ETH 7000004839 Part1
ETH 7000004839 Part1
TENDER DOCUMENT
Proposed Construction of Multi-Specialty Hospital
at land bearing C.T.S. No – 681A/8B, 681A/3,
681A/4 of village Nahur in S-Ward, Bhandup,
Mumbai
Page 1
NAME OF PROJECT: - PROPOSED MULTI-SPECIALITY BHANDUP
HOSPITAL AT LAND BEARING C.T.S.NO681A/88,681A/3,681A/4 OF
VILLAGE NAHUR IN S-WARD, BHANDUP MUMBAI
Page 2
SHASHI PRABHU & ASSOCIATES
H T P A N E L
1 SCOPE
Shop Drawings:
Before starting the work, the contractor shall submit to the Construction
Manager/Consultants for his approval in the prescribed manner, the
shop/execution drawings for the entire installation.
Large scale drawings showing fixing detail equipment and showing coordination
with other services.
Page 3
SHASHI PRABHU & ASSOCIATES
Instruction/Maintenance Manual:
The Contractor shall prepare and produce instruction, operation and maintenance
manuals in English for the use, operation and the maintenance of the supplied
equipment and installations, and submit to the Construction
Manager/Consultants in (8) copies at the time of handing over. The manual shall
generally consist of the following:
Operating instructions.
Manufacturers catalogues.
Drawings.
Completion Certificate:
Guarantee:
At the close of the work and before issuance of final certificate of completion by
the Construction Manager/ Consultants, the contractor shall furnish written
guarantee Indemnifying the Client against defective materials and workmanship
for a period of one year after completion. The contractor shall hold himself fully
responsible for reinstallation or replacement, free of cost to Client, the following:
Page 4
SHASHI PRABHU & ASSOCIATES
Staff:
The contractor shall employ competent fully licensed qualified, full time
ELECTRICAL WORKS engineers to direct the work of ELECTRICAL WORKS
installation in accordance with the drawings and specifications.
The engineers shall be available at all times at site to receive instructions from the
Construction Manager., in the day to day activities throughout the duration of
contract. The engineer shall correlate the progress of the work in conjunction with
all the relevant requirement of the supply authority.
The Contractor shall at his own cost provide for the protection and safety of the
persons working in the area, safety barriers around all openings in every location
and at the periphery and edges of all slabs, staircases and stairwells, lift shafts,
ducts etc., all to the approval and satisfaction of the Construction Manager.
However, contractor shall take appropriate safety precautions suitable for specific
locations/ situations and as instructed by the Construction Managers.
The Contractor shall, in general, be fully responsible for all matters with regard to
every form of safety during construction and in connection with the execution of
the Works, and the Contractor shall take all necessary precautions and provide at
his cost everything necessary to ensure such safety at all times. Should any
accidents occur due to the Contractor's failure to comply with such safety
requirements and to take all other safety measures necessary, the Contractor
shall be fully responsible for all such accidents and he shall bear and pay for all
costs and damages in connection therewith and as a consequence there of.
Disposal Of Rubbish From The Works And The Site And Provision Of Safety
Netting/Screens By Contractor:
The Contractor shall at all times keep the Works and the site in clean, neat and
tidy condition. All rubbish from the Works and the site shall be collected and
deposited in large bins provided on the site for such purpose by the Contractor at
his own cost. The rubbish from such bins shall be regularly carted away by the
Contractor to rubbish tips and dump yards beyond the site.
At no time or stage shall any rubbish be thrown over the edges of slabs or through
any openings or shafts or ducts or stairwells.
The Contractor shall, at his own cost and to the approval and satisfaction of the
Construction Manager, provide safety netting/screens at the periphery of all slabs
and at all openings, shafts, ducts and stairwells and/or canopies to prevent any
rubbish or material falling over or into such areas and endangering the safety of
the persons working below. Should the Contractor fail to provide such safety
measures and to take other necessary precautions in accidents that may occur,
he shall bear all costs and damages as decided by Construction Manager in
connection therewith and as a consequence there of.
The Construction Manager shall have powers to withhold amounts from payment
certificates in case of Contractor's persistent noncompliance with provisions of
Contractor Signature MCGM
Page 5
SHASHI PRABHU & ASSOCIATES
The Client shall provide adequate storage/office space to the contractor for his
use. The space has to be maintained/constructed by the contractor as per his
usage requirements.
All spaces allotted to the contractor, as described above shall be vacated and all
structures removed from site at any time as and when required and directed by
the relevant authorities or by the Client, unconditionally and without any
reservation. The authorities or the Client will not be obliged to give any reason for
such removal. Upon receiving instructions to vacate the space, the contractor
shall immediately remove all his structures, materials, etc., from the spaces and
clear and cleanup the site to the satisfaction of the Construction Manager.
It shall be the specific responsibility of the Contractor to safeguard the site and
ensure that no illegal encroachments are made by outside elements within the
area allotted to the Con tractor. Upon completion of the work or earlier as required
by Client/Authorities, the Con tractor shall vacate the land totally without any
reservations. Necessary Bond to this effect on a stamp paper shall be signed by
the contractor in a prescribed form.
In order to achieve the milestone and completion dates and to keep pace with the
approved construction programme, the Contractor shall be permitted to carry out
his work beyond the normal working hours or in shifts. The Contractor shall be
responsible for obtaining any necessary permission from the relevant authorities
that may be required for him to carry out the work beyond the normal working
hours or in shifts. Also, the Contractor shall give prior notice to and make
arrangements with the Construction Manager for the supervision of work carried
out beyond the normal working hours or in shifts. The Contractor shall make his
own arrangements in respect of the provision of adequate lighting and any other
facilities that may be required for carrying out the work beyond the normal
working hours or in shifts. No extra payments shall be made to the Contractor for
or in connection with any such overtime or shift work. The Contractor will not be
required to bear the overtime expenses of the Construction Manager in respect of
the supervision of such overtime or shift work of the Contractor.
The period and time limit for Completion of the Works shall be as per client’s
requirement from the date of issue of Work Order to commence works or handing
over of site in respect of the award of Contract. This time period shall be inclusive
of the mobilization period and monsoon period.
Contractor Signature MCGM
Page 6
SHASHI PRABHU & ASSOCIATES
It is the intent of the Client, Architect and Construction Manager that this project
will be executed in a spirit of team and full professional integrity. Contractor is
expected to cooperate with all the agencies involved in the project to fulfill this
objective.
The contractor shall clearly indicate the list of materials proposed to be used by
him & enclose the same with the tender.
Before procurement, Contractor will discuss with Client for preferred makes.
Reference Points:
Contractor shall provide permanent bench marks, flag tops and other reference
points for the proper execution of works and these shall be preserved till the end
of the work.
All such reference points shall be in relation to the levels and locations, given in
the architectural and ELECTRICAL WORKS drawing.
Reference Drawings:
The Contractor shall maintain one set of all drawings issued to him as reference
drawings. These shall not be used on Site. All important drawings shall be
mounted on boards and placed in racks indexed, no drawings shall be rolled.
All correction, deviations and changes made on the site shall be shown on these
reference drawings for final incorporation in the completion drawings. All
changes to be made shall be initialed by Engineer in Charge or Architect.
Vendor shall prepare Shop Drawings with all details after checking the feasibility
at Site which shall be approved by the Consultants before execution. No work
will be carried out without approval of Shop drawing by the Consultant.
Handing Over:
Page 7
SHASHI PRABHU & ASSOCIATES
Complete certificate has to be obtained from the consultant to certify the quality
of work and performance of the system.
Contractor has to handover operator manual of the system with catalogue and
Technical Data of equipment supplied.
The switch gear panel and components mounted shall confirm to the following
latest revisions of relevant Indian or equivalent British or International standards.
In case of any conflict between the following standards and this specification, the
requirements of this specification shall prevail.
IS: 2516(Part1 sec.2) Specifications for circuit breakers. General & Definitions(for
voltages above 1000V A.C.).
IS: 4710 Switches and switch isolators (above 1 KV but not exceeding
11 KV.)
IS: 3427 Degree of protection provided for metal enclosed switch gear
and control gear.
Page 8
SHASHI PRABHU & ASSOCIATES
IS: 3618 Phosphate treatment of iron and steel for protection against
corrosion.
IS: 5 Painting.
1.2 CONSTRUCTION:
1.2.1 The switch gear panel shall be metal enclosed, rigid, free standing, floor mounted,
draw out, dead front type and fabricated from standard prefabricated, cold rolled
sheet steel units. The vertical units shall be assembled in such away that uniform
height can be achieved while line up of each vertical units on floor.
1.2.2 The minimum thickness of the sheet steel shall not be less than 2.5 mm.
Necessary stiffeners shall be provided.
1.2.3 The switchboard shall be totally enclosed, vermin -proof, except bus bar
compartment. Degree of protection of enclosure shall be minimum IP56 as per IS:
3427. If necessary, openings for natural ventilation louvered with wire mesh shall
be provided. For bus bar compartment wire mesh shall be such as to protect
against object of 1.0 mm size and above.
1.2.4 All doors, removable covers, gland plates and other openings shall be gasket all
round the perimeter with neoprene gaskets.
1.2.5 Switch gear shall be provided with an ISMC channel as a base frame. Minimum
height of the base frame shall be of 100 mm.
1.2.6 All doors shall be supported by strong hinges of concealed type and braced in
such a manner as to ensure freedom from sagging, bending and general
distortion of panel or hinged parts.
1.2.7 Switchboards shall be suitable for site conditions as specified in the Technical
Data Sheet.
1.2.8 Each unit of the switch gear shall be provided with necessary internal sheet metal
barrier to form separate components for buses/Indicating instruments/protective
relays/control and power cable connection etc. Compartment for cable connection
shall allow adequate space for cable pulling, termination and connection work
with energised switch gear. Suitable arc propagation barrier shall also be
provided. Preferably independent pressure release valves shall be provided for
different compartments. Terminal strips for outgoing control cable connection
Page 9
SHASHI PRABHU & ASSOCIATES
1.2.9 After isolation of the power and control connection of a circuit, it shall be possible
to safely carry out maintenance or a repair work in a compartment with the bus
bars and adjacent circuits alive.
1.2.10 At a future date, it shall be possible to extend the switch gear in either direction.
Ends of the bus bars shall be suitably drilled for this purpose. Panels at the
extreme ends shall have openings which shall be covered with plate screw to the
panel with necessary gaskets.
1.2.11 Switch gear shall be vertical isolation and horizontal draw out type.
1.2.12 All draw out circuit breaker trucks/trolley of the same rating for all outgoing
breakers shall be identically wired/equipped for complete interchangeability at
site. `Service', `Test', `Draw Out' positions of the draw out carriage of the
switchboard shall be provided. Automatic safety shutters shall be provided to
ensure the inaccessibility of all live parts after the breaker is drawn out.
1.2.13 Dummy panels required for rear extensions for cable terminations or to mount the
components shall be included in the offer and details of each type of such panels
shall be furnished along with offer.
It shall not be possible to draw out the carriage with circuit breaker closed. The
breaker feeder trolley shall remain inside the cubicle even in the `drawout'
position. There shall be distinct overall door for the breaker compartment and it
should be lockable. Suitable interlocks to prevent following faulty operations shall
be provided.
1.3.4 Pulling out of auxiliary circuit plug with breaker in service position.
1.3.5 Pushing in breaker to service position with auxiliary circuit plug not in position.
1.3.6 Opening of compartment door with isolating switch in ON position and vice versa.
Necessary mechanical and electrical interlocks between H.T. and L.T. switch gears
shall be provided in closing and tripping circuits of breakers which shall be a part
of the specification. The total bill of material and scheme designed by the
manufacturer will be subject to client/consultant's approval and any addition or
deletion shall be binding to the manufacturer on the basis of unit rates available
in the offer.
1.4 ACCESSIBILITY:
Contractor Signature MCGM
Page 10
SHASHI PRABHU & ASSOCIATES
1.4.2 Unused CT secondary terminals must be short circuited and wired to the terminal
block. All terminals shall be shrouded with plastic covers to prevent accidental
contact.
1.5.1 The switchboard shall comprise 3 phase bus bars as indicated in the Technical
Data Sheet or SLD which shall extended through all units of the switch gear. All
phase bus bars shall be of uniform cross section throughout the switch gear and
shall be sized to carry continuously the current specified in the Technical Data
Sheet or SLD. Bus bars shall be housed in a separate air insulated chamber and
shall be accessible for inspection only with special tools. Wire guards/mesh shall
be provided inside the sheet steel enclosure to allow visual inspection of bus bars,
CT's, PT's and cable terminations and to avoid accidental touch when rear cover is
removed.
1.5.3 Bus bars shall be supported at regular intervals and both, bus bars and the
supports shall be adequately sized and braced to withstand the specified short
circuit level without permanent deformation. Dynamic stresses shall be calculated
on the basis of the specified peak short circuit currents. All bus supports shall be
of non carbonizing material resistant to acids and alkalis and shall have non
hygroscopic characteristics such as SMC, DMC epoxy bonded fiber glass.
1.5.4 Thermal design of the bus bars shall be based on installation of the switch gear in
ventilated conditions. The cooling air volume shall take into account only the bus
enclosure.
1.5.5 The maximum operating temperature of the bus bars at the maximum design
temperature inside the panel shall be as per IS: 1272 and IEC 298
1.5.6 Bus bars shall be sleeved with colour coded type sleeve having insulation level
suitable for nominal system voltage. If the insulating sleeve is not coloured bus
bar shall be colour coded with coloured bands at suitable intervals.
Page 11
SHASHI PRABHU & ASSOCIATES
1.5.7 All bus bars joints and bus tap joints shall be of the bolted type and shall be
shrouded. Spring washers shall be provided to ensure good contact at the joint
locations and suitable contact grease shall be applied just before making a joint.
1.5.8 Positive/live terminal or bus bar shall be located at the top or on the left for
vertical and horizontal layout respectively.
1.5.9 Sequence of Red, Yellow, Blue phases shall be left to right and top to bottom for
horizontal and vertical layout respectively.
1.6.1 The incoming and outgoing power cable connection shall be through
PILC/XLPE/PVC cables of various sizes as indicated in the Technical Data Sheet
or SLD. Ample space for connection for these cables shall be provided at the rear
of the switchboard. In order to avoid accidental contact in the cable compartment
while carrying out inspection by opening the back cover, a removable expanded
metal barrier shall be provided in the cable compartment.
1.6.2 The cable entry of the switchboard shall be from the bottom.
1.6.3 Cable lugs and the requisite bushes for sealing power cable entries shall be
supplied along with the switchboard.
1.6.4 `Cupal' washers shall be provided for copper busbar to aluminum cable
terminations.
1.6.5 The switchboard shall be supplied complete with supports for clamping outgoing
and incoming cables. Terminal blocks shall not be used to support cables. The
distance available between cable gland plate and terminal lug shall not be less
than 750 mm for switchgear upto 11 KV. cables.
1.6.6 In case, cable termination cannot be accommodated in side the panel, a suitable
box for mounting at the rear side and at the bottom of panel shall be supplied.
Earth strip shall also be brought to this box. In lieu of this a dummy panel may be
provided.
1.6.7 The individual switchgear panel shall have adequate space and terminal busbar
clearance for accommodating no. of cables as specified in Technical Data Sheet
and SLD. The type of cable termination units to be considered shall be heat
shrinkable type.
1.7.1 Inside the cubicle the wiring for control, indication, signaling, protection and
instrument circuits shall be done with PVC insulated stranded conductors. The
insulation grade shall be 1.1 KV. The wiring shall preferably be enclosed in plastic
channels or neatly bunched together.
