Batangas Fence

This document is a bill of quantities for a perimeter fence project located in Batangas. It includes 7 items: general requirements, earthworks, rebar works, concreting works, masonry works, formworks, and consumables. The total cost is estimated at PHP 3,781,831.20, which includes materials, labor, and a grand total cost. The fencing project requires excavation, rebar installation, concrete pouring, block laying, plastering, and formwork to construct the fence columns, footings and walls.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
46 views1 page

Batangas Fence

This document is a bill of quantities for a perimeter fence project located in Batangas. It includes 7 items: general requirements, earthworks, rebar works, concreting works, masonry works, formworks, and consumables. The total cost is estimated at PHP 3,781,831.20, which includes materials, labor, and a grand total cost. The fencing project requires excavation, rebar installation, concrete pouring, block laying, plastering, and formwork to construct the fence columns, footings and walls.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 1

PROJECT: Perimeter Fence

LOCATION: Batangas
SUBJECT: Bill of Quantities
DATE: Monday,19 February 2024

NO. SCOPE OF WORK QTY. UNIT UNIT COST TOTAL COST

1.00 GENERAL REQUIREMENTS


Mobilization 1 lot 50,000.00 50,000.00
Temporary Facility 1 lot 150,000.00 150,000.00
Water Supply 1 lot 100,000.00 100,000.00
Water Supply 1 lot 100,000.00 100,000.00
2.00 EARTHWORKS
Clearing and Grubbing 1 lot 50,000.00 50,000.00
Excavation 216 cum 600.00 129,600.00
3.00 REBAR WORKS
3.01 Column Footing
12mm Dia. Rebar L=6m 272 pc/s 221.00 60,112.00
Tie Wire 3 roll 1,750.00 5,250.00
3.02 Column (30cm X 30cm)
12mm Dia. Rebar L=6m 408 pc/s 221.00 90,168.00
Tie Wire 4 roll 1,750.00 7,000.00
3.03 Wall Footing
10mm Dia. Rebar L=6m 560 pc/s 156.00 87,360.00
Tie Wire 3 roll 1,750.00 5,250.00
3.04 Wall
10mm Dia. Rebar L=6m 890 pc/s 156.00 138,840.00
Tie Wire 3 roll 1,750.00 5,250.00
4.00 CONCRETING WORKS
4.01 Column Footing
Cement 408 bag/s 240.00 97,920.00
Sand 38 cum 692.00 26,296.00
Gravel 55 cum 880.00 48,400.00
4.02 Column (30cm X 30cm)
Cement 350 bag/s 240.00 84,000.00
Sand 35 cum 692.00 24,220.00
Gravel 42 cum 880.00 36,960.00
4.03 Wall Footing
Cement 320 bag/s 240.00 76,800.00
Sand 32 cum 692.00 22,144.00
Gravel 38 cum 880.00 33,440.00
5.00 MASONRY WORKS
5.01 CHB LAYING
CHB 6" 20100 pc/s 18.00 361,800.00
Cement 1180 bag/s 240.00 283,200.00
Sand 130 cum 692.00 89,960.00
5.02 PLASTERING (BOTH SIDES)
Cement 1204 bag/s 240.00 288,960.00
Sand 184 cum 692.00 127,328.00
6.00 FORMWORKS
Phenolic Board 1/2" 40 pc/s 620.00 24,800.00
2x2 Coco Lumber 250 pc/s 70.00 17,500.00
2x3 Coco Lumber 250 pc/s 115.00 28,750.00
7.00 FORMWORKS
Consumables 1 lot 50,000.00 50,000.00
TOTAL COST 2,701,308.00
LABOR COST 1,080,523.20
GRAND TOTAL 3,781,831.20