Block Work

This document outlines the planned schedule for block work on the Samana Miami-1 project from January 18th to March 27th. It details 18 activities from ground level to the roof with planned start and finish dates. Masonry and plaster work is scheduled from January 18th to March 30th over 63 days. Block work specifically will take place from January 18th to March 27th over 60 days in 6 floor-to-floor sections consisting of 2 parts each.

Uploaded by

adilazam608
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
27 views

Block Work

This document outlines the planned schedule for block work on the Samana Miami-1 project from January 18th to March 27th. It details 18 activities from ground level to the roof with planned start and finish dates. Masonry and plaster work is scheduled from January 18th to March 30th over 63 days. Block work specifically will take place from January 18th to March 27th over 60 days in 6 floor-to-floor sections consisting of 2 parts each.

Uploaded by

adilazam608
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

Samana Miami-1 Block Work 26-Jan-24

Activity ID Activity Name Planned Start Planned Finish Original Duration Actual Start Actual Finish

(New EPS) 18-Jan-24 30-Mar-24 63d

Masonry & Plaster 18-Jan-24 30-Mar-24 63d

Masonry & Plaster 18-Jan-24 30-Mar-24 63d


Block Work 18-Jan-24 27-Mar-24 60d
Ground to Podium Floor 18-Jan-24 07-Feb-24 18d
A1000 Car Park 18-Jan-24 20-Jan-24 3d
A1010 Substation 25-Jan-24 27-Jan-24 3d
A1020 LV Room 29-Jan-24 31-Jan-24 3d
A1030 Retail Shop 01-Feb-24 03-Feb-24 3d
A1040 Enterance Lobby 05-Feb-24 07-Feb-24 3d
Podium to 1st Floor 08-Feb-24 14-Feb-24 6d
A1050 Part-1 08-Feb-24 10-Feb-24 3d
A1060 Part-2 12-Feb-24 14-Feb-24 3d
1st Floor to 2nd Floor 15-Feb-24 21-Feb-24 6d
A1070 Part-1 15-Feb-24 17-Feb-24 3d
A1080 Part-2 19-Feb-24 21-Feb-24 3d
2nd Floor to 3rd Floor 22-Feb-24 28-Feb-24 6d
A1090 Part-1 22-Feb-24 24-Feb-24 3d
A1100 Part-2 26-Feb-24 28-Feb-24 3d
3rd Floor to 4th Floor 29-Feb-24 06-Mar-24 6d
A1110 Part-1 29-Feb-24 02-Mar-24 3d
A1120 Part-2 04-Mar-24 06-Mar-24 3d
4th Floor to 5th Floor 07-Mar-24 13-Mar-24 6d
A1130 Part-1 07-Mar-24 09-Mar-24 3d
A1140 Part-2 11-Mar-24 13-Mar-24 3d
5th Floor to 6th Floor 14-Mar-24 20-Mar-24 6d
A1150 Part-1 14-Mar-24 16-Mar-24 3d
A1160 Part-2 18-Mar-24 20-Mar-24 3d
6th Floor to Roof 21-Mar-24 27-Mar-24 6d
A1170 Part-1 21-Mar-24 23-Mar-24 3d
A1180 Part-2 25-Mar-24 27-Mar-24 3d
Plaster 25-Jan-24 30-Mar-24 57d

Client: Samana SIA Holding Consultant: AREC Main Contractor: Reliant Contracting LLC
Sub: Aroos Alsaeed Plaster & Cladding Works L.L.C.