PH Bixby York 5433
PH Bixby York 5433
Single-family detached dwelling off Little Hob Moor, York, North Yorkshire
Building Data
Overhead drone photo from south side. Overhead drone photo showing west
elevation and pool room to rear.
Internal view prior to completion showing Internal view prior to completion showing
stair from living room. kitchen area.
Page
4
Sectional drawings
The building section is asymmetric, with the south face size and pitch optimised to PV
panels, and the north face brought down to reduce the ridge height and impact of the building
Page
5
mass. All rooflights are north-facing to avoid uncontrolled solar gains, and shading is
incorporated above south-facing windows, including a continuous press-aluminium
concealed gutter to the south-facing roof. External walls, roof and intermediate floor are all
constructed using timber I-joists. The superstructure sits on an insulated raft.
Floor plans
The ground floor plan is entered from the street at the eastern end, with a cloaks area and
shoe rack, and access to a shower/WC. The hallway wall splays so that the space opens up
as one moves into the combined living / dining / kitchen area, with a doorway off this
passage to a compact snug, and the stair leading off the main room. The living area has
extensive south-facing (shaded) glazing, and the dining area faces the evening sun, with
retractable shading and existing mature tree planting.
Page
6
The first floor layout arranges the rooms around a central landing space with a heigh
ceiling and overhead rooflight. The main bedroom suite with dressing and shower/WC has
windows looking over the garden and nearby woods, with the guest bedrooms, bathroom
and laundry to the north and east. The laundry has a chute which enables clothing to be
deposited into the laundry basket from the adjacent en-suite.
Page
7
Description of the construction
Ground floor
The ground floor is a fairly simple reinforced raft foundation, with cavity plinth walls
enclosing insulation and screed. A gas membrane is incorporated due to concerns over a
nearby former landfill site.
The walls are of timber frame panel construction, with the studs being timber I-joists giving a
300mm internal depth between internal and external sheathing. All junctions were modelled
using Psitherm software and the detailing was designed in liaison with the frame
manufacturer to enable the complex and accurate connections while minimising thermal
bridging.
Page
9
The roof is constructed using cassettes which are broadly the same as the wall panels – using
300mm timber I-joists as rafters which span between a glulam ridge beam and the wallplate
at eaves level. Both the eaves and ridge join are custom made to ensure tight fitting between
panels (individual timbers are cut to tolerances of 1mm each end, giving panel connection
tolerances of around 4mm) and, as with the wall panel connections, timer in the junction is
minimised to reduce thermal bridging, and connections were modelled using Psitherm.
Windows
Windows are Gaulhofer Fusionline 108 Pure units supplied by Ecowin. Generally:-
• Internal colour: Clear Laquer
• External colour: RAL 7016 (anthracite Grey) & 3000 (Fire Engine Red – front door)
• Ironmongery: Concealed Hinging, Standard Gaulhofer Handles
• Glass Ug: 0.5 W/m2K
• Frame Uf Laterally: 0.91 W/m2K
• Frame Uf Bottom: 1.01 W/m2K
• Psi Value: 0.028
• G Value: 0.52
• Average whole window U Value: 0.77W/m2K
Glazing units are generally:- 4mm toughened/coated-18mm-4mm toughened-18mm-4mm
toughened/coated. The window position within reveals was fine-tuned using Psitherm.
Page
11
Rooflights are Fakro FTT-U6 units with thermal flashing kit.
The airtight envelope
The airtightness strategy was to ensure a single layer of airtightness by the use of proprietary
airtightness membrane, and tapes / grommets / fittings etc from Proclima where required. In
general the two site managers of the two concurrent Passivhaus projects were both briefed on
general principles and key areas where extra care was required. In the case of Hob Moor
Passivhaus the timber frame from Buildakit came with internal airtightness membrane
already fitted and protected with internal battening / mineral wool insulation, held in place
using plastic straps.
The system works well, maintaining good air quality. A minor but annoying error was
locating the remote control unit in the plant cupboard rather than somewhere more remote
from the unit – for example in the kitchen.
Page
14
Heat supply
The low heating requirement of the house and the substantial photovoltaic installation led to
an early decision that the house would be all-electric, and an existing gas supply to the site
was removed (still unusual in UK at the time of construction). The PV array is setup to put
spare output into the DHW cylinder via an Immersion control unit. Following this, output is
available for domestic use and for space heating.
Space heating comprises a 1kW post heater on the supply air, and three electrically-heated
towel rails in the three bathrooms/showers, each on thermostatic control. The house performs
as per predicted demand so this generally works well; on occasions where it has been unused
for a while due to travelling away, and temperatures have fallen, a simple plug-in electric fan
heater is deployed until temperatures are back to normal.
In practice there has been a learning curve in respect of settings for the immersions and
immersion control unit. The fact that there is no one single control unit for heating nor for hot
water, led to a need to bring together advice from a number of sources. An email thread was
set in motion by the designer, becoming known as The Reservoir Dogs Thread as each
participant (PV installer, plumber, electrician, MVHR company, client etc) colour-coded their
contributions. This was helpful (and was broadened to include the clients on the concurrent
Derwent Road Passivhaus as similar issues existed there).
PHPP
The project was designed from scratch with the intention of being certified Passivhaus. All
design work was carried out in 3D on Vectorworks, with Artlantis being used as a
visualisation tool and to model sun and shading accurately. Psitherm was used for thermal
bridging calculations and modelling of options.
Page
15
As noted above, although formal monitoring equipment hasn’t been fitted, checking of bills
suggests that performance is in line with PHPP predictions. Possibly the only time when we
have been taken by surprise was during an unusually warm spell early in the spring. External
temperatures were high and the combination of this and low sun angles led to internal
overheating. The client has, to some extent, also had to overcome the “don’t open the
windows” advice which seems to come from anyone and everyone who doesn’t understand
Passivhaus; during hot spells a regime of purge ventilation at each end of the day along with
keeping windows/doors closed during the peak temperatures has maintained comfort levels.
As the graph below shows, windows are the largest heat loss component but provide much-
loved views of the garden and adjacent woodland, and contribute to summer life split indoors
and outdoors. The clients would not wish things different.
Page
16
Costs
The final contract sum for the project was just over £445,000, which works out as £3,056/m2
of TFA. This, though, includes external landscaping (driveway and extensive decking, site
fencing etc and also the substantial costs of the endless pool and the room it occupies.
Although this is not part of the heated volume, it is built to similar standards of insulation,
and on the same reinforced/insulated raft). The house also incorporates complex control
wiring as the client wanted to be able to control everything from room lighting to hi-fi via
phone app. A more realistic view of costs would be in the region of £2500-2600/m2.
User satisfaction
The clients are very happy with the house – which is doubly good as (noted earlier) the
designer now lives next door. They have eregularly taken part in Passivhaus Open Days
(including recording a video for the Covid lockdown event) and the local Open Eco Homes
scheme, together with events organised as part of York Environment Week. The house was
featured in the local paper shortly after completion.