1.7.2 10% spare terminals shall be provided on each terminal block. Conductors shall
be terminated with adequately sized compression type copper lugs for connection
to equipment terminal block. Terminal block shall be of Elemex/Connect well
Contractor Signature MCGM
Page 12
SHASHI PRABHU & ASSOCIATES
make. All auxiliary equipments terminals shall be made with pressure type
terminals. Sufficient terminals shall be provided on each terminal block to ensure
that not more than one outgoing wire is connected per terminal. Terminal strips
shall preferably be separated from power circuits by metal barriers or enclosures.
All spares contacts of aux. relays, timers etc. shall be wired upto the terminals.
1.7.3 Each wire shall be identified at both the ends by, correctly sized PVC ferrules.
Shorting links shall be provided for all CT terminals.
1.7.4 For CT circuits 2.5 sq. mm copper conductor shall be used. Other control wiring
can be with 1.5 sq. mm copper conductors.
1.7.5 Control cables shall enter the switchgear from the bottom/ top. It shall be
possible to have the control cable entry from both the left and right side corners at
the front portion of the switchgear without cutting any standard part of for these
cables are also included in the scope of supply of the switchboard. The cable
glands shall be compression type, supporting facilities shall be provided for
clamping the control cables. All control cables shall be with 2.5 sq. mm Cu
stranded conductors.
1.7.6 All inter panel control wiring shall be done by the switchgear supplier. The inter
panel wiring shall be taken through PVC sleeves or suitable grommets. Multi pin
plug shall be provided and should have scraping earth terminal.
1.7.7 Control cable cutout and gland plate shall be provided preferably at the place
where the power cable cutout will be provided. Gland plate for the control cables
shall be separate from those provided for the power cables.
Breaker tripping and closing devices shall be operated on D.C. supply. The rated
D.C. voltage shall be as specified in the Technical Data Sheet. The supply for
breaker opening, closing and indication devices shall be provided as under:
a) One D.C. feeder shall be provided for each bus section. The Bus coupler panel
may be fed from any of the two supplies.
b) One separate 240 V AC supply shall be provided for space heater etc.
Mechanical indication for breaker positions such as ON, OFF, spring charged, test
position/Service position shall be provided. Various Electrical indications with
colours are indicated below shall be provided.
Page 13
SHASHI PRABHU & ASSOCIATES
1.9.1 Continuous earth bus-bar running throughout the length of the switchboard
shall be provided. All doors and movable parts shall be connected to the earth bus
with flexible copper connections. Provision shall be made to connect the earthing
busbar to the plant earthing grid at two ends. All non-current carrying metallic
parts of the equipment shall be earthed . Earth bus shall be brought back to cable
compartment and earthing bolts shall be provided to ground cable Armour.
Mating surfaces of all bolted parts shall be specifically zinc passivated to ensure
continuity between them.
1.9.2 The material of the earth bus shall be copper or equivalent size of aluminum. The
earth bus size shall be minimum 180 mm2 copper upto short circuit withstand
capacity of 31.5 KA and 300 mm2 above 31.5 KA.
1.9.3 All instruments, relays and other components shall be connected to earth busbar
by means of 650 V grade, PVC insulated, stranded tinned copper conductor of 2.5
sq.mm.
1.10.1 A nameplate with the switchgear designation at the top of the central panel and
separate nameplate giving feeder details shall be provided at front and rear side of
each panel.
1.10.2 Name plates shall be provided for each equipment ( Lamps, PBs, Switches, Relays,
Auxiliary contactors etc.) mounted on the switchboard. Special warning plates
shall be provided on all removable covers or doors giving access to high voltage
cables, bus bars. Special warning label shall be provided inside the switchboard
also, wherever considered necessary. Identification tags shall be provided inside
the panels matching with those shown on the circuit diagram.
1.11.1 All metal surfaces shall be thoroughly cleaned and digressed to remove mill scale,
rust, grease and dirt. Fabricated structure shall be pickled and then rinsed to
remove any trace of acid . The under surface shall be prepared by applying a coat
of phosphate paint, and a coat of yellow zinc chromate’s primer. The under
Page 14
SHASHI PRABHU & ASSOCIATES
surface shall be made free from all imperfections before undertaking the finishing
coat.
1.11.2 After preparation of the under surface, the switchboard shall be spray painted
with two coats of final paint. Colour shade of final paint shall be smoke gray
shade no. 631 as per IS: 5 unless otherwise specified. The finished panels shall be
dried in stovings ovens in dust-free atmosphere. Panel finish shall be free from
imperfections like pinholes, orange peels, runoff, paint etc. The supplier shall
furnish painting procedure details along with the offer.
1.11.3 All unpainted steel parts shall be cadmium plated or suitable treated to prevent
rust corrosion. If these parts are moving elements, then these shall be greased.
1.12.1 Each vertical cubical shall be provided with space heater to prevent moisture
condensation and maintain required temperature. The space heaters shall be
located at the bottom of the switchboard and shall be controlled through a
thermostat with an adjustable setting with single pole MCB with overload and
short circuit release in the phase, link in the neutral. The thermostat shall
preferably be located in the metering/ relay chamber.
1.12.2 Space heater shall be of strip type rated for operation on a 240 V, single phase, 50
Hz., A.C. supply system.
1.13.1 The switchboard shall be suitable to be installed on a base frame supplied in one
piece along with foundation bolts. These base channels shall be dispatched two
months in advance from the date of dispatch of switchboard so that they can be
buried and grouted in the concrete floor. Ample dimensioned oblong holes shall
be provided at the bottom of all the switchboards for their installation of base
frame. In addition, the switchboard shall have an additional base channel at the
bottom with smooth surface.
1.14 BREAKERS:
1.14.1 Vacuum circuit breaker shall be used in the switchboard. Exact type and rating
shall be as indicated in the Technical Data Sheet.
1.14.2 10% spare VCB bottles of each ratings shall be supplied along with the
switchboard.
1.14.3 Vacuum circuit breaker shall be designed with low switching over voltage level
and long switching life. The interrupter shall be leak free with a target value of
vacuum life as 25 years.
1.14.4 The breakers shall have at least 8 NO + 8 NC spare auxiliary contacts. If these are
not available an auxiliary contactor shall be used to multiply the auxiliary
contacts of the breakers. All auxiliary contacts shall be wired to the terminal
block. Auxiliary contacts and limit switches shall be in dust tight enclosures.
Page 15
SHASHI PRABHU & ASSOCIATES
1.14.5 The breaker shall have motor operated spring charged mechanism. In addition to
this, it shall be possible to charge the springs manually, if required. In case the
limit spring fails to cut out the spring charging motor when the springs are fully
charged the motor shall be automatically decoupled and annunciation for this
shall be provided. The control circuit shall be suitable for local as well as remote
control. Breaker shall trip free and shall have an anti pumping device. Breaker
operating duty shall be 0-3'-CO-3'-CO except for switchgear line up having motor
feeders stage wise, receleration feature in which case the duty shall be 0-0.3"-
CO-3'-CO. Whenever a PT is mounted on the breaker carriage all auxiliary wiring
shall be done in PVC flexible conduits.
1.14.6 Adequate provision shall be made in Vacuum circuit breaker for motor switching
to limit the over voltage.
1.14.7 Mechanical trip push buttons shall be provided for all the breakers. Mechanical
closing device will not be acceptable for motor feeders. Complete motor assembly
should have interchangeability with identical rating of the breaker. Each motor
breaker feeder shall be provided with an operation counter.
1.14.8 All integral earthing system or separate earthing carriage be provided. After
withdrawing the circuit breaker, this can be inserted to facilitate earthing of the
cables. Unit rate in the panel shall be furnished.
Current transformers shall generally conform to IS: 2075. and of cast resin type
and shall be mounted on the switchgear stationary part. The C.T. ratings shall
be as shown in the Technical Data Sheet or SLD. For general guidance, the
protective current transformers shall have an accuracy class `5P' and an accuracy
limit factor greater than `10'. Low reactance C.T.s shall be used for protection.
Current transformers for instruments shall have an accuracy class 0.5 and an
accuracy limit factor less than 5.0. If a metering load is fed from a protection C.T.,
suitable 1/1 or 5/5 ratio interposing C.T.s shall be used.
a. The voltage transformers shall be cast resin and draw out type and provided with
primary and secondary fuses.
b. The draw-out mechanism shall disconnect the bus bars and V.T. primary and
secondary terminals shall be earthed. The primary connection shall be
disconnected before the V.T. or its primary fuses become accessible.
c. The voltage transformers shall have an accuracy class 1.0 from 10% to 120% of
normal voltage.
d. Secondary and tertiary windings of voltage transformer shall be rated for a three
phase line to line voltage of 110 V except as noted.
Page 16
SHASHI PRABHU & ASSOCIATES
These shall be of moving iron type. The accuracy class shall be 1.0 as per IS:
1248. The range shall be as indicated in the Technical Data Sheet or on the SLD.
Ammeters for motor feeders shall have non linear compressed scale at the end to
indicate motor starting current.
Unless stated otherwise these shall be of direct writing type with automatic chart
by means of a synchronous motor. The minimum chart length shall be of 24
hours. The chart speed shall be 30 mm/hour.
The KWH meter shall be 144 mm x 144 mm square, flush mounted, preferably in
a draw-out case. It shall be suitable for operation on 3 phase 3 wire system.
These shall be direct reading or digital type square pattern 144 mm x 144 mm
size, suitable for flush mounting and shall operate off a V.T. secondary voltage of
110 volts. The standard range shall be 45-50-55 Hz.
The power factor meter shall also be square pattern 144 mm x 144 mm size,
suitable for flush mounting and of digital type. The meter shall operate off 110
volts C.T. secondary voltage. The C.T. secondary current shall be as shown on the
SLD or Technical Data Sheet. The standard range shall be 0.5-1.0-0.5.
Page 17
SHASHI PRABHU & ASSOCIATES
All tripping relays shall be lockout type with hand reset contacts and shall be
suitable to operate off the specified d.c. voltage. These relays shall have self coil
cut - off contacts and shall be provided with hand reset operation indicators.
Tripping relays will be acceptable in non draw-out cases. The number of contacts
shall be as shown on the approved schematic drawings.
All protective relays shall be back connected, draw-out type, suitable for flush
mounting and fitted with dust tight covers. Alternatively, `plug in' type of relays
will also be acceptable. The relay cases shall have provision for insertion of test
plug at the front for `testing' and calibration' using an external power supply,
without disconnecting the permanent wiring. It shall be possible to short the
C.T.'s through the test plugs. Non protection relays can be in fixed execution.
All relays shall preferably be mounted in front of the panel and shall be as
specified in the Technical Data Sheet or SLD. The cur rent and voltage coils shall
be rated as specified.
All measuring relays shall have `built in' flags to indicate relay operation. It shall
be possible to reset the flag without opening the relay case. Anti fungus treatment
shall be provided for all relays.
Red push buttons shall be on the left side and green push buttons on the right
side. Push button ratings shall be 5A at 240 V AC or 2A at 110 V DC (inductive
load). Emergency stop push buttons shall be lockable in the operated position.
The key shall be released from the push button in both `Released' and `Operated'
positions and operation of the push button shall be possible in the key release
position. Push button knobs for emergency stop push buttons shall be released to
prevent accidental operation.
All control switches shall be rotary, back connected type having a cam operated
contact mechanism. Phosphor bronze contacts shall be used on the control
switches. Unless otherwise stated, circuit breaker control switches shall be 3
position spring return to `neutral' from both `ON' and `OFF' positions. They shall
have `pistol grip' handle. Number of ways, locking system, lost motion device if re-
quired etc. Two spare ways shall be provided on these switched.
Contractor Signature MCGM
Page 18
SHASHI PRABHU & ASSOCIATES
Ammeter and Voltmeter selector switches shall have ` make before break' feature
on its contacts. The selector switch shall generally have four positions, three for
reading three phase currents and phase to phase voltages respectively and the
fourth as off position.
1.18.2 Tests shall be carried out at the manufacturers' works under his care and
expense.
1.18.3 All routine tests as specified by the applicable standard code shall be conducted.
Type test certificates for the switchgear panel and CB from a recognized testing
organization shall be furnished with the offer. If client / consultant wishes type
test shall be carried out at laboratory in the suppliers region in clients /
consultants presence. The supplier shall also submit a list of guaranteed technical
particulars with the offer.
1.25 In addition specific tests shall be conducted to check mechanical and electrical
operation and switchboard wiring to this specification and approved schematic
drawings.
Page 19
SHASHI PRABHU & ASSOCIATES
b) Manual and electrical operation of CB/Relays shall be checked under the worst
conditions of auxiliary supply voltage.
c) Dry insulation test with power frequency voltage shall be conducted for the main
and auxiliary circuits.
d) Insulation resistance of the main and auxiliary circuits shall be checked.
e) Operation check shall be carried out for every control function as per the
approved schematic diagrams by manually stimulating the fault conditions and
operation of control switches/relays etc.
Type tests : impulse dielectric tests, power frequency dielectric tests, temperature
rise tests, mechanical operating tests, verification of degree of protection,
verification of electromagnetic compatibility.
1.19 DRAWINGS:
1.19.1 The manufacturer shall develop his own general arrangement and schematic
drawing adding necessary auxiliary devices, accessories, components particular to
supplied equipments etc. which are required for safe, convenient, efficient and
proper operation of the HT switchgear.
1.19.2 Manufacturer shall submit for owner/consultant's approval the single line
diagrams, general arrangement drawings, flooring and mounting detail drawings
and schematic diagrams.
Page 20
SHASHI PRABHU & ASSOCIATES
1.19.4 The manufacturer shall submit all the drawings in four copies for
owner/consultant's approval.
1.19.5 Manufacturer shall submit four prints and reproducible of schematic, GA and
wiring diagrams in final.
1.20 GUARANTEE:
The switchboard shall be guaranteed for trouble free operation for a period of 12
months from the date of commissioning or 30 months from the date of arrival at
site, whichever is earlier. Any defects discovered during this period shall be
rectified free of charge.
Page 21
SHASHI PRABHU & ASSOCIATES
busbars, droppers,
connectors and contact at
continuous current rating
under site reference
temperature
15 Busbar material Copper (tinned
Electolytic )
16 Cable entry Side
17 Thickness of sheet in mm
a. cold rolled Frame : 3
b. frame enclosure 2.5
c. Doors / Covers / Partitions 2.5
18 Colour finish shade 2.5
a. Interior Glossy white
b. Exterior Light gray semi
grade glossy
shade, epoxy
type 631, IS : 5
19 Earthing Bus
19.1 Material Copper
19.2 Size Suitable for 25
KA for 1 sec.
20 Earthing conductor
21.1 Material Copper
21.2 Size 30 x 6 mm
22 Bus bar insulation Air insulated,
PVC heat
shrinkable type
sleeved
23 Circuit Breakers
23.1 Type Vacuum
23.2 Voltage, frequency and no. 11 kv, 50 Hz., 3
of phases ph
23.3 Rated Operating duty 0-3’-CO-3’-CO
23.4 Rated current at site ( 400A
reference ambient temp)
23.5 Rated breaking capacity 350 MVA, 250
KA (rms)
23.6 Rated making current 47 KA ( peak)
23.7 Short time current 250 KA (rms)
withstand 4 for 1 sec.
duration
23.8 Total break time Less than 5
cycles
23.9 Type of operating suitable Manually and
for manual motor
mechanism
charged spring
and remote trip
and close
operations
Contractor Signature MCGM
Page 22
SHASHI PRABHU & ASSOCIATES
Page 23
SHASHI PRABHU & ASSOCIATES
Page 24
SHASHI PRABHU & ASSOCIATES
Page 25
SHASHI PRABHU & ASSOCIATES
core – 1
38.3 Accuracy class of protection 5 P 10
core – 24
39 Relays
39.1 T.P. IDMTL relay with 2 1 No.
O/C + 1E/F Element type
equivalent to CDG-61 of EE
make
39.2 D.C. fail alarm relay 1 No.
equivalent to VAA-21 of EE
39.3 High speed tripping relay 1 No.
equivalent to VAJH -13 of
Eeh
39.4 Antipumping relay 1 No
equivalent to VAA-11 of EE
4
39.5 Auxiliary relay for buccholtz 1 No.
alarm and trip relay
equivalent to VAA -21 of EE
make
39.6 Auxiliary relay for winding 1 No.
temperature alarm and trip
relay equivalent to VAA-21
of EE make
40 30 Volts DC shunt trip coil 1 No.
