Comparision Between PMC & IE
Comparision Between PMC & IE
Sr.
Existing scope of GHB agreement Scope of IE Agreement
No.
1 day to day supervision, monitoring and management of the works, project, quality As per cl. 2.4 of TOR of IE GSRTC,
assurance ,bill certification and payments etc., for various functional facilities Review, check and verify project report prepared by the Concessionaire
adhering to the respective contracts execution of work as per the REVIEW & - Technical guide for construction management
APPROVED drawings, specifications duly following extant procedures of - Construction control manual and various quality tools including works control
Employer/Architect / Consultant and also subject to such further variations and formats and check lists
modifications as the Employer may decide from time to time. - All project contracts/Agreements including Detailed Design and Engineering
PMC should prepare cash flow charts and update budget estimate as per actual contract, EPC contract, O & M contract
execution and keep Employer informed on all changes prior to implementation - Quality Assurance Plan and Quality Control provisions during the construction
and execution of works if any. stage
- Cost monitoring/control/value management criteria
- Variations.
2 Material Testing requirement and other services completely within the As per cl. 2.4.2 of TOR of IE GSRTC,
Contractor’s scope of work and as directed by Employer. Supervision of various tests (as per the provision of Concession Agreement) and
their certification
3 Preparation of periodical reports relating to time, cost and quality as directed by As per cl. 2.4.6 of TOR of IE GSRTC,
Employer. Periodic review of the project works as per agreed project programme in terms of
quality, completion stage and changes and corrective action thereof.
As per cl. 2.4.10 of TOR of IE GSRTC,
The Independent Engineer shall inspect the Construction Works and the Project
site and send the report of such Inspection (the "Inspection Report") setting forth
an overview of the status, progress, quality and safety of construction; Including
the work methodology adopted, the materials used and their sources, and
conformity of Construction Works with the Scope of the Project and the
specifications and standards. In a separate section of the Inspection Report, the
Independent Engineer shall describe in reasonable detail the lapses, defects or
deficiencies observed by it in the construction of the Project. The Inspection
Report shall also contain a review of the maintenance of the existing lanes in
conformity with the provisions of the Agreement. The Independent Engineer shall
send a copy of its Inspection Report to the GSRTC and the Concessionaire with
necessary opinion.
Comparison between the scope of work for Project Management Consultant of Gujarat Housing Board (GHB) & Independence
Engineering services for building projects.
Sr.
Existing scope of GHB agreement Scope of IE Agreement
No.
4 Scrutinizing, the construction methods proposed by the Contractor for carrying As per cl. 2.4.4 of TOR of IE GSRTC,
out the works to ensure that these are satisfactory with particular reference to the Scrutinize Good for Construction (GFC) drawings including variations thereof,
technical requirements and deployment of plant and machinery, project supervise the setting out of the works
implementation schedule and environment aspects as well as safety of works, As per cl. 2.3.9 of TOR of IE GSRTC,
personnel and the general public. The Independent Engineer shall review the detailed design, construction
methodology, quality assurance procedures and the procurement, engineering and
construction time schedule sent to it by the Concessionaire and furnish its
comments within 15 (fifteen) days of receipt thereof.
5 Ensure safety of structure by taking all necessary precautions and by not allowing As per cl. 2.4.5 of TOR of IE GSRTC,
excessive construction loads on floors and shall avoid such other factors, which Audit the safety of the project during construction and operation and maintenance
will endanger the safety of structure during construction. stage
6 Ensure the safety of personnel working at site/inspecting the site by taking As per cl. 2.4.16 of TOR of IE GSRTC,
precautions by putting barricades, night lamps near trenches, pits, open shafts, lift If at any time during the Construction Period, the Independent Engineer
shafts, edge of floors, terraces and such other places and to insist on compliance determines that the Concessionaire has not made adequate arrangements for the
of safety code such as use of helmets, etc, on work site. safety of workers and Users in the zone of construction or that any work is, being
carried out in a manner that threatens the safety of the workers and the Users in
the shall make a recommendation to the GSRTC forthwith, identifying the whole
or part of the Construction Works that should be suspended for ensuring safety in
respect thereof.
