Weekly Progress Report 29.02.2024

Uploaded by

gajendra_tsn1318
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
21 views

Weekly Progress Report 29.02.2024

Uploaded by

gajendra_tsn1318
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 89

PRESTIGE

BEVERLY HILLS
816 Units

PROJECT REVIEW – 29.02.2024

Ground Breaking Dt : 28.09.2021

Construction Start Dt : 01.02.2022

Committed Completion Dt : 30.01.2025


PROJECT DATA

AREA DETAILS BUILDING FEATURES SERVICES

23,283Smt/ Configuration 3B + GF +
Site Area 35Floors Total Electrical
5.75Ac’s 2,300 KVA
Load
22,76,836 Number of
Built up Area 3
SFT Towers Total No of DG 4 x 625Kva
G + 4F
Club House
17,17,420
816 Units Transformer 2 x 1600Kva
Saleable Area SFT
No of Units
T1 : 320
Carpet Area 10,66,819 T2 : 284 Total Water
Tower Wise 490 KLD
SFT T3 : 212 Requirement

Basement 5,59,416 SFT No of Lifts – 14 no (11P 200KL +


Capacity of Fire
Area (25%) Towers +3S) 3 no (2P 200KL +
Tank
Amenity Area No of Lifts – CH +1S) 100KL
54,542 SFT
(Club House) No of Parking 1330 Capacity of STP 525 KLD
PHYSICAL PROGRESS – SLAB STATUS
CONCRETE AND REINFORCEMENT

CONCRETE - TOTAL VS ACHIEVED

102,337
108,700

0 20,000 40,000 60,000 80,000 100,000 120,000


Total Units Completed Units % Total Achieved
108,700 102,337 94%

REINFORCEMENT - TOTAL VS ACHIEVED

8,699
9,240

0 2,000 4,000 6,000 8,000 10,000


Total Units Completed Units % Total Achieved
9,240 8,699 94%
PHYSICAL PROGRESS – FINISHES WORKS

900
800
700
600
500
400
300
200
100
0
Water Gypsu Balcon Floori UPVC Cornic Wood Civil Grouti Painti Painti
proofi m y ng Windo e en Final ng ng ng
ng railing ws Doors works (prime (1st
r) Coat)
Total Units 816 816 816 816 816 816 816 816 816 816 816
Completed Units 758 726 633 631 511 516 519 367 135 235 185
% Total Achieved 93% 89% 78% 77% 63% 63% 64% 45% 17% 29% 23%
PHYSICAL PROGRESS – MEP WORKS
900

800

700

600

500

400

300

200

100

0
PHE Fire DB FA& PA Electrica Switch
Piping Protecti Dressin Cabling l wiring Fixing
on g
Total Units 816 816 816 816 816 816
Completed Units 734 610 351 400 400 400
% Total Achieved 90% 75% 43% 49% 49% 49%
10000
20000
60000
70000
80000
90000

30000
40000
50000

0
100000
110000
120000
2,500 3,200 Feb-22

5,300 6,150 Mar-22

8,300 9,126 Apr-22

11,800 10,911 May-22

14,800 13,411 Jun-22

18,800 16,619 Jul-22

22,800 20,477 Aug-22

26,800 23,619 Sep-22

30,800 27,487 Oct-22

35,300 31,859 Nov-22

40,200 36,429 Dec-22

45,200 41,386 Jan-23

50,200 46,354 Feb-23

55,500 52,240 Mar-23

61,300 57,555 Apr-23

66,300 63,186 May-23

71,300 68,728 Jun-23

76,300 73,507 Jul-23

81,300 78,875 Aug-23


CONCRETE PLANNED V/S ACHIEVED

86,300 84,140 Sep-23

91,300 89,283 Oct-23

96,300 93,736 Nov-23

101,300 97,751 Dec-23


104,800 100,777 Jan-24

108,300 Feb-24

111,100 Mar-24

112,300 Apr-24
PHYSICAL PROGRESS – STRUCTURAL WORK
PHYSICAL PROGRESS – FLOORING WORKS
MANPOWER IN MANDAYS

1200
1300
1500

1000
1100

0
100
200
300
600
700
800
900

400
500
Feb-22 120 150
Mar-22 128 190
Apr-22 206 275
May-22 280 325
Jun-22 370 440
Jul-22 450 540
Aug-22 590 560
1400 Present Manpower Available: 870

Sep-22 630 665


Oct-22 702 725
Nov-22 750 805
Dec-22 840 860
Jan-23 810 940
Avg Daily Manpower Required for Fabuary 24: 930

Feb-23 820 985


Mar-23 850 990
Apr-23 950 1000
May-23 925 1075
Jun-23 970 1075
Jul-23 1060 1145
Aug-23 1100 1145
DURATION IN MONTHS

Sep-23 1100 1145


Oct-23 1100 1120
LABOUR DEPLOYMENT HISTOGRAM

Nov-23 1020 1050


Dec-23 1020 1050
Jan-24 900 930
Feb-24 870 880
Mar-24 835
Apr-24 755
May-24 725
Jun-24 650
Jul-24 630
Aug-24 560
Sep-24 545
CONCERNS/SUPPORT
KPIL:
1. To concentrate and complete above terrace works in T1-29 Feb 2024.
2. To speed up Grouting and Snag completion - 135/816.
3. To focus on External Grinding and handing over for painting works Need to deploy resources on priority.
4. Lift shafts to handover for Lift installation in TOWER-1
5. To commence Terrace Waterproofing without further delay