41 D.C. fail indication lamp 1 set
with ACCEPT and RESET
push buttons
42 Emergency trip lockable 1 No.
push button with keys P
43 Trip circuit healthy 1 set
indication lamp with push
button
44 Auto trip indication 1 No.
45 Spring charged indication 1 No.
46 Common alarm trip and 1 No.
non trip scheme with
ACCEPT, RESET push
buttons, relays and hotter
for audio indication
47 Space heater with ON-OFF 1 set
MCB, HRC fuses and
thermostat
48 Power pack unit for 30 volts 1 set
D C Output
49 Adopter / Dummy panel Quantity & unit
rate shall be
furnished by the
bidder
50 Prices for spares required Quantity & Unit
for 2 years maintenance
Page 26
SHASHI PRABHU & ASSOCIATES
Page 27
SHASHI PRABHU & ASSOCIATES
2.1 SCOPE
Page 28
SHASHI PRABHU & ASSOCIATES
2.3 RATING
The rating, voltage ratio, vector group and type of cooling of transformer, tap
changing gear shall be as specified in the enclosed data sheet.
It shall be possible to operate all transformers as per loading guide IS: 6600 up to
overload of 150% and there shall be no limitations imposed by bushing, tap
changes, auxiliary equipment etc. to meet this requirement.
A General:
B Core:
The magnetic circuit shall be constructed from high grade cold-rolled, non-ageing
grain oriented low loss high permeable silicon steel laminations and shall be of
‘Core’ type. The core shall be painted with suitable resin to protect it against
corrosion and other parts shall be hot dip galvanized. The lamination shall be free
of all burrs and sharp projections. The lamination Grade shall be indicated in the
Technical Data and shall be subject to the Engineer’s approval.
The joints of limbs and yokes shall be designed and constructed to keep the no
load losses and the hot spot temperature in the magnetic core as well as the noise
level as low as possible.
The insulation structure for the core to bolts and core to clamp plates shall be
such
All steel sections used for supporting the core shall be non-magnetic. They shall
be thoroughly shot or sand blasted, after cutting, drilling and welding.
Page 29
SHASHI PRABHU & ASSOCIATES
The design of the magnetic circuit shall be such as to avoid static discharges
development of short circuit paths within itself or to the earthed clamping
structure and production of flux component at right angles to the plane of lamination's
which may cause local heating.
The finally assembled core with all the clamping structures shall be free from
deformation and shall not vibrate during operation.
The core clamping structure shall be designed to minimize eddy current loss and
bolts shall not pass through the lamination for any purpose whatsoever. Fiber
glass or equivalent tapes of adequate strength shall be used for clamping the core
through and approved procedure.
The core shall be provided with lugs suitable for lifting the complete core and coil
assembly.
C Internal Earthing:
All internal metal plates of the transformer shall be earthed at one point only. The
magnetic circuit shall be connected to the clamping structure at one point only.
The frame work and clamping arrangements of core and coil shall be securely
earthed by copper strip connection to the main frame and enclosure. Two earthing
terminals shall be provided on the frame for external earthing. The terminals shall
be suitable for the earthing conductor of size indicated in the Data Sheets.
D WINDING
ii Both HV and LV windings of one phase shall be separately cast on one rigid
tubular coil co-axially arranged with no mechanical connection in between. The
complete coil assembly shall be cast under vacuum Into moulds, which forms the
insulation system. The coil shall be casted in epoxy resin with fiber glass covering
on the conductor to form a compact tubular spool for achieving high mechanical
strength.
iii The resin used for winding insulation shall be non-hygroscopic to prevent the
penetration of moisture into windings. It should be possible to energize the
Contractor Signature MCGM
Page 30
SHASHI PRABHU & ASSOCIATES
transformer without predrying even after a long period of service interruption. The
resin used shall be self-extinguishing and void free and shall be suitable for
temperate climate and 100% air humidity.
iv The transformer shall free of partial discharges atleast upto 1 .2 times of the rated
voltage and shall be able to withstand short circuits as well as switching and
atmospheric impulse as specified.
Adequate barriers shall be provided between windings and core as well as between
HV and LV windings.
E TANK
i Tank shall be made from good commercial grade low carbon steel and shall be of
welded construction.
iii The material used for gasket shall be cork neoprene or approved equivalent.
iv Tank shall be provided with lifting lugs a minimum of four jacking lugs and
suitable haulage holes.
v The tank cover shall be fitted with pockets for a thermometer and for the bulbs of
oil and winding temperature indicators. Protection shall be provided, where
necessary, for each capillary tube.
vi All wheels should be detachable and shall be made of cast iron or steel as
required.
vii Inspection cover on the top shall be provided (for small transformer of 500 KVA
and above). Tank cover shall be suitably sloped to prevent accumulation of
rainwater.
F Conservator:
Two nos. sensing elements (RTDs) shall be provided in each phase. The RTDs
shall be embedded at the hottest spot. The type of RTD shall be simplex and the material
shall be platinum
The cast coils are inserted on to the core limbs. The resin cast spacer blocks, end
blocks and separators are used as required. The end frames are then assembled.
H Terminals:
Page 31
SHASHI PRABHU & ASSOCIATES
The LT side terminals for the transformer shall be connected directly to switchgear
bus by direct bus bars. Horizontal/Vertical connections to busbars shall be
straight and without unnecessary joints. For bus connection the LV terminals shall be
extended upto the switchgear by bus bars. These bus bars will be connected to
the switchgear bus bars through copper flexible suitable for 100% rating. Formation
of star on the LV side is in the scope of transformers manufacture. The LV terminals
shall be located in such a manner to suit the level of LT switchgear bus bars (top entry).
Tap changing links provided on a separate mounting plate than on cast resin MV
windings so as to avoid any burnings of the links and resin arising out of loose
connections due to frequent changing of the links or due to human error.
The transformer shall have terminals designed to suite any special requirements
for BESCOM over & above IS. The HT/LT cable boxes shall be detachable type.
Flange for bus bar termination shall be provided at LT box as per the busbar used from
transformer to LT switchgear.
The neutral of the star connected winding shall be in two branches and shall be
brought out to two separate bushing terminals. One neutral bushing shall be
provided to facilitate leading the earth conductor down to the ground level. The
terminal shall be suitable for connecting to two separate earthing pads. Suitable
lugs shall be supplied by the Contractor for connecting the earthing conductors.
The second bushing shall be provided by side of the phase terminals for
connecting neutral to neutral bus bar in the switchgear buses. Location of the CTs for the
earth fault protection shall be in the common portion of the neutral i.e. before
bifurcation of the neutral in two branches
Page 32
SHASHI PRABHU & ASSOCIATES
B ON LOAD TAP Changer: OLTC with AVR and RTCC panel shall be provided if
required. REQUIRED FOR THIS APPLICATION.
A Transformer shall be fitted either with bushing insulators or with cable boxes, as
specified. Cable box should be air insulated type.
B Cable box shall have sufficient space to facilitate termination if more than one
cable terminations are specified, and to accommodate all cable joint fittings or
sealing ends including stress/cones etc. Links shall be provided of suitable length
for easy termination of cables. Necessary glands and cable sockets shall be
provided. Box shall have a drain plug to enable the filling medium removal
quickly. Armor earthing pads(2 nos.) shall be provided along-with cable
termination kit support.
C Non-magnetic cable gland plate shall be provided in the cable box, whenever
single core cables are specified.
A device for measuring the hot spot temperature of the winding shall be provided
winding temperature indicators consisting of:
Separate MCBs shall be provided for control supply (alarm and trip circuits).
Control supply shall not be taken from secondary side of the transformer
The contractor shall provide a marshalling box and shall mount the winding
temperature indicators in the marshalling box and shall marshalling to it all the
contacts/terminals of CT secondary and winding temperature indicators required
Contractor Signature MCGM
Page 33
SHASHI PRABHU & ASSOCIATES
for the transformer. The contractor shall provide the interconnection cabling
between the above equipment and the marshalling box. The winding temperature
indicator shall be flush mounted on the marshalling box door. This
interconnection shall be through wires in GI conduits or through armoured
cables. The insulation for the wires/cables shall be consistent with the ambient
temperature in the housing. Compression type brass cable glands required for
these interconnections shall be supplied by the contractor.
The marshalling box shall be mounted on the transformer housing. All doors,
covers and plates shall be provided with neoprene gaskets. Bottom of the
marshalling box shall be at least 600mm above floor level and provided with
removable bolted, un-drilled gland plate.
All contacts for alarm, trip and indication circuits shall be electrically free, wired
for auxiliary supply as specified and brought out to separate terminals at the
terminal block in the marshalling box. Terminal blocks shall be preferably of GE
power controls/Elmex. Terminals shall be rated for 10A. Wiring shall be with PVC
insulated, stranded, copper, conductor of sizes not smaller than 1.5 Sq mm for
control and 2.5 Sq mm of CT circuits. CT terminals shall be provided with
shorting facility. Engraved identification ferrules, marked to correspond with the
approved wiring diagrams shall be fitted to each wire. Ferrules shall be of yellow
colour with black lettering.
2.12 PAINTING
The inside of the enclosure shall be treated with matt paint of semi-glossy white.
Steel surfaces exposed to the weather shall be thoroughly cleaned and applied
first coat of zinc chromate, second coat of oil and weather resistant paint and final
coat of glossy oil and weather resistant non fading paint of shade no 632 of IS :5
(epoxy paint)
2.13 TESTS
A Routine tests : Routine test such as ratio test, open circuit test, short circuit
test, no load test, induced high voltage test, insulation resistant test,
measurement of winding resistance etc. shall be conducted as per IS : 2026.
Including CT polarity test, earth continuity test, OLTC operation test, oil dielectric
test.
Type tests : Type tests if required by client / consultant shall be carried out at
certified laboratory of the suppliers area shall be carried out. If not required by
client certificates for type test carried out for similar rating of transformer shall be
submitted by the supplier. Type tests shall be carried out for temp. Rise, impulse
voltage and short circuit analysis.
B Test certificates : Five copies of the routine test and type test certificates shall be
submitted for purchaser's record before dispatch of transformer, including test
certificates of bought out items.
2.14 INSPECTION
Page 34
SHASHI PRABHU & ASSOCIATES
2.15 GUARANTEE
Page 35
SHASHI PRABHU & ASSOCIATES
Any other information, if not specified above, but necessary for the evaluation of offer shall
be furnished by the supplier.
Page 36
SHASHI PRABHU & ASSOCIATES
1.0 GENERAL :
1.1 SCOPE :
This general specification together with the equipment sheets and attachments
defines the minimum requirements the design, performance, inspection, testing and
supply diesel engines for general industrial purposes.
1.2 The construction, design and rating of the diesel engine shall meet fully, the
requirements of the specified driven machine and the Vendor shall select and provide
the requisite ancillaries and controls with the diesel engine for its safe and
satisfactory operation.
1.3 No deviations or exceptions from this specification shall be permitted without the
written approval of the purchaser. Intended deviations supported by reasons there of
shall be separately listed by the vendor and submitted with the bid for the
consideration of the Purchaser.
1.4 Compliance with this specification shall not relieve the vendor of the responsibility of
furnishing equipment and accessories of proper design, materials and workmanship
to meet the specified operating conditions.
1.5 This general specification supplements the specific requirements contained in the
attached equipment data sheets. In the event of any contradiction between the two,
the information contained in the latter shall govern.
1.6 Other attachments of the Material Requisition from a apart of this specification.
1.7.1 The Net Calorific value of fuel is defined as the heat resulting from the complete
combustion of a unit quantity of fuel oil and air, without condensation of the water
vapor. A net calorific value of 9,720 Kcal/Kg (As per IS : 1460 Rev.2) shall be
considered while declaring the fuel consumption and for testing purposes.
1.7.2 The unit of horse power as defined in this specification is the metric horse power
equivalent to 4,500 n-Kg/Min. The horse power in F.P.S. system is equal to 1.014
metric horse powers.
1.7.3 Other terms used in this specification or in the equipment data sheets are as defined
in the latest edition of British Standard-5514.
2.1 The standard operating conditions shall be defined in the latest edition of B.S.-5514
unless otherwise mentioned specifically in the equipment data sheet.
Page 37
SHASHI PRABHU & ASSOCIATES
3.1 The diesel engine rating shall be the net output in brake horse power, which the
engine is capable of delivering continuously at the stated crank shaft speed under
the conditions specified under Clause 2.0 above, provided the engine is maintained
in good operating condition and is serviced / overhauled regularly as per the
schedules laid down by the Manufacturer.
3.2 No negative tolerance shall be allowed on the diesel engine rating specified by the
Vendor in the equipment data sheets.
3.3 The engine shall be capable of satisfactorily providing an output 10 percent in excess
of the continuous rating defined above, at the same speed for one hour in any period
of 12 hours consecutive running.
3.4 The normal power requirement of the engine driven radiator fan or the coolant pump
and the battery charging dynamo shall be clearly stated for the engine which is so
equipped.
3.5 Unless otherwise specified in the equipment data sheets, the site rating of the engine
shall be worked out considering the duration’s specified under the latest edition of
B.S.-5514 and the power absorb by all the engine driven ancillaries shall also be
deducted.
4.1 GENERAL:
4.1.1 The Diesel engine offered shall be of the regular production models of the
manufacturer for industrial applications and already type tested either at the
manufacturer's works or outside. The type test report shall be furnished to the pur-
chaser for his review if so desired.
In case the proposed engine model has not been type tested, vendor shall furnish
with the offer, a reference list of its existing industrial installation and at least three
of these engines, should have completed, 5,000 houses of running at site.
4.1.2 Unless otherwise specified in the equipment data sheets, the diesel engine shall be
provided with class A2 governing as per the latest edition of B.S. 5514.
4.1.3 The "Cyclic irregularity" of the diesel engine for direct coupling to an electric
generator, "angular deviation of p73 A.C. generators " driven by diesel engine for
parallel operation, and the "engine governor speed droop characteristics ", shall be
restricted to the values specified under the latest edition of B.S.-5514.
4.1.4 In case diesel engines are required to drive generators in parallel, the governor fuel
injection pumps provided should have identical characteristics and the speed-load
curves shall be made available to the purchaser's inspector for his scrutiny and
approval prior to load testing. The vendor shall maintain proper record for such
curves to ensure additional diesel engines if required in future with identical
characteristics, could be made available to the purchaser. A set of the said curves
shall also be furnished to the purchaser.
4.1.5 The vendor shall be responsible for carrying out torsion analysis of the dynamic
system as specified in the latest edition of British Standard-5514. The results in the
Contractor Signature MCGM
Page 38
SHASHI PRABHU & ASSOCIATES
fork of a report shall be submitted to the purchaser for scrutiny and reference, if
desired.
4.1.6 Vendor shall provide the flexible exhaust connection /s to connect the engine
exhaust to the exhaust piping. The required size of the exhaust piping should be
clearly specified by the Vendor.
4.1.7 If specified, the common base plate for mounting the diesel engine and the driven
equipment as well as the flexible coupling, shall be supplied by the vendor.
4.1.8 Vendor shall indicate in the bid, the ISO Noise Level rating of the diesel engine with
the offered exhaust silencer/s.
4.2.1 Diesel engines shall be capable of starting without the use of cold starting aids so
long the ambient temperature at the site is not below 4 oC. The vendor shall provide
suitable cold starting aids with diesel engine for quick starting below 4oC of ambient
and such aids shall be clearly detailed out along with the offer.
