SBJ+ 32 C5 COW 23 RE 011 0+operation,+maintenance+and+rehabiltation+strategy
SBJ+ 32 C5 COW 23 RE 011 0+operation,+maintenance+and+rehabiltation+strategy
18/91094
Document name:
Bjørnafjorden floating
bridge (K12) – Operation,
maintenance and
rehabilitation strategy
ADRESSE COWI A/S
Parallelvej 2
2800 Kongens Lyngby
Denmark
TLF +45 56 40 00 00
FAKS +45 56 40 99 99
WWW cowi.com
DECEMBER 2020
STATENS VEGVESEN
Bjørnafjorden floating
bridge (K12) – Operation,
maintenance and
rehabilitation strategy
A205696-002 A205696-002-D&V001
CONTENTS
1 Introduction 1-1
1.1 Abbreviations 1-2
13 References 13-55
BJØRNAFJORDEN FLOATING BRIDGE (K12) – OPERATION, MAINTENANCE AND REHABILITATION STRATEGY 1-1
1 Introduction
This document concerns the operation, maintenance and rehabilitation (in the
following named O&M) strategy for the Bjørnafjorden floating bridge concept
K12. Figure 1-1 provides an overview of the bridge. This document is based
upon phase 5 project documents as delivered to the Norwegian Public Road
Administration (Statens Vegvesen – SVV) in august 2019.
The O&M strategy is developed in a phase wise workflow. Phase 1, O&M system
description, is part of the VegRAMS process phase 1 - activity 1.4: operation,
maintenance and rehabilitation. The activity is detailed in /1/ section 5.5. Phase
2, O&M model, is part of the VegRAMS process phase 2 - activity 2.2: operation,
maintenance and rehabilitation model. The activity is detailed in /1/ section 5.9,
which has been adjusted to accommodate SVV's focus areas as expressed at
meetings 27.09.2020, 03.10.2020 and 23.10.2020.
The workflow is reflected in this document, where items 1-4 are established in
phase 1 and items 5-9 are established in phase 2. All items are listed below incl.
chapter reference:
1.1 Abbreviations
AUV: Autonomous Underwater Vehicle
CA: Corrosion Allowance
CRA: Corrosion Resistant Alloy
CP: Cathodic Protection
O&M: Operation and Maintenance
ICCP: Impressed Current Cathodic Protection
SDSS: Super Duplex Stainless Steel
SHMS: Structural Health Monitoring System
SVV: Statens Vegvesen (Norwegian Public Road Administration)
RBI: Risk-based Inspection
RCM: Reliability Centered Maintenance
RC-VAT: Remotely Controlled – Vertical Access Tool
BJØRNAFJORDEN FLOATING BRIDGE (K12) – OPERATION, MAINTENANCE AND REHABILITATION STRATEGY 1-3
The main purpose of the O&M strategy is to specify and implement requirements
for:
In order to ensure the above, the requirements are also needed for the following
items:
In general, all surfaces of all parts shall be easily accessible for inspection
(within arm's length) and maintenance (except completely closed steel
members). Submerged surfaces shall be inspected using Remotely Operated
underwater Vehicle (ROV). Special consideration shall be given to components
exposed to water during a possible drainage malfunction. All drainage systems
shall be easy to inspect, clean, maintain and replace.
For deformation, fatigue and wear prone details identified during detailed
design, the visual inspection shall be assisted by the outcome of a structural
health monitoring system (SHMS). Design of the SHMS shall be part of the
bridge design.
O&M planning for a bridge like the Bjørnafjorden floating bridge is associated
with a large degree of uncertainty. Therefore Statens Vegvesen (SVV) has
introduced risk-based methods for O&M analysis. The risk-based approach shall
benchmark existing practice (SVV handbooks etc.) and enhance the basis for
decision-making during establishment of an O&M strategy. Focus should be on
critical and vulnerable elements and systems and where savings in LCC and/or
increase in user availability are possible.
Based on the general level of detail of the conceptual design from phase 5, the
risk-based approach must be qualitative. Gradually, as the level of detail
increases, the risk-based analysis can become quantitative and detailed on a
case-by-case basis.
BJØRNAFJORDEN FLOATING BRIDGE (K12) – OPERATION, MAINTENANCE AND REHABILITATION STRATEGY 2-5
The design service life of the bridge is 100 years, ref. /3/. Elements and systems
that expectedly require replacement during the service life of the bridge, shall
be replaceable with minimal disturbance of road traffic as well as maritime
traffic, ref. /3/ on required uptime. Procedures for replacement of elements and
systems shall be planned, described and facilitated as part of the design
process, ref. /3/.
This O&M strategy comprise general descriptions and requirements. The O&M
strategy can be used as basis for formulation of requirements for the coming
project phases, in order to ensure minimal LCC and minimal traffic restrictions
during operation.
In parallel with the design and development of a BIM model, an O&M manual
should also be established with a description of the bridge, instructions,
inspection procedures, maintenance procedures, spare part management etc.
2.2 Personnel
The main tasks for an O&M organisation are:
› inspections
› maintenance
In connection with the establishment of the O&M organisation, the ratio between
in-house staffing and outsourcing, primarily to consultants and contractors, shall
be decided. This subject has not been detailed any further.
› fixed equipment:
- permanent installed equipment (fixed ladders, platforms, sensors,
surveillance cameras, fixation points for "rope access" etc.)
- in stock stored equipment – transported to the bridge when needed
(scaffolding etc.)
› moveable equipment:
- service vehicles for road patrol (clearing and cleaning, replacement of
2-6 BJØRNAFJORDEN FLOATING BRIDGE (K12) – OPERATION, MAINTENANCE AND REHABILITATION STRATEGY
› Easy and safe access for regular maintenance with minor consequence for
availability
› Easy and safe replacement of elements and systems with a design service
life less than 100 years
Access routes, work platforms and other equipment shall be selected and
arranged so that restrictions for traffic (vehicles, bikes, pedestrians and
maritime traffic) is kept to a minimum. The length of the bridge is decisive for
the design of access facilities (e.g. vehicle transport of personnel, materials and
equipment in the bridge interior between abutments and use of lift in the tower).
In general doors and stairs are preferred compared to hatches and ladders,
which are only to be used when geometry do not allow for doors and stairs.
Detailing of access routes shall be performed as part of the design process. The
level of detail shall match design maturity, i.e. handling of materials and
equipment that match current design and O&M strategies shall be accounted for.
BJØRNAFJORDEN FLOATING BRIDGE (K12) – OPERATION, MAINTENANCE AND REHABILITATION STRATEGY 2-7
It is highlighted that material specifications are treated by the Design Basis, see
/3/. The material specific requirements in the O&M strategy shall be included in
Design Basis requirements.
Detailing of the following above water objects could be performed, e.g. with due
reference to /6/:
› Bearings
› Surfacing
› Concrete structures
› Primary steel structures incl. coating and sacrificial anodes (incl. use of
super duplex SDSS in a 6.5 m high splash zone, ref. /6/)
› Concrete structures
It means that the outside surfaces shall be without any stiffeners, openings for
installation, bolted connections or other protruding elements so that coating can
be performed mechanically (e.g. using robots) and with top quality. In addition,
all external surfaces shall be "smooth", i.e. without joints where accumulation of
water, dirt and eventually corrosion may happen.
Surfaces that are dehumidified do not require repainting after the structure has
been erected and the dehumidification system is operating.
Activity Interval
Routine (løpende) inspection and non- Dependant on element/system (ref.
scheduled maintenance chapter 4)
Handover inspection Only once. Before handover.
Only once. Before end of guarantee
Warranty inspection
period
Yearly inspection Yearly
Principal inspection Every 5 years
When needed for a component or a
Special inspection
group of components
Individual component frequencies.
Scheduled maintenance
According to actual needs.
Repair When needed.
Individual component frequencies.
Replacement
According to actual needs.
› Snow removal
› Inspections
BJØRNAFJORDEN FLOATING BRIDGE (K12) – OPERATION, MAINTENANCE AND REHABILITATION STRATEGY 2-9
› Material tests
› Structural monitoring
The operation plan has an interface to the object model of Bjørnafjorden K12 as
well as integration interface to SVV Bridge Management System 'BRUTUS' and
the financial system 'Økosys'.
The maintenance plan comprises routine maintenance (day to day activities) and
scheduled maintenance and/or replacement.
Spare part requirements shall be part of the O&M manual. Requirements shall
be based on:
› O&M strategy
› Are spare parts off the shelf or a specialised product (with long delivery
time)?
A spare part example may be pontoons and their moorings, which both are
critical and vulnerable when considering ship impact. Therefor it shall be
considered to have a complete mooring line in stock, emergency contract with
ROV and AHTS (Anchor Handling Tug Supply vessel) contractor and possibly
establishment of a local drydock so that downtime in case of a ship impact with
a pontoon or anchor is minimised.