OTHER FINISHES:
1. 40% of required manpower available for internal painting works – 185/360 available front . Manpower need
to be increase & Speed up for both internal and external.
2. Balcony and Utility Texture works to complete along with the first coat paint.
MEP Works:
1. DB dressing and switch sockets fixing testing to be done up to 18th floor -25/02/24.
2. PHE – External shaft completion upto 25th floor in all 3 towers-29/02/2024.
MASTER SCHEDULE
COMPLETION SCHEDULE FOR PRESTIGE BEVERLY HILLS, KOKAPET, HYDERABAD
F M A M J Jl A S O N D J F M A M J Jl A S O N D J F M A M J Jl A S O N D J F M A
Sl DETAILS Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1
No 2022 2023 2024 2025
No of Months 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39
TOWER 1
1 Sub Structure Works 1 2 3 4 5 6 7 Aug-22
2 Super Structure Works 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 Jan-24
3 Finishes Works 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 Sep-24
TOWER 2
1 Sub Structure Works 1 2 3 4 5 6 7 8 Sep-22
2 Super Structure Works 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 Jan-24
3 Finishes Works 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 Sep-24
TOWER 3
1 Sub Structure Works 1 2 3 4 5 6 7 8 Oct-22
2 Super Structure Works 9 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 Feb-24
3 Finishes Works 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 Sep-24
Podium Slab Completion 1 2 3 4 5 6 7 8 9 10 11 Dec-22
Tower floor Mock UP 1 2 3 4 Mar-23
Club House
1 Structure Works 1 2 3 4 5 6 7 8 9 Jul-23
2 Masonry & Plastering 7 8 9 10 11 Sep-23
3 Finishes Works 10 11 12 13 14 Jan-24
MEP & OTHER Works
1 MEP Works Jan-23 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 Nov-24
2 Doors & Windows Feb-23 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 Oct-24
3 External Development Works 1 2 3 4 5 6 7 8 9 Nov-24
4 All Other Finishes Mar-23 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 Jan-25
5 Post Construction Approvals Sep-24 1 2 3 4
6 Handing Over 1 Dec-24
F M A M J Jl A S O N D J F M A M J Jl A S O N D J F M A M J Jl A S O N D J F M A
No. of Months 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39
Year 2022 2023 2024 2025
PROJECT MILESTONES
Sl No DESCRIPTION/TYPE OF WORK MILESTONE Remarks
1 Total Project Duration 36 months
2 Completion of Podium Nov-22 11th Month
3 Making Ready Floor Mock up Mar-23 14TH Month
4 Completion of Structure - Towers Jan-24 24TH Month
5 Completion of Club House Feb-24 25TH Month
6 Handover to Interiors – Club House April-24 27TH Month
7 Completion of Civil Finishes Sep-24 32ND Month
8 External Development Works Nov-24 34TH Month
9 MEP Works Nov-24 34TH Month
10 All other Finishes Jan-25 36TH Month
ORDER RELEASE STATUS
Sl. No Description Contractor Order Release Remarks
1 GFRC Jallis M/s. Alusystems Jan-24 Order Released
2 Invisible window Grills Jan-24 BOQ Shared
3 Panels - LT & HT Jan-24 BOQ Shared
4 Prepaid Meters Jan-24 BOQ Shared
5 GFRC Cor M/s. Classical Metal Jan-24 Order Released
6 Rising Main/Bus Duct M/s. Elins Switch Jan-24 Order Released
7 Rising Main/Bus Duct M/s. Elins Switch Jan-24 Order Released
8 PHE Pumps Jan-24 BOQ Shared
9 DG -Hi Side M/s. Empower Feb-24 Order Released
10 DG - Low Side M/s. Empower Feb-24 In Progress
11 Hardscape Works Feb-24 BOQ Shared
12 Hardscape Material Feb-24 BOQ Shared
13 Geysers M/s. Jaquar Feb-24 Order Released
14 Light Fixtures - Internal Mar-24 BOQ Shared
15 WTP M/s. Crystal Drops Mar-24 Order Released
16 Mech Ventilation and STP Exhaust Mar-24 BOQ Shared
17 Softscaping Apr-24 BOQ Shared
18 Irrigation Works M/s. Santech Apr-24 Order Released
19 Transformer Apr-24 BOQ Shared
TOWER- VIEWS
SITE PHOTOGRAPHS
SITE PHOTOGRAPHS
PRESTIGE
CLAIREMONT
928 Units

PROJECT REVIEW – 29.02.2024

Ground Breaking Dt : 18.01.2023

Construction Start Dt : 05.06.2023

Committed Completion Dt : 30.06.2026


PROJECT DATA

AREA DETAILS BUILDING FEATURES SERVICES

30,610 Smt/ 2B + 4P + G + 38F -


Site Area Total Electrical
7.56 Ac’s Configuration T1 & T4 2,918 KVA
2B + 4P + G + 33F - Load
Built up Area 32,60,745 SFT T2 & T3
Number of Total No of DG 6 x 625Kva
2B + 4P +
Saleable Area 23,86,720 SFT Towers
G + 3F Transformer 4 x 1000Kva
Club House
No of Units 928 Units Total Water
Carpet Area 14,84,985 SFT 740 KLD
Tower Wise T1 & T4: 334 Each Requirement
T2 & T3: 130 Each
Basement 8,74,025 SFT Capacity of Fire 2 X 200KL
Area (26.8%) No of Lifts
30 no (24P +6S) Tank +100 KL
Towers
Amenity Area 4 no (2P +2S)
59,364 SFT No of Lifts CH Capacity of STP 725 KLD
(Club House)
No of Parking 2171
PHYSICAL PROGRESS
CONCRETE - TOTAL VS ACHIEVED

34,428
182,409

0 50,000 100,000 150,000 200,000


Total Qty Completed Qty % Total Achieved
182,409 34,428 19%

REINFORCEMENT - TOTAL VS ACHIEVED

2,926
15,505

0 5,000 10,000 15,000 20,000


Total Qty Completed Qty % Total Achieved
15,505 2,926 19%
PHYSICAL PROGRESS

700

600

500

400

300

200

100

0
RW – Retainin Retainin Shear Shear Shear Footings Non Non
Raft g Wall g Wall Wall Wall Wall Tower Tower
(B2-B1) (B1-P1) (P1-P2) (P2-P3) (P3-P4) Columns Columns
(B2-B1) (B1-P1)
Total Qty 630 630 630 169 169 169 190 190 190
Completed Qty 615 600 405 155 106 47 150 138 43
% Total Achieved 98% 95% 64% 92% 63% 28% 79% 73% 23%
PHYSICAL PROGRESS– FOUNDATIONS
PHYSICAL PROGRESS– SLAB
PLANNED V/S ACHIEVED
S.no Description Schedule Date Revised Date No of days short fall

