2 Project Delivery System
2 Project Delivery System
General Construction
Contractor? Manager?
Design-Builder?
Multiple Trade
Contractors?
Independent A/E?
Selection and Payment
Will the Owner use:
Competitive
Selection?
Negotiated
GMP? Selection?
A/E
Owner
Design consultant
Prime
Contractor
A/E
Owner
Design consultant
➢ Conflicts between owner & G.C. and between A/E & G.C.
➢ The owner's role in this approach is minimal and is only to express his or
her objectives and specifications precisely before detailed design is started.
Owner
Some times
➢ Contractor as lead
➢ A/E as lead
➢ Joint Venture
Owner- Builder
Owner
Owner
Owner
Designer/ C.Mgr.
Construction
Design Team Const. Team
Contractor(s)
Professional Construction Management
➢Although this approach is likely to prove marginally more expensive
than the traditional approach, it offers greater guarantee of
performance and the potential to avoid time overruns and to reduce
the cost of claims.
A/E
Owner
Design consultant
Management
Contractor
Owner
A/E Construction
Design consultant Manager
Prime
Contractor
➢ Disadvantages: CM
❖ Involve additional fee
❖ C. Mgr. is not legally responsible for the designer and contractor.
❖ Success of the entire program depends on the skills of C. Mgr.
Built Operate Transfer (BOT)
➢ The term Build-Operate-Transfer (BOT) was first coined by
Minister of Turkey, in1984