The document summarizes a case study of a reinforced soil wall constructed along the approaches of structures on a highway project in India. A contractor was seeking a more economical alternative to a conventional reinforced concrete wall for retaining the approaches of bridges and ramps being constructed. Engineers proposed using a MacRes reinforced soil wall system with precast concrete panels and Paraweb reinforcement. The 300 meter long wall was up to 10.4 meters tall and was successfully completed within the scheduled timeline.

Uploaded by

Akhilesh Wable
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
76 views2 pages

6 LANING OF SOLAPUR BIJAPUR OF NH-13-Rev7-Sep23-EN

The document summarizes a case study of a reinforced soil wall constructed along the approaches of structures on a highway project in India. A contractor was seeking a more economical alternative to a conventional reinforced concrete wall for retaining the approaches of bridges and ramps being constructed. Engineers proposed using a MacRes reinforced soil wall system with precast concrete panels and Paraweb reinforcement. The 300 meter long wall was up to 10.4 meters tall and was successfully completed within the scheduled timeline.

Uploaded by

Akhilesh Wable
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

CASE HISTORY

Rev: 7, Issue Date 25.09.2023

RS WALLS FOR APPROACHES OF 4/6 LANING OF SOLAPUR


BIJAPUR OF NH-13
SOLAPUR-BIJAPUR, KARNATAKA, INDIA
Vertical Walls with Concrete Facing Panels

Problem
Client: NATIONAL HIGHWAYS AUTHORITY OF INDIA
NHAI had awarded the project of four/six laninig of Solapur Designer / Consultant: MACCAFERRI / L.N. MALVIYA
Bijapur of NH-13 in the state of Maharashtra & Karnataka to INFRA
be executed as BOT(toll) project on DBFOT pattern under Contractor: DRN INFRASTRUCTURE PRIVATE LIMITED
NHDP Phase-III to EPC Contractor M/s. IJM Infrastructure
Products used (Qty.)
Limited. EPC Contractor selected M/s. DRN Infrastructure
-300 RM (in
Engineers & Contractors to carry out the construction works. - Macres
multiple lines)
One Light Vehicular Under Passes (LVUP), one Flyover and
one ramp were to be constructed in this stretch and the Date of construction: 11/2018 - 03/2021
approaches of these structures were to be retained. Google Maps Google Earth
Reinforced Soil (RS) Wall was selected as the solution
instead of conventional reinforced concrete wall solution for
the approaches of these structures. The cost of the
conventional solution was very high and the contractor
wanted to have a system that is economical, flexible and
simple to construct.

Solution

Reinforced Soil (RS) Wall system (MacRes) with precast


concrete panels as fascia and Paraweb as reinforcement was
proposed due to its economy, flexibility, speed of
construction, aesthetic finish and long term performance.
Cruciform fascia panels with corrugations and Paraweb of
strengths varying from 30kN to 100kN were used in the
project. The connection between the panels and paraweb
was done by cavity connector casted in the panels. The
Backfill soil with angle of internal friction of 34 degrees was
used as reinforced fill. The maximum height of the RS Wall is
10.4m.
600mm wide aggregate filter media is considered with well
graded aggregate of size ranging between 19.1mm to
9.5mm. RS Wall Design was done as per British Standards
8006 and the Loads considered are Dead Load due to
Pavement crust, Live load from Traffic and Strip Load due to CONSTRUCTION IN PROGRESS
Crash barrier & friction slab. Analysis is done for both
External & internal Stability.
The total construction period of this project is 2.5 years.

PLACEMENT OF GEOTEXTILE AT PANEL JOINTS


PARAWEB LAYING IS IN PROGRESS ERECTION COMPLETED TILL TOP PANELS

TAIL END PORTION OF RS WALL AFTER CONSTRUCTION OF REINFORCED SOIL WALL

TYPICAL CROSS SECTION OF RS WALL

MACCAFERRI ENVIRONMENTAL SOLUTIONS PVT. LTD


D40, MIDC Ranjangaon, Tal-Shirur, Dist. Pune - 412 220
Tel: +91 2138 393000 , Email: [email protected]

You might also like