1 Tower 1 Podium4 slab 17-12-2023 25-03-2024 99

2 Tower 2 Podium4 slab 01-01-2024 15-03-2024 74

3 Tower 3 Podium4 slab 16-01-2024 20-03-2024 64

4 Tower 4 Podium2 slab 12-12-2023 22-03-2024 101


CONCERNS/SUPPORT

KPTL:

1. KPIL assured to maintain 400nos Carpenters and 260Nos bar benders by 25th February 2024.Present
Available Carpenters-340/400nos and Bar benders -235/260nos.
2. Cumulative concrete Planned v/s Achieved : 34,428/1,82,409Cum. 18%
3. Concrete planned for the month February - 6301Cum Till now Achieved - 4890Cum. 77%
4. As average of 60 days delay in structural works.
5. Submission of T2 panel drawings and T3 & T4 Shell drawings for approval.
6. 100% Completion of retaining wall from Basement 2lvl to Podium 1 lvl enabling for backfilling.
7. Completion of STP & Fire sump/Pump room works.
8. Commencement of Masonry works at Basement 2 & 1 lvl.
MASTER SCHEDULE
COMPLETION SCHEDULE FOR PRESTIGE CLAIRMONT, NEOPOLIS, HYDERABAD

Jl A S O N D J F M A M J Jl A S O N D J F M A M J Jl A S O N D J F M A M J
Sl DETAILS Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
No 2023 2024 2025 2026
No of Months 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39
TOWER 1
1 Sub Structure Works 1 2 3 4 5 6 7 Jan-24
2 Super Structure Works 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 Nov-25
3 Finishes Works 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 Feb-26
TOWER 2
1 Sub Structure Works 1 2 3 4 5 6 7 8 Feb-24
2 Super Structure Works 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 Aug-25
3 Finishes Works 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 Dec-25
TOWER 3
1 Sub Structure Works 2 3 4 5 6 7 8 9 Mar-24
2 Super Structure Works 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 Sep-23
3 Finishes Works 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 Dec-25
TOWER 4
1 Sub Structure Works 1 2 3 4 5 6 7 8 9 Mar-24
2 Super Structure Works 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 Nov-25
3 Finishes Works 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 Feb-26
Podium Slab Completion 1 2 3 4 5 6 7 8 9 Mar-24
Club House
1 Structure Works 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 Jul-25
2 Masonry & Plastering 7 8 9 10 11 12 13 14 15 16 Aug-25
3 Finishes Works 10 11 12 13 14 15 16 17 Sep-25
MEP & OTHER Works
1 MEP Works May-24 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 Apr-26
2 Doors & Windows Jun-24 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 Mar-26
3 All Other Finishes Jul-24 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 May-26

4 External Development Works 1 2 3 4 5 6 7 8 9 10 11 12 13 May-26

5 Post Construction Approvals 4 Dec-25 1 2 3 5 6 May-26


6 Handing Over 1 2 3 4 Jul-26
Jl A S O N D J F M A M J Jl A S O N D J F M A M J Jl A S O N D J F M A M J JI A S
No. of Months 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39
Year 2023 2024 2025 2026
MILESTONE
Sl No DESCRIPTION/TYPE OF WORK MILESTONE Remarks

1 Total Project Duration 36 months

2 Completion of Podium Apr-24 10 TH Month

3 Making Ready Floor Mock up Oct-24 16 TH Month

4 Completion of Structure – Towers Sep-25 26 TH Month

5 Completion of Club House Sep-25 26 TH Month

6 Handover to Interiors – Club House Oct-25 27 TH Month

7 Completion of Civil Finishes Dec-25 29 TH Month

8 MEP Works Apr-26 34 TH Month

9 External Development Works May-26 35 TH Month

10 All other Finishes Jun-26 36 TH Month


ORDER RELEASE STATUS

Sl. No Description Contractor Order Release Remarks


1 Excavation M/s Kmm Infra Oct-22 Order Released
2 Civil & Finishes M/s. KPIL Apr-23 Order Released
3 STP Dec-23 Dwg Received
4 Lifts Mar-24 BOQ Shared
5 PHE Mar-24 BOQ Shared
6 Fire Protection works Mar-24 BOQ Shared
7 Electrical works Apr-24 BOQ Shared
8 Swimming Pool MEP Apr-24 BOQ Shared
9 Cp & Sanitary fittings Jun-24
10 Door Hardware Jun-24
11 Wooden Doors Jun-24
12 UPVC Windows Jun-24
13 Fire doors Jun-24
14 False Ceiling - Toi & Cor Aug-24
15 Entrance Lobby Works Aug-24
16 Painting Works Aug-24
17 Gas Piping Dec-24
18 Swimming Pool Tiles Mar-25
19 GFRC Jallis Jun-25
20000
40000
60000
80000
140000
160000
180000
200000

0
100000
120000
4,065 5,852 Jul-23
10,798 10,804 Aug-23
16,718 13,837 Sep-23
23,388 18,505 Oct-23
30,508 21,550 Nov-23
37,678 25,267 Dec-23
44,998 29,544 Jan-24
52,353 Feb-24
59,764 Mar-24
67,203 Apr-24
74,710 May-24
82,242 Jun-24
89,779 Jul-24
97,341 Aug-24
104,373 Sep-24
111,405 Oct-24
117,747 Nov-24
124,039 Dec-24
130,281 Jan-25
136,473 Feb-25
142,615 Mar-25
CONCRETE PLANNED V/S ACHIEVED

148,707 Apr-25
154,749 May-25
160,766 Jun-25
166,758 Jul-25
172,750 Aug-25
178,692 Sep-25
184,409 Oct-25
MANPOWER IN MANDAYS

1000
1100
1200
1300
1400
1500
1600
1700
1800

0
1900
2000

100
200
300
400
900

500
600
700
800
Jun-23 180 200
Jul-23 285 350
Aug-23 320 525
Sep-23 372 550
Oct-23 538 715
Nov-23 584 875
Dec-23 650 965
Jan-24 771 1,029
Present Manpower Available : 840

