1) The work progress report provides status updates for various construction tasks across two tunnel locations (T12 and T13) for the month of February 2024. 2) At T12, second stage concrete work is 94 meters behind schedule, while cable trench concrete is 230 meters behind with no progress the prior week. 3) At T13, portal rockbolt work is 41 meters behind schedule and only 3 meters of progress the prior week, while invert closing tasks are ahead of schedule.

Uploaded by

Deepak Lal Das
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
7 views

FD

1) The work progress report provides status updates for various construction tasks across two tunnel locations (T12 and T13) for the month of February 2024. 2) At T12, second stage concrete work is 94 meters behind schedule, while cable trench concrete is 230 meters behind with no progress the prior week. 3) At T13, portal rockbolt work is 41 meters behind schedule and only 3 meters of progress the prior week, while invert closing tasks are ahead of schedule.

Uploaded by

Deepak Lal Das
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 1

Work progress Report for February 2024 Date: 19-02-2024

weekly
Target in Monthly Progress Balance work Progress From
Month of From 1st According to 10th
Sl. No. Location Unit Remarks
February'24 February'24 to 19th February'24 February'24 to
(Mtr) February'24 (Mtr) Montly Plan 16th
February'24

T12

1 T12P1 Second Stage Concrete 416 m 322.00 94 138.00 Up to Block No-17 Concreting Completed.

2 T12P1 Cable Trench Concrete 250 m 20 230 0.00 Block No-52 & 51 Concreting Completed.

3 T12P1 Sub-station Re-Mining 22.5 m 16.5 6.00 7.50 SS 1A-12.00Mtr, SS 1B-9.00Mtr

4 T12P1 Sub-station Ring Closer 30 m 0 30 0.00

5 T12P1 Sub-station Kerb & Invert Concrete 30 m 0 30 0.00

6 T12P2 Second Stage Cable Trench Side Wall 250 m 35 215 0.00 25 Mtr LHS & 45Mtr RHS

7 T12P1 Third Stage Concrete m 48

T13

8 T13P1 Portal Rockbolt Work 63 m 22.000 41.00 3.00 Grouting Is in Progress.

9 T13P1 Sub-Station niche 23.75 m 20.000 3.75 6.25 SS 1A-15.00Mtr, SS 1B-6.25Mtr

10 T13P1 Invert Closing 210 m 46.000 164.00 34.40


Kerb-24 m & Invert-24 m Concrete
11 T13P1 Kerb & Invert Concrete 100 m 24.000 76.00 24.00
Completed.
12 T13P2 Sub-Station niche 23.75 m 22.500 1.25 6.25 SS 2B-15.00Mtr, SS 2A-3.75Mtr

13 T13P2 Invert Closing 210 m 86.250 123.75 40.00


Kerb-24 m & Invert-36 m Concrete
14 T13P2 Kerb & Invert Concrete 100 m 24.000 76.00 24.00
Completed.