Lost File Name

1. The document is a checklist for confirming manual operation of the controllable pitch propeller (CPP) on the ship AL NISR. 2. The checklist includes checking if the CPP can move to full ahead (AH) and astern (AS) positions manually, recording blade angle and pressure readings during movement, and checking relief valve settings. 3. Pressure readings are to be recorded for various CPP positions and movements to confirm proper manual operation of the CPP system.

Uploaded by

ibrahim bayoumi
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
65 views

Lost File Name

1. The document is a checklist for confirming manual operation of the controllable pitch propeller (CPP) on the ship AL NISR. 2. The checklist includes checking if the CPP can move to full ahead (AH) and astern (AS) positions manually, recording blade angle and pressure readings during movement, and checking relief valve settings. 3. Pressure readings are to be recorded for various CPP positions and movements to confirm proper manual operation of the CPP system.

Uploaded by

ibrahim bayoumi
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

Machinery Division (Kobe) CHECK SHEET REXAS-42525-3 (1/3)

[ Confirmation of manual operation ]

Ship Name AL NISR Checking Date

Item CPP Manual Operation Type KST-200ZC/B1

1. Confirm manual operation and pressures at Rexpeller room


with CPP non-follow mode, M/E idle speed and clutch "OFF".

Press the valve


for manual operation

※If the pressure value is hunting, please write the range of value in the below table. (Ex. 5~7 MPa)

Result of inspection
Checking items PORT STBD
Check if CPP can move to full AH and AS by manual □ Possible □ Possible
01)
valve operation (valve 61). □ Impossible □ Impossible
Confirm the angle on blade angle transmitter under Full AH : deg Full AH : deg
02)
above condition. Full AS : deg Full AS : deg
AH to AS AH to AS
AH press : MPa AH press : MPa
03) Check each pressure during CPP movement. (AH max to AS max). AS press : MPa AS press : MPa
Pump Del : MPa Pump Del : MPa
Time : Sec Time : Sec
AS to AH AS to AH
AH press : MPa AH press : MPa
04) Check each pressure during CPP movement. (AS max to AH max). AS press : MPa AS press : MPa
Pump Del : MPa Pump Del : MPa
Time : Sec Time : Sec
Full AH Full AH
Check each maximum pressure at full AH to confirm
AH press : MPa AH press : MPa
05) the relief valve No. 63 setting point.
AS press : MPa AS press : MPa
NOTE: Keep pressing the valve during the checks.
Pump Del : MPa Pump Del : MPa
Full AS Full AS
Check each maximum pressure at full AS to confirm
AH press : MPa AH press : MPa
06) the relief valve No. 63 setting point.
AS press : MPa AS press : MPa
NOTE: Keep pressing the valve during the checks.
Pump Del : MPa Pump Del : MPa