Feb-24 840 1,089


Mar-24 1,139
Apr-24 1,209
Avg Daily Manpower Required for Feb 24: 1089

May-24 1,314
Jun-24 1,444
Jul-24 1,489
Aug-24 1,514
Sep-24 1,554

DURATION IN MONTHS
Oct-24 1,554
Nov-24 1,534
Dec-24 1,514
Jan-25 1,454
Feb-25 1,420
LABOUR DEPLOYMENT HISTOGRAM

Mar-25 1,420
Apr-25 1,365
May-25 1,310
Jun-25 1,290
Jul-25 1,240
Aug-25 1,150
Sep-25 980
Oct-25 745
Nov-25 600
Dec-25 415
Jan-26 305
PHYSICAL PROGRESS – STRUCTURAL WORK
WORK DONE VALUE – WEEK
Completed % Total Value of
Sl No Description of Item Unit Total Qty Last week
Qty Achieved Work Done

1 Overall Concrete Cum 1,82,409 34,428 19% 1,386 86,48,640

2 Reinforcement MT 15,505 2,926 19% 118 71,86,410

3 Shuttering Smt 12,31,330 82,324 7% 2,181 11,99,550

TOTAL 1,70,34,600
SITE PHOTOGRAPHS- TOWERS
TOWER-01 TOWER-02

TOWER-03 TOWER-04
SITE PHOTOGRAPHS
SITE PHOTOGRAPHS
SITE PHOTOGRAPHS
PRESTIGE
TRANQUIL
906 Units

PROJECT REVIEW – 29.02.2024

Ground Breaking Dt : 12.08.2020

Construction Start Dt : 18.01.2021

Committed Completion Dt : 30.01.2024


PROJECT DATA

AREA DETAILS BUILDING FEATURES SERVICES

31,600Smt/
Site Area Configuration 3B/2B + GF +
7.8Ac’s Total Electrical Load 2,320 KVA
34Floors
Built up Area 22,42,429 SFT Number of Towers 4 2 x 750Kva
Total No of DG
2 x 500Kva
Saleable Area 16,17,367 SFT Club House G + 4F
Transformer 2 x 1600Kva
No of Units 906 UNITS
Carpet Area 10,60,265 SFT T1 & T2: 278 EA
Tower Wise T3 & T4: 175 EA Total Water
570 KLD
6,25,062 SFT Requirement
Basement Area
(28%) No of Lifts – Towers 18 no (14P +4S)
No of Lifts – CH 2 no (1P +1S)
2x200Cum +
Amenity Area Capacity of Fire Tank
51,843 SFT 150Cum (CH)
(Club House)
No of Parking 1400
Capacity of STP 670 KLD
PHYSICAL PROGRESS – FINISHES WORKS

1000
900
800
700
600
500
400
300
200
100
0
Floori UPVC Painti Cornic Wood Civil Painti Tile Painti
ng Windo ng e en Final ng Grouti ng
ws (prime doors Works (1st ng (2nd
r) coat) coat)
Total Qty 906 906 906 906 906 906 906 906 906
Completed 905 906 906 906 906 906 894 894 640
% of Achieved 100% 100% 100% 100% 100% 100% 99% 99% 71%
PHYSICAL PROGRESS – MEP WORKS

1000
900
800
700
600
500
400
300
200
100
0
Electrical Switch CP & PHE
wiring Fixing Sanitary Commiss
Fixing ioning
Total Qty 906 906 906 906
Completed 886 876 720 635
% of Achieved 98% 97% 79% 70%
FLATS STATUS

KPIL MEP TESTING KPIL COMPLETION Customer


Sl.No Description UOM Total CRM INSPECTION
STATUS STATUS Handover

1 T1 No's 278 272 205 173 26

2 T2 No's 278 178 176 81 22

3 T3 No's 175 95 50 29 2

4 T4 No's 175 130 51 25 4

TOTAL 675 482 308 54


CONCERNS/SUPPORT
KPTL:
1. To declare flat readiness status -482/906 nos.
2. Common area snag points to be attend and to handover
3. Pending grouting works in podium to be completed
MEP:
1. KPIL to handover all Basements & service rooms with 100% completion of snag works

FINISHES:
1. Morph to deploy adequate manpower for door touch ups and handover-246 /906 no’s
2. Morph to complete snagging at clubhouse and to submit handover documents
MASTER SCHEDULE
COMPLETION SCHEDULE FOR PRESTIGE TRANQUIL, KOKAPET, HYDERABAD
F M A M J Jl A S O N D J F M A M J Jl A S O N D J F M A M J Jl A S O N D J F M A
Sl DETAILS Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1
No 2021 2022 2023 2024
No of Months 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39
TOWER 1
1 Sub Structure Works 1 2 3 4 5 6 Jul-21
2 Super Structure Works 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 Jan-23
3 Finishes Works 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 Sep-23
TOWER 2
1 Sub Structure Works 1 2 3 4 5 6 7 Aug-21
2 Super Structure Works 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 Jan-23
3 Finishes Works 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 Sep-23
TOWER 3
1 Sub Structure Works 1 2 3 4 5 6 7 8 Sep-21
2 Super Structure Works 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 Feb-23
3 Finishes Works 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 Sep-23
TOWER 4
1 Sub Structure Works 1 2 3 4 5 6 7 8 Sep-21
2 Super Structure Works 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 Feb-23
3 Finishes Works 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 Sep-23
Podium Slab Completion 3 4 5 6 7 8 9 10 11 Dec-21
Tower floor Mock UP 12 13 14 Mar-22
Club House
1 Structure Works 1 2 3 4 5 6 7 8 9 10 11 Sep-22
2 Masonry & Plastering 7 8 9 10 11 12 13 Nov-22
3 Finishes Works 10 11 12 13 14 15 Feb-23
MEP & OTHER Works
1 MEP Works Jan-22 1 2 3 4 5 6 7 8
9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 Nov-23
2 Doors & Windows Feb-22 1 2 3 4 5 6 7
8 9 10 11 12 13 14 15 16 17 18 19 20 21 Oct-23
3 All Other Finishes Mar-22 1 2 3 4 5 6
7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 Jan-24
4 External Development Works 1 2 3 4 5 6 7 8 9 Nov-23
5 Post Construction Approvals Sep-23 1 2 3 4
6 Handing Over 1 Dec-23
F M A M J Jl A S O N D J F M A M J Jl A S O N D J F M A M J Jl A S O N D J F M A
No. of Months 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39
Year 2021 2022 2023 2024
PROJECT MILESTONES

