QC Daily Report

This document provides a weekly progress report for the construction of a 220/110/10 kV substation. It summarizes that concrete pouring and waterproofing have been completed for the control building foundation. Excavation of the switchyard is also finished. Quality tests conducted include slump tests and density tests. Upcoming work includes further excavations, surveying, and concrete pouring. Materials delivered include steel reinforcement. Safety inspections have been performed and security reporting is ongoing. Progress updates are provided for various construction components, and staffing information includes personnel from the client, contractor, consultant, and subcontractors currently on and off site.

Uploaded by

Ibrahim Danish
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
10 views

QC Daily Report

This document provides a weekly progress report for the construction of a 220/110/10 kV substation. It summarizes that concrete pouring and waterproofing have been completed for the control building foundation. Excavation of the switchyard is also finished. Quality tests conducted include slump tests and density tests. Upcoming work includes further excavations, surveying, and concrete pouring. Materials delivered include steel reinforcement. Safety inspections have been performed and security reporting is ongoing. Progress updates are provided for various construction components, and staffing information includes personnel from the client, contractor, consultant, and subcontractors currently on and off site.

Uploaded by

Ibrahim Danish
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 4

Project Name Desing,Supply,Construction Erection,Testing and Commissioning of 220/110/10 kV

Turkmenenergogurlushik”
Contract No. G-83/G2G Contractor Concern of the Ministry of
Energy of Turkmenistan
Date September 5, 2023 Consultant Top Azma
34’ 22.359’
Location Herat Province Coordinates
62’ 13.868’
Noor-Ul-Jihad
Area Substation Schedule Achieved (%)

Team

1. The Work that has been completed


1.1 PCC pouring of control building.
1.2 Waterproofing of a part of control building by Isogam
1.3 Excavation of Switch yard
1.4 Compaction of Switch yard

2. Quality tests that has been done


2.1 Fresh concrete test of PCC which include slump test, temperature, and cube sampling for compressive
strength.
2.2 Field density test from Switch yard.

3. Schedule for (Tomorrow or upcoming working day)


3.1. Control building foundation and basement footing excavations.
3.2. Site survey and leveling of the control building and switchyard.
3.3. Excavated extra deposed soil and materials removing.
3.4. Concrete PCC for control building basement foundation footing.
3.5. FDT test for switch yard.

4. Materials/Equipment Deliveries
4.1 Steel reinforcement delivered to the site.

5. Health, Safety, and Environmental


1. General site inspection has been done.
2. All site personnel has protective equipment.

1
3. Inspection of Hand and power tools has been done.
4. Inspection of equipment has been done by TEG HSE.

6. Security (SIR Filed: Yes/No) – Yes

7. Work progress achieved till date


7.1. Control building foundation and basement excavations have been completed 45%.
7.2. Site survey and leveling of the control building and switchyard have been completed 30%.
7.3. Site mobilization canopy installation is in progress has been completed 70%.
7.4. Electricity trench excavation from main source to the site camp has been completed 65%.
7.5. Excavated extra deposed soil and materials removing is have been completed 28%.
7.6. Compaction of control building basement foundation footing has been completed 100%.

8. Staff on Site
A. DABS Personnel
No. Name Title On-Site Off-Site

Gholam Sediq Site Engineer ✓


1 Aheed

B. Contractor
No. Name Title On-Site Off-Site
Site
1 Abulrauf Kanishka Construction ✓
Manager
2 ✓
Mohammad Tareq Timory QC Manager
3 ✓
Aziz Ansari HSE
4 ✓
Ab Tahir Kohan Coordinator
5 ✓
Askanderof Mardan Site Engineer

C. Consultant
No. Name Title On-Site Off-Site
1 Abdul Sami Lab Technician ✓

2
D. Sub-contractor
No. Name Title On-Site Off-Site
PM ✓

QC ✓

HSE ✓

Surveyor ✓

Site Engineer ✓

Skilled ✓
Worker
Skilled ✓
Worker
Skilled ✓
Worker
Skilled ✓
Worker
Skilled ✓
Worker

3
Slump test of PCC Mortar Sampling

PCC pouring for control building Waterproofing of control building by Isogam

Site inspector: Engineer Ghulam Sediq Aheed

Signature:

Date: September 9, 2023