2-10 BJØRNAFJORDEN FLOATING BRIDGE (K12) – OPERATION, MAINTENANCE AND REHABILITATION STRATEGY
› Moveable ladders
› Scissor lift
› Hoists
› Bearings
› Lighting equipment
3 O&M organisation
3.2 Organisation
Requirements for the O&M-organisation, number and qualifications, are
described in Table 3-1. The structure of the organisation is based on similar
organisations that manage other international bridges of similar size (without a
toll station that increases the operational setup). It is recommended that the
organisation is adjusted according to SVV's needs and plans.
Table 3-1: O&M-organisation. *)Part time/full time depends on whether or not an O&M-
organisation for several fjord-bridges is established.
Table 4-1 Operation plan for elements and systems. Frequencies based on international
best practice and SVV handbooks.
Derived
Inspection type Description Frequency First time
actions
Before taking
Clearing (debris etc.) and cleaning Daily bridge in
operation
Snow removal As needed
Before taking
Primary steel and coating Yearly bridge in *)
operation
Roadway and footway/bicycle Before taking
track. Incl. drainage and Weekly bridge in *)
barriers/railings operation
Before taking
Cable system Weekly bridge in *)
operation
Before taking
Overhead sign structures and signs Monthly bridge in *)
operation
Before taking
Routine inspection (løpende inspeksjon) Mechanical installations Weekly bridge in *)
operation
Before taking
Service roads Daily bridge in *)
operation
Before taking
Critical electrical system incl.
Daily bridge in *)
lighting
operation
Before taking
Non-critical electrical system incl.
Weekly bridge in *)
lighting
operation
Before taking
Dehumidification system Monitoring bridge in *)
operation
Before taking
Access facilities incl. inspection and
Weekly bridge in *)
maintenance equipment
operation
Before taking
Structural Health Monitoring
Test as appropriate bridge in *)
System (SHMS)
operation
Hand-over inspection (Ferdigbefaring) Visual inspection. Registration of Before handover
One time **)
Entire bridge defects and deficiencies of project
Guarantee inspection Before end of
Visual inspection related to remedy
(Reklamasjonsinspeksjon) One time agreed guarantee **)
of defects and deficiencies
Entire bridge period
General inspection
Within 1 year
(Enkel inspeksjon) Visual inspection Yearly **)
after handover
Entire bridge
Principal inspection
Within 5 year
(Hovedinspeksjon) Visual inspection 5-year interval **)
after handover
Objects above water
Principal inspection Visual inspection using special
(Hovedinspeksjon) methods and equipment (see the As needed As needed **)
Objects below water following text)
As needed As needed
Special inspection according to according to
Extended visual inspection, surveys
(special inspeksjon) outcome of SHMS outcome of SHMS **)
and material tests
On selected bridge parts/components and/or visual and/or visual
inspection inspection
*)
- instantly remedy of some of the observed defects
- description of needed inspection and maintenance actions
**)
Preparation of inspection and maintenance action list
BJØRNAFJORDEN FLOATING BRIDGE (K12) – OPERATION, MAINTENANCE AND REHABILITATION STRATEGY 4-15
› In case of an incident (e.g. ship impact) the manager shall rely on the
results of the risk analysis (that specify any operational measures) and
qualified inspections and assessments in order to minimise downtime.
The inspection program of the O&M manual should (in line with SVV current
steps towards a risk-based inspection approach) be based on a risk-based
approach. This should lead to considerable savings on operation, when
compared to handbook-based inspection approach, especially when considering
inspection of surfaces not readily accessible.
The structural health monitoring system (SHMS) shall be used, among others,
for monitoring on non-visible load response from deformations, fatigue and
wear. SHMS can be divided in two main parts:
Figure 4-1 presents an overview of a SHMS. The SHMS can be used, among
others, for verification of bridge design during the first years of operation. In
addition, it can be assessed whether it should be used in connection with special
elements and systems where the remaining service life needs to be evaluated
(e.g. fatigue or wear). It is expected that the mooring line prestress shall be
monitored continuously.
4-16 BJØRNAFJORDEN FLOATING BRIDGE (K12) – OPERATION, MAINTENANCE AND REHABILITATION STRATEGY
Figure 4-1: SHMS concept. Abbreviations are WIM: Weigh In Motion, ITS: Intelligent
Traffic System, DAU: Data Acquisition Unit.
› Periodic maintenance/replacements
› graffiti removal
› pothole repair
Table 4-2: Periodic maintenance/replacement of elements and systems with a service life
less than 100 years. *) Further detailing if the surface is exposed to de-icing
salt spray.
5 Emergency preparedness
An emergency preparedness plan shall be prepared in parallel with the design of
the Bjørnafjorden floating bridge. Among others, risk analyses shall form basis
for development of the plan. It shall be updated as the design matures. This
process shall ensure the involvement of the relevant authorities, so that the final
design is optimal considering the input from the authorities.
The overall purpose of the emergency preparedness plan is, among others:
› ensure a clear and distinct division of tasks and responsibilities between the
emergency preparedness stakeholders
› List of contacts
BJØRNAFJORDEN FLOATING BRIDGE (K12) – OPERATION, MAINTENANCE AND REHABILITATION STRATEGY 6-19
› inspections
The risk is in principle a summation of all risks related to all (identified) possible
failures that may occur for the component in the operation period. A risk is
defined as the product of the likelihood of the failure to occur and the
consequences of the failure.
As part of the Bjørnafjorden floating bridge, critical and vulnerable elements and
systems have an impact on service life and maintenance requirements. For each
element/system a criticality class and a vulnerability class are evaluated.
Evaluated classes are shown in Appendix B. In Table 6-1 elements and systems
with non-acceptable (C3, C4, R3, R4) criticalities and/or vulnerabilities are
summarised. It is expected that all non-acceptable criticalities and vulnerabilities
will be mitigated during design incl. establishment of operation and maintenance
procedures.
6-20 BJØRNAFJORDEN FLOATING BRIDGE (K12) – OPERATION, MAINTENANCE AND REHABILITATION STRATEGY
In Table 6-2 the maximum criticality class and the maximum vulnerability class
are shown for every element/system class. According to the RBI/RCM approach,
an analysis of design requirements (e.g. reliability, durability/service life and
resilience) and O&M (inspection, maintenance and rehabilitation) shall be
performed for elements/systems that have an estimated value 3 or 4 (C3, C4,
R3, R4). In many cases the optimal solution is known. In other cases, an
BJØRNAFJORDEN FLOATING BRIDGE (K12) – OPERATION, MAINTENANCE AND REHABILITATION STRATEGY 6-21
In agreement with SVV focus areas, the following element groups are analysed
in the following chapters:
› Mooring lines
The above 3 element groups are all unusual elements for major cable supported
bridges.
6-22 BJØRNAFJORDEN FLOATING BRIDGE (K12) – OPERATION, MAINTENANCE AND REHABILITATION STRATEGY
In the splash zone the pontoons are made of SDSS in full material thickness.
The top and bottom plate as well as the side plates below the splash zone
(equivalent to 6,5 m from the top plate), are constructed in carbon steel S420.
Bulkhead, diaphragm, stiffeners etc. inside the pontoons as well as the columns
are also constructed in carbon steel S420.
Several transitions and joints between different steel types will occur, which
require special handling to guarantee a sufficiently high quality, see /8/. The
same issues will apply for different types of surface treatments in different
zones.
7.1.1 Welds
The documents /2/ "Preferred solution, K12 – Appendix O" and /8/ "Material
selection, surface treatment and corrosion protection for floating bridge
Bjørnafjorden", describe amongst other requirements for welding of SDSS and
carbon steel. It is concluded in /8/ that the welding of the different steel types is
manageable if sound qualified welding procedures are established and
restrictions on critical material parameters are introduced. In /8/ the possibility
of a pre-treatment of the carbon steel by buttering in order to avoid hot or cold
cracking is described. An example of buttering before welding is shown in Figure
7-2.
In the Design Basis, it should be maintained that the design of welds must take
the greatest possible account of execution and future maintenance.
Now, possible critical areas and details that are not considered in the documents
/2/ and /8/ are assessed, where there may be special requirements for the
execution of welding joints or the execution can have special effect on durability
and hence on the extent of O&M.
difficult to clean adequately and to apply the surface treatment in correct layer
thickness. Even on a relatively easily accessible area and on a simple rectilinear
weld seam, corrosion can occur if adverse conditions are present.