Sl No DESCRIPTION/TYPE OF WORK MILESTONE MONTH WISE

1 Total Project Duration 36 months

2 Completion of Podium Oct-21 09TH Month

3 Making Ready Floor Mock up Feb-22 12TH Month

4 Completion of Structure - Towers Jan-23 24TH Month

5 Completion of Club House Feb-23 25TH Month

6 Handover to Interiors – Club House April-23 27TH Month

7 Completion of Civil Finishes Sep-23 32ND Month

8 External Development Works Nov-23 34TH Month

9 MEP Works Nov-23 34TH Month

10 All other Finishes Jan-24 36TH Month


ORDER RELEASE STATUS
Sl. No Description Contractor Target Close Remarks
1 Panels - LT & HT M/s. Vidyut Tech Dec-22 Order Released
2 Prepaid Meters M/s. Ripple Dec-22 Order Released
3 Rising Main/Bus Duct M/s. Elins Switch Board Dec-22 Order Released
4 DG -Hi Side M/s. EMPOWER Dec-22 Order Released
5 DG - Low Side M/s. GTV POWER Dec-22 Order Released
6 PHE Pumps M/s. Revolve Engineers Dec-22 Order Released
7 Mech Ventilation and STP Exhaust M/s. KNND Feb-23 Order Released
8 Softscaping M/s. Hyderabad Plants Feb-23 Order Released
9 Irrigation Works M/s. Santech Feb-23 Order Released
10 Transformer M/s. VIJAY VIDYUTH Feb-23 Order Released
11 Geysers M/s Jaquar Feb-23 Order Released
12 Exernal Power Supply M/s SLN Projects Feb-23 Order Released
13 EV Car Charging Points M/s. Belectriq Apr-23 Order Released
14 Safety and Security M/s. Nexus safety Apr-23 Order Released
15 OWC M/s. Waste Is Gold Apr-23 Order Released
16 Solar Water Heating/Solar Power Powertronix Apr-23 Order Released
17 AC Copper Piping Sriven engg Apr-23 Order Released
18 Light Fixtures - External M/s VKA Power master Apr-23 Order Released
19 Kids Play & Outdoor Gym Equipment M/s. Feetoff Ground Apr-23 Order Released
OVER ALL- VIEW
TOWER VIEWS
CLUB HOUSE PHOTOGRAPHS
CLUB HOUSE PHOTOGRAPHS
SITE PHOTOGRAPHS
SITE PHOTOGRAPHS
PRESTIGE VAISHNAOI
RAINBOW WATERS
150 units

PROJECT REVIEW – 29.02.2024

Ground Breaking Dt : 06.06.2023

Construction Start Dt : 01.12.2023

Committed Completion Dt : 01.12.2026


PROJECT DATA

AREA DETAILS BUILDING FEATURES SERVICES

9848 Sq.mt/ Configuration 2B + 5P +


Site Area Total Electrical
2.42 Acres 2CH+34F 1200 KVA
Load
11,10,166
Built up Area Number of
SFT Total No of DG 3 x 380 Kva
Towers + Club 1
Saleable Area 8,39,279 SFT House 1250
Transformer
kva+500 Kva
Carpet Area 4,84,895 SFT No of Units 150 Units
Total Water
380 KLD
Basement No of Lifts – Requirement
3,16,623 SFT
Area Tower & club 6no (4P + 2S)
House Capacity of Fire 200KL +
Amenity Area Tank 300KL
(Club House) 34,563.2 SFT
No of Parking 508
Capacity of STP 185 KLD
CONCRETE AND REINFORCEMENT
CONCRETE - TOTAL VS ACHIEVED

1,773
53,551

0 10,000 20,000 30,000 40,000 50,000 60,000


Total Qty Completed Qty % Total Achieved
53,551 1,773 3.31%

REINFORCEMENT - TOTAL VS ACHIEVED

671
5,828
0 1,000 2,000 3,000 4,000 5,000 6,000
Total Qty Completed Qty % Total Achieved
5,828 671 11.51%
PHYSICAL PROGRESS

3000

2500

2000

1500

1000

500

0
RW RAFT TOWER RWALL
PCC Raft PCC
Total Qty 270 2563 270
Completed Qty 235 2,563 196
% Total Achieved 87.04% 100.00% 72.59%
10000
30000
50000

20000
40000
60000

0
406 416 Dec-23
1606 1005 Jan-24
6406 Feb-24
7795 Mar-24
9184 Apr-24
10573 May-24
11962 Jun-24
13351 Jul-24
14929 Aug-24
16507 Sep-24
18085 Oct-24
20170 Nov-24
22254 Dec-24
24338 Jan-25
26423 Feb-25
28507 Mar-25
30591 Apr-25
32676 May-25
34760 Jun-25
36844 Jul-25
38929 Aug-25
CONCRETE PLANNED V/S ACHIEVED

41013 Sep-25
43098 Oct-25
45182 Nov-25
47266 Dec-25
49351 Jan-26
51435 Feb-26
53519 Mar-26
54319 Apr-26
54769 May-26
MANPOWER IN MANDAYS

0
100
200
300
400
500
Dec-23 30 50
Jan-24 93 129
Feb-24 192 182
Mar-24 196
Apr-24 208
May-24 227
Jun-24 257
Present Manpower Available: 192

Jul-24 270
Aug-24 289
Sep-24 310
Oct-24 332
600 Avg Daily Manpower Required for February 24: 182

Nov-24 371
Dec-24 418
Jan-25 493
Feb-25 532
Mar-25 542
Apr-25 551
May-25 551
DURATION IN MONTHS

