Line BalancingLINE BALANCING
The Line balancing is to Design a smooth
production flow by allotting processes to
worker so as to allow each worker to
complete the implied workload within an
even time.LINE BALANCING (process orGANIZATION)
It is a system where you meet the production expectations
and can find the same amount of work in process (WIP)
in each operation at any point of the day.
In production , line balancing is useful tool. Line
Balancing strategy is to make the production line
stretchy enough to absorb external & internal
indiscretion. This strategy involves setting a planned rate
of production for necessary materials to be fabricated
within a particular time frame. Additionally , successful
line balancing requires assuring that every line segments
production quota can be met within the time frame using
the available production capacity. This is an efficient tool
to develop the throughput of assembly lines & work cells
while decreasing manpower requirements & Expenses.LINE BALANCING (process orcanization)
Line Balancing is slightly different from assembly line
balancing. Assembly line balancing involved the action
of assembling different parts together. It involves many
production lines while normal line-balancing may only
involve one production line. Assembly line balancing is
the problem of assigning operations to workstations
along an assembly line in such a way that the
assignment be best in some sense. The efficiency
difference between an optimal & a sub-optimal
assignment can yield economies reaching huge amount
per year. Most of the small & medium industries do not
use line balancing method in the production line.| OBJECTS OF LINE BALANCING
1)
2)
3)
4)
5)
6)
7)
8)
9)
Manage the work loads among assemblers
Recognize the location of Bottleneck.
Decide no of workstation
Decrease Production Cost.
Assigning task to each work station in such a way that there is little
idle time.
Agreed quality maintenance of the garments
Reduce maintenance costs
Maximum outputs at the desired time.
Regular/Smooth Material flow
10) Maximum usage of manpower and machine capacity.tine
Balancing
(Types)
a a
Static Dynamic
Balance Balance
ee
Static Balance denotes long term differences in capacity over a
period of several hours or longer Static imbalance results in under
utilization of workstations, machines & people.
Dynamic Balance refers to short term differences in capacity such
as over a period of minutes, hours at most. Dynamic imbalance
occurs from product mix changes and difference in work time
dissimilar to product mixLine Balancing operates under two circumstances:
Precedence Constraint : Products can not progress to
other station if it doesn’t complete necessary task at that
station. It should not across other station because certain
part needs To be performed before other activities.
Cycle Time Restrictions : Cycle time is maximum time
for products spend in every workstation. Different
workstation has different cycle time.IMPORTANT TERMS IN LINE BALANCING
Cycle Time : Maximum amount of time allowed at each work
station. This can be found by dividing required units to
production time available per day. This is the time expressed in
minutes between two simultaneous products coming of the end
of production line. Gaither & Fraizre (2001) described that
cycle time demonstrates how often the production line can
generate the product with current resources & staffing. It is a
precise indicator to signify how the line is currently set up to
run. The calculation of cycle time takes into consideration of the
entire production quantities. If multiple ines are producing the
same product , then the composite cycle time is less than the
actual lapse time of any individual line.IMPORTANT TERMS IN LINE BALANCING (CONT...)
Lead Time : Summation of production times along the
assembly line. (Read details from Internet)
Idle Time : A period when system is not used but is available.
Work Station : A physical area where a worker with tools/one
or more m/c or unattended m/c’s such as robot perform specific
task in a production line ( Gaither & Fraizer 2001)aacRTA TERMS IN LINE BALANCING (CONT...)
Downtime : Downtime explained as the time that is non value
added .
Transportation : Any movement in factory can be considered as
waste. Double handling & excessive movements are likely to cause
damage & deterioration with the distance of communication
between processes proportional to time taken. It takes to feedback
reports of poor quality & needs corrective action.
Unnecessary Inventory : There is a problem with extra inventory.
Inventory will increase the lead time, Preventing quick
identification of problems and increasing space. Significant
storage costs are wasted which absolutely lower the
competitiveness of the organization of value stream.
aaacRTA TERMS IN LINE BALANCING (CONT...)
Work in Process: WIP is made up of all garments & Their parts
that are not completely finished yet. OR Work in process refers to
the number of gmts that are under production at any given time.
Throughput conversion from materials to finished goods garments
are at different stages of completion but all are considered WIP.
* Ques 1 : What does it mean by having high WIP?? What
impact does it create on cut flow???