In the figure a buttweld is shown with the root of the weld facing the interior
surfaces of the pontoon. The exposed surface of the weld root is much smaller
than the opposite side of the buttweld and the surface of the root side is also
much more even than the opposite side (especially with an x-shaped weld
seam). Since the environment inside the pontoon is expected to be less
aggressive than the outside, it should be investigated whether welding seams
can be turned so that the root is situated on the outside of the pontoon. It
7-26 BJØRNAFJORDEN FLOATING BRIDGE (K12) – OPERATION, MAINTENANCE AND REHABILITATION STRATEGY
At joints between top and side plates on pontoons, there will occur a transition
between stainless steel (upper side plates) and carbon steel (lower side and top
plates). The joint between horizontal and vertical plates is marked with a red
circle in Figure 7-5.
Consideration must be given to how the joints of horizontal and vertical plates
are to be designed. Some principal assembly types are shown in Figure 7-6 and
assessed for maintenance and service life issues, but not from a structural
capacity or execution point of view.
Figure 7-6 Examples of weld types between top and side plates
The top plates must have a slope towards the sides, which shall ensure
drainages of the surface. The recommended slope for a self-draining surface
should be no less than 25‰. At the joint detail shown in Figure 7-6-A, it is
likely that the weld will form an edge (groove or dent) that prevents free
drainage of water from the pontoon surfaces.
At the weld shown in Figure 7-6-B the risk for forming a groove or dent along
the edge will be less. However, the surface area of the weld will become much
BJØRNAFJORDEN FLOATING BRIDGE (K12) – OPERATION, MAINTENANCE AND REHABILITATION STRATEGY 7-27
larger and require extensive finishing work in order to ensure a smooth surface
that does not collect debris and ensures good drainage from the top of the
pontoon.
At the joint in Figure 7-6-C the weld is placed on the side plate, whereby water
from the top of the pontoon has a free flow to the outside of the vertical side
plate.
For all three variants shown in Figure 7-6 the water and with this is debris from
the surface of the top plates will run directly down the side plates. It is good
practice to design a drip mould at the edge of the surface that is drained so that
underlying surfaces are not unnecessarily contaminated, see Figure 7-7. The
Design Basis should require that vulnerable details must be designed with
respect for good drainage conditions. Horizontal surfaces should be fabricated
with a slope no less than 25‰.
If the top plate is designed as shown in Figure 7-7 the overhang will act as a
drip mould and the weld is located in a less exposed zone.
7-28 BJØRNAFJORDEN FLOATING BRIDGE (K12) – OPERATION, MAINTENANCE AND REHABILITATION STRATEGY
Figure 7-8 Weld between top and side plates designed with an overhang.
Type and location of welds along with a possible drip mould should be designed
with focus on the production.
The joint between the bottom and side plates are below the waterline and are
therefore outside the splash zone. The plates are therefore all designed in the
same type of carbon steel S420, but the problems with regard to surface
treatment and location of welds are to a certain extent similar, however a drip
mould is not relevant.
Joints between columns and pontoons are also located outside the splash zone,
so the materials will presumably be designed as carbon steel S420 with a
surface treatment. The same recommendations apply to the design as described
in the previous section.
The joints between columns and pontoons should be detailed in a future phase
with special focus on drainage and cleaning of the joints.
In ref. /2/ and /8/ a number of topics are described that must be in focus when
the surface treatments are applied, emphasising on good workmanship and best
practice:
› Layer thickness
› Rounding of edges
› Cleanliness of surfaces
› Surface roughness
› Chloride contamination on surfaces
› Conditions during application: temperature, dew point, relative humidity
› Workmanship: Operator knowledge and experience, equipment and QC
inspection
In addition to the above listed topics the design shall emphasize that all surfaces
shall be easy to paint and clean. This means that during the design e.g. it must
be taken into account that water can easily run off surfaces and that edges and
chambers are created so that no water and debris can accumulate.
7-30 BJØRNAFJORDEN FLOATING BRIDGE (K12) – OPERATION, MAINTENANCE AND REHABILITATION STRATEGY
According to the recommendations in /8/ all components above the splash zone
must be fabricated in carbon steel S420 with a coating type SVV System 2
(standard surface treatment system in accordance with SVV Handbook R762).
Figure 7-12 shows the recommended build-up of the surface protection system
over a weld on a flat SDSS-surface from ref. /8/.
BJØRNAFJORDEN FLOATING BRIDGE (K12) – OPERATION, MAINTENANCE AND REHABILITATION STRATEGY 7-31
Figure 7-12 Example of corrosion protection build-up over a weld in accordance with /8/
and secondly the pre-treatment is more difficult to produce. Hence these are
items that require special attention during design and fabrication.
Interior surfaces in columns and all inactive ballast tanks are protected against
corrosion by dehumidification. Interior surfaces in active ballast tanks of the
pontoons are protected from corrosion by a combination of coating and cathodic
protection. Recommended coating systems and cathodic protection are
described more detailed in ref. /8/.
As a part of the cathodic protection systems, sensors are installed to monitor the
potential differences in the steel between anodes and sensors. If the potential
difference is below a threshold value, the corrosion protection in the area is no
longer fully ensured and therefore indicate that replacement of anodes is due.
The number of sensors to be installed should be chosen to cover a
representative section of the structural parts to be cathodic protected without
necessarily monitoring the entire pontoon. It must also be considered whether
all pontoons should be monitored, or a representative selection would be
sufficient.
If the anodes are designed for an expected service life of 30-40 years, anodes
should typically be inspected the first time after 15-20 years. The intervals of
the inspection can be based on the monitoring in a combination with inputs from
inspections. The extent of inspections can be adjusted according to experience
with the system.
In Figure 7-14 the anodes are shown installed on bespoke plates in a rail device,
in which the anodes can be pulled up to the upper side of the pontoon and
handled. A remote-controlled tool, attached to a rail on top of the pontoon, can
be used to clean and/or replace anodes on the pontoon exterior.
There are several items concerning the access equipment tool shown that could
be problematic and should be investigated further as detailed below.
The anodes are arranged in a rail device which is connected to the pontoon. The
rail thereby passes over zones with stainless steel SDSS and carbon steel S420.
It is assessed that there will be a very high risk of corrosion problems in the
form of galvanic corrosion when different materials are connected. The rail
device is also located in the splash zone, which increases the risk of developing
corrosion around the connections (welds, bolts or similar), as shown in Figure
7-15.
7-34 BJØRNAFJORDEN FLOATING BRIDGE (K12) – OPERATION, MAINTENANCE AND REHABILITATION STRATEGY
Figure 7-15 Typical example of corrosion between different materials. The dark colour
indicates corrosion
There is a high risk that marine growth will build-up on and around rails and
spread out on adjacent surfaces. In order to ensure full functionality of the rail
devices cleaning and maintenance of the system will be required to some extent.
That could become extensive before the system comes into use after
approximately 15 years.
Anodes on the underside of the pontoons are likely to be required. These anodes
cannot be reached by the proposed rail devices and therefore a different form of
access will be required.
- General cleaning
General cleaning must be performed on the outside of the column exterior and
on the top of pontoons. General cleaning means removal of debris and
BJØRNAFJORDEN FLOATING BRIDGE (K12) – OPERATION, MAINTENANCE AND REHABILITATION STRATEGY 7-35
contamination, that over time could lead to damages of the coating. General
cleaning is considered a part of the normal operation that is organised and
performed by the operation organisation.
7.3 Accessibility
The operation and maintenance tasks described in section 7.2 require access
facilities that suit the frequency and duration of the individual tasks. In section
10 an access strategy is described.
As described in section 10 there should be access from the columns to the top
side of the pontoons. From the pontoons, inspections, cleaning and spot repairs
of coating on columns and top side of pontoons are performed. Safe access on
the upper side of the pontoons can be guaranteed by the use of harnesses in
combination with fall protection equipment or by installing permanent guard rails
at the perimeter of the pontoon. The extent of maintenance on guard rails is
considered to become unacceptably large in relation to the benefits of
restriction-free access on the pontoons. Hence rails should come in use when all
other solutions are exhausted. Permanent anchor points for rope access require
to some extent maintenance and with the number of inspections and other tasks
to be performed from the top of the pontoons a permanent safety guardrail in
combination with rope access/fall protection equipment should be considered in
special situations. Access from the column to the edge of the pontoon can be
established by guardrails, which create a more easily accessible evacuation
7-36 BJØRNAFJORDEN FLOATING BRIDGE (K12) – OPERATION, MAINTENANCE AND REHABILITATION STRATEGY
Access to the external surfaces on the columns can be established using ladders,
lift, scaffold or rope access. Visual routine inspection and general cleaning can
primarily be performed from the top of the pontoons. Access by ladder is limited
to low heights and cannot fully cover the access to the columns. Lifts or
scaffolding must be lifted from the bridge deck to the top of the pontoon, which
can cause interference with traffic to a certain extent. Alternatively, equipment
could be transported by boat to the pontoons. This will require more planning
and mobilisation. Rope access would not disturb the traffic on the bridge and can
be mobilised at short notice, however it requires access in form of hatches from
the bridge girder at the columns. Alternatively rope access could be created
from a self-propelled inspection gantry. The gantry will in that case be parked
adjacent to a column and be occupied during the inspection periods and
therefore not available for other tasks. The access strategy to the external
surfaces of the column should preferably be a combination of measures.