Jun-25 551
Jul-25 552
LABOUR DEPLOYMENT HISTOGRAM

Aug-25 552
Sep-25 552
Oct-25 552
Nov-25 542
Dec-25 542
Jan-26 539
Feb-26 506
Mar-26 449
Apr-26 311
May-26 201
ORDER RELEASE STATUS
Sl. No Description Contractor Order Release Remarks
1 Excavation M/s JAI BHAVANI Jul-23 Order Released
2 Civil M/s. KPIL Dec-23 Order Released
3 STP Dec-23 Dwg Received
4 Lifts Apr-24
5 PHE Sep-24
6 Irrigation Works Sep-24
7 Fire Protection works Sep-24
8 Electrical works Sep-24
9 Cp & Sanitary fittings Feb-25
10 Door Hardware Feb-25
11 Wooden Doors Feb-25
12 UPVC Windows Feb-25
13 Fire doors Mar-25
14 False Ceiling - Toi & Cor Mar-25
15 Entrance Lobby Works Mar-25
16 Painting Works Apr-25
17 Swimming Pool MEP Apr-25
18 Marble Procurement May-25
19 Gas Piping Sep-25
ORDER RELEASE STATUS – MARKETING OFFICE
Sl. No Description Contractor Order Release Remarks
1 Civil M/S KPIL Dec-23 Order Relesed
2 PHE Jan-24
3 Electrical works Jan-24 BOQ Shared
4 Cp & Sanitary fittings Jan-24 BOQ Shared
5 Wooden Doors Jan-24 BOQ Shared
6 Door Hardware Jan-24 BOQ Shared
7 UPVC / Aluminium Windows Jan-24 BOQ Shared
8 False Ceiling - Toi & Cor Jan-24 BOQ Shared
9 Painting Works Jan-24 BOQ Shared
10 Hardscape Works Jan-24 BOQ Shared
11 Hardscape Material Jan-24 BOQ Shared
12 Glazing Works Jan-24 BOQ Shared
13 Light Fixtures - Internal Jan-24 ID
14 Softscaping Jan-24 BOQ Shared
15 Safety and Security Jan-24
16 AC Copper piping / HVAC Jan-24 BOQ Shared
17 Light Fixtures - External Jan-24
18 Children Play Equipment Jan-24
19 Signages - Internal & External Jan-24
MASTER SCHEDULE
COMPLETION SCHEDULE FOR PRESTIGE VAISHNOI RAINBOW WATERS, HYDERABAD
D J F M A M J Jl A S O N D J F M A M J Jl A S O N D J F M A M J Jl A S O N
Sl
DETAILS Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
No
2023 2024 2025 2026
No of Months 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36
TOWER
1 Sub Structure Works 1 2 3 4 5 6 7 8 9 10 Oct-24
2 Super Structure Works 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 Apr-26
3 Finishes Works 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 Jun-26
Podium Slab Completion 5 6 7 Aug-24
Tower floor Mock UP 16 17 18 19 27-Jul-25
Club House
1 Structure Works 8 9 25-Oct-24
2 Masonry & Plastering 19 10-Jul-25
3 Finishes Works 18 19 27-Jul-25
MEP & OTHER Works
1 MEP Works 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 31-Aug-26
2 Doors & Windows 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 28-Jul-26
3 All Other Finishes 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 31-Aug-26
4 External Development Works 1 2 3 4 5 6 7 8 9 10 11 12 31-Aug-26
5 Post Construction Approvals 1-Mar-26 1 2 3 4 5 31-Aug-26
6 Handing Over 1 2 3 4 30-Sep-26
D J F M A M J Jl A S O N D J F M A M J Jl A S O N D J F M A M J Jl A S O N
No. of Months 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36
Year 2023 2024 2025 2026
PROJECT MILESTONE

Sl No DESCRIPTION/TYPE OF WORK MILESTONE Remarks


1 Total Project Duration 36 months
2 Completion of Podium Aug-24 08TH Month
3 Making Ready Floor Mock up Jul-25 20th Month
4 Completion of Structure - Towers Apr-26 29th Month
5 Completion of Club House structure Oct-24 11th Month
6 Handover to Interiors – Club House Jul-25 20th Month
7 Completion of Civil Finishes Jun-26 30th Month

8 External Development Works Aug-26 33rd Month

9 MEP Works Aug-26 33rd Month

10 All other Finishes Aug-26 33rd Month


CONCERNS/SUPPORT

KPTL:
1. KPIL To Mobilize required Manpower with respect to Carpenters to achieve the Target Dates.
Available Carpenters – 20/60nos
2. Completion of Retaining wall Raft Balance : 35 Rmt
3. Completion of B2-B1 level retaining wall 196/270 Rmt.
4. 2nd Labour colony Setup .
5. Marketing office External masonry and gypsum manpower to be Deploy.
SITE PHOTOGRAPHS
SITE PHOTOGRAPHS
THE
PRESTIGE CITY
HYDERABAD
4647 APARTMENTS &
119 VILLAS .
PROJECT REVIEW – 29.02.2024

Ground Breaking Dt : 30.01.2024

Construction Start Dt : 15.02.2024

Committed Completion Dt : 31.12.2027


PROJECT DATA

AREA DETAILS BUILDING FEATURES SERVICES

Site Area 31 Acres . Configuration 3B + GF +


41Floors Total Electrical Load 14,800 KVA

Built up Area 1,28,57,018 SFT Number of Towers 13


Total No of DG 7 x 1850KVA
Club House 2 No’s (G + 3F)
Saleable Area 97,04,162 SFT 2 x 1600KVA
Transformer
No of Units 4647 Units 11 x 1850KVA
Carpet Area 61,43,460 SFT Total Water
4200 KLD
105 No’s (92P Requirement
No of Lifts – Towers
Basement Area 33,28,316 SFT +13S)
No of Lifts – CH 1000KLD +
5 No’s (3P +2S) Capacity of Fire Tank
800KLD
Amenity Area No of Car Parking 9565 No’s 2200 KLD
(Club House) 1,49,452 SFT No of Bike Parking 640 No’s Capacity of STP 1650 KLD
STATUS OF EXCAVATION

Completed % Total
Sl. No Description of Item Unit Total Qty Last Week Remarks
Qty Achieved

1 Soil Excavation Cum 3,45,138 3,21,228 93% 0


2 Rock Excavation Cum 4,92,720 3,29,370 67% 5900 Rock carting WIP
3 Back Filling Cum 163920 0 0% 0

EXCAVATION STATUS
600
ThousandS

400
200
0
Soil Excavation Rock Excavation Back Filling
Total Qty Completed Qty
STATUS OF RETAINING WALL
TPCH -TOWER AREA RETAINING WALL STATUS
Overall Status
SI.No Description Unit Quantity Achieved Status Remark
1 Raft Excavation RMT 1800 360 20%
2 Raft PCC RMT 1800 102 6%
3 Raft Reinforcement RMT 1800 102 6%
4 Raft RCC RMT 1800 - -
5 RC Wall Reinforcement (Upto B2 Level ) RMT 1800 - -
6 RC Wall (Up to B2 Level ) RMT 1800 - -
RETAINING WALL STATUS
2000
1600
1200
RMT

