Specifications 1
Specifications 1
agreement which in most cases controls the quality of materials and works.
Sometimes, specifications may be used to describe matters which could not be
explained clearly by drawings/sketches. This chapter explains the different types
of specifications and their necessity.
In case of disputes between the owner and contractor with respect to the method of
construction, quality and quantity of materials used, equipments and machineries
used etc, the specifications play the major role in solving the disputes and arriving
at a settlement.
Importance of Specifications Drawings and Specifications form two important
contract documents. Information such as dimensions, type of construction, etc.
Which can be easily expressed graphically For each proposed work, numbers of
drawings are prepared to explain the details of foundations, basement,
superstructure, roof and floors joinery etc., whatever attempt is made to furnish
complete working drawings, it becomes necessary to describe the drawing in
detail.
This description in works without sketches and sometimes with line sketches
giving details of standard materials, method of construction and the requirements
of workmanship of construction etc., is called specification.
The specifications define the quality of materials and workmanship. Hence this will
help the contractor to quote correct rates for the different items of works.
Specifications help the owner to check and satisfy with the works.
The specifications are broadly divided into three categories as
General specifications give general idea of the whole work or structure and are
useful for preparing the estimate. These general specifications doe not form part of
the contract document.
They are used in the estimates by the person who prepares the estimates.
The detailed specification of an item of work specifies the qualities and quanitites
of materials, the proportion of mortar, workmanship, the method of preparation and
execution and the method of measurement.
The detailed specifications are arranged as for as possible in the same sequence
or order as the work is carried out
The following provisions are made in the detailed specifications. a General provisions
Technical provisions.
General provisions
General provisions
These are also known as conditions of contract and they apply to the work as a whole. In
this document, the conditions governing the contract are written. The following groups
of conditions of contract are generally accommodated under the general provisions.
i. Conditions relating to documents
ii. Conditions relating to the general obligations of the contractor These pertain to
Acts, bye-laws and regulations .Fencing, watching and lighting of the work spot
Insurance.
When the work, or a structure or project is taken up0, instead of writing detailed
specification every time, the printed standard specifications are referred in the
contract document and other documents pertaining to the work.
In the case of Civil Engineering Works, the specifications shall contain the following
The Sand used for mortar shall be clean, sharp, heavy and gritty.
It should be free from clay, salt, mica and organic impurities.
It shall not contain harmful chemicals in any form.
Medium and fine sand are to be used in mortars.
Coarse sand shall be sifted through 600 micron sieve and used in mortars for
plastering works.
2. Detailed Specification for first class bricks:
The earth used for molding the bricks shall be free from organic matters salts and
chemicals. The size, weight and colour of the burnt bricks should be uniform. The
adjacent faces of the bricks are to be right angles to each other.
The bricks shall be free from cracks, flaws and lumps.
They should not break where dropped, from 1 metre height, on the ground.
The size, weight and colour of the burnt bricks should be uniform. The adjacent
faces of the bricks are to be right angles to each other.
The bricks shall be free from cracks, flaws and lumps. They should not break where
dropped, from 1 metre height, on the ground.
5. Detailed Specification for water for concrete:
Water used for mixing and curing concrete shall be clean and free from injurious
amounts of oils, acids, alkalis, salts, sugar, organic materials or other substances
that may be deleterious to concrete or steel.
Potable water may be used for mixing concrete.
The suspended organic solid matter in the water shall not exceed 200 mg/l and
inorganic solid matter shall not exceed 3000 kg/l, the pH value of water shall be
not less than 6.
6. Detailed Specification for coarse aggregate:
The aggregate to be used in reinforced cement concrete shall be of blue granite
stone, machine crushed and well graded with a nominal size of 20 mm. It shall be
hard, dense, durable strong and free from flakes.
The aggregate shall not contain harmful materials such as coal, mica clay, shells,
organic impurities etc.
The whole area of construction is to be cleared of tees, grass, roots of trees etc.,
complete and leveled horizontally to enable easy marking of centre line of the
building.
The compressive strength, crushing value etc of the aggregate shall be in
accordance with the requirements of IS:383 – 1970.
Various factors influence the cost estimation of a construction project.
Preparation of a construction cost estimate for any project is a very complex process
which consists of many variable factors.
Every variable has to be correctly estimated based on proper study, past experience
and research to calculate total project cost of construction.