7 Monitor the variations and deviations from the original designs, concept and work As per cl. 2.4.3 of TOR of IE GSRTC,
order and keep the Employer informed including obtaining prior approvals from Examine and approve any change on scope of work or variation as per contractual
the Employer whenever required. provision
Comparison between the scope of work for Project Management Consultant of Gujarat Housing Board (GHB) & Independence
Engineering services for building projects.
Sr.
Existing scope of GHB agreement Scope of IE Agreement
No.
8 Monitor the quality of the work, material testing – its reports & frequency and As per cl. 2.4.11 of TOR of IE GSRTC,
control the quality as per specification, relevant codes and as per sound For determining that the Construction Works conform to Specifications and
engineering practices. Standards, the Independent Engineer shall require the Concessionaire to carry out,
- Maintain the registers for mandatory tests to be conducted for all materials or cause to be carried out, tests on a sample basis, to be specified by the
before incorporation in work. The guidelines may be taken from the Engineer in Independent Engineer in accordance with Good Industry Practice for quality
charge regarding the registers to be maintained. assurance The Independent Engineer shall issue necessary directions to the
- Inspect and approve the materials at site as per specifications before they are Concessionaire for ensuring that the tests are conducted in a fair and efficient
used in work. manner with cost and risk of Concessionaire, and shall monitor and review the
- Responsible for obtaining good workmanship with respect to lines, levels and results thereof.
plumb at all stages of work with reference to working drawings and ensure correct
dimensions of all elements.
- Ensure that work proceeds as per tender conditions and specifications. All
material brought to site to be of approve quality and make, rejected material is
removed from site and work executed is of high standard, good workmanship and
desired quality.
9 Evolve and implement a system for the quality assurance of the works. The As per cl. 2.4.12 of TOR of IE GSRTC,
system of control of quality of material and completed works shall also include The sample size of the tests, to be specified by the Independent Engineer, shall
sampling method and acceptance criteria. The sampling method and the comprise 10% (ten per cent) of the quantity or number of tests prescribed for each
acceptance criteria shall be based on statistical methods and the recommendations category or type of tests in the Quality Control Manuals; provided that the
of the relevant IS codes and State R&B specifications. Independent Engineer may, for reasons to be recorded in writing, increase the
aforesaid sample size by up to 10% (ten per cent) for certain categories or types of
material tests.
10 Prepare and present monthly progress reports to the Employer/Engineer-in-charge, As per cl. 2.4.9 of TOR of IE GSRTC,
containing description of project activities. The Independent Engineer shall prepare the monthly progress report and send its
comments there on to the GSRTC and to Concessionaire.
Comparison between the scope of work for Project Management Consultant of Gujarat Housing Board (GHB) & Independence
Engineering services for building projects.
Sr.
Existing scope of GHB agreement Scope of IE Agreement
No.
11 Co-ordinate with all agencies working at site, liaison with local authorities for As per cl. 2.4.7 of TOR of IE GSRTC,
proper permissions / commencement certificate / completion certificate, etc. Examining the works and accordingly issue provisional completion stage and final
completion stage certificate
12 Prepare an integrated housekeeping, operation and maintenance manual for proper As per cl. 2.4.20 of TOR of IE GSRTC,
upkeep of the premises. The Independent Engineer shall aid and advise to the Concessionaire in preparing
the Maintenance Manual.
13 Check all the stipulated items of Work by Contractor and estimation of BOQS. As per cl. 2.3.6 of TOR of IE GSRTC,
Review check and verify design and working drawings, specifications, analysis of
rates and bills of quantities.
Comparison between the scope of work for Project Management Consultant of Gujarat Housing Board (GHB) & Independence
Engineering services for building projects.
Sr.
Additional scope of GHB agreement Additional Scope of IE agreement
No.
1 - As per cl. 2.1 of TOR of IE GSRTC,
The Independent Engineer shall undertake a joint survey of the existing properties with
the Technical Person of GSRTC to identify the properties that need to be dismantled and
disposed off.
2 - As per cl. 2.1 of TOR of IE GSRTC,
The Independent Engineer shall determine and certify the salvage value of the existing
properties including but not limited to all civil structures, workshop, machinery,
furniture, debris, materials as directed etc. the Independent Engineer shall also estimate
the cost of dismantling and disposed off these materials.
3 - As per cl. 2.3.1 of TOR of IE GSRTC,
To review the Concessionaire’s Master Plan, Drawings, design proposal and prepare a
design review report within 7 (seven) days after receiving the drawing/ documents.