4.2.2 Where the diesel engine is specified / offered with battery starting arrangement, the
starter motor shall be capable of starting the engine without having to disengage the
driven machine with the help of a clutch. Where the diesel engine is equipped with a
dual starter the synchronizing switch and the corresponding wiring / connection
with the starter motor shall be provided by the vendor.
In case of diesel engines driving fire water pumps, besides the engine mounted
dynamo and voltage regulator, the Vendor shall also provide automatic battery
charging equipment suitable for taking power from an alternating current power
source and mounted on a free standing type of a panel.
The battery charger if specified in the equipment data sheet, shall be capable of
delivering a current equal to 100 percent of the 20 hour discharge rate of the battery
and also equipped with charging rate selector device.
4.2.3 Where the diesel engine is specified / offered with compressed air starting, the
Vendor shall also provide the air compressor driven by a diesel engine / electric
motor and equipped with necessary instruments and controls as specified in the
equipment data sheets.
The air receiver supplied by the vendor shall provide batteries and battery charging
equipment (see clause B. above) for operating the electrical controls of the diesel
engine.
4.2.4 If as specified in the data sheets, the diesel engine is required to start / stop
automatically, the vendor shall provide the necessary controls
(automatic-cum-manual) in the engine panel and the interconnecting wiring and
piping from the panel to the engine and starting equipment. A pilot lamp shall be
provided in the line side of the starting equipment circuit to indicate that the
controller is in the automatic position. In the event the engine does not start after
three attempts have been made, the controller shall stop all further cranking and
Contractor Signature MCGM
Page 39
SHASHI PRABHU & ASSOCIATES
operate the audiovisual alarm. AD.C. motor driven per lubrication pump with timer
suitably interlocked with the starting system shall be provided by the vendor.
Whenever the unit is arrange for automatic shut down, a running period time set for
a specific time interval, and shall be provided.
4.3.1 When radiator cooled engines are offered, the diesel engine shall be provided with a
radiator for mounting on the common base plate, complete with the suction / blower
fan, temperature control valve and a radiator guard.
4.3.2 Where the engine cooling is achieved by closed circuit cooling water system, the
vendor shall provide the complete jacket water (primary water) circuit, heat
exchanger with the make-up tank and its piping, as well as the raw water (secondary
water) circuit including but not limited to the following :
4.3.2.1 Raw water pump with driver, unless the raw water is required to be obtained
from the discharge of the pump driven by the diesel engine.
4.3.2.2 Raw water piping (prefabricated ) and fittings, as specified in the equipment
date sheets.
4.4.1 A fuel float (surge) tank if recommended by the manufacturer, shall be supplied with
the diesel engine along with its interconnecting piping / hoses.
4.4.2 The daily service fuel tank shall be equipped with as air breather, shielded level
gauge, strainer and a hand hole of not less than 150 mm diameter, besides the
required fuel connections and a drain plug. The capacity of tank shall be as specified
in the equipment data sheets.
4.4.3 The inside surfaces of the fuel tank and the float tank shall be coated with Enamel
Red or Black of I.C.I. or its equivalent and the outside surface to be given two coats of
the oil resistant primer paint. Both the fuel tank and the float tank, shall be
hydrostatic tested at a pressure not less than 0.35 kg /Cm2.
5.1 The inspector representing Purchaser shall have entry to the plant while and
wherever work for the equipment is being performed.
5.2 The vendor shall have the responsibility of providing purchaser's inspector with all
requisite facilities / equipment for carrying out satisfactory testing.
5.3 The diesel engines shall be tested in the presence of purchaser's inspector in
accordance with the latest edition of B.S. -5514 or any other equivalent standard as
agreed to with the purchaser before the finalization of order.
5.4 The routine load and fuel consumption test shall be of the following duration :
Contractor Signature MCGM
Page 40
SHASHI PRABHU & ASSOCIATES
5.5 Unless otherwise specified, 10% overload provision shall be kept while setting the
fuel stop for the site running.
5.6 The hydrostatic test certificates for the heat exchanger / intercoler , fuel tanks and
other pressure vessels shall be furnished to the purchaser's inspector for his review
and approval at the time of load testing of the diesel engine.
5.7 The engine control panel/s after assembly and wiring, shall be functionally tested in
the presence of the purchaser's inspector.
6.1 Immediately upon completion of all tests and inspections, all exposed machined
surfaces shall be cleaned and coated with a suitable rust preventive by the vendor
and the unmachined surface shall be painted by at least two coats of red oxide
primer.
6.3 All untapped opening shall be provided with 4mm thick metal closures with full
rubber gaskets and bolted by not less than 4 bolts. All connections including those
for instruments, instrument leads, lubricating oil and the like shall be identified with
securely attached tags indicating the type of connection, the instrument or the line
description as applicable.
6.4 The equipment shall be crated for domestic / export shipment as specified in the
data sheets considering for storage at job site for at least 6 months. Lifting load-out,
and handling instructions shall be securely attached to the exterior of the largest
packing in a well marked weather proof container. Upright position lifting points,
weight (including packing and dimensions shall be clearly identified with item no.,
serial no., package no., and the names of the equipment.)
7.0 PROPOSAL :
7.1 Proposals shall be accompanied with completely filled in Data Sheets. The vendor
shall not use his own data sheets.
7.2 The proposals must include either a specified statement that all equipment is in
accordance with the purchaser's specifications or exceptions, if any, to this general
specification including attachments shall be clearly brought out by the vendor on
separate sheets, supported with suitable reasons thereof for the consideration of the
purchaser.
7.3 Additions or exclusions from the scope of supply shall be clearly brought out on
separate sheets giving reasons for such deviations for the purchaser's approval.
7.4 Rating (HP) curves for the diesel engine for different duties and their interpretation as
per the applicable standard, shall accompany the proposal.
7.5 The drawings and data as listed under "prints with Quote" on the vendor data
requirement sheet attached with this specification shall be provided.
Page 41
SHASHI PRABHU & ASSOCIATES
7.6 The vendor shall also submit a separate proposal for carrying out supervision of the
installation and commissioning of diesel engine/s offered indicating per item rates,
no. of specialists proposed to be deputed, completion time and a list indicating
nature and quantity of consumable/ tools required and any other terms.
8.0 SCOPE:
8.1 This specification define the requirements of design, manufacture, testing and supply
of self excited emergency generator complete with automatic voltage regulator,
control panel, generator breaker and other accessories as specified in the material
requisition.
8.2 Unless otherwise specified the emergency generator shall be supplied complete with
b) Electric panel including control cubicle and associated auxiliary devices, relay panel
and generator breaker battery and charger (unless otherwise specified).
c) Air inlet and outlet for generator cooling (inlet shall be oriented to suit local plant
layout).
f) Lube oil system integral with the prime mover lube oil system.
i) Any other part / accessories not specifically mentioned above but considered
necessary for safe and reliable operation.
Unless they are in variance with the clause of this specification the diesel engine
driven generator and their components shall comply with the latest edition of the
applicable standards listed below:
Page 42
SHASHI PRABHU & ASSOCIATES
The dip or rise in system voltage load variations is dependent on the leakage voltage
drop of the machine which shall be kept to the minimum.
In case of sudden application of full load at rated power factor the voltage drop shall
not exceed 15% of the rated voltage. The rated voltage shall be restored within 0.5 to
0.8 second depending on the size of the machine.
The voltage regulation of the machine shall be within +/- 2 % of the nominal voltage
under following conditions :
a). Between no load and nominal load with p.f. of 0.8 lag to unity.
b). With the machine cold or warm.
c). At a speed drop of approximately 3% of the nominal speed.
The maximum permissible deviation from the sine wave shall be 5%. The harmonic
content of the voltage shall be less than 3% measured between phases off load and
up to nominal rating for a power factor of 0.8 lag to unity and with symmetrical
distortion free consumers in circuit.
Contractor Signature MCGM
Page 43
SHASHI PRABHU & ASSOCIATES
The Generator shall be suitable for continuous operation at rated load for frequency
variation of +/- 3% of rated value in addition the vendor shall furnish the short time
under-frequency operating limits.
10.7 Overloads :
The generator shall be capable of withstanding without injury the effect of a 10%
overload for one hour and 50% overload for one minute.
The generator shall be capable of withstanding without damage, a three phase, a line
to line, line to earth or two line to earth short circuit for a period of 3 seconds when
operating at rated speed and with an excitation corresponding to 5% over voltage at
no load.
Generator sets shall be suitable for parallel operation amongst themselves, or with
other generating sets or with other sources (Grid supply) at operating voltage and
under load conditions up to rated value. The set shall be provided with Electronic
governor system.
Excitation system shall be provided with short circuit support equipment (Series
compounding) to maintain three times the rated current for three seconds in case of
short circuit to ensure proper fault clearance in outgoing feeders.
11.1 The generator design shall meet the requirement specified in data sheet and shall be
suitable for the site conditions specified therein.
11.2 The generator shall be mounted on a common base frame together with the prime
mover unless otherwise agreed. The generator shall be provided with necessary lifting
hooks and two earth terminals for connection to main earth grid.
11.3 The generator winding shall be class "F" insulation with temperature limitation for
class "B" the windings and overhangs shall be braced to withstand the short circuit
forces. For machines rated 1000 KW and above shall have six no. RTDs suitably
distributed in stators winding.
11.4 The stators windings shall be brought out to six insulated terminals in two separate
terminal boxes. The alternator shall, therefore, be provided with three separate
terminal boxes i.e. for the line and neutral stators connections and for control
connections. The terminal box for the line terminals shall have sufficient space for
the termination of cable size specified in data sheet. The neutral box shall in addition
to space for neutral earthing cable have sufficient room for current transformers
Contractor Signature MCGM
Page 44
SHASHI PRABHU & ASSOCIATES
used for protection of generator. Star connection shall be formed in the neutral side
terminal box. The terminal box for control cables shall contain properly marked
terminals for all internal equipment e.g. embedded temperature detectors etc. All
terminals shall be stud type. The terminal boxes shall be complete with lugs and
double compression cable glands. Current transformers shall be as specified in data
sheet.
11.5 All parts and accessories shall be suitable to withstand stresses due to over speed /
overload / short circuit conditions specified.
11.6 Bearings shall be double shielded and relubricated. Grease in the bearing enclosure
shall provide additional lubrication to bearing as well as provide sealing against dust
and moisture.
11.7 The generator shall be air cooled unless otherwise agreed generator enclosure shall
be as specified in data sheet.
11.8 The direction of rotation of the rotor of the machine shall be compatible with that of
the prime mover. A clear indication of the direction of rotation shall be given on
either end of the machine.
11.9 Space heaters shall be installed within the enclosure, location and max. surface
temperature of the heaters shall be such that no damage can be caused to any
insulation. Heaters shall suitable for operation on a single phase 240V AC supply
unless otherwise specified.
A suitable double pole switch shall be mounted on or adjacent to the stators frame or
enclosure for the manual switching off of the heaters.
11.10 Field winding shall have class "F" insulation with excellent electrical and mechanical
properties. The field winding shall be capable of operating at a field voltage of 125%
of rated load field voltage for at least one minute starting from stabilized
temperatures at rated conditions.
11.11 All cabling on the generator set skid shall be in GI cable trays/ conduits. All cables
shall be identified close to their termination point. Double compression type cable
glands shall be used for cable termination.
11.12 A rating plate of corrosion resistant material shall be fixed on the generator frame
and shall give the following information:
a) Manufacturer's name.
b) Serial Number, Type and frame reference
c) Rated output in MVA & MW
d) Rated power factor, frequency and voltage
e) Rated stators current and speed in Rev. / Min.
f) Class of insulation
g) Phase rotation (CW or CCW)
h) Customer's indent no.
i) Year of manufacture
j) Weight rotor and stators in KG.
Page 45
SHASHI PRABHU & ASSOCIATES
The generator shall be provided with brush less type solid state excitation system
with automatic voltage regulator. The excitation system shall include the automatic
voltage regulator, AC exciter and rotary rectifier. The field of the exciter shall be fed
from the stators winding through a suitable transformer and AVR. AC Voltage
generated in the AC exciter shall be rectified by the rotary rectifier assembly and fed
to the main field circuits. The rotor windings of the AC exciter, the rectifier assemble,
main field winding of the generator and other accessories on rotor part shall be
rigidly fastened to the shaft and the connection with different items shall be
anti-loosening type.
The exciter capacity shall be at least 20% more than the maximum requirement at
any time. The exciter winding shall be insulated with class "F" insulation.
Automatic solid state voltage shall be provided with the following features as a
minimum.
The Current and potential transformers required to feed the AVR from the generator
terminal shall be adequately rated.
The emergency generator set shall normally be in an unattended area. The Control
system shall operate in fail safe mode and shall include all controls and protection
necessary for the safe operation of the package. The generator set shall function as
per one of the following schemes:
14.1 The Local generator control panel for the generator set shall comprise of the following
unless otherwise specified in the attached data sheet.
Page 46
SHASHI PRABHU & ASSOCIATES
Any other accessory require to make the generator set operational as a package shall
be included in scope of supply . If required the generator control panel shall be split
into various functional sections viz. protection, metering and control, regulation etc.
The generator break shall also be part of the control panel unless otherwise
specified. The breaker rating shall be as specified in the drawing. The
protective relays in the Gen. Control panel shall act to trip this breaker on fault
conditions unless otherwise specified. This breaker also serves the purpose of
local isolation.
All motor starters for generator set auxiliaries shall be DOL type.
Unless otherwise specified , the DC control supply required for relays , controls,
closing/tripping of generator breaker, annunciation circuit and for any other
purpose shall be met by a DC system consisting of battery and battery charger of
suitable capacity to be supplied by the generator set manufacturer . The battery shall
be sized for two hours load cycle a maximum. Battery charger shall be of the
constant voltage type with current limiting feature and facilities for automatic and
manual, normal and quick charging of batteries . Charger shall be sized for boost
charging of batteries with 10 to 14 hours.
14.2 The panel shall be free standing , metal enclosed, dust and vermin proof type with a
hinged door and having a degree of protection IP 51 as per IS:51 as per IS:2147
unless otherwise specified . Power and control equipment shall be segregated inside
the panel as far as practicable. The maximum light of the operation handle/switches
shall not exceed 1000 mm. and the minimum height not below 300 mm. All
hardware shall be corrosion resistant and bolts, nuts and washers shall be made of
galvanized zinc passivated of cadmium plated high quality steel. Unless otherwise
specified the panel shall be suitable for bottom cable entry. Necessary glands shall be
provided with the panel.
All auxiliary devices for control, indication, measurement and alarm such as push
buttons control/selector switches, indicating lamps, metering instruments,
annunciation’s etc. shall be mounted on the front door of the panel. Adequate
number of potential free contacts shall be provided in the control panel for any
remote control, monitoring of the generator set.
14.3 All switches shall be load - break, heavy duty type. All fuses shall be
non-deteriorating HRC cartridge pressure filled, link type. The contractor shall be
air-break type having AC-3 duty rating. Thermal overload relays shall be three
element, positive acting, ambient temperature compensated type with adjustable
setting range and built in protection feature against single phasing. All indicating
instruments shall be moving iron, flush mounting type and of 96 mm x 96 mm
square pattern. All control / selector switches shall be rotary back connected type
having a cam-operated contact mechanism with knob type handle. "STOP" push
buttons shall be stay put type.
Page 47
SHASHI PRABHU & ASSOCIATES
14.4 Wiring for power, control and signaling circuits shall be done with PVC insulated
copper conductors having 660 / 1100 V grade insulation. Minimum size of control
wires shall be 2.5 mm "ELEMEX" type terminals shall be acceptable for wires up to
10mm2 size and for conductors larger than 10 mm2 bolted type terminals with
crimping lugs shall be provided. A minimum of 10% spare terminals shall be
provided on each terminal block.
