Methode of Statement Lightning Protection & Earthing System Review 4
Methode of Statement Lightning Protection & Earthing System Review 4
Submitted By :
B. RESPONSE
A – No objection.
B – No objection subject to comments.
C – Submission incomplete. See comments / Resubmit with missing details.
D – Submission rejected. See comments / Resubmit.
E – Other comments
C. COMMENTS
Date: Date:
Page 1 of 1
ROJECT 3RD STOREY BUILDING DATA CENTER NONGSA BATAM INDONESIA
Owner : Consultant Management : Main Contactor :
Contents
1.0 PURPOSE 7.5 Earth Pit
2.0 SCOPE OF WORK 7.6 Earthing Conductors
3.0 REFERENCE 8.0 EXCUTION WORK FOR EARTHING Of LIGTHNING
4.0 RESPONSIBILITIES PROTECTION
5.0 PROCEDURE 9.0 STANDART PROCEDURE
5.1 General Description 10. SAFETY CONTROL
5.2 Material 11 INSPECTION AND TESTING PROCEDURE
5.3 Material Handling and Storage 11.1 Inspection
6.0 HEALTH AND SAFETY 11.2 Field Test
7.0 INSTALLATION OF EARTHING SYSTEM 11.3 Soil resistivity testing
7.1 Procedure to conduct the exothermic conection 12. QUALITY CONTROL AND ASSURANCE
7.2 Earthing cable installation 13. HEALTH & SAFETY RISK AND CONTROL
7.3 Ensure that the copper cable is free of dirt/oil and dry keeping 13.1 Working with welding machine and exothermic welding
7.4 Earth rod installation
1
ROJECT 3RD STOREY BUILDING DATA CENTER NONGSA BATAM INDONESIA
Owner : Consultant Management : Main Contactor :
3
ROJECT 3RD STOREY BUILDING DATA CENTER NONGSA BATAM INDONESIA
Owner : Consultant Management : Main Contactor :
4.0 Responsibilitas
No. Designation Qty Responsibility
Responsible for overall commercial, contractual & technical performances associated with specific
1 Project Manager 1
project. Reporting to the Project Director.
2 M&E Engineer 4 Planning and supervising installation activities.
Inspect, verify, and prepare work statement for a quality installation works. Material storage, fit for use
3 QA / QC Engineer 2 tools and equipment, and installation works
To provide toolbox and guidance to work and to ensure that work is carried out in a safe manner.
4 Safety Officer 1
Obtain permit to work, control the sequence according to MOS, approved shop drawings, and MSA,
ensure mechanical aspects of the work are according to the specifications, ensure safe practices are
5 Supervisor 3-5 followed and ensure quality of workmanships during execution. Ensure material temporary storage and
protection meet vendor and standards requirement . Ensure tools being used for installation are
calibrated and meet vendor and standards requirement
4
ROJECT 3RD STOREY BUILDING DATA CENTER NONGSA BATAM INDONESIA
Owner : Consultant Management : Main Contactor :
4.0 Responsibilitas
No. Designation Qty Responsibility
Bertanggung jawab atas keseluruhan kinerja komersial, kontrak & teknis yang terkait dengan proyek
1 Project Manager 1 tertentu. Melaporkan kepada Direktur Proyek.
3 QA / QC Engineer 2 Memeriksa, memverifikasi, dan menyiapkan metode kerja untuk pekerjaan instalasi yang berkualitas.
Penyimpanan bahan, alat dan perlengkapan layak pakai, dan pekerjaan pemasangan.