800
400
0
Raft Excavation Raft PCC Raft Raft RCC RC Wall RC Wall (Upto
Reinforment Reinforcement B2 Level )
(Upto B2 Level )
Total Qty Completed Qty
STATUS OF VILLAS

Villas Structure Work Status


S.No Description Unit Quantity Achieved Status Remark
1 EXCAVATION Nos 119 3 3%
2 PCC Nos 119 2 2%
3 FOOTING Nos 119 1 1%
4 COLUMNS (Upto Plinth) Nos 119 - -
5 GF- GRADE SLAB Nos 119 - -
40000
80000

0
120000
160000
200000
240000
280000
320000
360000
400000
440000
480000
520000
560000
600000
640000
680000
720000
760000
800000
840000
4,000 Feb-24
10,000 Mar-24
19,000 Apr-24
33,000 May-24
51,000 Jun-24
73,000 Jul-24
97,000 Aug-24
123,000 Sep-24
149,000 Oct-24
175,000 Nov-24
201,000 Dec-24
227,000 Jan-25
253,000 Feb-25
279,000 Mar-25
305,000 Apr-25
329,000 May-25
353,000 Jun-25
377,000 Jul-25
401,000 Aug-25
425,000 Sep-25
449,000 Oct-25
473,000 Nov-25
497,000 Dec-25
521,000 Jan-26
545,000 Feb-26
569,000 Mar-26
CONCRETE PLANNED V/S ACHIEVED

593,000 Apr-26
617,000 May-26
641,000 Jun-26
665,000 Jul-26
689,000 Aug-26
713,000 Sep-26
735,000 Oct-26
753,000 Nov-26
765,000 Dec-26
773,000 Jan-27
MANPOWER IN MANDAYS

1200
1800
2400
3000
3300
3900
4500

1500
2100
2700
3600
4200

0
300
600
900
Feb-24 180 513
Mar-24 875
Apr-24 1,138
May-24 1,500
Jun-24 1,763
Jul-24 2,165
Aug-24 2,488
Sep-24 2,910
Oct-24 3,183
Present Manpower Available : 180

Nov-24 3,545
Dec-24 3,625
Jan-25 3,715
Avg Daily Manpower Required for Jan 24:355

Feb-25 3,765
Mar-25 3,875
Apr-25 3,875
May-25 3,800
Jun-25 3,775
Jul-25 3,695

DURATION IN MONTHS
Aug-25 3,695
Sep-25 3,695
Oct-25 3,675
Nov-25 3,705
Dec-25 3,705
Jan-26 3,730
Feb-26 3,730
LABOUR DEPLOYMENT HISTOGRAM

Mar-26 3,730
Apr-26 3,730
May-26 3,680
Jun-26 3,490
Jul-26 3,190
Aug-26 2,830
Sep-26 2,615
Oct-26 2,228
Nov-26 1,925
Dec-26 1,563
Jan-27 1,290
ORDER RELEASE STATUS - RESIDENTIAL TOWERS
Sl. No Description Contractor Order Release Remarks
1 Excavation M/s Kams Infra Aug-23 Order Released
2 Civil - Structural Works M/s. KPIL Jan-24 LOI Released
3 Civil - Finishes Jun-24
4 STP Jun-24
5 Lifts Jun-24
6 PHE Sep-24
7 Fire Protection works Sep-24
8 Electrical works Sep-24
9 Swimming Pool MEP Sep-24
10 Cp & Sanitary fittings Mar-25
11 Door Hardware Mar-25
12 Wooden Doors Mar-25
13 UPVC Windows Mar-25
14 Fire doors May-25
15 False Ceiling - Toi & Cor May-25
16 Entrance Lobby Works May-25
17 Painting Works Jun-25
18 Gas Piping Jun-25
19 Irrigation Works Jun-25
ORDER RELEASE STATUS - VILLAS
Sl. No Description Contractor Order Release Remarks
1 Excavation M/s Kams Infra Aug-23 Order Released
2 Civil - Structural Works M/s. KPIL Feb-24
3 Civil - Finishes Feb-24
4 STP Mar-24
5 PHE May-24
6 Irrigation Works May-24
7 Lifts Jun-24
8 Painting Works Jun-24
9 Electrical works Jun-24
10 Swimming Pool MEP Sep-24
11 Cp & Sanitary fittings Sep-24
12 Door Hardware Sep-24
13 Wooden Doors Sep-24
14 UPVC Windows Oct-24
15 Fire Protection works Oct-24
16 Fire doors Oct-24
17 False Ceiling - Toi & Com Nov-24
18 Swimming Pool Tiles Nov-24
19 Elevation Façade Nov-24
CONCERNS / SUPPORT REQUIRED

KAMS INFRA :

• To Clear Excess Rock from Site .


• To make Clearance ready for foundation works.

KPIL :

• Schedule for Submission of Structural drawings for Peer review .


• Submission of Foundation drawings for Retaining Wall , Rafts & Footings.
• Confirmation on Aluminium Shuttering New Sets Planned for Towers .
• Confirmation on Aluminium Shuttering Sets Planned for Villas.
• Update on Mobilisation of Manpower .
• Confirmation of Batching Plant Setup & Operation .
• Review on Master Schedule .
PROJECT MILESTONES - RESI

