PERT Slides
PERT Slides
PERT
Statistics Summary
METU CVE434 Construction Planning PERT
DATA DISTRIBUTION
Reference: https://www.mathsisfun.com/data/standard-normal-distribution.html
METU CVE434 Construction Planning PERT
DATA DISTRIBUTION
heights of people
iq scores
errors in measurements
blood pressure
points on a test
Reference: https://www.mathsisfun.com/data/standard-normal-distribution.html salaries
METU CVE434 Construction Planning PERT
NORMAL DISTRIBUTION
Reference: https://www.mathsisfun.com/data/standard-normal-distribution.html
METU CVE434 Construction Planning PERT
Measured Heights
Mean calculated
Reference: http://www.mathsisfun.com/data/standard-deviation.html
METU CVE434 Construction Planning PERT
Difference of each
measurement to
the mean
Reference: http://www.mathsisfun.com/data/standard-deviation.html
METU CVE434 Construction Planning PERT
Reference: http://www.mathsisfun.com/data/standard-deviation.html
METU CVE434 Construction Planning PERT
STANDARD DEVIATION
Reference: https://www.mathsisfun.com/data/standard-normal-distribution.html
METU CVE434 Construction Planning PERT
68.3% LIKELY
VERY LIKELY
95.5%
YOU SHOULD
KNOW THESE
PROBABILITIES.
ALMOST NOT PROVIDED
CERTAINLY IN THE EXAM!
99%
Reference: https://www.mathsisfun.com/data/standard-normal-distribution.html
METU CVE434 Construction Planning PERT
Z table for
percentages
under the curve
Applicable for
positive z
values!
METU CVE434 Construction Planning PERT
NORMAL DISTRIBUTION
X Z
(Z – 0) / 1 = (X – µ) / Ϭ
Z = (X – µ) / Ϭ
Reference: https://www.mathsisfun.com/data/standard-normal-distribution.html
METU CVE434 Construction Planning PERT
PERT
METU CVE434 Construction Planning PERT
PERT uses an activity duration called “the expected mean time (te)” with
uncertainty information
The uncertainty can be expressed either as
the “standard deviation (σte)” or
the “variance (vte)” of the duration.
There is a distribution for activity duration!
METU CVE434 Construction Planning PERT
In order to calculate te, σte, vte the analyst has to estimate the distribution
through three different durations for each activity.
1) The optimistic time (to): is the time estimate where a particular activity
may be completed if everything goes well and exceptionally good luck is
experienced.
2) The most likely time (tm): is the time estimate in which a particular
activity can most often be completed under normal conditions.
3) The pessimistic time (tp): is the time estimate in which particular activity
may be completed under an adverse situation, such as having unusual and
unforeseen complications.
METU CVE434 Construction Planning PERT
Optimistic
time
Pessimistic
time
Time
to tm te tp
0
Activity completion with in this
range is anticipated
METU CVE434 Construction Planning PERT
DURATION CALCULATIONS
Assumption:
Mean duration is
to+4tm+tp taken as the
te = arithmetic mean
6 of the mid-point
between to and tp
We have 6 x σte tp − to and the most
between the to - tp σte = likely time (tm),
range 6 weighed as
double.
FORMULAE
ARE 2
tp − to 2
PROVIDED IN vte = (σte) = ( )
THE EXAM! 6
METU CVE434 Construction Planning PERT
PROBABILITY DISTRIBUTIONS
An activity duration is characterized with its te and σte.
There is a % 99 chance that the duration will stay in to - tp range, namely te ±
3σte.
There is a % 68.3 chance that duration lies in te ± σte.
There is a % 95.5 chance that duration lies in te ± 2σte.
99% of area
68,3% of area
95,5% of area
-3 -2 -1 xത +1 +2 +3
METU CVE434 Construction Planning PERT
PROBABILITY OF TS
(PROJECT DURATION)
The probability of meeting the desired scheduled time (TS) is obtained by
determining the percentage of the area cut off by this time from the total area
beneath the normal distribution curve
probability
peak or mode at expected mean
event time
time
TS TE
shaded area
Probability of TS = %
area under curve
METU CVE434 Construction Planning PERT
Assuming that the project duration has a normal distribution due to Central
Limit Theorem, the probability of completing an activity by any specific time
"TS", can be determined by using the Z-Table where
TS − TE
Z= TS = TE + ZσTE
σTE
Where; calculation of
scheduled time of
Z: number of standard deviations from the start an event based on
"TE": Critical path (project) mean given risk level
PERT PROCEDURE
1. Plan activities and logic as in CPM, but instead of assigning a fixed duration,
assign 3 duration estimates to, tp, and tm.
2. Translate 3 time estimates into a probability distribution, than find te and σte,
vte.
3. Use each activity’s te as its duration and find the critical path just as we did in
CPM.
4. Combine the activities on the critical path to get probability distribution for
each critical path (E(T), VAR(T)).
5. Using critical path’s distribution, make interferences about the likelihood of
the project being completed on before or after any given date (Assumption:
critical path doesn’t change).
METU CVE434 Construction Planning PERT
D
2 5
A I
F
B G
1 4 7
PERT PROCEDURE
ADVANTAGES OF PERT
Unlike CPM, the total project time is not a single figure, but expressed with a
NORMAL DISTRIBUTION.