Untuk menyediakan kotak peralatan dan panduan untuk bekerja dan untuk memastikan bahwa
4 Safety Officer 1 pekerjaan dilakukan dengan cara yang aman.
Mendapatkan izin untuk bekerja, mengontrol urutan sesuai dengan MOS, gambar kerja yang disetujui,
dan MSA, memastikan aspek mekanis pekerjaan sesuai dengan spesifikasi, memastikan praktik
keselamatan diikuti dan memastikan kualitas pengerjaan selama pelaksanaan. Pastikan penyimpanan
5 Supervisor 3-5
dan perlindungan sementara material memenuhi persyaratan vendor dan standar. Pastikan alat yang
digunakan untuk pemasangan dikalibrasi dan memenuhi persyaratan vendor dan standar
6 Pekerja 10-15 Melaksanakan seluruh aspek kegiatan pada perkerjaan instalasi system grounding dan penangkal petir.
5
ROJECT 3RD STOREY BUILDING DATA CENTER NONGSA BATAM INDONESIA
Owner : Consultant Management : Main Contactor :
5. Procedure 5. Prosedur
5.1 General Description 5.1 Gambaran Umum
The work on installing the grounding system and lightning Pekerjaan pemasangan grounding system dan proteksi petir
protection will be carried out at the Data Center Building, 3rd Floor, akan dilakukan di Gedung Data Center Lantai 3 Nongsa Batam
Nongsa Batam Indonesia. Indonesia.
The following tools shall be arranged before starting work. All Alat-alat berikut harus diatur sebelum mulai bekerja. Semua
materials are as per specification and approved material submittal: bahan sesuai spesifikasi dan penyerahan bahan yang disetujui.
- Copper clad Earth Rods , Earth Rod to Tape - Copper clad Earth Rods , Earth Rod to Tape
- Clamps Earth Rod to Cable Clamp Ubolt Clamps - Clamps Earth Rod to Cable clamp , Ubolt Clamp
- Concrete Earth Inspection Housing Cable - Concrete Earth Inspection Housing Cable
- Lugs earth bars lightning protection - Lugs earth bars lightning protection
- Metodhs Flexible copper braid bonds - Metodhs Flexible copper braid bonds
6
ROJECT 3RD STOREY BUILDING DATA CENTER NONGSA BATAM INDONESIA
Owner : Consultant Management : Main Contactor :
- Welding machine & welding mold ( Expiry of exothermic - Mesin las & cetakan las (masa pakai cetakan las eksotermik
welding mold is functing of frequency of application and shall bergantung pada frekuensi penggunaan dan harus sesuai
be as per the manufacturer recommendation ) Welding rod rekomendasi pabrikan), Batang las.
Safety requirements tools such us safety shoes, safety helmet, Peralatan persyaratan keselamatan seperti sepatu keselamatan, helm
safety glasses, uorescent vest, and safety gloves to ensure keselamatan, kacamata keselamatan, rompi neon, dan sarung tangan
maximum ability of safe work and dust mask. keselamatan untuk memastikan kemampuan kerja yang aman dan masker
5.3 MATERIAL HANDLING AND STORAGE debu secara maksimal.
On receipt of the Earthing materials at site necessary precautions 5.3 PENANGANAN DAN PENYIMPANAN BAHAN
shall be for unloading, shifting & storage as follows: Pada saat menerima material grounding system di lokasi, tindakan
Material shall be stored in a covered / dry space at all the time to pencegahan yang perlu dilakukan adalah pembongkaran, pemindahan &
avoid corrosion. All materials received at site shall be inspected and penyimpanan sebagai berikut:
ensured that the materials are as per approved material submittal. Bahan harus disimpan di tempat tertutup/kering setiap saat untuk
menghindari korosi. Semua material yang diterima di lokasi harus
diperiksa dan dipastikan bahwa material tersebut sesuai dengan
- Metode ikatan jalinan tembaga fleksibel penyerahan material yang disetujui.