14.5 An adequately sized earth bus shall be provided in the panel for connection to the
main earth grid. All non current carrying metallic parts of the mounted equipment’s
shall be earthed. Doors and movable parts shall be earthed using flexible copper
connections.
14.6 Engraved nameplates shall be provided for all devices mounted on the front of the
panel. Nameplate or polyester adhesive stickers shall be provided for each equipment
mounted inside the panel.
15.1 All metal surfaces shall be thoroughly cleaned of scale, rust and grease etc. prior to
painting. Cleaned surfaces shall be given two coats of primer and prepared for final
painting. Final finish shall be free from all sorts of blemishes.
15.2 The equipment shall be shipped to site suitably packed to prevent any damage. Each
package shall have labels to show purchaser's name, purchase order and equipment
no. suitable lifting lugs etc. shall be provided and lifting points shall be clearly
marked on the package. Packing shall be suitable for storage at site for a minimum
period of 6 months.
16.1 The owner or his authorized representative may visit the works during manufacture
of equipment to assess the progress of work as well as to ascertain that only quality
raw materials are used for the same. He shall be given all assistance to carry out the
inspection.
16.2 Detailed test procedure along with the facilities available at vendors works shall be
furnished along with the bid Owner's representative shall be given minimum four
weeks advance notice for witnessing the final testing. Test certificates including test
records and performances curves etc. shall be furnished by the vendor.
16.3 Tests
Equipment shall be tested to conform to the appropriate standards and the following
tests shall be conducted in the presence of purchaser's:
16.3.1 Functional tests, continuity tests and high voltage test on control panel to
establish the performance called for in the specification.
16.3.2 Power frequency voltage test on switch gear and mechanical / electrical
operational check.
16.3.3 Routine tests for alternator as per IS : 4722.
16.3.4 Over speed test (1.2 times the rated speed for 2 minutes)
Page 48
SHASHI PRABHU & ASSOCIATES
16.3.5 Transient response tests for sudden application and rejection of loads of 25%,
50%, 75% and 100% of rated capacity.
16.3.6 Wave form test (type test results are acceptable)
16.3.7 Phase sequence test.
16.3.8 Vibration test
16.3.9 Noise level test.
16.3.10 Dimensional and alignment test.
16.3.11 String test.
Scope :
The contractor shall design, supply, install test and commission the HSD tank,
fittings and accessories as per requirements of the following BIS codes :
TANK
The U.G. tank shall conform to IS 10987-1992 with respect to lining, corrosion,
storage under ambient temperature, atmospheric conditions, stresses, design
fabrication and installation.
The compliance of the above standards does not absolve the manufacturer from
compliance of statutory norms and provisions by Dept of explosives, CCOE and / or
concerned statutory inspection agencies.
The Welding process shall conform to IS 813-1986. All welding shall be double butt
welds. When the shell length is produced from more than one single plate, the
longitudinal seams shall break point at intermediate circumferential seams. In case
of longitudinal seams, such seams shall be situated at the upper third or top center
line. All end plates shall be stiffened.
The plates used shall conform to IS 1730-1989. The thickness of plates used shall
have a corrosion allowance of 1.5 mm.
Bolts and nuts shall conform to IS 1367 (Part III) and IS 1367 (Part VI) 1980.
The tank shall be designed for a pressure of 0.05mPA when full of water. The tank
design shall be capable of withstanding the earth pressure of 1.40mPA when tank is
empty.
UG tanks shall have hinged and bolted manhole of minimum 500 mm diameter,
fabricated in water proof manner.
Contractor Signature MCGM
Page 49
SHASHI PRABHU & ASSOCIATES
For filling of tanks from top, necessary fill connection pipe with 45 degrees
champers shall be provided. The fill up shall terminate at 100 mm above bottom of
tank.
Provisions for sensing low level of fuel and transmitting the same to building
automation system shall be envisaged.
The tank shall have calibrated dip rod of non sparking brass material of size 12 mm
square.
The tank shall be fitted with vent pipe of not less than 4 M height, bending
downwards and the tip covered with two layers of non corrodible metal wire mesh of
11 meshes.
Two nos earthing bolts of minimum 12 mm size shall be provided on the end plate
of either side of tank at about 200 to 300 mm below top level to facilitate 50 x 6 GI
earth strip terminations.
The external surfaces of the tank shall be thoroughly cleaned free of rust scale,
grease etc and painted with one coat of approved primer paint.
The entire interior surface shall be cleaned of rust, scales, grease etc and shall be
primed twice with fuel prior to dispatch.
The tolerance in diameter of the tank shall be within plus or minus 0.35% of
specified diameter.
The HSD tank shall be MS construction, horizontal cylindrical in shape with dished
ends.
The tank shall be all welded construction and shall be suitable for storage of HSD
up to maximum temperature of 40 deg. C at atmospheric pressure. Shell thickness
of tank shall be 6 mm and thickness of dished ends 8 mm.
Tanks shall be painted externally and internally to prevent corrosion. The internal
surface of the storage tanks shall be thoroughly cleaned with wires brush / emery
paper to remove rust, scale etc and treated with coat of suitable oil resistant paint.
The external surface of the tank shall be thoroughly cleaned with wire brush /
emery paper to remove rust, scale etc. and painted with one coat of zinc chromate
primer followed by two coats of finishing paint (Bitumen based).
All the oil supply pip shall be MS heavy class as per IS 1239 Part 1. All fittings shall
be of heavy duty. Flanges shall be conforming to ASA class 150 weld necks and
material to IS 226.
Page 50
SHASHI PRABHU & ASSOCIATES
All valves shall be ball type and of body bonnet, gland nut of bronze material with
brass or SS ball only.
The strainers shall be of cast iron body with FM or bronze mesh for fine filtration of
the oil.
The HSD supply pipes from HSD yard to respective day oil storage tank shall be laid
underground. These pipes shall be provided with corrosion proof and weather proof
treatment.
CLEANILINESS
The area around the vessels shall be kept free from readily ignitable materials, such
as weeds and long dry grass by providing stone pitching.
EARTHING
HSD tank and pipe lines shall be provided with copper earthing and earthed in
efficient manner.
NO SMOKING
A permanent notice with letters minimum 5 cms high prohibiting smoking and
naked lights shall be fixed to the fence surrounding the area.
FIRE PROTECTION
The area where tanks, pumping equipment, loading and unloading facilities are
provided; shall be well protected from fire by providing fire hydrants and fire
extinguishers. (Shall be part of FFTG tender)
The contractor shall arrange the inspection, approval and license for the proposed
HSD oil installation by the Chief Inspector / Controller of Explosives as given below:
The contractor shall upon the award of the work shall prepare working drawings for
the HSD installation and submit the drawings to the consultants for their
provisional approval. The drawings so approved by the consultants shall be
submitted to the Chief inspector / Controller of Explosives for his scrutiny and
approval.
It shall be the responsibility of the contractor to arrange test and safety certificates
under rules 126 after the installation is commissioned.
Page 51
SHASHI PRABHU & ASSOCIATES
Scope
The scope of this section comprises the supply and laying of pipes, pipe fittings and
valves. Testing and balancing of all HSD piping required for the complete
installation as shown on the drawings. All piping inclusive of fittings and valves
shall follow the applicable BIS codes.
1. Pipes shall be MS class “B” and fittings shall be welded type fittings conforming
to relevant BIS codes. All jointing in the pipe system shall generally be by
welding flanges, unless otherwise mentioned or directed at site. All welding shall
be done by qualified welders and shall strictly conform to BIS code of procedure
for manual metal arc welding of mild steel.
2. All pipes and their steel supports shall be thoroughly cleaned and given on
primary coat of red oxide paint before being installed. All welded piping shall be
subject to the approval at site.
3. Threaded joint fittings shall be malleable casting of pressure rating suitable for
the piping system. Fittings used on welded piping shall be of the wieldable type.
4. Tee-off connections shall be through equal or reducing tees otherwise ferrules
welded to the main pipe shall be used. Drilling and tapping of the walls of the
main pipes shall not be resorted to.
SCOPE
This specification covers the design, manufactures and testing of three phase
medium voltage squirrel cage induction motors.
STANDARDS
Unless they are at variance with the clauses of this specification, the squirrel
cage induction motors and their components shall comply with the latest
applicable Indian standards listed below. Where Indian standards do not exist,
the relevant IEC, British or German (VDE) standards shall apply.
Page 52
SHASHI PRABHU & ASSOCIATES
2.19 IS – 8223 Dimensions and output ratings for foot mounted rotating
electrical machines with frame numbers 355 to 1000.
2.20 IS – 8289 Specification for electrical equipment with type of protection ‘n’.
2.23 IS – 9628 Specification for three phase induction motors with type of
protection ‘n’.
2.25 IS – 12065 Permissible limits of noise level for rotating electrical machines.
Page 53
SHASHI PRABHU & ASSOCIATES
2.28 IS – 13555 Guide for selection and application of three induction motors for
different types driven equipment.
3. OPERATING CONDITIONS
a) The terminal voltage differing from its rated value by not more than +/- 6 %,
or
b) The frequency differing from its rated value by not more the +/- 3 % or
c) Any combination of (a) and (b).
3.3 Starting
Unless otherwise specified motors shall be designed for direct –on-line starting.
Motors shall be designed for re-acceleration under full load after a momentary
loss of voltage with the residual voltage being 100% out of phase.
Unless otherwise specified, all motors shall be suitable for starting under
specified load conditions with 75 percent of the rated voltage at the terminals.
Page 54
SHASHI PRABHU & ASSOCIATES
Motors shall be suitable for their direction of location. In case unidirectional fan
is provided for motors, direction of rotation for which the motor is designed shall
be permanently indicated by means of an arrow. A painted arrow shall not be
acceptable. directional arrow should be manufactured from corrosion resistant
material. When a motor is provided with bi-directional fans, a double headed
arrow should be provided.
4. PERFORMANCE
4.1 Motors shall be rated for continuous duty (SI) unless otherwise specified.
4.2 The starting current (as % rated current) shall not 600% for motors upto and
including 75 KW and 550% for motors above 75 KW subject to tolerance.
4.3 Starting torque and minimum torque of the motor shall be compatible with
speed torque curve of the driven equipment under specified operating conditions.
For heavy duty drives such as blowers, crushers etc. high starting torque motors
shall be provided. In case where characteristics of driven equipment are not
available while selecting the motor, minimum starting torque shall be 110% of
rated value for motors up to 75KW and shall be 90% of rated value for motors
above 75 KW.
4.4 The pull out torque at the rated voltage shall be not less than 175 percent of the
rated load torque with no negative tolerance. Unless otherwise agreed, the pull
out torque shall not exceed 300 percent of the rated load torque.
4.5 The minimum value for product of efficiency and power factors for motors rated
upto and including 37 KW shall be as per IS – 8789.
The minimum value for product of efficiency and power factors of 2 pol, 4-pole,
and 6-pole motors rated above 37 KW shall be as given below.
Efficiency and power-factor figures for motors having synchronous speeds of 750
r.p.m. and below shall be as agreed between the purchaser and manufactured.
Page 55
SHASHI PRABHU & ASSOCIATES
b) Phase Connections
The windings shall be connected in delta. However, for motors rated 2.2 KW
and below, star connection may be accepted.
If star- delta starting is required, this will be specified in the data sheet and
the motor windings shall be fully insulated for delta connection.
c) Winding Terminations
The ends of the windings shall be brought out into a terminal box. They shall
be terminated by means of terminals mounted on an insulating base made of
no-hygroscopic and non-flammable material.
All motors shall be with six terminals and suitable links to connect them in
star or in delta except for motors rated up to and including 202 KW which
may be accepted with three terminals.
Page 56
SHASHI PRABHU & ASSOCIATES
The terminal box shall be of sturdy construction and large enough to facilities
easy connection of the cables. Terminal box cover shall be provided with
handles to facilitate easy removal.
The terminal box shall be provided with cables lugs and entries for suitable
cables glands corresponding to the number and size of specified cable. Nickel
glands shall be supplied along with the motor for mentioned cable sizes.
Unless otherwise specified the terminals, cable lugs, terminal box, cable
entries and cable glands shall be suitable for the cable sizes as specified
below for 2 pole, 4 pole or 6 pole motors :
NOTE : Cable sizes motors having synchronous speeds 750 rpm and
below shall be as agreed between the purchase and
manufacturer.
Cable Type
e) Phase Marking
appropriate phase markings as per IS : 4728 shall be provided inside the
terminal box. The marking shall be non-removable and indelible.
Page 57
SHASHI PRABHU & ASSOCIATES
Motors for use in safe areas shall be normal industrical degree of motor
enclosures including terminal boxes and bearing housing shall be IP 55 as per IS
: 4691.
Motors for use in hazardous areas (Zone 1 or Zone 2) shall have type of
protection Ex(d) Or Ex(e) or Ex (n) as specified in the data sheet and shall meet
the requirements of applicable Indian standards. Ex(d) type of motors shall have
a BIS marking on the name plate.
Motors for outdoor use shall be suitable for installation and satisfactory
operation without any protective shelter or canopy. Motor casing shall be
provided with a suitable drain for removal of condensed moisture except in case
of flameproof motors.
Vertical motors with downward shaft shall be provided with fully covering rain
canopies. Vertical motors with upward shaft e.g. on fin-fan coolers, shall be
adequately protected, (such as cowls/canopies) against ingress of water into the
enclosure or the bearing housing even when standing still for long periods of
time. Motors designed to handle external thrust from the pump shall be supplied
with a thrust bearing at the non-driving end.
All internal and external metallic parts which may come into contact with
cooling air, shall be of corrosion resistant material or appropriately treated to
resist the corrosive agents which may be present in the atmosphere. Screws and
bolts shall be hot dip galvanized or zing passivated to protect against corrosion.
Unless otherwise agreed, motors shall have standard frame size for various
output ratings as stipulated in IS : 1231.
Motors shall have grease lubricated ball or roller bearings. In all cases, the
bearings shall be chosen to provide a minimum L-10 rating life of 5 years, (40
000 hours) at rated operating conditions. (The L-10 rating life is the number of
hours at constant speed that 90% of a group of identical bearings will complete
or exceed before the first evidence of failure). Unless otherwise specified the
bearing shall be adequate to absorb axial thrust produced by the motor itself or
due to shaft expansion. Vertical motors shall be provided with thrust hot liquids
where the driven machine operates at high temperatures, bearings shall be
cooled by a shaft mounted fan. This shall ensure efficient ventilation of the
bearing and disperse the heat transmitted from the driven object by conduction
or convention. For motors operating in hazardous areas fans shall be of an anti-
static non-sparking material.
Page 58
SHASHI PRABHU & ASSOCIATES
5.5 Rotor
The rotor shall be of squirrel cage type, dynamically balanced to provide a low
vibration level and long service life for the bearings. The accepted values of peak
to peak vibration amplitudes for a motor at rated voltage and speed on a
machined surface bedplate with the motor leveled and with a half-key or
coupling fitted shall not exceed those given in IS-12075. Die cast aluminium
rotors for motors in hazardous areas may be accepted provided the same are
type tested and approved by competent authorities.
Necessary nuts and spring washers shall be provided for earth connection.
An additional earth terminals shall be provided inside the terminal box as stated
in 5.1
6 MISCELLANEOUS ACCESSORIES
All motors rated above 30KW shall be provided with 240 V anti-condensation
heaters, sized and located so as to prevent condensation of moisture during
shut-down periods. Motors rated 30 KW and below shall be provided with anti-
condensation heaters if specified in the requisition. Motors meant for humid
location such as cooling tower fans, sump pump motors etc. shall be provided
with space heaters irrespective of the motor rating in the motor data sheet. The
Page 59
SHASHI PRABHU & ASSOCIATES
heaters shall permanently remain ‘ON’ when the motor is not in service and as
such shall not cause damage to the windings.