Inspections and cleaning of columns are in general performed from the pontoon
top and only in special cases or on high columns inspections must be performed
by rope access from the inspection gantry. Spot repairs of the coating are
preformed from scaffolding that can be transported inside column and bridge
girder. It requires equipment for transportation inside the bridge and all hatches
must be designed for general access. Sizes of hatches for access must be
specified in the Design Basis.
The bridge girder inspection gantry must be opened in the middle when passing
the columns. The open gantry must be stabilized during the column passage e.g.
on gantry beams as shown in Figure 7-16. From the open gantry there will be
surfaces on the bridge girder that are inaccessible for inspection or maintenance
works. Therefor access to these surfaces must be established in another way
(e.g. by a lift) when maintenance or inspection is required.
BJØRNAFJORDEN FLOATING BRIDGE (K12) – OPERATION, MAINTENANCE AND REHABILITATION STRATEGY 7-37
Access to the sides of the pontoons above water must primarily be performed
from boat or barge. The sides of the pontoon are fabricated in SDSS in the
splash zone and any spot repairs on the coating are primary for esthetic
reasons. Should the pontoon be completed with a drip mould as shown in Figure
7-8 spot repairs may be required. The works could be accomplished from the top
of the pontoons. Inspection and removal of marine growth can be performed
form a boat or barge.
A floating dry dock could come into use if a large very extensive repair is
required on a pontoon e.g. after a ship collision. The dry dock will create dry
access to all exterior surfaces of the pontoon and form an enclosed space in
which the climate can be controlled for optimal working conditions, minimizing
downtime due to weather. A cofferdam is used to establish dry access to the
outside of the pontoon in the event of more local damages that require repairs.
A dry dock or a cofferdam are not needed in the construction period of the
bridge and would not be fabricated until a requirement occur in the operation
period of the bridge.
› Grillage
› Gantry
The concepts have been developed with the aim of creating fully access of the
submerged surfaces of the pontoon so that inspection and maintenance can be
performed.
OceanTech recommends that consoles are installed at the side of the column
underneath the bridge girder as shown in Figure 8-3.
As the consoles will restrict the passage of the inspection gantry and therefor
also restrict access to the soffit of the bridge girder, the size and location of the
consoles should be assessed in more detail.
OceanTech states that there is no suitable dry dock on the market and therefore
it must be manufactured from scratch if required. OceanTech estimates that a
dry dock can be acquired for approx. NOK 99 million and approx. NOK 6 million
for mobilisation, 20 days operation and demobilisation.
For safety reasons the mooring lines cannot be anchored to the dry dock.
Therefore, mooring lines must temporary be anchored to buoys or the adjacent
pontoon. On the basis of the technical and economic analysis in ref. /10/ this
work must be performed using tugboats and anchor vessels.
an early stage. Experience from other major bridge projects shows that
technically and economic optimal access facilities will be ensured by involvement
early in the design.
8.3 Cofferdam
OceanTech have worked with a technical and economic concept for a cofferdam
to provide dry access to the side of pontoons. This concept is illustrated in
Figure 8-4.
OceanTech estimates that a cofferdam can be acquired for approx. NOK 7 million
and mobilization is estimated to approx. NOK 6 million for operation in 10 days
and subsequently demobilization.
The cofferdam will be an appropriate tool for repairing minor but significant
damages in the submerged and splash zone of the pontoons.
The size of the cofferdam is not only given by O&M considerations, but the
layout must in coming stages also be analyzed based on a quantitative risk
analysis which amongst other describes the consequences of a ship collision. The
8-42 BJØRNAFJORDEN FLOATING BRIDGE (K12) – OPERATION, MAINTENANCE AND REHABILITATION STRATEGY
The size of the ballast tanks varies in width (ballast tank A and B) and shape
(ballast tank C) as shown in Figure 8-6. In particular the rounded sections
(ballast tank C) at the ends of the pontoons require a robust concept for the
cofferdam if it should be able to cover all types of ballast tanks and all shapes of
the pontoon.
In ref. /9/ a brief description on how to seal the joint between pontoon and
cofferdam is include. However, it is not described how the cofferdam is attached
to the pontoon. This should be investigated further including a procedure for
reestablishment of the coating on the pontoon after the cofferdam is
demobilized.
9-44 BJØRNAFJORDEN FLOATING BRIDGE (K12) – OPERATION, MAINTENANCE AND REHABILITATION STRATEGY
9 Mooring of pontoons
9.1 Concept
The two consortia that in the conceptual stage 5 have worked with a floating
cable stay bridge solution over Bjørnafjorden, have described two concepts for
anchoring the mooring lines to the pontoons:
Anchoring at the side of pontoons (described in ref. /7/ App. A, drawing 701) is
shown in Figure 9-1.
Figure 9-1 Concept of mooring system (ref. /7/ appendix A, drawing 701)
Anchoring to the centre of the pontoons in mooring pools (ref. /15/) is shown in
Figure 9-2.
9.2 Materials
SINTEF recommends in a preliminary conclusion after comparing AMC and OON
design that the following material, corrosion protection and other protection
systems are used (see ref. /8/):
It is noted that the two consortia estimate different service lives for top and
bottom chains. Top chain materials and dimensions are similar in the two
consortia, whereas there is a difference in the dimensions for bottom chains. The
latter obviously gives a different lifespan. From an O&M perspective a solution
with a longer service lifespan is recommended.
From an operation and maintenance aspect mooring pools will cause a number
of challenges. The solution with the central anchoring of the mooring lines
creates several surfaces and transitions zones on the pontoons which must be
inspected and possibly maintained. Furthermore, considerations must be given
to provide safe access to the mooring pools during inspection and maintenance.
From the cathodic protection hydrogen gases can develop and accumulate in the
9-46 BJØRNAFJORDEN FLOATING BRIDGE (K12) – OPERATION, MAINTENANCE AND REHABILITATION STRATEGY
mooring pools and they must therefore be ventilated before workers can access
the cavity safely.
On the top of the pontoons, mooring pools must be secured so that there is no
danger of falling into the hole. If a railing would be installed around the mooring
pools, it must be assessed whether access to the columns will be restricted.
In the side anchoring solution, the chain stopper and fairled will to an extent be
protected by the cathodic protection installed on the pontoons. In the mooring
pools chain stopper and fairled cannot benefit from the cathodic protection and
the elements therefore require a separate corrosion protection.
As pointed out above there are a number of O&M disadvantages to the current
OON concept, but it should be further investigated whether the concept can
bring savings that outweigh the disadvantages.
The top and bottom chains are recommended in ref. /8/ to be designed with a
corrosion allowance of 0.8mm/year in the splash zone and 0.2 mm/year for fully
submerged items. Should the corrosion rate turn out to be higher than expected
or service lifespan of the element is to be extended, the possibility of
implementing a cathodic protection system should be considered. Since cathodic
protection using sacrificial anodes are likely to have only a limited effect on
chains, it could be considered to use impressed current cathodic protection
(ICCP).
The failure of one or two mooring lines and the acceptable replacement times
are assessed in the AMC document ref. /12/. The design is considered to be a
relatively robust concept.
10 Access strategy
This chapter outlines the access strategy for execution of O&M activities on the
bridge. This includes access for personnel, equipment and materials.
The following design phases shall detail, how access facilities facilitate optimal
O&M (e.g. based on material choice and dimensions). The project Design Basis
shall detail robust requirements for access facilities that balances technical (incl.
safety for personnel) and economic consequences.
› Shared use path (SUP) which also shall provide access for an Under-Bridge
Inspection Unit
› Service roads, i.e. roads other than the above that also provide access to,
or close to, the bridge
› Interior and exterior stairs, platforms, doors and hatches. Exterior doors
and hatches shall be equipped with a locking system. Doors and hatches
shall be watertight. Passage from roadway level to the bottom of the
pontoons shall be possible. Passage from roadway level to tower top and
bottom and between tower legs beneath the roadway girder. Passage 'from
A to B' includes transport of personnel, materials and equipment.
Verification shall be performed as part of the design. At certain locations,
e.g. in piers, a shaft for hoisting of materials and equipment will be
beneficial. This also needs to be verified as part of the design. In addition, it
shall be possible to inspect, maintain and replace bearings from permanent
access facilities. As a secondary access and evacuation route passage from
pier interior to pontoon exterior shall be possible. This allow for entering or
exiting the bridge by boat.