7
ROJECT 3RD STOREY BUILDING DATA CENTER NONGSA BATAM INDONESIA
Owner : Consultant Management : Main Contactor :
Any discrepancies, damage etc., found will be noticed and Setiap perbedaan, kerusakan, dll., yang ditemukan akan diperhatikan
reported dan dilaporkan
for further action. Material found not suitable for site use will be untuk tindakan lebih lanjut. Material yang ditemukan tidak sesuai untuk
removed from site immediately. Storage of exothermic welding penggunaan dilapangan akan segera dikembalikan dari lapangan.
materials should be in a clean, dry, “NO SMOKING” area and should Penyimpanan bahan las eksotermik harus berada di tempat yang bersih,
be restricted to access by authorized personnel only. Storage condition kering, “DILARANG MEROKOK” dan harus dibatasi aksesnya oleh
shall be such that exothermic welding materials are not subject to rough personel yang berwenang saja. Kondisi penyimpanan harus sedemikian
handling or physical damage. Storage shall be in cool place and in rupa sehingga bahan las eksotermik tidak terkena penanganan yang kasar
condition no humidity and moisture. Earthing Pit Installation All boxes atau kerusakan fisik. Penyimpanan harus di tempat sejuk dan dalam
or container of material should be stored in accordance with container kondisi yang tidak lembab. Pemasangan Earthing Pit Semua kotak atau
(carton) or label marking “This Side Up” wadah material harus disimpan sesuai dengan wadah (karton) atau
labelnya menandai “Sisi Ini Ke Atas”
8
ROJECT 3RD STOREY BUILDING DATA CENTER NONGSA BATAM INDONESIA
Owner : Consultant Management : Main Contactor :
These materials must be stored under shelter to protect the boxes Bahan-bahan ini harus disimpan di bawah naungan atau penutup
from the elements and raised to protect them from dampness or wet untuk melindungi kotak dari cuaca buruk dan ditinggikan untuk
surface ( puddles ). melindunginya dari kelembapan atau permukaan basah ( genangan air ).
6. Health And Safety 6. Kesehatan dan Keselamatan
Ensure only trained Authorized & licensed persons only shall Pastikan hanya orang yang berwenang dan berlisensi saja yang boleh
operate the power tools and do the Installation and Testing job. beroperasi perkakas listrik dan melakukan pekerjaan Instalasi dan
Necessary PPE to be used while working in energized to be worn while Pengujian.
working in energized circuits. Ensure adequate lighting is provided in APD yang diperlukan untuk digunakan saat bekerja di lingkungan
the working area at night time and if inside the building area to be well berenergi untuk dipakai saat bekerja di sirkuit berenergi. Pastikan
illuminated. Ensure service area/work area openings are provided with pencahayaan yang memadai tersedia di area kerja pada malam hari dan jika
barricade, tape, safety nets and warning signage to be provided. berada di dalam area bangunan, berikan penerangan yang baik. Pastikan
Calibrated Instruments only to be used. bukaan area servis/area kerja dilengkapi dengan barikade, pita pengaman,
Power supply used to take temporary power supply shall not have any jaring pengaman dan rambu peringatan. Instrumen yang sudah dikalibrasi
joints. Ensure LOTO procedure to be followed and implement saja yang boleh digunakan. Catu daya yang digunakan untuk mengambil
comprehensive logout & tag out during execution of work. Earthing Pit
Installation catu daya sementara tidak boleh mempunyai sambungan apa pun. Pastikan
9
ROJECT 3RD STOREY BUILDING DATA CENTER NONGSA BATAM INDONESIA
Owner : Consultant Management : Main Contactor :
prosedur LOTO diikuti dan diterapkan logout & tag out yang
komprehensif selama pelaksanaan pekerjaan.
7. Installation Of Earthing System 7. Pemasangan Sistem Pembumian
7.1 Procedure to conduct the exothermic connections 7.1 Prosedur untuk melakukan sambungan eksotermik
- Fix the connection selector to the handle clamp as per the - Pasang pemilih sambungan ke klem pegangan sesuai kebutuhan
require sizes of conductor to be welded. ukuran konduktor yang akan dilas.
- Place the conductor in the mould, ensure that connection - Tempatkan konduktor dalam cetakan, pastikan pemilih sambungan
selector is used in accordance to theconductor to be welded. yang digunakan sesuai dengan konduktor yang akan dilas.
- Close the handle clamp and lock in the lock position, drop the - Tutup klem pegangan dan kunci pada posisi terkunci, jatuhkan
metal retaining disc,into the bottom of the mould crucible. cakram penahan logam ke bagian bawah wadah cetakan.
