Pfi Es-48
Pfi Es-48
RANDOM EXAMINATION
Prepared by
Pipe Fabrication Institute Engineering Committee
Copyright by
--`,,```,,,,````-`-`,,`,,`,`,,`---
WEB SITE
www.pfi-institute.org
Random Examination
Expectations, Guidelines and Methodology
4.3. When random examination is specified, the 5.1.1.1. Random Examination is to be performed
extent of random examination must be clearly on a lot basis. Once the percentage of
defined in the contract documents. Random welds in a lot are examined and accepted
examination can be applied to: and the welds representing the work of
each welder in that lot have been
4.3.1. Circumferential butt and miter welds on a examined and accepted, all remaining
project. welds in that lot (i.e., those that were not
examined) are Code-acceptable provided
4.3.2. Circumferential butt and miter welds within they are visually acceptable and pass
specific line classes or systems on a project, hydrostatic testing. See paragraph
4.3.3. Circumferential butt and miter welds within 341.3.1.
particular parts of systems (e.g., high- 5.1.1.2. Since B31.3 places responsibility for
pressure parts of a steam system) performing examination on the
4.3.4. Circumferential butt and miter welds in Fabricator or Contractor who is doing the
specific locations (e.g., piping inside welding, lot selection is the prerogative
buildings) of the Fabricator or Contractor in the
absence of arrangements in which a lot is
4.3.5. Other schemes that satisfy the Owner or his established by contract. B31.3 recognizes
engineer. that lot selection can be a source of
4.3.6. Volumetric examination is not normally dispute and suggests2 that the quantity or
applied to nozzle or branch connection extent of a designated lot should be
welds or to fillet welds. established by agreement between the
contracting parties before the start of
4.4. When the purchaser wishes to impose additional work. See Section 6 for various methods
random examination, and the applicable code of defining a lot.
--`,,```,,,,````-`-`,,`,,`,`,,`---
5.1.1.3. Since B31.3 places responsibility for lots, and more than one welding process may be
performing examination on the included in a lot.
Fabricator or Contractor who is doing the
welding, lot definition is the prerogative 6.3. In defining a lot, the fabricator/contractor should
of the Fabricator or Contractor in the consider the following:
absence of contractual arrangements in
which a lot is established by contract. 6.3.1. The lots should be of a size that can be
easily managed. Small lots may result in
5.1.2. The welds to be examined must include the
increased cost because paperwork will
work product of each welder, whose welds
increase and the total number of welds
are part of any designated lot, but B31.3
examined on the project will increase
does not require that the given percentage of
beyond the percentage required. Conversely,
each welder’s work within a lot be
large lots lead to increased risk when
examined.
progressive sampling is required.
5.1.3. When a weld is rejected, B31.3 paragraph
6.3.2. Welds should be examined shortly after the
341.3.4 requires “progressive sampling” of
required lot size has been achieved in order
other welds made by the welder who made
to obtain the desired effect on the quality of
the defective weld. Welds made by other
the work.
welders within the lot that have either been
examined and accepted or have not been 6.3.3. It may be necessary to examine the initial
examined would not be subject to welds made within each lot prior to the
progressive sampling. completion of all the welds within that lot, to
provide timely feedback.
5.2. Should the purchaser or his representative
demand additional nondestructive examination 6.3.4. The results obtained in examination of one
within a lot after that lot of welds has been lot should not be considered in the
accepted, such additional examination is outside evaluation or extent of examination applied
the provisions of B31.3. Defects found by this to any other lot.
additional examination shall be repaired and the
6.3.5. A tracking method that clearly documents
weld re-examined. The cost of any additional
welds in each lot should be established.
examination, and any subsequent repairs and re-
examination, shall be the responsibility of the 6.3.6. Welds selected for each lot must fall into the
--`,,```,,,,````-`-`,,`,,`,`,,`---
organization requiring the additional same percentage of examination.
examination. Approval of the customer’s
contracting officer may be required for increases 6.4. Some lot definitions are show below.
in the extent of examination since such
examination would usually be compensable 6.4.1. Daily: All the welds completed by all
changes to the contract. welders, and are accepted by visual
examination on any day shall be considered
a lot. The number of welds to be examined
6. Establishing a Lot shall be calculated based on the size of the
6.1. Contract requirements for establishing lots or for lot and the percentage of welds that are
selection of welds to be examined should be required to be examined.