BJØRNAFJORDEN FLOATING BRIDGE (K12) – OPERATION, MAINTENANCE AND REHABILITATION STRATEGY 10-49
› Elevator in tower leg (from the bottom to the top with the possibility to stop
and exit in between, incl. stop and exit at crossbeam and at roadway level
› Bucket truck
› Underbridge inspection unit (travel along the shared use path in one side of
the bridge girder and along the shoulder / slow lane on the other side of the
bridge)
› Boat or barge
› Divers equipment
11.1 Introduction
The purpose of risk-based1 inspection (RBI) and reliability centred maintenance
(RCM) planning is to ensure that inspections and scheduled replacements are
performed before compromising safety as well as minimising life cycle costs. The
latter has been a goal for O&M planning during the past decades, where
sampling/theme-wise inspections are common.
Deterioration and failure of elements and systems are associated with a large
degree of uncertainty. Risk- and reliability-based methods are excellent methods
when dealing with uncertain processes.
In many countries (as in Norway) handbooks specify rules for inspection and
maintenance which are robust, when dealing with a portfolio of structures of
different age, geometry, material etc. Often these structures undergo principal
inspection every 5-6 years. Handbook-based inspection and maintenance rules
may not be economic optimal when considering major bridges with many similar
details, difficult access and with an almost daily staffing. RBI and RCM methods
can be used for economic optimisation of inspection and maintenance with due
consideration of reliability, safety and any other constraints.
RBI has been applied in the oil and gas industry (incl. offshore) during the latest
decades.
11.2 RBI
RBI comprise elements and systems for which the failure pattern is predictable
and for which the remaining, acceptable deterioration can be determined based
on the result of a condition evaluation. One example is corrosion of a steel girder
as failure mode, where coating constitutes the protection system. RBI shall
contain a description of inspection type, location and interval. The inspection
program shall be optimised according to a vulnerability criterion (vulnerability,
see Appendix A) for every element/system.
1
In some projects the evaluation of consequences is omitted. Then the
expression 'reliability-based inspection' is used.
BJØRNAFJORDEN FLOATING BRIDGE (K12) – OPERATION, MAINTENANCE AND REHABILITATION STRATEGY 11-51
11.3 RCM
RCM comprise elements and systems for which the failure pattern is predictable
but for which the remaining, acceptable deterioration cannot be determined
based on the result of a condition evaluation. Such elements and systems are
often mechanical, hydraulic and/or electrical. RCM shall contain inspection
interval (if possible), mitigation measures, maintenance interval and needed
spare parts in order to maintain a acceptable level of safety.
11.4 Method
The use of RBI and RCM methods shall ensure that:
› Inspection plans are evaluated and optimised during the operational phase
based on inspection results in order to prolong service life, optimize
inspection frequency and prevent escalation of damages.
During RBI and RCM planning each element and system is analysed and the
optimal individual strategy is established. These individual strategies are then
combined and adjusted in order to establish an optimal inspection plan for the
entire bridge (the results of this report shall contribute to an increased and
systematic detailing of O&M during the next phases of the project).
12-52 BJØRNAFJORDEN FLOATING BRIDGE (K12) – OPERATION, MAINTENANCE AND REHABILITATION STRATEGY
12.1 Introduction
The purpose of a Structural Health Monitoring System (SHMS) is to provide data
for:
› verification of design
SVV wants a lean SHMS that collects, processes and presents 'need to know' and
not 'nice to know' data. The reasons are listed below:
› a SHMS comprise elements and systems with a short service life / become
obsolete quite fast, i.e. O&M related costs are significant
The data evaluation module may, if needed, comprise the following modules:
The data evaluation module for elements and systems above and below water is
described in the following section.
› Correlation of GPS and tilt-meter readings with results obtained from the
finite element analyses used to design the bridges
› To assess the combined load effects of wind, wave, tidal currents and
traffic loads in order to update service life models
As part of the remaining service life module, the following shall be included
(possibly as a campaign):
› Fatigue in welded joints of the orthotropic steel deck. To this aim, strain
and external exposure data (traffic and temperature) shall be combined into
appropriate fatigue accumulation models to determine the remaining fatigue
life.
As part of the extreme event notification (e.g. ship impact), the following shall
be included:
12-54 BJØRNAFJORDEN FLOATING BRIDGE (K12) – OPERATION, MAINTENANCE AND REHABILITATION STRATEGY
13 References
/1/ Bjørnafjorden, VegRAMS: Mandat og føring for arbeidet
2020-17-04
/3/ Design Basis Bjørnafjorden, Side- and anchored floating bridge, rev. C,
2014-03-07
/4/ Bjørnafjorden Suspension Bridge, K1 & K2 Life Cycle Cost Study, doc.
no. SBJ-20-C3-AAS-40-RE-001 Rev 0, 02.06.2017
/11/ Inspection philosophy and scope estimates for the marine componnets,
Bjørnafjorden, ferry free E39, Statens Vegvesen.
A component can either be an element (e.g. stay cable, bolt) or a system (e.g.
dehumidification system, structural health moniroting system). A system may
also comprise one or more elements.
Criticality:
The risk is in principle a summation of all risks related to all (identified) possible
failures that may occur for the component in the operation period. A risk is
defined as the product of the likelihood of the failure to occur and the
consequences of the failure.
Vulnerability:
1 Criticality Class
2 Vulnerability Class
https://cowi.sharepoint.com/sites/A205696-project/Shared Documents/70-WorkSubmitted/10-Documents/D&V/Fase1and2_ver2/APP1_Analyse_FDV_BFJ_A205696_002.docx
1-2 BJØRNAFJORDEN FLYTEBRU (K12) – APPENDIX A RISK BASED INSPECTION, MAINTENANCE AND REHABILITATION (METHODOLOGY)
› Correct maintenance strategy is proposed for all elements and systems with
adequate attention towards critical and/or vulnerable elements and
systems.
https://cowi.sharepoint.com/sites/A205696-project/Shared Documents/70-WorkSubmitted/10-Documents/D&V/Fase1and2_ver2/APP1_Analyse_FDV_BFJ_A205696_002.docx
BJØRNAFJORDEN FLYTEBRU (K12) – APPENDIX A RISK BASED INSPECTION, MAINTENANCE AND REHABILITATION (METHODOLOGY) 1-3
The method has been used in its full extent, as far as bridges are concerned, in
Detailed Design of the Messina Strait Bridge in Italy as well as several existing
bridges such as Queen Elisabeth II crossing in UK. Ref. /1/ describe a semi-
quantitative use of the method.
The method is especially valid for unique structures, as the Bjørnafjord cable-
stayed bridge, for which the complexity and the number of components of
certain types call for theme-wise I, M and R plans. Further, it is for such project
appropriate to benchmark design towards Operation and Maintenance and
thereby ensure that O&M concerns are integrated in the design.
https://cowi.sharepoint.com/sites/A205696-project/Shared Documents/70-WorkSubmitted/10-Documents/D&V/Fase1and2_ver2/APP1_Analyse_FDV_BFJ_A205696_002.docx
2-4 BJØRNAFJORDEN FLYTEBRU (K12) – APPENDIX A RISK BASED INSPECTION, MAINTENANCE AND REHABILITATION (METHODOLOGY)
The analysis will for each component define if the component is related to RBI or
to RCM.
E.g. a component type is rated very vulnerable, if criticality is very high and
by experience time for failure development is short - days or hours.
3 The design is carried out (not part of the current stage of the VegRAMS
process). The designs of all RCM components rated high or very high are
https://cowi.sharepoint.com/sites/A205696-project/Shared Documents/70-WorkSubmitted/10-Documents/D&V/Fase1and2_ver2/APP1_Analyse_FDV_BFJ_A205696_002.docx
BJØRNAFJORDEN FLYTEBRU (K12) – APPENDIX A RISK BASED INSPECTION, MAINTENANCE AND REHABILITATION (METHODOLOGY) 2-5
adjusted until their criticalities can be reduced to either low or medium. The
designs of all RBI components rated vulnerable or very vulnerable are
adjusted until their vulnerabilities can be reduced to either robust or semi-
robust.
Consequence of failure
To apply this approach, rating of the consequences and probabilities are needed
for each component. Table 2.1 shows a semi-quantitative allocation of
consequence which serve as basis for the criticality analysis. A factor of 4 has
been applied between the different consequence classes, 1-4, so a proper
differentiation between functional failure consequences can be made. The
considered ratings of consequences comprise four types of consequences:
› Unavailability
› Costs
› Environmental damage
Definition of the four consequences and the interrelation between the different
consequence categories are described in the following.