- Ensure that the metal retaining disc is correctly,completely - Pastikan cakram penahan logam terpasang dengan benar,terpasang
seated and cover up the tap hole. sepenuhnya dan tutupi lubang cetakan.
10
ROJECT 3RD STOREY BUILDING DATA CENTER NONGSA BATAM INDONESIA
Owner : Consultant Management : Main Contactor :
- Deposit the welding power into the crucible and spread mould - Masukkan bubuk las ke dalam wadah dan sebarkan dibagian tepi
edge as a role of starting power cetakan sebagai bantuan tenaga awal proses pembakaran
- Close the mould lips, and ignite with the gas torch - Tutup bibir cetakan dan nyalakan dengan gas torch / mesin las
- Open the mould after a few seconds where the reaction is praktis. Buka cetakan setelah beberapa detik dimana reaksi selesai
completed or the metal has been solid. atau logamnya telah dipadatkan .
- Do not touch the welding surface after the reaction - Jangan menyentuh permukaan pengelasan setelah reaksi
- Clean up the mould for the next joint - Bersihkan cetakan untuk sambungan selanjutnya
7.2 EARTHING CABLE INSTALLATION 7.2 INSTALASI KABEL BUMI
- The earthing conductor, bare copper cable shall be installed as
- Earthing Conductor, bare copper cable harus dipasang sesuai
per approved shop drawing.
shop drawing yang disetujui.
- Ensure that the copper cable is straight (not wavy) so that it ts
- Pastikan copper cable dalam posisi lurus (tidak bergelombang)
nicely into the exothermic,
sehingga dapat masuk dengan baik ke dalam cetakan eksotermik,
mould prior to the exothermic welding.
sebelum di mulai pengelasan eksotermik.
11
ROJECT 3RD STOREY BUILDING DATA CENTER NONGSA BATAM INDONESIA
Owner : Consultant Management : Main Contactor :
7.3 Ensure that the copper cable is free of dirt / oil and dry keeping. 7.3 Pastikan copper cable bebas dari kotoran/minyak dan tetap kering
- Size and type of supplementary conductors shall be as per the - Ukuran dan jenis konduktor pelengkap harus sesuai dengan yang
approved disetujui
- Shop drawings and stipulated in the contract specification. - Shop drawing dan ditetapkan dalam spesifikasi kontrak.
- Earthing conductors for equipment chassis and neutral and all - Earthing conductors untuk chasis peralatan dan netral serta semua
other panels and mechanical equipment and metal work, shall panel lainnya serta peralatan mekanis dan pekerjaan logam, harus
be as per approved shop drawing. sesuai dengan shop drawing yang disetujui.
7.4 EARTH ROD INSTALLATION 7.4 PEMASANGAN BATANG BUMI
- The copper rod is to be driven into the ground by means - Copper rod ditancapkan ke dalam tanah dengan menggunakan
hammer drill / sledge hammer. hammer drill/palu godam.
- Make sure the rods are coupled with coupling and driving studs - Pastikan rods dipasangkan dengan kopling dan tiang penggerak
before hammering as it will protect the thread or the head of the sebelum dipukul dengan palu kepala dari rods di pasang proteksi untuk
rods from damaged. menghindari kerusakan.
12
ROJECT 3RD STOREY BUILDING DATA CENTER NONGSA BATAM INDONESIA
Owner : Consultant Management : Main Contactor :
- While sitting earth rods, ensure that resistance areas associated - Saat memasang earth rods, pastikan area resistensi yang terkait
with individuals rods do not overlap. Spacing of parallel dengan masing-masing rods tidak tumpang tindih. Jarak earth rods
installed earth rods of length L Shall be L to 2L. yang dipasang paralel dengan panjang L Harus L hingga 2L.
- Earth rods are to be located at a distance greater than 1 m - Earth rods harus ditempatkan pada jarak lebih dari 1 m secara
horizontally from foundations of buildings. horizontal dari pondasi bangunan.