agreed upon by the contracting parties. When the
purchaser will be responsible for selection of the 6.4.2. Daily Multiple lots: All the welds
random welds in a lot, the purchaser’s completed by all welders, and accepted by
representative will need to be readily available to visual examination on any day shall be
avoid impeding work flow. The process of broken up into separate lots and each lot
selection should also be included in such examined individually (e.g., 65 welds are
agreement, (e.g., select from the list of welds in a completed in a day; if the lot size is 20, those
lot, select the weld(s) after visual examination, 65 welds shall be separated into 4 lots of a
etc.) convenient sizes of 20 or fewer and the
welds to be examined shall be selected from
6.2. The welds in a lot do not need to be of the same each lot). If the required number of welds to
material, thickness or size. Butt welds and miter achieve the required lot size has not been
welds do not need to be segregated into different obtained, the welds that have been
completed each day shall be considered a lot.
6.4.3. By Welder: Only the welds of a single 6.4.9. Welds along a run until the required
welder are included in the lot. When the number is reached. Field work only. Not
welds made by a welder achieve the required suitable for sizes and wall thicknesses where
lot size, that group of welds shall be achieving a lot of a particular size takes an
considered a lot. Since more than one extended period of time.
welder may make a weld, that weld shall be
6.5. Shipping of Lots: For shop fabrication, no item
included only in one welder’s lot.
in a lot shall be shipped before the required
6.4.4. Truck Load: All welds on all of the examination of that lot is completed and that lot
assemblies to be loaded on a single truck has been accepted.
shipment may be considered a lot.
Acceptance of the whole lot should be 7. Documentation of Sampling
completed prior to loading the truck.
7.1. Welds making up lots should be documented
6.4.5. All Welds on a Job: All the welds on a job concurrently with the progress of fabrication.
may be considered a lot. This option should Joints should be logged as final visual inspection
not be selected unless the project is very is completed for each spool piece or as erection
small. welds are made. Any form of tracking and
6.4.6. Spool Grouping: Each project shall be documenting lots is acceptable provided:
subdivided into "lots" as required for
convenience and flow of work through the 7.1.1. The welds which make up the lot are clearly
shop. The "lot" may consist of different identified
piping systems with the same percentage 7.1.2. The number of welds from each welder is
requirements for random radiography. Only clearly identified
piping with the same radiographic
percentage requirements (e.g. 5% and 20% 7.1.3. The weld(s) selected for examination are
systems) should be included in the same clearly identified
"lot". 7.1.4. All of the requirements for initial selection
6.4.7. All the Welds in a Piping System or Line: and progressive selection have been met.
When drawings identify the customer’s
piping system, all welds in each system can
be considered a lot. Another alternative is to
choose lots by line or group of lines. This
option is generally only suitable for field
welding. In a shop environment, this method
is discouraged because it increases costs due
to impeded work flow, added material
handling and delayed delivery.
6.4.8. All Welds in a Room or other Easily-defined
Space: Field work only.
--`,,```,,,,````-`-`,,`,,`,`,,`---
Technical Bulletins
TB1 R13 Pressure - Temperature Ratings of Seamless Pipe Used in Power Plant Piping Systems - ELECTRONIC VERSION
TB3 R13 Guidelines Clarifying Relationships and Design Engineering Responsibilities Between Purchasers’ Engineers and Pipe Fabricator or Pipe
Fabricator or Pipe Fabricator Erector
TB5 R13 Information Required for the Bidding of Pipe Fabrication
TB7 R04 Guidelines for Fabrication and Installation of Stainless Steel High Purity Distribution Systems
TB8 R13 Recommended practice for the fabrication of polyvinylidene fluoride (PVDF) piping
TB9 R13 Customary Fitting, Forging, Plate and Bar Materials used with Pipe
ELECTRONIC VERSION
--`,,```,,,,````-`-`,,`,,`,`,,`---
CHARTER MEMBERS
CONTRACTOR MEMBERS
ASSOCIATE MEMBERS
AFFILIATE MEMBERS
HONORARY MEMBERS
PFI Standards and Technical Bulletins are published to serve proven needs of the pipe
fabricating industry at the design level and in actual shop operations. Hence, such needs
are continually considered and reviewed by the Engineering Committee of the Pipe
Fabrication Institute to provide recommended procedures, which have been demonstrated
by collective experiences to fulfill requirements in a manner for Code compliance.
However, as the PFI Standards are for minimum requirements the designer or fabricator
always has the option of specifying supplementary conditions in the form of requirements
beyond the scope of the PFI publications.