Cranes - Function Test
Cranes - Function Test
2
CRANES USE & OPERATION PAGE 24 OF 30
Appendix 1
CRANE LOAD TEST PROCEDURE
1.0 PURPOSE
The purpose of this procedure is to establish a consistent generic approach for the function & load testing
of hydraulic and conventional crawler and wheel-mounted cranes on all Bechtel non-nuclear power
projects.
2.0 SCOPE
2.1 This procedure is applicable to cranes used for construction purposes, which have previously been
qualified for use. It is not intended to give direction to qualify new equipment.
2.2 This procedure does not address non-conventional lifting machinery such as custom cranes, telescoping
gantries, gin poles, etc. Such machinery shall be tested using specific procedures prepared by the
manufacturer or other competent person.
2.3 Refer to manufacturer operations and maintenance manuals, applicable jurisdictional codes, standards,
and regulations for any requirements (i.e., in the U.S. – applicable sections of ASME B30 series crane
standards). In the absence of local or regional standards, utilize applicable OSHA/ANSI regulations and
standards as guides. Contact BEO Rigging Operations for assistance in identifying and obtaining
applicable standards.
3.0 REQUIREMENTS
3.1 The work process for crane load testing is shown in Attachment 1-1 and Attachment 1-2, and as specified
below.
Bechtel Confidential
©Bechtel Corporation 2009, 2005, 2000. Contains information that is confidential and proprietary to Bechtel or its affiliates, clients or
suppliers, and may not be used, reproduced or disclosed without Bechtel’s prior written permission. All rights reserved.
No. 4MP-T81-01904 Rev. 2
CRANES USE & OPERATION PAGE 25 OF 30
3.3.1 Load brakes shall be tested and adjusted to manufacturer specifications prior to performing any
machine load test. The manufacturer’s specifications generally call for a single part line to be utilized
for these brake checks to prevent a multi-part line from masking any potential problems. The
Preliminary Brake Check Procedure using Single part line all hoisting drums is as follows:
The lower of the two capacities above will be the limiting factor in planning the
test.
4. Determine the test weight needed, taking into account all loading the brakes will be subjected
to.
5. This test must be carried out at a boom length and radius well within the rated capacity of the
crane.
6. Lift the load approximately 6 inches off the ground.
7. Move the hoist control to the neutral position allowing the brake to set.
8. Hold the load with the brakes only.
9. The load should remain suspended with the brakes set according to manufacturer
specifications for a period of five minutes.
10. If required, replace or repair braking system to comply with manufacturer’s specifications.
The lower of the two capacities above will be the limiting factor in planning the
test.
4. Determine the test weight needed taking into account all loading the brakes will be subjected
to.
5. This test must be carried out at a boom length and radius well within the rated capacity of the
crane.
6. Lift the load approximately 6 inches off the ground.
7. Apply the brake.
8. Hold the load with the brakes only.
Bechtel Confidential
©Bechtel Corporation 2009, 2005, 2000. Contains information that is confidential and proprietary to Bechtel or its affiliates, clients or
suppliers, and may not be used, reproduced or disclosed without Bechtel’s prior written permission. All rights reserved.
No. 4MP-T81-01904 Rev. 2
CRANES USE & OPERATION PAGE 26 OF 30
9. The load should remain suspended with the brakes set according to manufacturer
specifications for a period of five minutes.
10. If required, re-adjust or repair the brake to comply with manufacturer’s specifications.
3.3.2 Locate suitable test weight. The weight must either be a stamped certified weight or weighed with a
certified and/or calibrated dynamometer or scale. If local jurisdictional codes, standards, or
regulations are more stringent, and require a "certified weight", then one must be used.
Common sense must prevail when choosing a "suitable test weight". It should have
readily available pick points and not be of a geometry that would require special rigging
fixtures and calculations to determine the center of gravity. If a piece of equipment is
used as a “test weight”, it should be rigged such that the slings and rigging will not
damage the equipment.
3.3.3 Use certified rigging (i.e., slings, shackles, spreaders, etc.) for all loads. Refer to BESH Core Process
CP-223, Cranes and Lifting Operations for general guidelines and sling use, as well as rigging
equipment inspection and techniques.
3.3.4 While it is not required, documentation of crane load tests using photographs has proven to be an
effective medium to communicate what transpired.
3.4.1 A rated load test is to be conducted by, or under the direction of, a qualified person:
• Prior to initial use (when manufactured)
• Following maintenance on cranes in which load sustaining parts have been altered, replaced, or
repaired
• When required by legislation
• When required by contractual conditions
The replacement of the rope is specifically excluded from this requirement. However, a functional
test of the crane under a normal operating load should be made prior to putting the crane back in
service.
CAUTION: The crane shall not be loaded to more than 100 percent of its rated chart capacity
without prior written approval from the crane manufacturer. If a 110 percent load
test is required by the project, then manufacturers’ approval and test plan shall be
obtained.