- Conductive ller such as Marcionite or Bentonite or equal ller - Bahan penghantar konduktif seperti Marcionit atau Bentonit atau
that will not corrode is to be provided around the Rod. bahan sejenisnya yang tidak menimbulkan korosi harus disediakan
- Once the desired depth is reached, the grounding conductor will di sekeliling Rod.
be connected to the clamp terminal rod and secured securely - Setelah kedalaman yang diinginkan tercapai, grounding conductor
akan disambungkan ke clamp terminal rod dan diikatkan dengan
- A resistivity check must be carried out (for electrical, the
aman
recommended value does not exceed 1 Ohm and for lightning
- Pemeriksaan resistivitas harus dilakukan (untuk elektrikal, nilai
protection does not exceed 5 Ohm). yang disarankan tidak melebihi 1 Ohm dan untuk lightning
- The number of rods driven into the ground will be dependable - Jumlah rod yang ditancapkan ke dalam tanah akan bergantung
to the soil resistivity on that particular area and as per approved pada resistivitas tanah pada area tersebut dan sesuai shop drawing
shop drawing. yang disetujui.
- Additional rods and network shall be driven if needed to active - Rod dan jaringan tambahan harus digerakkan jika diperlukan
5 ohm resistivity. untuk mendapatkan nilai resistivitas 5 ohm.
7.5 EARTH PIT 7.5 EARTH PIT
Precast, square or circular section concrete hand hole (minimum Hand hole beton pracetak, persegi atau lingkaran (diameter
450mm internal diameter), with concrete cover and extending to dalam minimal 450 mm), dengan penutup beton dan memanjang
150mm below top of earth rod. Cover earth rod connector with suitable hingga 150 mm di bawah bagian atas batang tembaga. Tutupi
protective compound, which can be easily removed for inspection. konektor batang tembaga dengan senyawa pelindung yang sesuai,
Connector is not to be covered with back ll material and is to remain yang dapat dengan mudah dilepas untuk diperiksa. Konektor tidak
clean. Install the inspection pit and ensure that it is ush with the external boleh ditutup dengan bahan bagian belakang, dan harus tetap
ground / road level. Minimum length of Rod is 2.4m, extendable as bersih. Pasang lubang inspeksi dan pastikan sejajar dengan
necessary to obtain required earth resistance, Ground Resistance Tester permukaan tanah/jalan bagian luar. Panjang minimum Batang
Ensure that the earth pit is free from dirt and rubbish. adalah 2,4m, dapat diperpanjang seperlunya untuk mendapatkan
14
ROJECT 3RD STOREY BUILDING DATA CENTER NONGSA BATAM INDONESIA
Owner : Consultant Management : Main Contactor :
15
ROJECT 3RD STOREY BUILDING DATA CENTER NONGSA BATAM INDONESIA
Owner : Consultant Management : Main Contactor :
16
ROJECT 3RD STOREY BUILDING DATA CENTER NONGSA BATAM INDONESIA
Owner : Consultant Management : Main Contactor :
17
ROJECT 3RD STOREY BUILDING DATA CENTER NONGSA BATAM INDONESIA
Owner : Consultant Management : Main Contactor :
8. Execution Work For Earthing Of Lightning Protection 8. Pelaksanaan Pekerjaan Untuk Pembumian Proteksi Petir
- Drive the earth rods into the earth by hammer. - Dorong earth rods ke dalam tanah dengan palu
- Excavate a trench with standard dimensions or as mentioned in - Gali parit dengan dimensi standar atau seperti yang disebutkan
speci cations to link earth rods together by soft drawn bare dalam spesifikasi untuk menghubungkan earth rod dengan drawn
copper wire. bare copper wire yang ditarik lembut.
- Link earth rods to Grounding network. Testing and record - Hubungkan earth rods ke Grounding network. Menguji dan
earthing resistant value. mencatat nilai tahanan tanah.
- Joints shall be protected against rust by cold galvanized paint. - Sambungan harus dilindungi dari karat dengan cat galvanis dingin.
