NSPM - Assignment 2 Sample Answer
NSPM - Assignment 2 Sample Answer
DAN KOMUNIKASI
PROJECT MANAGEMENT
ASSIGNMENT 2
Part A:
Detail about the work created in the WBS
3 Project Execution
3.1 Meeting
3.1.1 Meet with group members and understand the progress
3.2 Preparation of risk recovery procedure (Lag)
3.3 Installation of the firewall
3.3.1 Install firewall in system that buy from the authority
3.4 Configure with requirement (Lag)
3.5 Testing
3.6 User training
3.6.1 End-user training
3.6.2 System administrator training
4 Project Control
4.1 Project Status meeting
4.1.1 Update progress of project to manager
4.2 Goal tracking
4.2.1 Monitor project follow with the objective
4.3 Progress tracking
4.3.1 Follow up the progress that meet with the milestone
4.4 Budget tracking
4.4.1 Monitor the spend of budget on every spending
4.5 Risk management
4.5.1 Identify, analyse and control the threat
5 Project Closure
5.1 Project analysis
5.1.1 Examine the aspect of project in detail
5.2 Project audit (Lag)
5.2.1 Assure the result meet expectation by audit it
5.3 Project report
5.3.1 Provide details implementation of this project
5.3.2 Submit the full document to the manager
5.4 Meeting
5.4.1 Present the implementation result to the manager
Quality Requirements
- To ensure this project able to finish in time
- To control the cost will not exceed with available budget
- To ensure the complete protection of firewall to Oil Tek’s system
Acceptance Criteria:
- The firewall that setup after this project able to protect the assets of organization from the 90% of
malicious attack up to five years. This project still consider success even the cost of project might
greater than expectation of 15% and complete time 5 more days as planned before.
Predecessor: (Only step 4, 3.6.1 and 3.6.2 used SS, the rest used FS)
Milestones:
1. Project Initiation 1/ 11/ 2021 – 2/ 11 /2021
2. Project Planning 3/ 11 /2021 – 6/ 11/ 2021
3. Project Execution 7/ 11/ 2021 – 7/ 1/ 2022
4. Project Closure 8/ 1 /2022 – 8 / 2 /2022
WBS Dictionary
Project Title: WBS Development Date Prepared: 29/10/2021
Work Package Name: Oil Tek Firewall Implementation WBS ID: From the WBS
Description of Work:
Sufficient detail delivery to ensure common understanding by stakeholders.
Milestones: Due Dates:
1. Project Initial 1. 1/ 11/ 2021 – 2/ 11 /2021
2. Project Planning 2. 3/ 11 /2021 – 6/ 11/ 2021
3. Project Execution 3. 7/ 11/ 2021 – 7/ 1/ 2022
4. Project Control 4.8/1/2022 – 9/2/2022
5. Project Closure 5.10/2/2022 – 10/3/2022
Labour Material
ID Activity Resource Total Cost
Hours Rate Total Units Cost Total
From Activity list or schedule From Resource Total Labou Hours Amoun Cost Units X Labour +
requirements effort. r rate. X rate. t cost. Material.
1 Project Initiation
Communication 6 60 360 0 0 0
Leader, Cost
Meeting Leader, Process
and People
-Communicate with manager and Leader,
1.1 360
understand the available budget, Procurement
human resources, requirements, Leader, Project
scope and objective of this project. Manager, Quality
Leader, Risk
Analysis Leader
Communication 4 60 240 0 0 0
Leader, Cost
Leader, Process
Formation of Project Team
and People
Leader,
1.2 -assignation of Project member 240
Procurement
and manager from Oil Tek to join
Leader, Project
during the task.
Manager, Quality
Leader, Risk
Analysis Leader
2 Project Planning
Communication
Leader, Cost
Leader, Process
and People
Leader,
2.1 Analysis and design
Procurement
Leader, Project
Manager, Quality
Leader, Risk
Analysis Leader
Communication 6 60 360 0 0 0
Leader, Cost
Leader, Process
Analysis the requirement,
and People
resources, budgets and select
Leader,
2.1.1 appropriate brand of firewall 360
Procurement
Leader, Project
Manager, Quality
Leader, Risk
Analysis Leader
3 Project Execution
Project Manager, 12 60 720 0 0 0
Communication
Leader, Cost
Meeting Leader, Process
and People
3.1 720
Meet with group members and Leader,
understand the progress Procurement
Leader, Quality
Leader, Risk
Analysis Leader
Cable, 60 60 3600 0 0 0
Communication
Leader, Computer,
Cost Leader, Oil
Tek Management
System, Process
and People
Leader,
3.5 Testing 3600
Procurement
Leader, Project
Manager, Quality
Leader, Risk
Analysis Leader,
Router, Server,
Smartphone,
Switch
4 Project Control
Communication 12 60 720 0 0 0
Leader, Cost
Leader, Process
and People
Project Status Meeting
Leader,
4.1 720
Procurement
-update the progress to manager
Leader, Project
Manager, Quality
Leader, Risk
Analysis Leader
Communication 2 60 120 0 0 0
Leader, Cost
Leader, Process
Goal Tracking and People
Leader,
4.2 120
-monitor project following the Procurement
objective Leader, Project
Manager, Quality
Leader, Risk
Analysis Leader
Communication 6 60 360 0 0 0
Leader, Cost
Leader, Process
Progress Tracking and People
Leader,
4.3 360
-follow up the progress that meet Procurement
with the milestone Leader, Project
Manager, Quality
Leader, Risk
Analysis Leader
Project Manager, 6 60 360 0 0 0
Risk Analysis
Budget Tracking
Leader, Quality
4.5 Leader, 360
-monitor the spend of budget on
Procurement
every spending
Leader, Cost
Leader
5 Project Closure
Communication 25 60 1500 0 0 0
Leader, Cost
Leader, Process
Project Analysis and People
Leader,
5.1 1500
-examine the aspects of project in Procurement
details Leader, Project
Manager, Quality
Leader, Risk
Analysis Leader
Communication 50 60 3000 0 0 0
Leader, Cost
Leader, Process
and People
Provide details implementation of Leader,
5.3.1 3000
this project Procurement
Leader, Project
Manager, Quality
Leader, Risk
Analysis Leader
1 45 45 1 300 0 345
Submit the full document to the
5.3.2 Project Manager
manager
Meeting 3 60 180 0 0 0
5.4 Project Manager 180
-present the implementation result
to the manager
Quality Requirements:
1. To ensure this project able to finish in time
2. To control the cost will not exceed with available budget
3. To ensure the complete protection of firewall to Oil Tek’s system
Acceptance Criteria:
The firewall that setup after this project able to protect the assets of organization from the 90% of malicious attack up to five years. This
project still consider success even the cost of project might greater than expectation of 15% and complete time 5 more days as planned
before.
Predecessor:
Only step 4, 3.6.1 and 3.6.2 used SS, the rest used FS