Furthermore, it is foreseen that closure of one lane or one side of the bridge will
cause minimal congestion if nothing at all, i.e. cost of possible congestion will
https://cowi.sharepoint.com/sites/A205696-project/Shared Documents/70-WorkSubmitted/10-Documents/D&V/Fase1and2_ver2/APP1_Analyse_FDV_BFJ_A205696_002.docx
2-6 BJØRNAFJORDEN FLYTEBRU (K12) – APPENDIX A RISK BASED INSPECTION, MAINTENANCE AND REHABILITATION (METHODOLOGY)
not be considered. Because of this, the relation between costs and unavailability
measured in closure of a single lane is a guestimate.
Table 2.1 provides ratings for each type of consequence with four levels of
ratings. For the failure of a given type of component, it will be the most severe
consequence rating, which determines the overall rating.
Table 2.1 Consequence ratings for failure of a given type of component. *'Disastrous'
consequences are handled as a part of ULS verification. (1 EUR is
approximately 10.5 NOK)
https://cowi.sharepoint.com/sites/A205696-project/Shared Documents/70-WorkSubmitted/10-Documents/D&V/Fase1and2_ver2/APP1_Analyse_FDV_BFJ_A205696_002.docx
BJØRNAFJORDEN FLYTEBRU (K12) – APPENDIX A RISK BASED INSPECTION, MAINTENANCE AND REHABILITATION (METHODOLOGY) 2-7
Likelihood of occurrence
Probability of failure, which may cover a large range of events, may in the
conceptual design phase be rated qualitatively into five levels. The probabilities
are defined based on the likelihood of failure to occur during the service life for
the population of each type of component:
› Very unlikely
› Unlikely
› Occasional
› Likely
› Very likely
Criticality
Based on the range of consequences and probabilities for a failure, Table 2.2
provides the criticality rating of a given component. The table shows the
criticality matrix with a rating into very high, high, medium, low and
inconsiderable. A colour coding of red, yellow and green has been applied to
indicate the criticality rating. Moreover is for convenience below the matrix
inserted a value for the criticality classes.
The matrix shall be used qualitatively in the current stage of the VegRAMS
process. Later in the design stage a quantitative approach can be used for some
components.
› remove/reduce impacts
https://cowi.sharepoint.com/sites/A205696-project/Shared Documents/70-WorkSubmitted/10-Documents/D&V/Fase1and2_ver2/APP1_Analyse_FDV_BFJ_A205696_002.docx
2-8 BJØRNAFJORDEN FLYTEBRU (K12) – APPENDIX A RISK BASED INSPECTION, MAINTENANCE AND REHABILITATION (METHODOLOGY)
Table 2.2 Criticality matrix. *System or element failures that could result in 'disastrous'
consequences are handled as a part of the ULS design.
Criticality classes, C0: Inconsiderable, C1: Low, C2: Medium, C3: High, C4: Very High
Vulnerability
The time to failure for a certain degradation mechanism is the time over which
the progress of failure can be observed by inspection, monitoring or by other
means based on normal best practice. For example, an overload failure of a
lamella in an expansion joint will happen immediately (classified as hours),
whereas a failure of topcoat on towers will happen over several years. The
same holds for gradual deformation versus a brittle failure mode.
Table 2.3 shows a set of vulnerability rates, depending on criticality class and
time to failure:
› Robust (R1)
› Vulnerable (R3)
Vulnerability classes, R0: Very Robust, R1: Robust, R2: Semi-Robust, R3: Vulnerable, R4:
Very Vulnerable
https://cowi.sharepoint.com/sites/A205696-project/Shared Documents/70-WorkSubmitted/10-Documents/D&V/Fase1and2_ver2/APP1_Analyse_FDV_BFJ_A205696_002.docx
BJØRNAFJORDEN FLYTEBRU (K12) – APPENDIX A RISK BASED INSPECTION, MAINTENANCE AND REHABILITATION (METHODOLOGY) 2-9
For each of these components the relevant alternative designs may be analysed
in future stages of the project. The set of solutions giving minimum LCC for the
total assemblage shall be selected.
It should be noted that time for damage tolerance has not been accounted for in
the above framework for categorisation into RBI or RCM elements/systems.
https://cowi.sharepoint.com/sites/A205696-project/Shared Documents/70-WorkSubmitted/10-Documents/D&V/Fase1and2_ver2/APP1_Analyse_FDV_BFJ_A205696_002.docx
2-10 BJØRNAFJORDEN FLYTEBRU (K12) – APPENDIX A RISK BASED INSPECTION, MAINTENANCE AND REHABILITATION (METHODOLOGY)
Default
Criticality Criticality class principal
inspection interval
Inconsiderable C0 5 years or more
Low C1 5 years
Medium C2 2 years
High C3 1 year
Very High C4 6 months or less
For some RCM systems and elements with continuous monitoring there is no
need for inspections at all, because it is known at all time, whether the system
or element is working or not and may not need maintenance. However, for
many systems there is a need for service inspections in order to have the
system running at all times (and in order to ensure an optimal maintenance
plan), and in those cases the default inspection interval is nice to know.
Default
Vulnerability Vulnerability class principal
inspection interval
Very Robust R0 5 years or more
Robust R1 5 years
Semi-Robust R2 2 years
Vulnerable R3 1 years
Very Vulnerable R4 6 months or less
The proposed default inspection interval may be optimized during further RBI
analyses.
https://cowi.sharepoint.com/sites/A205696-project/Shared Documents/70-WorkSubmitted/10-Documents/D&V/Fase1and2_ver2/APP1_Analyse_FDV_BFJ_A205696_002.docx
BJØRNAFJORDEN FLYTEBRU (K12) – APPENDIX A RISK BASED INSPECTION, MAINTENANCE AND REHABILITATION (METHODOLOGY) 2-11
› Areas where design changes during construction phase have been made.
If it is identified that the above areas degrade differently, they may be treated
separately in the I&M-plan, if it is beneficial from an economical point of view.
Inspection and maintenance planning utilises the results of the initial Inspection
and Maintenance Activity Analysis (IMAA) and has the objective of creating an
overall optimal inspection and maintenance programme. This is achieved by
performing similar works at the same time. The main relations to be considered
are:
› Type of activity
› Activity intervals
› Needed competences
› Cost
https://cowi.sharepoint.com/sites/A205696-project/Shared Documents/70-WorkSubmitted/10-Documents/D&V/Fase1and2_ver2/APP1_Analyse_FDV_BFJ_A205696_002.docx
2-12 BJØRNAFJORDEN FLYTEBRU (K12) – APPENDIX A RISK BASED INSPECTION, MAINTENANCE AND REHABILITATION (METHODOLOGY)
› Geographic location
› Access facilities
› Consumption of man-hours
› Robustness/redundancy
› Acceptance criteria
At the present stage such an optimized plan has not been elaborated as:
› Important changes during the construction phase are important input and
needed.
› Acceptance criteria’s
https://cowi.sharepoint.com/sites/A205696-project/Shared Documents/70-WorkSubmitted/10-Documents/D&V/Fase1and2_ver2/APP1_Analyse_FDV_BFJ_A205696_002.docx
BJØRNAFJORDEN FLYTEBRU (K12) – APPENDIX A RISK BASED INSPECTION, MAINTENANCE AND REHABILITATION (METHODOLOGY) 2-13
› Mitigation measures
› Inspection interval
› Maintenance type
› Maintenance interval
› Repair time
› Inspection result
https://cowi.sharepoint.com/sites/A205696-project/Shared Documents/70-WorkSubmitted/10-Documents/D&V/Fase1and2_ver2/APP1_Analyse_FDV_BFJ_A205696_002.docx
3-14 BJØRNAFJORDEN FLYTEBRU (K12) – APPENDIX A RISK BASED INSPECTION, MAINTENANCE AND REHABILITATION (METHODOLOGY)
3 References
/1/ Messina Bridge – Reliability Based Inspection and Reliability Centered
Maintenance – The Challenge, Poul Linneberg et al., IABMAS 2012
https://cowi.sharepoint.com/sites/A205696-project/Shared Documents/70-WorkSubmitted/10-Documents/D&V/Fase1and2_ver2/APP1_Analyse_FDV_BFJ_A205696_002.docx
13-58 BJØRNAFJORDEN FLOATING BRIDGE (K12) – OPERATION, MAINTENANCE AND REHABILITATION STRATEGY
2) Failure mode: Identify for each element the set of functional failures
Remarks:
All default parameters should be verified by supplier information or other relevant reference.