Sl No DESCRIPTION/TYPE OF WORK MILESTONE Remarks

Start End

1 Total Project Duration (incl Finishes) 42 months

2 Completion of Podium Feb-24 Apr-25 15th Month

3 Making Ready Floor Mock up Jun-25 Sep-25 20th Month

4 MEP Works - Basement Sep-24 Dec-25 23rd Month

5 Completion of Club House + Finishes Jun-25 Sep-26 32nd Month

6 Completion of Super Structure - Towers Jun-24 Dec-25 33rd Month

7 External Development Works Jun-26 Jan-27 36th Month

8 Handover to Interiors – Club House Sep-26 Mar-27 36th Month

9 Completion of Civil Finishes Jan-25 Jun-27 42nd Month

10 MEP Works - Commissioning Dec-24 May-27 42nd Month


MASTER SCHEDULE
COMPLETION SCHEDULE FOR THE PRESTIGE CITY, HYDERABAD
J F M A M J Jl A S O N D J F M A M J Jl A S O N D J F M A M J Jl A S O N D J F M A M J Jl A S O N D J F M
Sl DETAILS Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1
No 2024 2025 2026 2027 2028
No of Months 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51
TOWER 1 , 2, & 3
1 Sub Structure Works 1 2 3 4 5 6 7 8 9 10 Oct-25
2 Super Structure Works 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 Jun-26
3 Finishes Works 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 Dec-26
TOWER 4, 5, & 6
1 Sub Structure Works 1 2 3 4 5 6 7 8 9 10 Jan-25
2 Super Structure Works 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 Sep-26
3 Finishes Works 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 Mar-27
TOWER 7, 8, & 9
1 Sub Structure Works 1 2 3 4 5 6 7 8 9 10 Feb-25
2 Super Structure Works 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 Oct-26
3 Finishes Works 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 Apr-27
TOWER 10, 11,12, & 13
1 Sub Structure Works 1 2 3 4 5 6 7 8 9 10 Apr-25
2 Super Structure Works 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 Dec-26
3 Finishes Works 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 Jun-27
Podium Slab Completion 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 Apr-25
Tower floor Mock UP 1 2 3 4 Sep-25
Club House
1 Structure Works 1 2 3 4 5 6 7 8 9 10 11 12 May-26
2 Masonry & Plastering 9 10 11 12 13 14 Jul-26
3 Finishes Works 13 14 15 16 17 18 Dec-26
MEP & OTHER Works
1 MEP Works - Basements Sep-24 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 Aug-26
MEP Works Dec-24 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 Aug-27
2 Doors & Windows Jan-25 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 Jul-27
4 All Other Finishes Feb-25 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 Oct-27
3 External Development Works Feb-26 1 2 3 4 5 6 7 8 9 10 11 12 Jan-27
5 Post Construction Approvals Mar-27 1 2 3 4 5 6 Oct-27
6 Handing Over Jul-27 1 2 3 4 5 6 Dec-27
J F M A M J Jl A S O N D J F M A M J Jl A S O N D J F M A M J Jl A S O N D J F M A M J Jl A S O N D J F M
No. of Months 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51
Year 2024 2025 2026 2027 2028
EXCAVATION WIP
SITE PHOTOGRAPHS
SITE PHOTOGRAPHS
PRESTIGE
ORCHARDS
CLUB HOUSE

PROJECT REVIEW – 29.02.2024

Construction Start Dt : 15.06.2023

Committed Completion Dt : 30.03.2024


PROJECT DATA
CLUB HOUSE

Site Area 46, 726 Sft

Saleable Area 29, 375 Sft

Total Built-up Area 39, 052 Sft

Electrical Load 200 KVA

DG Requirement 250 KVA

Water Requirement 20 KLD

Capacity of STP 20 KLD


PHYSICAL PROGRESS CIVIL

8,000

7,000

6,000

5,000

4,000

3,000

2,000

1,000

0
Excavati Backfillin Concrete Reinforc Shutteri Block Plasterin Water
on g ement ng work g proofing
Total 2,900 2,550 1,700 175 7,800 3,200 6,105 1,428
Completed 2,800 2,355 1,672 170 7,491 1,255 179 561
% Total Achieved 97% 92% 98% 97% 96% 39% 3% 39%
Schedule Tracking

No of days short
Sl No Description Schedule Date Revised Date
fall

1 Second floor Pour -2 25.09.2023 31.12.2023 Completed

2 Terrace Floor slab 15.10.2023 30.01.2023 Completed

3 Above Terrace Works 05.11.2023 27.01.2023 OHT works WIP

4 Swimming pool raft & wall 20.01.2023 15.03.2023 WIP

5 MEP Works 30.03.2023

6 Finishing works Internal & External 30.03.2024

7 ID finishing works 30.06.2023


PROJECT MILESTONE

Sl No DESCRIPTION/TYPE OF WORK MILESTONE Remarks


1 Total Project Duration 6 months
2 Completion of Structure Jan-24 01TH Month
3 Completion of Civil Finishes Mar-24 03th Month
4 Handover to Interiors – Club House April-24 04th Month
5 Completion of MEP Works May-24 05th Month
6 External Development Works May-24 05th Month
7 All other Finishes Jun-24 06th Month
ORDER RELEASE STATUS – CLUB HOUSE
Sl. No Description Contractor Order Release Remarks
1 Lifts Jan-24 In Progress
2 PHE M/s. Santech Dec-23 Order Released
3 HVAC Jan-24 BOQ Shared
4 Fire Protection works Dec-23 BOQ Shared
5 Electrical works Dec-23 BOQ Shared
6 Panels - LT & HT Jan-24 BOQ Shared
7 DG -Hi Side Jan-24 BOQ Shared
8 DG - Low Side Jan-24 BOQ Shared
9 Transformer Jan-24 BOQ Shared
10 Safety and Security- CCTV Jan-24 BOQ Shared
11 Glazing Works Jan-24 BOQ Shared
12 Wooden Doors Jan-24 BOQ Shared
13 Door Hardware Jan-24 BOQ Shared
14 Fire doors Jan-24 BOQ Shared
15 Cp & Sanitary fittings M/s Motiram(Kohler) Jan-24 Order Released
16 Swimming Pool MEP Jan-24 In Progress
17 Hardscape Works Jan-24 BOQ Shared
18 Children Play Equipment Jan-24 In Progress
19 MCM Cladding works Jan-24 BOQ Shared
20 Softscaping Jan-24 BOQ Shared
21 Swimming Pool Tiles Jan-24 BOQ Shared
CONCERNS/SUGGESTION

PEPL

1. Required all ID Concept Drawings including MEP


2. Required MEP contractor on Board due reason unable to give front to masons
3. ID Flooring and cladding Layouts required as to mobilization of materials getting delay

CIVIL: KPIL

1. KPIL Should increase masons from 4 no's to 10 no's


CLUB HOUSE PHOTOGRAPHS
CLUB HOUSE PHOTOGRAPHS