It enables to obtain much more information about the project. Given a target
date T*, probability that the project time will be greater than T* can be
calculated.
E.g.: Probability that T is less/greater than a certain value T* can be evaluated
from standard normal distribution function tables.
T ∗ − 𝐸(𝑇)
P(T<T∗) = P(z <
VAR(T)
METU CVE434 Construction Planning PERT
SHORTCOMINGS OF PERT
How accurate can be to, tp, tm?
In construction projects usually there is no enough data related with activity
durations. Therefore, accuracy depends on the ability of the estimator.
PERT is based on many assumptions.
Activity times, in fact, cannot always be modeled by continuous functions all
the time. Different probability distributions may be more appropriate.
(Simulation technique may solve this problem)
Critical path may change, then, joint probabilities must be used.
Many researchers criticize PERT because it has computational difficulties and
at the end, obtained results do not worth all those time consuming
computations.
METU CVE434 Construction Planning PERT
Examples
METU CVE434 Construction Planning PERT
EXAMPLE - 1
DURATIONS (DAYS)
ACTIVITY OPTIMISTIC (to) MOST LIKELY(tm) PESSIMISTIC (tp)
A 2 4 7
B 5 8 14
C 4 6 8
D 2 2 2
E 7 10 21
EXAMPLE - 1
Calculate "te", "σte", and "Vte" for individual activities, and "TE" , "VE", and
"σE" for entire path.
DURATIONS (DAYS) EXPECTED STANDARD VARIANCE
EXAMPLE - 1
1) The probability that the project will finish by the end of day 34?
TS − TE 34 − 32
Z= = = 0.67
σE 2.972
28 30 32 34 36
METU CVE434 Construction Planning PERT
EXAMPLE - 1
2) The probability that the project will finish on the 32nd day?
The probability that the project will finish on the 32nd day:
Pr("TS"=32)=Pr("TS"≦32)-Pr("TS"≦31)=0.5-0.367=0.133=13.3%
TS − TE 31 − 32
Z= = = −0.34 → Pr (TS≦31)=1−0.633=0.367
σE 2.972
28 30 32 34 36
METU CVE434 Construction Planning PERT
EXAMPLE - 1
3) The probability that the project will finish at least 2 days early?
TS − TE 30 − 32
Z= = = −0.67
σE 2.972
From Z table, we find that Pr ("TS"≦30)=1-0.749=0.251=25.1%
28 30 32 34 36
METU CVE434 Construction Planning PERT
EXAMPLE - 1
4) The probability that the project will finish on the 32nd day±1 day?
28 30 32 34 36
METU CVE434 Construction Planning PERT
EXAMPLE - 2
ACTIVITY DESCRIPTION to tm tp
1-2 A 8 8 8
1-3 C 7 9 11
1-4 B 8 10 24
2-4 Dummy 0 0 0
2-5 D 3 5 13
3-6 E 12 13 32
4-5 F 6 7 8
4-7 G 10 11 18
4-6 H 8 10 36
5-7 I 8 8 20
6-7 K 8 8 8
Calculate the probabilities that the project will finish later than 30, 34, and 36
days?
METU CVE434 Construction Planning PERT
EXAMPLE - 2
EXAMPLE - 2
EXAMPLE - 2
METU CVE434 Construction Planning PERT
EXAMPLE - 2
The project has a total expected duration ("TE") of 34 days, and a variance of
28.94.
P(T>30)=1-P(z<(30−34)/5.38)=1-z(-0.74)=1-0.23=0.77
P(T>34)=1-P(z<0)=0.5
P(T>36)=1-P(z<(36−34)/5.38)=1-0.64=0.36
METU CVE434 Construction Planning PERT
EXAMPLE - 3
3 Calculate the times
C for event 7 that
correspond to +ഥ 1 σ,
1 A 2 B 4 D 5 F 6 G 7 ഥ 2 σ, and +
+ ഥ3 σ
from the mean value
of event 7’s time
E
to tm tp
A 3 4 6
B 4 6 7
C 3 3 4
D 5 6 7
E 8 10 12
F 11 12 14
G 3 3 3
Estimated times
METU CVE434 Construction Planning PERT
EXAMPLE - 3
3 Calculate the times
C for event 7 that
correspond to +ഥ 1 σ,
1 A 2 B 4 D 5 F 6 G 7 ഥ 2 σ, and +
+ ഥ3 σ
from the mean value
of event 7’s time
E
to tm tp te σte vte
A 3 4 6 4.17 0.5 0.25
B 4 6 7 5.83 0.5 0.25
C 3 3 4 3.17 0.17 0.03
D 5 6 7 6 0.33 0.11
E 8 10 12 10 0.67 0.44
F 11 12 14 12.17 0.5 0.25
G 3 3 3 3 0 0
Estimated times Calculate by using formulas
METU CVE434 Construction Planning PERT
EXAMPLE - 3
E(T)=31.17
ഥ 0.93%68.3
31.17+
V=0.86 σ=0.93
Ranges ഥ 1.85%95.5
31.17+
ഥ 2.79%99
31.17+