The heater leads shall be brought out to separate terminal box of the same
specification and grade of protection as the main power terminal box excepting
that the cable glands provided shall be suitable for two core 4 sq. mm aluminum
conductor, armored cable or 3 x 2.5 sq. mm. copper conductor armored cable.
A warning label with indelible red inscription shall be provided on the motor to
indicate that the power line and the heater supply shall be isolated before
carrying out any work on the motor.
A stainless steel name plate manufactured from series 300 stainless steel and as
required under specification IS-325 shall be provided on each motor. In addition
to the motor rating plate a separate motor plant equipment number plate shall
be fixed in a readily visible position. This number shall be indicated in the data
sheets attached with purchase requisition.
7. NOISE LEVEL
The permissible noise level shall not exceed the stipulations laid down in IS –
12065.
8. MOTOR VIBRATIONS
Motor vibrations shall be within the limits of IS – 12075 unless otherwise
specified for the driven equipment.
9. CRITICAL SPEEDS
The first actual critical speed of stiff rotors shall not be lower than 125% of the
synchronous speed. For flexible rotors this shall be between 60% and 80% of the
synchronous speed; the second actual critical speed shall be above 125% of the
synchronous speed.
10. PAINTING
Internal and external parts of the casing and all metal parts likely to come in
contact with the surrounding air shall be protected with anti-acid paint that will
resist the particular ambient condition.
Page 60
SHASHI PRABHU & ASSOCIATES
The vendor shall give at least 4 weeks advance notice to the purchaser,
regarding the date of testing to enable him or his representative to witness the
tests.
The motors shall be tested in accordance with IS : 325 and IS : 4029. Type test
including any specific test to ascertain compliance with these specification shall
be carried out on one sample from each KW rating and frame size. Routine tests
shall be carried out on all motors. In addition measurement of vibration and
noise level (if desired) shall form a part of route tests.
a) KW rating, make, frame size, full load speed, mounting, enclosure type and
specific type of construction {Ex(d), Ex(n) etc.}.
b) For heavy duty drives starting torque, starting time and lock rotor withstand
time of the motor shall also be furnished.
12.2 After placement of order, vendor shall furnish all necessary data / drawings /
documents including but not limited to the following:
Page 61
SHASHI PRABHU & ASSOCIATES
4. Horse power
7. Flywheel Require
Page 62
SHASHI PRABHU & ASSOCIATES
a) At shop
b) At site
22. Tool kits Require
Note :
Page 63
SHASHI PRABHU & ASSOCIATES
ALTERNATOR
DATA SHEET - B
1. Make :
2. Rating : 1010KVA
6. Rated current :
8. Frequency : 50 Hz.
Page 64
SHASHI PRABHU & ASSOCIATES
Page 65
SHASHI PRABHU & ASSOCIATES
1.0 Scope:
Whether called for specifically or not, all accessories required for normal operation
of equipment are deemed to be considered as a part of the contractor’s scope of
supply. Hardware / fabricated supports required for mounting and installation of
the panels is within the scope of work.
It is not the intent to specify completely herein, all details of design and
construction of the equipment. However, the equipment shall conform in all
respects to high standard of Engineering, design and workmanship and be capable
of performing in continuous commercial operation up to the Manufacturer’s
guarantees in a manner acceptable to the Engineer, who will interpret the meaning
of the drawings and specifications and shall be entitled to reject any work or
material which is not full accordance therewith.
All the Panel’s shall be metal clad, totally enclosed, rigid, floor mounted, air -
insulated, cubical type suitable for operation on three phase / single phase, 415 /
230 volts, 50 Hz.
Should conform to Indian Electricity Act and rules (till last amendment) & approved
as per FIA norms.
Applicable IS Standards
Page 66
SHASHI PRABHU & ASSOCIATES
2.1 Construction :
Switchboard connection
All connection and tap offs shall be through adequately sized connectors appropriate
for fault level at location. This shall include tap off to feeders and instrument/control
transformers.
For unit ratings upto & including 63 amps, PVC insulated copper conductor wires of
adequate size to carry full load current shall be used. The terminations of such
Page 67
SHASHI PRABHU & ASSOCIATES
interconnections shall be crimped. Solid connections (busbars) shall be used for all
rating above 63A.
All nut bolts for busbar shall be high tensile cadmium plated with 2 plain washer and
1 spring washer. Hardware should be provided at cable termination end.
The different busbars shall be the main busbars, distribution busbars and auxiliary
busbars.
The busbars shall be made of electrolytic Al. with current density of 0.8A/Sqmm.
The compartments shall be located inside a metal enclosure with walls providing
protection against direct contact with live parts and guaranteeing a degree of
protection IP 2X. The frame, the external panels (doors, side and rear panels, tops)
and internal elements (ducts) shall be made of 2 mm thick steel sheet metal and
protected by an epoxy-paint coating.
The max height of panel shall be 2375mm including the base channel of 75 x 40 mm
ISMC coloured black.
Sheet metal elements in the immediate proximity of high current flow generating
potential eddy current shall be made of aluminium.
Drawers or air circuit breakers shall have four different positions: connected, test,
disconnected and removed. With drawability of upstream and downstream power
circuits and of auxiliary circuits shall be total, i.e. in compliance with standard IS –
8326.
The construction system shall provide a complete set of elements for installing fixed
or with drawable switching and protective devices, measurement devices and control
/ monitoring devices in the switchboard.
The drawers shall be designed such that the rated degree of protection (IP, as per IS
2147: 1962) is maintained whatever their position (connected, test, disconnected,
removed).
Contractor Signature MCGM
Page 68
SHASHI PRABHU & ASSOCIATES
Switchboard Compartmentalization
Sheet steel hinged lockable doors for each separate compartment shall be provided
and duly interlocked with the breaker in "ON" and "OFF" position.
For all Circuit Breakers separate and adequate compartments shall be provided for
accommodating instruments, indicating lamps, control contactors and control MCB
etc. These shall be accessible for testing and maintenance without any danger of
accidental contact with live parts of the circuit breaker, busbars and connections.
Panel should be single front operated and cable Entry should be at TOP. Busbar and
cable allay access should be from front only.
Each switchgear cubicles shall be fitted with label in front and back identifying the
circuit, switchgear type, rating and duty. All operating device shall be located in front
of switchgear only.
A horizontal wire way with screwed cover shall be provided at the top to take
interconnecting control wiring between vertical sections.
Separate cable compartments running the height of the switchboard in the case of
front access boards shall be provided for incoming and outgoing cables. Outgoing all
control and power terminals should be KUT type.
Cable compartments shall be of adequate size for easy termination of all incoming
and outgoing cables entering from bottom or top. The construction shall include
necessary and adequate and proper support shall be provided in cable compartments
to support and clamping the cable in the cable alley / cable chamber.
Page 69
SHASHI PRABHU & ASSOCIATES
Vendor shall provide dimensions of MCC. Final GA layout will be approved by TPL.
Bus bars shall be made of high conductivity, high strength Al. of ETP grade. Bus bars
shall be of rectangular cross sections suitable for full load current for phase bus bars
and full rated current for neutral bus bar. Bus bar shall be suitable to withstand the
stresses of fault level as specified in SLD. The certification for conductivity of the Al.
shall be made available from third party certifying agency if required by engineer.
The minimum clearances to be maintained for enclosed indoor air insulated bus bars
for medium voltage applications shall be as per IS guidelines. The bus bar shall be as
per current density of 0.8 A/Sq.mm Cross Section area.
The bus bar shall be housed in separate compartment and shall be isolated with 3
mm thick FRC sheet to avoid any accidental contact. The bus bar shall be arranged
such that min. clearances between the bus bars are as mentioned below:
The bus bar and interconnection shall be insulated with heat shrinkable PVC sleeves
and shall be colour coded in Red / Yellow / Blue / Black / Green to identify the three
phases / neutral and earth of the system . The bus bar shall be supported on
unbreakable, non-hygroscopic DMC insulated supports (no bakelite material should
be used in panel) at sufficiently close intervals to prevent bus bar sag and shall
effectively withstand electromagnetic stresses in the event of short circuit capacity of
65KA RMS symmetrical fault for 1 sec and peak short circuit withstand of 105KA
minimum.
All bus bar connections shall be done by drilling holes at factory in bus bars and
connecting by chromium plated bolts and nuts. Additional cross section of bus bar
shall be provided in all panels to cover up for the holes in the bus bars. Spring and
flat washers shall be used for tightening of bolts.
All Cu/Al joints (if any) shall be connected with bi-metal sheet.
Contractor Signature MCGM
Page 70
SHASHI PRABHU & ASSOCIATES
All voltmeter and ammeter and other instruments shall be flushed mounted type of
size 96X96 mm conforming to class 1.0 to IS 1248 for accuracy. All voltmeter shall be
protected with suitable SCPD device.
Instruments and indicating lamps shall not be mounted on the Circuit Breaker
Compartment (in case of ACB) door for which a separate and adequate compartment
shall be provided and the instrumentation shall be accessible for testing and
maintenance without danger of accidental contact with live parts of the Switchboard.
For MCCBs, instruments and indicating lamps can be provided on the compartment
doors.
The current transformers for metering and for protection shall be mounted on the
solid copper bus bars with proper supports.
On all the incomers of switch boards ON/OFF indicators lamps shall be provided
suitable for operation on AC 230 volts supply. All lamps shall be protected with
proper protection device. Where phase indicator lamps are to be provided, these shall
be associated with necessary ON/OFF toggle switch. All the lamps shall have testing
facility.
For instruments control MCB shall be used (Fuse with link not accepted)
2.4 Wiring
All wiring for relays and meters shall be with PVC insulated copper conductor wires.
The wiring shall be coded and labelled with approved ferrules for identification. The
minimum size of copper conductor control wires shall be 1.5 sq. mm. Runs of wires
shall be neatly bunched and suitably supported and clamped. Means shall be
provided for easy identification of wires. Identification ferrules shall used at both end
of wires. All control wires meant for external connections are to be brought out on a
terminal board. The cables shall be suitable for withstanding 105 deg C.
Anti- condensation heaters shall be fitted in each cubicle together with an ON/OFF
isolating switch suitable for electrical operation at 230 volts A.C 50 Hz single phase of
sufficient capacity to raise the internal ambient temperature by 5º C. The electrical
apparatus so protected shall be designed so that the maximum permitted rise in
temperature is not exceeded if the heaters are energized while the switchboard is in
operation. As a general rule, the heaters shall be placed at the bottom of the cubicle.
The Switchboard shall be provided with panel mounting type ventilation fans in each
panel with switchgear rated for 2000 amp and above or as required by engineer. The
fan shall be interlocked with switchgear operation. The degree of enclosure protection
Contractor Signature MCGM
Page 71
SHASHI PRABHU & ASSOCIATES
to be maintained even with fans. The fans shall be fitted with temperature sensors for
automatic operation.
2.7 Earthing
Continuous earth bus sized for prospective fault current to be provided with
arrangement for connecting to station earth at two points. Hinged doors / frames to
be connected to earth through adequately sized flexible braids. Calculations shall be
provided for the earthing strip size as per the fault level of the panel. Min size of earth
bus shall be 50 x 6 mm Al.
Sheet steel used in the fabrication of switchboards shall undergo a rigorous cleaning
and surface treatment seven tank process comprising of alkaline degreasing,
descaling in dilute sulphuric acid and a recognized phosphating process after which
a coat of primer paint compactively with the final paint shall be applied over the
treated surface. Final paint coat of oven baked powder coating, of minimum 75
micron thickness, of sheet approved by Engineer-in-Charge shall then be provided.
Painting shade shall be Siemens Grey-RAL 7032.
Identification labels of Aluminium with black base and silver fonts shall be provided
on all feeders / lamps / panel name plate / relays / contactors etc. These shall
indicate the feeder number and feeder designation also along with rating of the
switchgear. Sample for the same shall be first approved by engineer.
2.10 Installation
Splices shall be implemented to ensure the electrical continuity of the horizontal bus
bars, auxiliary buses and the protective conductor between adjacent sections.
It shall be possible to secure the sections to a floor that is flat (max variation within 2
mm/m:)
➢ by anchoring directly to a concrete floor using anchor bolts;
➢ by securing to ordinary metal profiles.
Extensions to the low-voltage electrical switchboards shall be possible on either side
(right or left).
The low-voltage electrical switchboards shall ensure the safety of life and property as
well as provide a high level of continuity of service.
- Switching safety shall be ensured by a mechanical device preventing on-load
withdrawal & on-load access to live parts, except by strictly following a defined
procedure & using defined tools.
- Operating safety shall be ensured by the use of compartments in compliance
with standard IEC 60439-1 and according to form types 3b.
- Current interruption shall be of the "visible break isolation" or "positive contact
indication" type as defined by standard IS 13947: 1993.
Page 72
SHASHI PRABHU & ASSOCIATES
Optionally, the safety of persons shall be enhanced by a version complying with the
requirements of standard IEC 61641 concerning the propagation of an arc inside
electrical switchboards. Test certificates shall be available.
Provisions must be made, around the equipment critical zones, for visual/infrared
inspection during equipment operation, with respect to operator safety.
Earthed metal or insulated shutters shall be provided between drawout and fixed
portion of the switchgear such that no lives parts are accessible with equipment
drawn out. Degree of protection within compartments shall be at least IP 2X.
IP rating for all PCC’S/MCCB in wet area like pump room shall be IP-65. (to be
confirmed with engineer before quoting)
The panels shall be equipped complete with all type of required number of air circuit
breakers, switch fuse unit, contactor, relays, fuses, meters, instruments, indicating
lamps, push buttons, equipment, fittings, busbar, cable boxes, cable glands etc. and
all the necessary internal connections /wiring as required and as indicated on
relevant drawings. Components necessary for proper complete functioning of the
panels but not indicated on the drawings shall be supplied and installed on the
panels.
All part of the panels carrying current including the components, connections, joints
and instruments shall be capable of carrying their specified rated current
continuously, without temperature rise exceeding the acceptable values of the
relevant specifications at any part of the panels.
All units of the same rating and specifications shall be fully interchangeable.
2.13 L. T. Switchgears:
2.13.1 General:
The type, size, and rating of the components shall be as indicated on the relevant
single line diagrams0.
2.13.2 Miniature Circuit Breaker (MCB) / MPCB / ELCB:
MCB / MPCB shall be quick make and break and break type conform with IS: 8828
(1996). The housing shall be heat resistant and having high impact strength. The
fault current of MCBs / MPCBs shall not be less than 10000 amps, at 230 volts.
Contractor Signature MCGM
Page 73
SHASHI PRABHU & ASSOCIATES
The MCBs shall be flush mounted and shall be provided with trip free manual
operating mechanism with mechanical "ON" and "OFF" indications.
The circuit breaker dollies shall be of trip free pattern to prevent closing the breaker
on a faulty current.
The MCB / MPCBs contact shall be silver nickel and silver graphite alloy and tip
coated with silver. Proper arc chutes shall be provided to quench the arc
immediately. MCB's / MPCBs shall be provided with magnetic fluid plunger relay for
over current and short circuit protection. The over load or short circuit devices shall
have a common trip bar in the case of DP and TPN miniature circuit breakers. All the
MCB's / MPCBs shall be tested and certified as per Indian Standard, prior to
Installation.
MPCB with extended support should be consider along with front operating
mechanism. MPCB should be with all accessories like; auxiliary contacts, door
rotary mechanism etc.
The RCCB should suffices all the requirements of IS as per code IS - 12640 - 1988.
The RCA should be current operated and not on line voltage.
iii) The RCCB should have a torroidal transformer witch has the main conductors of
primary (P - N) which check the sum of the current close to zero.
iv) All metal parts should be inherently resistant to corrosion and treated to make
them corrosion resistant.
xi) Its mechanical operation life should be more than 20,000 operations.
xii) It should provide full protection as envisaged by IE rules - 61-A, 71 - ee, 73 - ee,
1985 and also rule 50 of IE rule1956.