This is an initial IMAA analysis and results should be benchmarked against LCC and further I&M studies related to eg. supplier information.
https://cowi.sharepoint.com/sites/A205696-project/Shared Documents/70-WorkSubmitted/10-Documents/D&V/Fase1and2_ver2/Risk based Inspection and Maintenance -
Bjørnafjorden_Fase2_rev01
Sheet: Basis (Print)
1/4
Risk based Inspection and Maintenance
E39 Bjørnafjorden Bridge - Operation and Maintenance
62 62
Concequence of failure
Cost
Criticality
Likelihood
Fatalities
Element no.
Vulnerability
Unavalibality
Environment
handbook V441
max(consequence)
Time for failure development
Cost
Criticality
Likelihood
Fatalities
Element no.
Vulnerability
Unavalibality
Environment
handbook V441
max(consequence)
Time for failure development
Cost
Criticality
Likelihood
Fatalities
Element no.
Vulnerability
Unavalibality
Environment
handbook V441
max(consequence)
Time for failure development
Cost
Criticality
Likelihood
Fatalities
Element no.
Vulnerability
Unavalibality
Environment
handbook V441
max(consequence)
Time for failure development
Loss of protection to steel or concrete structures. Permeability of Consequences of steel failure caused by corrosion could
11.02 Roadway - Surfacing surfacing causing corrosion of steel box girder or degradation of 5 5 5 3 5 be disastrous, however considered very unlikely. 1 3 10 Years 1
concrete box girder.
12.00 H2 Road sign
12.01 Road signs - analog Rodent bites, Wear and tear. 1 1 1 1 1 Defects have effect on road safety 3 1 1 Days 2
12.02 Road signs - LED display Malfunction, rodent bites, Wear and tear. 1 2 1 1 2 Defects have effect on road safety 3 2 1 Days 3
13.00 H2 B9.2 Electrical systems - Critical
Failure may impose a severe risk for ships, flights and
Eg. trafic light, navigation ligthing for ships and
13.01 Malfunction, rodent bites, Wear and tear. 5 5 5 3 5 other vehicles. Impact may leed to serious damage to the 2 3 1 Hours 4
flights , essential monitoring systems
bridge
14.00 H2 B9.2 Electrical system - Non-critical
Eg. internal navigation lighting in box girder, non-
14.01 Malfunction, rodent bites, Wear and tear. 1 1 3 1 3 Failure may impose a risk to O&M personel 2 2 1 Hours 3
essential monitoring systems
15.00 H15 Railings (Crash barriers and other railing)
18.01 SHMS Malfunction & Wear and tear & Rodent bites 3 2 1 0 3 On a long term failure may impose a risk for the structure 2 2 1 Hours 3
Failure and detection analysis Inspection and Maintenance Activity Analysis (IMAA)
Key parameter
Recommendations - to monitor
Spare part
Can failure be Recommended (Usual signs of
Mitigation measures Recommended Comments to requirement in
Element Name Functional Failure Detection eliminated or principal degredation
other than Maintenance Inspection/maintenance order to
method managed in ways inspection related to
Criticality
[Years]
Element no.
maintenance stategy strategy minimize repair
Vulnerability
RCM or RBI
[∆tI] (Years)
other than strategy concrete and
time (if critical)
maintenance? steel is not
listed)
Corrosion is a consequence
Periodic
of a failing protection
Periodic corrective/prev
system. Time for damage
1.02 Prestressing tendons Degradation of tendons elements 3 1 Yes Inspection None 5 5 RBI (5) - Inspection every entive
tolerance is therefore set to
5 years maintenance
5 years, which is the same as
(PIBM)
the protection system.
Corrosion is a consequence
Periodic
of a failing protection
Stainless steel, Periodic corrective/prev Relative
Steel girder - Structural Corrosion, internal: Bridge girders - Dehumidification system. Time for damage
2.01 3 1 Yes Inspection however this is not 5 5 RBI (5) - Inspection every entive None humidity inside
Steel, internal surfaces are subject to internal corrosion. system tolerance is therefore set to
cost optimal. 5 years maintenance girder.
5 years, which is the same as
(PIBM)
the protection system.
Continuos
Installation of two monitoring of
Periodic
smaller humidity and air
Periodic corrective/prev Inspection interval should be
Steel girder - dehumidification units (5 or flow inside the
2.02 System malfunction 0 0 Yes Inspection None 2 2 RCM - Inspection every entive provided by the supplier of Filters
Dehumidification System rather than one large more) Steel Box Girder
2 years maintenance the system
in each dehumidified should give a
(PIBM)
bridge girder section. warning if the
system is failing
Key parameter
Recommendations - to monitor
Spare part
Can failure be Recommended (Usual signs of
Mitigation measures Recommended Comments to requirement in
Element Name Functional Failure Detection eliminated or principal degredation
other than Maintenance Inspection/maintenance order to
method managed in ways inspection related to
Criticality
[Years]
Element no.
maintenance stategy strategy minimize repair
Vulnerability
RCM or RBI
[∆tI] (Years)
other than strategy concrete and
time (if critical)
maintenance? steel is not
listed)
Corrosion is a consequence
Periodic
of a failing protection
Corrosion, internal: - Dehumidification Stainless steel, Periodic corrective/prev Relative
Steel columns - interior system. Time for damage
4.01 Columns are subject to corrosion in 3 1 Yes Inspection system however this is not 5 5 RBI (5) - Inspection every entive None humidity inside
surfaces tolerance is therefore set to
indoor environment - EMC System cost optimal. 5 years maintenance columns.
5 years, which is the same as
(PIBM)
the protection system.
Continuos
monitoring of
Periodic
humidity and air
Periodic corrective/prev Inspection interval should be
Steel columns - (5 or flow inside the
4.02 System malfunction 0 0 Yes Inspection None 5 5 RCM - Inspection every entive provided by the supplier of Filters
Dehumidification System more) columns should
5 years maintenance the system
give a warning if
(PIBM)
the system is
failing
Periodic
Monitoring should be
Fatigue in welds: - SHMS, measuring Periodic corrective/prev Hot spots
installed, however this can
4.04 Steel columns - Weldings Columns are subject to fatigue from 4 2 Yes Inspection loads on bridge (fatigue 5 2 RBI (2) - Inspection every entive identified
only be carried out at
traffic, wind, etc.. levels and cycles) 2 years maintenance during design.
selected spots.
(PIBM)
Key parameter
Recommendations - to monitor
Spare part
Can failure be Recommended (Usual signs of
Mitigation measures Recommended Comments to requirement in
Element Name Functional Failure Detection eliminated or principal degredation
other than Maintenance Inspection/maintenance order to
method managed in ways inspection related to
Criticality
[Years]
Element no.
maintenance stategy strategy minimize repair
Vulnerability
RCM or RBI
[∆tI] (Years)
other than strategy concrete and
time (if critical)
maintenance? steel is not
listed)
Visual
Periodic
inspection and
Corrosion, internal: - Dehumidification Stainless steel, Periodic corrective/prev X amount of
Steel anchor box - internal (5 or assessment of
5.03 Anchor boxes are subject to 0 0 Yes Inspection system however this is not 5 5 RBI - Inspection every entive None Coating system
surfaces more) Coating
corrosion in indoor environment - EMC System cost optimal. 5 years maintenance for spot repairs.
Condition
(PIBM)
Indicator, CC.
Continuos
monitoring of
Periodic
humidity and air
Periodic corrective/prev Inspection interval should be
Steel anchor box - (5 or flow inside the
5.04 System malfunction 0 0 Yes Inspection 5 5 RCM - Inspection every entive provided by the supplier of Filters
Dehumidification System more) anchor box
5 years maintenance the system
should give a
(PIBM)
warning if the
system is failing
Visual
Periodic
inspection and
Stainless steel, Periodic corrective/prev X amount of
Steel anchor box - Coating Degradation of coating due to (5 or assessment of
5.05 0 0 Yes Inspection None however this is not 5 5 RBI - Inspection every entive Coating system
system indoor environment more) Coating
cost optimal. 5 years maintenance for spot repairs.
Condition
(PIBM)
Indicator, CC.
6.00 Tower foundation
Periodic
Periodic corrective/prev
Degradation of concrete and
6.01 Reinforced Concrete 3 1 Yes Inspection None 5 5 RBI (5) - Inspection every entive
reinforcement
5 years maintenance
(PIBM)
https://cowi.sharepoint.com/sites/A205696-project/Shared Documents/70-WorkSubmitted/10-Documents/D&V/Fase1and2_ver2/Risk based Inspection and Maintenance -
Bjørnafjorden_Fase2_rev01
Sheet: IMAA
4/9
Risk based Inspection and Maintenance
E39 Bjørnafjorden Bridge - Operation and Maintenance
Failure and detection analysis Inspection and Maintenance Activity Analysis (IMAA)
Key parameter
Recommendations - to monitor
Spare part
Can failure be Recommended (Usual signs of
Mitigation measures Recommended Comments to requirement in
Element Name Functional Failure Detection eliminated or principal degredation
other than Maintenance Inspection/maintenance order to
method managed in ways inspection related to
Criticality
[Years]
Element no.
maintenance stategy strategy minimize repair
Vulnerability
RCM or RBI
[∆tI] (Years)
other than strategy concrete and
time (if critical)
maintenance? steel is not
listed)
Corrosion is a consequence
of a failing protection
- Galv wires.
