought on site for installation
at the proper location
location.
Welding
ed g - 1
To carryy out the welding
g process,
p , the pipe
p p sections are
temporarily supported along the edge of the trench and aligned.
The various pipe sections are then welded together into one
continuous length, using manual, semiautomatic or automatic
welding
ldi procedures.
d
Welding
ed g - 2
As p
part of the quality-assurance
q y process,, each welder must pass
p p
qualification tests to work on a particular pipeline job, and each weld
procedure must be approved for use on that job in accordance with
federally adopted welding standards.
W ld qualification
Welder lifi i takes
k place
l before
b f the
h project
j begins.
b i Each
E h welder
ld
must complete several welds using the same type of pipe as that to be
used in the project. The welds are then evaluated by placing the
welded material in a machine and measuring the force required to pull
the weld apart. It is interesting to note that the weld is actually
stronger than the pipe itself.
A second level of quality
quality-assurance
assurance ensures the quality of the ongoing
welding operation. To do this, qualified technicians take X-rays of the
pipe welds to ensure the completed welds meet federally prescribed
quality standards. The X-ray technician processes the film in a small,
po table da
portable darkroom
k oom at the site
site. If the technician detects any
an flaws,
fla s the
weld is repaired or cut out, and a new weld is made. Another form of
weld quality inspection employs ultrasonic technology.
Coating
Coa g-1
After the pipe is welded, the welds are examined,
usually by X-ray, and a coating is applied to the
welded areas at the ends of the pipe sections to
prevent corrosion
corrosion.
Coating
Coa g-2
Several different types of coatings may be used to
coat field joints, the most common being fusion bond
epoxy or polyethylene heat-shrink sleeves.
Once the pipeline is lowered into the ground, the trench is carefully
backfilled, to ensure that the pipe and its coating are not damaged.
Backfilling
a g
Care is taken to protect the pipe and coating from sharp rocks and
abrasion
b as the
h backfill
b kf ll is returned
d to the
h trench.
h
In areas where the gground is rockyy and coarse, the backfill material is
screened to remove rocks or the pipe is covered with a material to
protect it from sharp rocks and abrasion.
Alternatively, clean fill may be brought in to cover the pipe. Once the
pipe is sufficiently covered, the coarser soil and rock can then be used
to complete the backfill.
Testing
es g - 2
Hydrostatic testing is not the only means for detecting pipe defects.
For example, inline inspection (ILI) technologies are used that permit
the identification of specific
p types
yp of defects, such as corrosion.
But because not all lines can be inspected with ILI tools and because of
yp of defects that are not currentlyy detected byy ILI
the need to find types
technology, hydrostatic testing is an accepted method for
demonstrating the fitness of a pipeline segment for service.
Site
S e Restoration-
es o a o 1
Finally, the construction right
Finally right-of-way
of way is restored as
closely as possible to its original condition.
Site
S e Restoration-
es o a o 2
The right-of-way
right of way is carefully graded,
graded and in hilly
areas, erosion-prevention measures such as
p
interceptor dikes - which are small earthen mounds
constructed across the right-of-way to divert water -
are installed.
..\VIDEO\PIPELINE-36pIPE wITH 6
cONCRETE cOATING LOWERING.wmv
Sign
S g Mark
a