It should conform to all national and international standards like IS: 8828-1993, IS:
12640-1988, BS 4293 - 1983, CEE 27 (International commission Rules for the
approved of electrical equipment).
Contractor Signature MCGM
Page 74
SHASHI PRABHU & ASSOCIATES
2.13.3 Fuse:
Fuses shall be of high rupturing capacity (HRC) fuse links and shall be in accordance
with IS : 2000-1962 and having rupturing capacity of not less than 35 MVA at 415
Volts.
The ACB shall meet with IS : 2516 part I, II and III. Each pole of the ACB's shall be
equipped with over current, earth fault and short circuit release. The ACB's shall be
equipped with under voltage trip only on those used as main incomer of all sources,
bus coupler and inter connector. The trip devices shall be direct acting.
The ACB's shall have an arc-quenching device on each pole. The ACB's shall have
auxiliary contacts for signalling, interlocking etc. The ACB's shall have slow close
facilities for checking contact operation and contact gap adjustment.
All contacts subject to arcing shall be tipped with arc resisting material. Main
contacts shall be silver plated, multi-finger and spring-loaded type. Facilities shall be
provided to isolate the circuit breaker for inspection purpose.
Prevent the breaker from being isolated unless it is in the "OFF" position.
Prevent the breaker from being racked in to the service position unless it is in the
"OFF" position.
Prevent the breaker from being accidentally pulled completely "OFF" the guide rail.
Safety shutters of insulating material shall be provided to prevent access to all live
contacts, when the breaker is in the inspection position or completely withdrawn.
Air circuit breaker shall be capable of clearing the maximum fault current, which can
occur.
The breaker plates shall have an ON-OFF indicators, spring charge indicators,
provision to padlock manual handle and provision to lock draw-out mechanism.
Electrically operated breaker shall have provision for emergency manual closing by
inserting a tool through the fuse plate. A control isolating switch shall be provided on
the fuse plate to isolated the supply to the charging motor.
The breaker shall be have feature such as to indicate voltage status / trip / fault
alarm indicators / remote operation from BMS – ON/OFF, shunt trip release and
motorised reclosing / contacts for remote indication of open / close / trip wired to
BMS, communication modules providing LAN interface with BMS and draw out
pattern with test facility provision.
Contractor Signature MCGM
Page 75
SHASHI PRABHU & ASSOCIATES
All ACB releases shall be with long time + short time + instantaneous + earth fault
selective protection.
2.13.5 Moulded Case Circuit Breaker:
2.13.5.1 General
Moulded-Case Circuit Breakers (MCCB) shall comply with IS 13947: 1993
standards.
- they shall be of utilisation category A on all the operational voltage range – till
250A and category B on all the operational voltage range – for any rating with
adjustable short time delay (if specified) with a rated service breaking capacity (Ics)
equal to the ultimate breaking capacity (Icu) up to 500V for the greater ratings
- They shall have a rated operational voltage of 690 V AC (50/60 Hz),
- They shall have a rated insulation voltage of 800 V AC (50/60 Hz),
- They shall be suitable for isolation, as defined by IS 13947: 1993 for the
Overvoltage Category IV for a rated insulation voltage up to 690 V .
The manufacturer shall implement non polluting production processes that do not
make use of chlorofluorocarbons, chlorinated hydrocarbons, ink for cardboard
markings, etc
MCCBs shall be mounted in panel as fixed type versions in 3-pole and 4-pole
versions. A safety trip shall provide advanced opening to prevent connection and
disconnection of a closed circuit breaker
MCCBs shall be designed for both vertical and horizontal mounting, without any
adverse effect on electrical performance. It shall be possible to supply power either
from the upstream or downstream side
MCCBs shall provide class II insulation between the front and internal power
circuits
2.13.5.2 Construction, Operation, Environment
For maximum safety, the power contacts shall be insulated in an enclosure made of
a thermosetting. material from other functions such as the operating mechanism,
the case, the trip unit and auxiliaries
All poles shall operate simultaneously for circuit breaker opening, closing and
tripping.
MCCBs shall be actuated by a toggle or handle that clearly indicates the three
positions: ON, OFF and TRIPPED.
Page 76
SHASHI PRABHU & ASSOCIATES
MCCBs shall be able to receive a device for locking in the “isolated” position, with
up to 3 padlocks, Ø8 maximum.
MCCBs shall be equipped with a “push to trip” button in front to test operation and
the opening of the poles.
MCCB rating, “push to trip” button, performances and contact position indication
must be clearly visible and accessible from the front, through the front panel or the
door of the switchboard.
2.13.5.3 Current Limitation, Discrimination, Durability
MCCBs shall comprise a device, designed to trip the circuit-breaker in the event of
high-value short-circuit currents. This device shall be independent of the thermal-
magnetic or electronic trip unit.
MCCBs, the current ratings of which are identical with the ratings of their trip
units, shall ensure discrimination for any fault current up to at least 35 kA rms,
with any downstream circuit-breaker having a current rating less or equal to 0.4
times that of the upstream circuit-breaker.
The MCCB shall trip in case the environmental conditions of the circuit-
breaker get out of their specified range. However, it will be possible to
overrule this feature.
2.13.5.4 Auxiliaries and Accessories
Page 77
SHASHI PRABHU & ASSOCIATES
The addition of a motor mechanism or a rotary handle shall in no way affect circuit
breaker characteristics:
- Only three stable tripping mechanism positions (ON, OFF and TRIPPED) shall be
possible with the motor mechanism,
- Suitability for isolation shall be provided by positive contact indication (ON and
OFF) in front of the motor mechanism module
The addition of a motor mechanism module or a rotary handle, etc., shall not mask
or block device settings
It shall be possible to equip MCCBs with devices indicating faults without tripping
the circuit breaker
2.13.5.5 Protection Functions
General Recommendations
MCCBs with ratings up to & including 250 A shall be equipped with fully
interchangeable trip units in order to ensure the protection against overcharge and
short-circuit. The trip units shall be of thermal magnetic adjustable type.
Page 78
SHASHI PRABHU & ASSOCIATES
MCCBs with ratings over 250 A shall be equipped with microprocessor based trip
units with O/C / S/C & E/F.
2.13.5.6 Common Features
Electronic trip units shall comply with IS 13947: 1993 standard (measurement of
rms current values, electromagnetic compatibility, etc.)
The trip units shall not augment overall circuit breaker volume
Characteristics
- Long time protection (LT)
Selectable Ir threshold settings from 36% to 100 % of the trip unit rating
- Short time protection (ST)
Isd threshold shall be adjustable from 1,5 to 10 times the thermal setting Ir,
The time delay shall be either adjustable or fixed at 40 ms,
- Instantaneous protection
The threshold shall be either adjustable or fixed (starting from 1.5 times In and up
to a value between 11 and 15 times In, depending on the rating)
The following monitoring functions shall be integral parts of electronic trip units:
- 2 LED for load indication, one lighted above 90 % of Ir, and one lighted above 105
% of Ir
- a test connector shall be installed for checks on electronic and tripping
mechanism operation using an external device.
Thermal Memory
In the event of repeated overloads, the electronic trip unit shall optimise protection
of cables and downstream devices by memorising temperature variations.
Options:
Page 79
SHASHI PRABHU & ASSOCIATES
It shall be possible to install all options for the electronic trip unit:
- High-threshold earth-fault protection,
- Auxiliary contact to indicate the cause of tripping (long time, short time,
instantaneous, earth fault if requested),
- Data transmission via a BUS, in particular all the trip unit settings, current
measurements for each phase, tripping causes, circuit breaker status.
It shall be possible to install a specific module that can provide the data
transmission, in particular all the trip unit settings, all electrical parameters
(current, energy, THD, voltage, etc.) measurements for each phase, tripping causes,
circuit breaker status, control and alarms.
2.13.6.1 The contactor shall meet with the requirements of IS: 2959.
2.13.6.2 Contactors shall be air break and electromagnetic type rated for uninterrupted
duty as defined in relevant IS.
2.13.6.3 The main contacts shall be of silver or silver alloy.
2.13.6.4 The insulation for the coils shall be of class ‘f’.
2.13.6.5 Each contactors shall be provided with 2 normally open and 2 normally closed
auxiliary contacts.
2.13.6.6 The contactors shall be in accordance to type 2 co-ordinations for short circuit
protection.
2.13.6.7 The contactor shall be suitable for uninterrupted duty (AC3) category.
2.13.6.8 All 3 Contactor sizes should be identical rating in Star-Delta feeders.
2.13.6.9 The electrical and mechanical endurance shall be as specified in IS code.
2.13.6.10 For all starters, component sizing shall be as per type-II co-ordination chart
prescribed by switchgear manufacturer + Contactor shall be one rating higher
than specified in type-2 coordination.
2.13.6.11 Remote start, stop, interlock wire should be wire up at terminals apart than
PLC/BMS/SCADA signals/commands.
2.13.6.12 Outgoing terminal of Starter should be 3Ph+E.
2.13.6.13 Auto-Manual Status and ON-OFF-Trip potential free signal required for
BMS/PCL wherever asked.
2.13.6.14 Thermal overload relays shall be of three elements positive acting ambient
temperature compensated type with adjustable settings.
2.13.6.15 Thermal overload relays shall be of self/hand reset type as specified in the
schedule.
2.13.6.16 All control terminals to OCS / PLC shall wired to single compartment.
(marshalling box).
2.13.6.17 Separate control terminal blocks shall provide for control wiring.
- From MCC to field in cable chamber.
- From MCC to OCS / PLC in marshalling jb.
- Al, Ao, Di & Do shall be provided on separate terminal block.
2.13.6.18 Following control signal exchange between OCS / PLC & MCC panel shall be
considered for AHU panel & package systems in process mcc —
a. From MCC panel to DES / PLC
- On, off & trip feedback — separate continuous potential free contacts.
- For VFD feeders — 4—2oma speed (rpm) feedback.
- Potential free contact for remote selection.
Contractor Signature MCGM
Page 80
SHASHI PRABHU & ASSOCIATES
Parameters to be monitored shall be Frequency, Line to line and average and line to
neutral and average voltage, phase wise and average current, phase wise and total
KVA, KW and P.F. reading and KWH monitoring.
User programmable facility for delta 2e and star 3e measurement, C.T. and P.T.
ratios, sliding window auto sync. And auto scrolling of parameters shall be
available.
Sensing shall be 3 phase, 4 wire measuring True RMS with voltage input range of
110 to 415 V nominal and current input of 5 amps or 1 amps as per field
configuration. Current range shall be from 50 mA to 7.5 A and burden on PT or CT
shall be app 0.2 VA.
Accuracy for kW / kWh shall be as per IS 1377 / CBIP88 and for all other
parameters shall be +/- 0.5% of full scale + 0.5% of reading + 1 digit. Digital
readout shall be of 3 rows of 4 digits each (12.5 mm size) with 7 segments bright
red LED. Input frequency shall be 50Hz / 60Hz +/- 5%. Power factor range shall be
0.5 lag – unit – 0.8 lead.
Resolution for power parameters shall be for 4 digits and energy parameters shall
be 8 digits. Display update shall be at every 15 seconds for demand parameters and
Page 81
SHASHI PRABHU & ASSOCIATES
1 sec for other parameters. Display sequence shall be parameter followed by value.
Temperature range shall be 0-50oC and humidity <95% non-condensing.
Where called for, CT's shall provide for current measuring. Each phase shall be
provided with separate CT of class I accuracy and VA burden as shown in SLD for
operation of associated metering and controls. Current transformer shall be in
accordance with IS: 2705 - 1964 as amended up to date.
The push button unit shall comprise of the contact element, a fixing holder, and
push button actuator. The push button shall be momentary contact type. The
contacts shall be of silver alloy and rated at 10 Amps continuous current rating. The
actuator shall be of stranded type and colour as per its usage for ON, OFF and Trip.
Indicating Lamp shall be LED type and shall supplied complete with translucent
covers to diffuse the lamp light. Indicating lamps shall be part of push buttons where
ever both are required and shall have testing facilities. Protection in form of MCB /
HRC fuse shall be provided for the lamps.
Selector Switches shall be of the heavy duty rotory type, with plates clearly marked to
show the operating position. They shall be of the semi-flush mounted type with only
the front plate and operating handle projecting.
Contractor Signature MCGM
Page 82
SHASHI PRABHU & ASSOCIATES
Circuit breaker control switches shall be of the spring return to neutral type.
The panel vendor / contractor shall be responsible for carrying out necessary study
for type 2 co-ordination for complete system with fault discrimination. All the data
considered for the study shall be discussed with the engineer.
2.15 Testing
Type test certificates for all switchgears and panel of similar rated busbar shall be
provided for
a) Short circuit withstand test
b) IP protection.
c) All switchgears and other components.
d) Temperature rise test
Page 83
SHASHI PRABHU & ASSOCIATES
1.1 General
1.1.1 Scope
Whether called for specifically or not, all accessories required for normal operation
of equipment are deemed to be considered as a part of the contractor’s scope of
supply. Hardware / fabricated supports required for mounting and installation of
the ATS is within the scope of work.
It is not the intent to specify completely herein, all details of design and
construction of the equipment. However, the equipment shall conform in all
respects to high standard of Engineering, design and workmanship and be capable
of performing in continuous commercial operation up to the Manufacturer’s
guarantees in a manner acceptable to the Engineer, who will interpret the meaning
of the drawings and specifications and shall be entitled to reject any work or
material which is not full accordance therewith.
The automatic transfer switches and controls shall conform to the requirements of:
IEEE Standard 446 - IEEE Recommended Practice for Emergency and Standby
Power Systems for Commercial and Industrial Applications
1.2 Products
The transfer switch shall be electrically operated and mechanically held. The
electrical operator shall be a momentarily energized, single-solenoid mechanism.
Main operators which include overcurrent disconnect devices, linear motors or
gears shall not be acceptable. The switch shall be mechanically interlocked to
ensure only two possible positions, normal or emergency. The switch shall be rated
for AC-33A duty cycle for mixed load application as mentioned in IEC 60947-6-1.
Page 84
SHASHI PRABHU & ASSOCIATES
All transfer switch sizes shall use only one type of main operator for ease of
maintenance and commodity of parts.
The switch shall be positively locked and unaffected by momentary outages, so that
contact pressure is maintained at a constant value and contact temperature rise is
minimized for maximum reliability and operating life.
All main contacts shall be silver composition. Switches rated 600 amperes and
above shall have segmented, blow-on construction for high withstand and close-on
capability and be protected by separate arcing contacts.
Inspection of all contacts shall be possible from the front of the switch without
disassembly of operating linkages and without disconnection of power conductors.
Switches rated 600 amps and higher shall have front removable and replaceable
contacts. All stationary and moveable contacts shall be replaceable without
removing power conductors and/or bus bars.
Where neutral conductors must be switched as shown on the plans, the AS shall be
provided with fully rated complete overlapping neutral transfer contacts. The
neutrals of the normal and emergency power sources shall be connected together
only during the transfer and retransfer operation and remain connected together
until power source contacts close on the source to which the transfer is being made.
The overlapping neutral contacts shall not overlap for a period greater than 100
milliseconds. Neutral switching contacts which do not overlap are not acceptable.
A single controller shall provide twelve selectable nominal voltages for maximum
application flexibility and minimal spare part requirements. Voltage sensing shall
be true RMS type and shall be accurate to 1% of nominal voltage. Frequency
sensing shall be accurate to 0.2%. The panel shall be capable of operating over a
temperature range of -20 to +60 degrees C and storage from -55 to +85 degrees C.
Page 85
SHASHI PRABHU & ASSOCIATES
1.3 Operation
A four line, 20 character LCD display and keypad shall be an integral part of the
controller for viewing all available data and setting desired operational parameters.