Periodic system. Time for damage
- PE-coating Design
Periodic corrective/prev tolerance is therefore set to
- HDPE coating anchorages in a
8.01 Stay cables Material loss in wires 3 1 Yes Inspection 5 5 RBI (5) - Inspection every entive 5 years, which is the same as None
- Structural Health way to make
5 years maintenance the protection system. Due
Monitoring System easy inspection.
(PIBM) to the number and nature of
(SHMS)
protection systems this
interval may be increased.
Periodic
Periodic corrective/prev
Galvanisation of wires in Special
8.02 Degradation of galvanisation. 2 1 Yes None 5 5 RBI (5) - Inspection every entive None
cable inspection
5 years maintenance
(PIBM)
Periodic
Periodic corrective/prev
Special
8.03 Grease (fedt) Loss of material 2 1 Yes None 5 5 RBI (5) - Inspection every entive None
inspection
5 years maintenance
(PIBM)
Periodic
Periodic corrective/prev
Special
8.04 PE sheet Degradation of PE sheet 2 1 Yes None 5 5 RBI (5) - Inspection every entive None
inspection
5 years maintenance
(PIBM)
Periodic
A proper
Periodic corrective/prev
Degradation of material. Caused by (5 or amount of HDPE-
8.05 HDPE 0 0 Yes Inspection None 5 5 RBI - Inspection every entive None
weather impact more) repair kit for
5 years maintenance
spot repairs.
(PIBM)
Periodic
A proper
Corrosion anchouage: Anchorages Periodic corrective/prev
Dehumidification of amount of Visual
8.06 Stay cabel anchors in deck and tower are subjected to 3 1 Yes Inspection None 5 5 RBI (5) - Inspection every entive None
anchorages Coating system inspection
corrision from weather variations 5 years maintenance
for spot repairs.
(PIBM)
Key parameter
Recommendations - to monitor
Spare part
Can failure be Recommended (Usual signs of
Mitigation measures Recommended Comments to requirement in
Element Name Functional Failure Detection eliminated or principal degredation
other than Maintenance Inspection/maintenance order to
method managed in ways inspection related to
Criticality
[Years]
Element no.
maintenance stategy strategy minimize repair
Vulnerability
RCM or RBI
[∆tI] (Years)
other than strategy concrete and
time (if critical)
maintenance? steel is not
listed)
Corrosion is a consequence
Periodic
of a failing protection
Corrosion, internal: - Dehumidification Periodic corrective/prev Relative
Steel pontoons - interior system. Time for damage
9.01 Pontoons are subject to corrosion 3 1 Yes Inspection system. 5 5 RBI (5) - Inspection every entive None humidity inside
surfaces tolerance is therefore set to
in indoor environment - Cathodic protection 5 years maintenance pontoons.
5 years, which is the same as
(PIBM)
the protection system.
Continuos
monitoring of
Periodic
humidity and air
Periodic corrective/prev Inspection interval should be
Steel pontoons - (5 or flow inside the
9.02 System malfunction 0 0 Yes Inspection Monitoring 5 5 RCM - Inspection every entive provided by the supplier of Filters
Dehumidification System more) pontoons
5 years maintenance the system
should give a
(PIBM)
warning if the
system is failing
Periodic
Corrosion, external: Periodic corrective/prev Splash zone elements are
Steel pontoons - exterior
9.03 Pontoons are subject to corrocion 3 1 Yes Inspection None 5 5 RBI (5) - Inspection every entive produced in a corrosion
surfaces
due to weather variations. 5 years maintenance resistant alloy SDSS
(PIBM)
Periodic
Fatigue in welds: Periodic corrective/prev
Splash zone elements are in a
9.04 Steel pontoons - Weldings Pontoons are subject to fatigue 4 2 Yes Inspection None 5 2 RBI (2) - Inspection every entive
corrosion resistant alloy SDSS
from traffic, waves, etc. 2 years maintenance
(PIBM)
Periodic
Aproper amount
Degradation of coating due to Periodic corrective/prev
Steel pontoons - Coating Cathodic protection of Coating
9.05 weather conditions and material 3 1 Yes Inspection 5 5 RBI (5) - Inspection every entive
system outside splash zone system for spot
durability 5 years maintenance
repairs.
(PIBM)
Visual
Periodic
A proper inspection and
Degradation of top cating due to Periodic corrective/prev
amount of assessment of
9.06 Steel pontoons - Top coat weather conditions and material 3 1 Yes Inspection None 5 5 RBI (5) - Inspection every entive
Coating system Coating
durability 5 years maintenance
for spot repairs. Condition
(PIBM)
Indicator, CC.
Periodic
Degradation of cathotic protection Evaluate to use Fresh Periodic corrective/prev Monitoring
Steel pontoons - interior (5 or
9.07 if they detach or bad connection 0 0 Yes Inspection waterdue to less 5 5 RBI - Inspection every entive Extra anodes current flow
cathodic protection (if any) more)
with steel corrosion 5 years maintenance from anode
(PIBM)
Key parameter
Recommendations - to monitor
Spare part
Can failure be Recommended (Usual signs of
Mitigation measures Recommended Comments to requirement in
Element Name Functional Failure Detection eliminated or principal degredation
other than Maintenance Inspection/maintenance order to
method managed in ways inspection related to
Criticality
[Years]
Element no.
maintenance stategy strategy minimize repair
Vulnerability
RCM or RBI
[∆tI] (Years)
other than strategy concrete and
time (if critical)
maintenance? steel is not
listed)
Key parameter
Recommendations - to monitor
Spare part
Can failure be Recommended (Usual signs of
Mitigation measures Recommended Comments to requirement in
Element Name Functional Failure Detection eliminated or principal degredation
other than Maintenance Inspection/maintenance order to
method managed in ways inspection related to
Criticality
[Years]
Element no.
maintenance stategy strategy minimize repair
Vulnerability
RCM or RBI
[∆tI] (Years)
other than strategy concrete and
time (if critical)
maintenance? steel is not
listed)
Corrosion is a consequence
Loss of protection to steel or Periodic
of a failing protection
concrete structures. Permeability of To be designed easy for Periodic corrective/prev
system. Time for damage
11.02 Roadway - Surfacing surfacing causing corrosion of steel 3 1 Yes Inspection winter maintenance 5 5 RBI (5) - Inspection every entive
tolerance is therefore set to
box girder or degradation of tasks. 5 years maintenance
5 years, which is the same as
concrete box girder. (PIBM)
the protection system.
Immediately
Eg. trafic light, navigation plan or perform Spare parts
Periodic
ligthing for ships and flights Malfunction, rodent bites, Wear corrective/perio Essential electrical part should be Alarm if not
13.01 3 4 Yes Inspection Back up system 0,001 2 RCM (1) - Inspection every
, essential monitoring and tear. dic preventive should be checked daily stored at site for working correct
2 years
systems maintenance a quick fix
(CBM)
Key parameter
Recommendations - to monitor
Spare part
Can failure be Recommended (Usual signs of
Mitigation measures Recommended Comments to requirement in
Element Name Functional Failure Detection eliminated or principal degredation
other than Maintenance Inspection/maintenance order to
method managed in ways inspection related to
Criticality
[Years]
Element no.
maintenance stategy strategy minimize repair
Vulnerability
RCM or RBI
[∆tI] (Years)
other than strategy concrete and
time (if critical)
maintenance? steel is not
listed)
Immediately
Failing sensors can be
plan or perform
Redundancy for Periodic detected by missing output Essential spare
Malfunction & Wear and tear & corrective/perio Alarm if not
18.01 SHMS 2 3 Yes Inspection System Check essential sensors 0,003 2 RCM (2) - Inspection every or deviating output. Periodic part should be
Rodent bites dic preventive working correct
should be established 2 years inspections deals with the stored
maintenance
overall health of the system
(CBM)
Key parameter
Recommendations - to monitor
Spare part
Can failure be Recommended (Usual signs of
Mitigation measures Recommended Comments to requirement in
Element Name Functional Failure Detection eliminated or principal degredation
other than Maintenance Inspection/maintenance order to
method managed in ways inspection related to
Criticality
[Years]
Element no.
maintenance stategy strategy minimize repair
Vulnerability
RCM or RBI
[∆tI] (Years)
other than strategy concrete and
time (if critical)
maintenance? steel is not
listed)