- Bolt connections of copper wire with hot dip galvanized steel - Sambungan baut kawat tembaga dengan batang baja galvanis hot
bar and copper wire with copper bar should reach mechanical e dip dan kawat tembaga dengan batang tembaga harus mencapai
ect and electrical e ect. efek mekanis dan efek elektrik.
- During the driving of the rods into the earth, it is better to - Pada saat rods ditancapkan ke dalam tanah, sebaiknya ukur nilai
measure value of the resistance to earth in order to quantity of tahanan terhadap tanah sesuai dengan jumlah batang pentanahan
necessary grounding rod. yang diperlukan.
18
ROJECT 3RD STOREY BUILDING DATA CENTER NONGSA BATAM INDONESIA
Owner : Consultant Management : Main Contactor :
9. Standard Procedures
- All equipment’s connected to power supply must be grounded. 9. Prosedur Standar
- All metal parts, structural steel, cable trays, piping, reinforced - Semua peralatan yang terhubung ke sumber listrik harus
concrete must be grounded. Soil Resistivity Test groundingkan.
- All joints shall be according to shop drawing. - Semua bagian logam, baja struktural, Tray kabel, pipa, beton
bertulang harus diarde.
10. Safety Control - Semua sambungan harus sesuai dengan shop drawing.
- Store safely materials that are susceptible to water damage. 10. Kontrol Keamanan
- Aman kan matrial yang rentan rusak karena air. Jauhkan dari air
Keep away from water if necessary .
jika diperlukan.
- Keep workplace and amenities is always clean. Barricade and - Menjaga tempat kerja dan fasilitasnya selalu bersih. Barikade dan
sign post are available around the site work. papan tanda tersedia di sekitar lokasi pekerjaan.
11. Inspection And Testing Procedures 11. Prosedur Inspeksi Dan Pengujian
11.1 INSPECTION 11.1 INSPEKSI
19
ROJECT 3RD STOREY BUILDING DATA CENTER NONGSA BATAM INDONESIA
Owner : Consultant Management : Main Contactor :
- The Earthing System must be visually inspected by the owner's - Earthing System harus diperiksa secara visual oleh perwakilan
representative during installation owner selama pemasangan
- The contractor shall not allow back-flooding of the trench or pit - Kontraktor tidak boleh membiarkan adanya banjir pada parit atau
where the system is installed prior to inspection by the owner's lubang di mana sistem ini dipasang sebelum inspeksi oleh
representative. Standby submersible pump to avoid perwakilan owner.Standby kan pompa celup untuk menghindari
waterlogging. terjadi nya genangan air dalam parit.
- Material delivered shall be inspected under the Engineer’s - Bahan yang diserahkan harus diperiksa di bawah pengawasan
supervisor about type and size of earth conductors shall be as Pengawas Teknis mengenai jenis dan ukuran earth conductor
shown on the approved shop drawings and stipulated in harus seperti yang ditunjukkan pada shop drawing yang disetujui
specification. dan ditentukan dalam spesifikasi.
- Shop-drawing approved, Material approved. - Shop-drawing approve, Material approve
Test method of visual Metode pengujian visual
Check quality of grounding conductor and grounding electrode Periksa kualitas grounding conductor dan grounding electrode yang
delivered on site. Check installation (connection, routing, and quantity) dikirimkan di lokasi. Periksa pemasangan (koneksi, routing, dan kuantitas)
according to approved shop drawings. sesuai dengan shop drawing yang disetujui
20
ROJECT 3RD STOREY BUILDING DATA CENTER NONGSA BATAM INDONESIA
Owner : Consultant Management : Main Contactor :
21
ROJECT 3RD STOREY BUILDING DATA CENTER NONGSA BATAM INDONESIA
Owner : Consultant Management : Main Contactor :
- The instrument shall be equipped with ammeter reading directly in - Instrumen harus dilengkapi dengan pembacaan ammeter langsung
Ohms or fractions thereof to indicate the ground value of the dalam Ohm atau pecahannya untuk menunjukkan nilai dasar
electrode under test. All testequipment including test meter shall be elektroda yang diuji.
provided and one copy of the ground megger manufacturer’s
- Update sertifikat kalibrasi alat uji .
directions, including the method shall be provided.