There are many factors which affect the construction cost estimate and have
significant impact on project cost and they are as following:
1. Similar Construction Projects
For the construction estimate, the best reference will be similar construction
projects. The final cost of those similar projects can give the idea for the new
construction project cost calculation. The final cost of past project needs to be
factored with current construction cost indices.
8. Reputation of Engineer
Smooth running of construction is vital for project to complete in time. The cost of
projects will be higher with sound construction professional reputation. If a
contractor is comfortable working with a particular engineer, or engineering firm,
the project runs smoother and therefore is more cost-effective.
9. Regulatory Requirements
Approvals from regulatory agencies can sometimes be costly. These costs also need
to be considered during cost estimate.
Cost estimation for construction projects should also need to consider costs of
insurance for various tools, equipments, construction workers etc. General insurance
requirements, such as performance bond, payment bond and contractors general
liability are normal costs of construction projects. In some special projects, there can
be additional requirements which may have additional costs.
11. Size and Type of Construction
Project For a large construction project, there can be high demand for workforce. For
such a requirements, local workmen may not be sufficient and workmen from
different regions need be called. These may incur extra costs such projects and also
for the type of construction project where specialized workforce is required.
14. Contingency
It is always advisable to add at least 10% contingency towards the total project costs
for unforeseen costs and inflation.
What should be included in a specification?
Price format.
For Services: day/hourly/all-inclusive rates (total cost)
Quality.
Quantity.
Required supplier experience.
Size / dimensions.
Performance.
Installation / maintenance / servicing / warranty.
Particular electric specifications
Accessories (general)
All single core cables must be delivered in such a way to show the labels of
producen, seals or other proof of origin and the contractor, must obtain certificates
of routine tests against a given order, when requested by the Engineer.
The number of cables to be installed in conduits or trunking must be such as to
permit easy drawing in without damaging the cables and must never be more than
40%.
Installation shall comply with the Local Electricity Authority’s regulations
Flexible cables (with some multiple core wires for every wire).
All the cables must have approval certificate from relevant local authority and
fabric certificate.
PVC insulation of the cable multiple wire or with single wire easy conductor from
temper conductor isolating with PVC upper final sheath must resist 600/1000V.
All the cables put within tubes shall be isolated with high conduction PVC.
Flexible cable consist of multi-striped wire and depending on what we have:
Three wire cable, 1 neuter, 1 earth (for mono phase system)
Four wire cable, 3 phase and 1 neuter (for three phase system, without earthing)
Five wire cable,3 phase and 1 neuter and 1earthing(for three phase system, with
earthing)
Flexible cable must have colored wire for identification. BLACK shall be used for
neuter conductor, GREEN/YELLOW shall be used for earth conductor and
RED/BLUE and YELLOW for phase conductors.
Same colors shall be used for connections on the same phase conductors. Same
colors shall be used for connections on the same phase of supply throughout the
installation.
Channels and accessories
Electric installation can be done in two ways:
Under plaster inserted in flexible PVC tube
Above plaster in PVC channels
Distribution boxes, depending on the system to be used, are under plaster and
above plaster so that the way of fixing them is with plaster or screw.
Materials and their technical characteristic are the same as for flexible tube.
Dimensions of distribution boxes vary according to the circumstances and need.
They are in circle form, square, rectangle and their shutter covers are with different
colors It is important that connections of wires/cables inside draw boxes shall be
realize with joined clamp (point).
Flexible connection
Flexible connections are used usually in laboratories and consist of the electric
line runs near device with ending draw box and from here into device that will be
connected one flexible connection is used outside wall.
For this outlet cable from the draw box must be well insulated within technical
condition.
Cable is to be with two insulation layers and inside flexible tube. Its connection
with the device shall be made in its holder.
System of channels
All lamps must be suitable for 220 volts operation and be complete with control
gear.
The characteristics of metal halide lamps shall be such that they will start with a
10% reduction in rated voltage.
Luminaries and other auxiliary equipment must be manufactured according to the
European standards, or approved similar as follow:
Type 1131 Punto, JM-IS glass diffuser, IP55, biege color.
Spot light
Outside area; in sports ground, in the area in the front of school, at the main gate of
the school luminaries of flower garden etc. As spotlights for indoor area (gymnastics
hall) can be put suspend ceiling or inside wall.
They must be put in such a way to light better all the hall and not preventing (blinding)
sport persons/students during their exercises. Number of spotlights depends on:
The space of the hall that is to be lit
Type of spotlight