* Ques 2 : How can we manage WIP?
Work Flow : work flow is the movement of materials & gmts
parts through the conversion process.
* Ques : How do work flow reduce during production??
aIMPORTANT TERMS IN LINE BALANCING (CONT...)
Unnecessary Motion: Involve the ergonomics of production
where operation might have to stretch , bend and pick up when
these actions actually could be avoided. It is not only tires the
worker but also leads to poor productivity.
Inappropriate Processing : Over-complexity of a process
discourages ownership & encourages the employees to over
produce to recover the large investment in the complex m/c. It
encourages poor quality & takes corrective action.URARTART TERMS IN LINE BALANCING (CONT...)
Balancing : The process of planning a smooth workflow with a
steady supply of work for each operation.
Buffer: A planned backlog of work that is available for processing
for each operation.
Bottleneck: Delay in Transmission that slow down the production
rate. This can be overcome by balancing the line. OR
Constraint to throughput that limits the volume of work that can be
completed in a workday. Once a bottleneck is determined ,
engineers study the operation to determine whether it can feasibly
be improved. It may mean operating during breaks & lunch times,
adjusting routings using other methods , scheduling the operation
for a second shift. Buying an additional m/c or changing to new
technology for the operation.‘_ TERMS IN LINE BALANCING (CONT...)
Pitch Time : Ref value for synchronization in the division of labor
works is called pitch time. Pitch time provides average time
allotted to each worker
Bottleneck process
160
140 = ——.
120
100
80
60
40
20
°
Work Allotment time
8 c ° E F c
>
—eName of worker (in order of process)
Pitch Diagram
hlBOTTLENECK PROCESS
The time at which the longest time is required is called bottleneck
process. The state of line organization should be evaluated as
“Organization Efficiency” using the pitch time & bottleneck process
time.
Pitch time
Organization Efficiency (%) =—————"" —_ x 100
Bottleneck process time
100
= ——_——___ x 100
140
Ques ; How to reduce the no. of bottleneck process 2222STEPS IN SOLVING LINE BALANCING
1. There are four steps in solving line balancing described by G. Andrew
(2006)
2. Drawing Precedence Diagram: Precedence diagram needs to be drawn to
demonstrate a relationship between workstations. Certain process begins
when previous process was done.
3. Determining cycle time : Cycle time is longest time allowed at each station.
This can be expressed by this formula.
Cycle time = Available time / Desired Output
4. This means the products needs to leave the workstations before it reaches its
cycle time.
5. Assigning tasks to workstation : The tasks distributions should be taken
after completing a time cycle. Its good to allocate tasks to workstation in the
order of longest task times.LB OF A T-SHIRT /OPERATION
BREAKDOWN OF A T-SHIRT
Seque Description M/C Type smv Total SMV
nce
No m/c Man m/c Man
1 Front & Back part helper AS 0.45
matching
2 Shoulder join both | 4T O/L 0.46 0.46
side
3 Neck Rib make S/N 0.16 0.16
4 Neck join ATO/L 0.24 0.24
5 Sleeve matching helper 0.45 0.45
with body
6 Sleeve join 4T O/L 0.76 0.76
F/A
7 Sleeve hem ATO/L 0.40 0.40
or F/ASeque Description M/C Type SMV Total SMV
nee
No m/c | Man m/c Man
8 Side Seam 4TO/L 09 0.90
9 Body hem 40/L 0.50 0.50
F/L
10 | Label attach S/NL/S 0.60 0.60
11 | Thread cut helper 0.70 0.70
Total 5.62 min
AT O/L= 4 thread overlock F/L = Flat lock
SMV = Standard minute value
S/N L/S = Single needle Lock stitchTh Moelse lay cut plon + 4"
E D4 of
pd Lo - plotnp
tees LA ~ bled beck
elrouldere WN
Join G op Gomme une}
Ne we | Dred rob mohe
ae os
sly. 7
join Med, joiw
ew. GR)
Sein \yorg
gly: | Am A
bem >) Ch) oe fon. ah Ban om
side 50 71 I cit
geo (4 D/L Gat) side sone,
el Fi 717 by
ok Sy Gs a side Gear.
cv. Soin
on ve [TAIE) Bot
ete AN gre ar’ Coy Soi oh
Lapede [x] [Petre | me Thirtéed: Bat
Toviea J"