- Updating of calibration certi cate of test instruments. - Resistansi minimum berdasarkan kapasitas konduktor yang
- The minimum resistance based on the allowable capacity of the diijinkan adalah:
22
ROJECT 3RD STOREY BUILDING DATA CENTER NONGSA BATAM INDONESIA
Owner : Consultant Management : Main Contactor :
23
ROJECT 3RD STOREY BUILDING DATA CENTER NONGSA BATAM INDONESIA
Owner : Consultant Management : Main Contactor :
- The measurement value obtained is in accordance with the - Nilai pengukuran yang di dapat ,sesuai dengan nilai tahanan yang
agreed or mutually agreed resistance value. di sepakati atau di setujui bersama.
24
ROJECT 3RD STOREY BUILDING DATA CENTER NONGSA BATAM INDONESIA
Owner : Consultant Management : Main Contactor :
12. Quality Control And Assurance 12. Pengendalian Mutu dan Jaminan
- Material used will be as approved by the Engineer. The sizes - Bahan yang digunakan akan disetujui oleh Engineer. Ukuran dan
and routes routing will be as per the approved shop drawing. routes routing akan sesuai dengan gambar yang disetujui.
- Earthing materials shall be stored in a place free of water and - Earthing material harus disimpan di tempat yang bebas air dan
properly covered to avoid any damages due to weather a ect. tertutup rapat untuk menghindari kerusakan akibat pengaruh cuaca.
- Combined resistance of earth electrodes is to be measured - Resistansi gabungan dari elektroda bumi harus diukur selama
during dry season and checked against speci ed resistance. musim kemarau dan diperiksa terhadap resistansi yang ditentukan.
13. Health & Safety Risk And Control 13. Pengendalian dan Risiko Kesehatan & Keselamatan
The safety procedure generally has to be applied for all Prosedur keselamatan secara umum harus diterapkan untuk semua
Engineers, Supervisors, Workers as following bellow: Engineering, Supervisor, Pekerja sebagai berikut:
- Make sure that all personal protection equipment (PPE) be
- Pastikan semua alat pelindung diri (APD) tersedia di lokasi
provided on site before starting work such as helmet, safety
sebelum mulai bekerja seperti helm, sepatu keselamatan,
boot, safety glasses, glove, mask etc.
kacamata keselamatan, sarung tangan, masker, dll.
- Make sure that PPE must be wear in the correctly way when
- Pastikan APD harus dipakai dengan benar saat bekerja.
working.
25
ROJECT 3RD STOREY BUILDING DATA CENTER NONGSA BATAM INDONESIA
Owner : Consultant Management : Main Contactor :
- Tools and equipment’s shall be inspected by authorized person - Peralatan dan perlengkapan harus diperiksa oleh petugas yang
before carried out the work berwenang sebelum melaksanakan pekerjaan.
- Barricades and sign posts for warning shall be provided on site. - Barikade dan tanda peringatan harus disediakan di lokasi
- Fire extinguishers shall be provided on site wherever - Alat pemadam kebakaran harus disediakan di lokasi dimana
exothermic welding works and always ready to use. pengelasan eksotermik dilakukan dan selalu siap digunakan.
13.1 WORKING WITH WELDING MACHINE AND 13.1 BEKERJA DENGAN MESIN LAS DAN PENGELASAN
EXOTHERMIC WELDING EKSOTHERMIK
- Ensure worker wear safety glasses, gloves, helmet etc. - Pastikan pekerja memakai kacamata keselamatan, sarung tangan,
- Fire extinguisher shall be always ready at work place. helm dll.
- Welding machine must be checked carefully before using. - Alat pemadam kebakaran harus selalu siap di tempat kerja.
- Welder must be qualified and skill. - Mesin las harus diperiksa dengan teliti sebelum digunakan.
- Welder harus berkualitas dan terampil.