3.4.2 Rated load tests will, by their nature, always be “critical” lifts according to Standard Work Process
Procedure 4MP-T81-01903, Construction Rigging Work Operations. They must be planned and
executed in the same manner as any other critical lift, requiring a written lift plan and review and
approval by a Bechtel CRE.
3.4.3 Determine/confirm deductions from the gross capacity chart for the following:
• Manufacturer approved attachments
• Load block
• Overhaul ball
• Wire rope
• Rigging
Bechtel Confidential
©Bechtel Corporation 2009, 2005, 2000. Contains information that is confidential and proprietary to Bechtel or its affiliates, clients or
suppliers, and may not be used, reproduced or disclosed without Bechtel’s prior written permission. All rights reserved.
No. 4MP-T81-01904 Rev. 2
CRANES USE & OPERATION PAGE 27 OF 30
3.4.4 Determine test load required based upon available weights and load charts to achieve 100 percent
capacity.
3.4.5 Refer to in-cab load charts and select a radius at which the total test load will be 100 percent of gross
capacity.
For cranes with automatic safe load indicators and alarms, in order to achieve a 100
percent lift, the LMIs may need to be overridden. The systems are generally equipped
with override switches to aid in the performance of these load tests.
3.4.8 If any load sustaining parts are altered, replaced, or repaired during the execution of any correction
actions (maintenance or repairs) ,then a load test will be required.
3.4.9 All repairs and maintenance shall be recorded and placed in the equipment file.
3.4.10 At the completion of a successful load test, all results shall be recorded and placed in the Equipment
file. Refer to Attachment B for a sample Load Test form.
3.4.11 Written reports shall be reviewed and filed by an appointed or authorized person, showing test proce-
dures and confirming the adequacy of repairs or alterations.
3.5 Project Specific Load Testing
Should the project or customer have a specific load test requirement, this load test shall not exceed 100
percent of the Crane or Lifting Device load chart capacity. These test needs are usually a result of a
Heavy or Critical lift where a "pre-lift" verification of the crane is mandated by the project. These types of
project-specific load tests are in addition to the required "rated load tests" previously discussed.
If a 110 percent load test is required, manufacturers’ approval must be obtained.
4.0 ATTACHMENTS
4.1 Attachment 1-1 – "Load Test Process" Flow Chart
4.2 Attachment 1-2 – "Load Test" Flow Chart
4.3 Attachment 2 – "Example" Load Test Form
Bechtel Confidential
©Bechtel Corporation 2009, 2005, 2000. Contains information that is confidential and proprietary to Bechtel or its affiliates, clients or
suppliers, and may not be used, reproduced or disclosed without Bechtel’s prior written permission. All rights reserved.
No. 4MP-T81-01904 Rev. 2
CRANES USE & OPERATION PAGE 28 OF 30
Attachment 1-1
Load Test Process
Bechtel Confidential
©Bechtel Corporation 2009, 2005, 2000. Contains information that is confidential and proprietary to Bechtel or its affiliates, clients or
suppliers, and may not be used, reproduced or disclosed without Bechtel’s prior written permission. All rights reserved.
No. 4MP-T81-01904 Rev. 2
CRANES USE & OPERATION PAGE 29 OF 30
Attachment 1-2
Load Test
Bechtel Confidential
©Bechtel Corporation 2009, 2005, 2000. Contains information that is confidential and proprietary to Bechtel or its affiliates, clients or
suppliers, and may not be used, reproduced or disclosed without Bechtel’s prior written permission. All rights reserved.
No. 4MP-T81-01904 Rev. 2
CRANES USE & OPERATION PAGE 30 OF 30
Attachment 2
LOAD TEST FORM (Example)
" Sa m ple "
LO AD TE ST
E q u ip m en t N u m b er : 1 4 - 0 00 0 S eri al N u m be r: 4 1 00 7
M ake M a nito w oc M od e l 4 1 0 0w S e r 1 1
No tes o n L if t:
B r ake fu n ctio n m e ets r eq u ire m en ts, w e h eld th e tes t l o ad o n th e b ra kes w ith n o evid e n ce o f d ri ft d o w n o f th e lo a d .
D e sc rib e if l oad li ne b ra ke s h el d l oad w i thuo t an y c r eep dow n for a g iv en perio d "s ay " 5 m inu tes .
D e s cr ip t io n o f D ed u ct i o n s D ed u ct i o n s f ro m G ro s s C a p a c it y D e d u c t io n s fro m G ro s s C a p a ci t y
U S P ounds K ilo g ra m s
S ign a tu re O p e ra to r D a te
Bechtel Confidential
©Bechtel Corporation 2009, 2005, 2000. Contains information that is confidential and proprietary to Bechtel or its affiliates, clients or
suppliers, and may not be used, reproduced or disclosed without Bechtel’s prior written permission. All rights reserved.