Operational parameters shall also be available for viewing and limited control
through the serial communications input port. The following parameters shall only
be adjustable via DIP switches on the controller:
Voltage and frequency on both the normal and emergency sources (as noted below)
shall be continuously monitored, with the following pickup, dropout and trip setting
capabilities (values shown as % of nominal unless otherwise specified):
Parameter Sources Dropout / Trip Pickup / Reset
Undervoltage N&E,3 70 to 98% 85 to 100%
Overvoltage N&E,3 102 to 115% 2% below trip
Underfrequency N&E 85 to 98% 90 to 100%
Overfrequency N&E 102 to 110% 2% below trip
Voltage unbalance N&E 5 to 20% 1% below dropout
The controller shall be capable (when activated by the keypad or through the serial
port) of sensing the phase rotation of both the normal and emergency sources. The
source shall be considered unacceptable if the phase rotation is not the preferred
rotation selected (ABC or CBA).
Source status screens shall be provided for both normal & emergency to pro-vide
digital readout of voltage on all 3 phases, frequency, and phase rotation.
1.3.3 Time Delays
Page 86
SHASHI PRABHU & ASSOCIATES
Two time delay modes (which are independently adjustable) shall be provided on re-
transfer to normal. One time delay shall be for actual normal power failures and
the other for the test mode function. The time delays shall be adjustable from 0 to
60 minutes. Time delay shall be automatically bypassed if the emergency source
fails and the normal source is acceptable.
A time delay shall be provided on shut down of engine generator for cool down,
adjustable from 0 to 60 minutes.
A time delay activated output signal shall also be provided to drive an external
relay(s) for selective load disconnect control. The controller shall have the ability to
activate an adjustable 0 to 5 minute time delay in any of the following modes:
The controller shall also include the following built-in time delays for optional
Closed Transition and Delayed Transition operation:
All time delays shall be adjustable in 1 second increments, except the extended
parallel time, which shall be adjustable in .01 second increments.
All time delays shall be adjustable by using the LCD display and keypad or with a
remote device connected to the serial communications port.
A three position momentary-type test switch shall be provided for the test /
automatic / reset modes. The test position will simulate a normal source failure.
The reset position shall bypass the time delays on either transfer to emergency or
retransfer to normal.
A SPDT contact, rated 5 amps at 30 VDC, shall be provided for a low-voltage engine
start signal. The start signal shall prevent dry cranking of the engine by requiring
the generator set to reach proper output, and run for the duration of the cool down
Page 87
SHASHI PRABHU & ASSOCIATES
setting, regardless of whether the normal source restores before the load is
transferred.
Auxiliary contacts, rated 10 amps, 250 VAC shall be provided consisting of one
contact, closed when the ATS is connected to the normal source and one contact
closed, when the ATS is connected to the emergency source.
LED indicating lights (16 mm industrial grade, type 12) shall be provided; one to
indicate when the ATS is connected to the normal source (green) and one to indicate
when the ATS is connected to the emergency source (red).
LED indicating lights (16 mm industrial grade, type 12) shall be provided and
energized by controller outputs. The lights shall provide true source availability of
the normal and emergency sources, as determined by the voltage sensing trip and
reset settings for each source.
The following features shall be built-in to the controller, but capable of being
activated through keypad programming or the serial port only when required
by the user:
An In phase monitor shall be provided in the controller. The monitor shall control
transfer so that motor load inrush currents do not exceed normal starting currents,
and shall not require external control of power sources. The in phase monitor shall
be specifically designed for and be the product of the ATS manufacturer.
The controller shall be capable of accepting a normally open contact that will allow
the transfer switch to function in a non-automatic mode using an external control
device.
The controller shall provide an internal engine exerciser. The engine exerciser shall
allow the user to program up to seven different exercise routines. For each routine,
the user shall be able to:
At the end of the specified duration the switch shall transfer the load back to normal and run
the generator for the specified cool down period. A 10-year life battery that supplies
power to the real time clock in the event of a power loss will maintain all time and
date information.
Page 88
SHASHI PRABHU & ASSOCIATES
The controller LCD display shall include a “System Status” screen which shall be
readily accessible from any point in the menu by depressing the “ESC” key a
maximum of two times. This screen shall display a clear description of the active
operating sequence and switch position. For example,
Normal Failed
Load on Normal
TD Normal to Emerg
2min15s
The controller shall contain a diagnostic screen for the purpose of detecting system
errors. This screen shall provide information on the status input signals to the
controller which may be preventing load transfer commands from being completed.
The controller shall have the ability to log data and to maintain the last 99 events,
even in the event of total power loss. The following events shall be time and date
stamped and maintained in a non-volatile memory:
1. Event Logging
1. Data and time and reason for transfer normal to emergency.
2. Data and time and reason for transfer emergency to normal.
3. Data and time and reason for engine start.
4. Data and time engine stopped.
5. Data and time emergency source available.
6. Data and time emergency source not available.
2. Statistical Data
1. Total number of transfers.
2. Total number of transfers due to source failure.
3. Total number of days controller is energized.
4. Total number of hours both normal and emergency sources are
available.
A full duplex RS485 interface & Ethernet TCP/IP RJ45 socket shall be installed in
the ATS controller to enable serial communications. The serial communications
shall be capable of a direct connect or multi-drop configured network. This module
shall allow for the seamless integration of existing or new communication transfer
devices through Modbus open protocol. The proprietary protocols are not
acceptable.
Page 89
SHASHI PRABHU & ASSOCIATES
The ATS/BPS shall be rated to close on and withstand the available RMS
symmetrical short circuit current at the ATS/BPS terminals with the type of
overcurrent protection shown on the plans.
The ATS/BPS shall be UL-1008 and IEC-60947-6-1 complied & in accordance with
UL 1008 listing and be labeled in accordance with that standard's 1½ and 3 cycle,
long-time ratings. ATS/BPS which are not tested and labeled with 1½ and 3 cycle
(any breaker) ratings and have series, or specific breaker ratings only, are not
acceptable.
The ATS rated 800A and above must be tested for 18/30 cycles short time
withstand capacity matching breaker fault level to enable use of ACB as a back up
protection device with short time delay setting for providing discrimination with the
downstream breakers.
1.0 Scope :
This specification covers design, manufacture, supply, installation, testing,
commissioning of thyristorised zero crossing – Real Time Power Factor Correction
(RTPFC) system with capacitor banks and harmonic filters suitable for continuous
duty. The capacities given in SLD are for reference only and are to be verified by
contractor after doing complete reactive load analysis and also necessary changes if
required in the rating of capacitors and harmonic filters is within scope of
contractor. All necessary hardware / supports required for installation of the panel
is scope of the works.
2.0 Standards :
The design, manufacture and performances of the power factor correction panel
with capacitor banks shall comply with all currently applicable statutes, regulations
and safety codes in the locations of installations. The capacitors used will also
conform to the latest applicable Indian / British / IEC standards. In particular, the
equipment shall conform to the latest revisions of the following.
IS : 13340 , 13341 & 12672 Capacitors for power system.
IS : 2208 , 13703 HRC cartridge fuse and links upto 600V
IS : 8828 MCB
IS : 13947 MCCBs
When the above standards are in conflict with these specifications, this
specification shall prevail.
Capacitor bank shall comprise of identical three phase capacitors in case of RTPFC.
The individual capacitor unit shall be manufactured out of MPP design, comprising
of bi-axially oriented metalised polypropylene film. Capacitor shall be tubular
(Cylindrical) MPP self filling type. The capacitor shall consist of many such elements
in series / parallel combinations for getting desired kVAr output. The dielectric
losses of capacitor shall be restricted to 0.5 watts per kVAr. The phase terminal
connections of the capacitor unit shall be brought out at the top, for suitable
connections. The capacitor shall be provided with suitably rated discharge resistor.
Contractor Signature MCGM
Page 90
SHASHI PRABHU & ASSOCIATES
The capacitor shall be provided with over pressure interrupter mechanism, which
will automatically disconnect faulty capacitor unit from the network without
bursting, bulging or exploding the capacitor.
The rating of the step should be decided by due consideration of de-rating due to
harmonic reactors, so as to ensure that each capacitor feeder delivers net output
equivalent to the step rating. PF capacitors should be rated for minimum 480/525
VAC, 3-ph, 50 Hz and shall be suitable to operate continuously with the harmonic
filters.
Each feeder shall be provided with 7 % detuned harmonic filter reactor 440 V, 3-
phase, 50 Hz of step rating. This reactor should be anti-resonance type, copper
wound, low noise with high linearity-low loss core (CRGO lamination of 46/51
grade insulation class F). The linearity of the reactor should not be less than 1.5 In
and suitable for continuous operation at system voltage without excess heating.
One no temperature switch should be provided internally with terminals brought
outside for control.
The capacitor control panel shall operate in Automatic mode as specified in the data
sheet. The panel for capacitor shall be fabricated from 2 mm thick sheet steel and
shall be finished with 7tank process followed by powder coating.
Earthing terminal shall be provided as per clause No 4.0 of this specification. The
panel shall be provided with suitably rated T.P. copper bus bar supported on epoxy
insulator. Each capacitor unit shall be connected to main bus bar through thyristor
of suitable rating with safety margin. Protective HRC/MCBs /MCCBs fuses of
suitable rating shall be provided with base / holder as mentioned in the drawing.
Connection shall be made with PVC insulated flexible copper cables having
crimped copper lugs. All capacitor units shall be earthed; sufficient ventilation shall
be provided to limit the temperature rise to maximum 85oC. Cooling fans shall be
provided to each heat sink as per requirement. Suitable exhaust fans shall be
provided in order to dissipate the internal heat of the panel and maintain the
internal temperature rise of the panel within safe limits. The operation of fans shall
be automatic with temperature sensor. Drawing pocket shall be provided at the
door of each panel. A 15-amp switch & socket and the lamp holder shall also be
provided for panel illumination at the suitable location.
The main Bus bar shall be terminated on suitably rated SFU /MCCB /SDU / ACB.
Detachable gland plates shall be provided with suitable knockout for incoming cable
connection from bottom/top as specified. Capacitor unit shall be mounted a frame of
adequate strength construction.
The panel shall be mounted on MS channel section at the bottom for easy
installation. The panel shall be provided with lifting hooks /eye bolts for handling.
Automatic Power Factor Correction Relay shall be provided with all related circuits
and three load CT’s for each phase in order to control/ achieve target Power Factor
OR unity as per setting.
The controller shall be capable of correcting Power Factor within 2 to 120 sec in case
of RTPFC. The capacitor shall be switched ON and OFF using thyristors from APFC
controller.
Page 91
SHASHI PRABHU & ASSOCIATES
6.0 EARTHING
Page 92
SHASHI PRABHU & ASSOCIATES
Page 93
SHASHI PRABHU & ASSOCIATES
Page 94
SHASHI PRABHU & ASSOCIATES
5. LIGHT FIXTURES
A. SPECIFICATIONS
Light fixtures as mentioned in the BOQ with the catalogue nos and makes shall be
installed. The fixtures shall be complete with ballast and shall be prewired by the
manufacturer.
Fans of the approved makes and size shown in the drawing shall be used and
install in the hook type M.S. box used by the CLIENT.
B. WORKMANSHIP
The fixture shall be installed on wall / ceiling as directed and as per manufacturer's
instruction, with necessary accessories for surface, concealed, suspended from
ceiling, bracket mounting etc. The job also includes connection of fixture with
respective outlet point with heat resistant wires through heat resistance sleeve and
PVC connector. The exhaust fan shall be installed complete with M.S. angle iron
mounting frame/ ring, G.I. louvers, wire mesh and plug at the end of the cord
including wiring & earthing etc. Proper earthing shall be provided to the fixtures
C. MODE OF MEASUREMENT
The unit rate shall be considered for fitting one fixture. The rate shall include
following
All fixing accessories, mounting bracket, ballast condensers and control gear
wherever applicable.
Supplying and fixing Ball and socket joints wherever required.
Earthing of fittings.
Electrical connections to fittings/fans from the junction box/ceiling rose.
Installation and interconnection of Electronic regulators for ceiling fans.
Supplying and fixing 300 mm. GI down rod for ceiling fans.
Page 95
SHASHI PRABHU & ASSOCIATES
6.0 UPS
1.0 Scope
The present special contract specifications constitute a call for best offers for the
supply of:
Where no exceptions are shown, the requirements of the present specifications will
be considered as accepted.
The UPS will have a CE mark as specified by Directives 73/23, 93/68, 89/336,
92/31 and 93/68.
The UPS will be designed and produced according to the following specifications:
The Uninterruptible Power System (UPS) will include the following operational
components:
The IGBT Rectifier/Battery charger will have an input isolating switch and a PWM
digital vector control system (DSP based) which, in addition to normal functions
Contractor Signature MCGM
Page 96
SHASHI PRABHU & ASSOCIATES
(AC/DC conversion), will automatically correct the input power factor to a value >
0.90 and limit the harmonic rejection to the mains at a THDI value < 3% at full
output load, and a THDi value < 7% for any other condition.
For the battery charger function, this converter will include built-in fuses and a
control circuit for the voltage and battery recharging current. The ripple current to
the batteries will be less than 0.05 C10. A microprocessor control function will
perform the following operations:
The IGBT inverter will have a PWM digital vector control system (DSP based),
capable of converting DC voltage from the IGBT rectifier or battery into AC voltage.
A rated output filter will create an output voltage sinusoidal envelope.
The control circuit, in addition to normal functions, will automatically adjust
nominal output power in accordance with ambient temperature.
Inverter should be able to deliver full active power at Unity power factor (KVA=KW)
UPS should support the full Power factor range (Lagging & leading) of load without
any deration in power rating
The static bypass switch will feature a separate power input and will consist of the
following:
• Static switches (SCR type), which can support overloads and short circuits
downstream of the UPS
• A back feed detection circuit as specified by IEC/EN 62040-1-1, clause 5.1.4
• A bypass and maintenance bypass input isolating switch with auxiliary
indicator contact
• An output load switch.
The control logic will be handled by digital algorithms (using vector control
techniques), similar to those used for the rectifier and the inverter. The static
bypass shall be equipped with a back feed protection device compliant with clause
5.1.4 of IEC/EN 62040-1-1; and a relay signal contact for the control of the
external back feed isolator to be installed on the bypass line upstream from the
UPS.
3.5 Batteries
Page 97
SHASHI PRABHU & ASSOCIATES
The VRLA, WET or NiCad batteries will feature an enclosure made of self-
extinguishing material.
The batteries will be housed in one or more racks/ cubicles and will be protected by
fuses located on each pole and via a dedicated switch.
This section describes the different operating modes of the Uninterruptible Power
System.
The UPS, using the above-mentioned digital vectorial control (DSP system), will be
able to operate both in double conversion and digital interactive modes.
The operating mode may be factory set by the manufacturer during testing or by the
customer using the appropriate diagnostic and control software.
The IGBT inverter will be synchronized with the bypass line so that the load can be
transferred from the inverter (conditioned line) to the bypass supply (direct line) and
vice versa without any break in the supply to the load.
In all operating modes, the battery charger will provide the power necessary to keep
the battery fully charged.
In this operating mode, under normal service conditions, the load will always be
supplied from the inverter, guaranteeing maximum protection for the load.
Upon failure or reduction of the primary AC source, the load will be supplied by the
battery through the inverter. During this phase, power will be drawn from the
battery. Visible and audible signals will alert the user to this operating state. The
remaining autonomy time will be calculated by a diagnostic algorithm.
The user will be alerted of these anomalous operating conditions via the alarm.
In this operating mode, under normal service conditions, the load will always be
supplied from the direct line through the bypass static switch. The quality of the
direct line will be monitored constantly using algorithms operated in real time by the
Contractor Signature MCGM
Page 98
SHASHI PRABHU & ASSOCIATES
If the direct line is outside the permitted tolerances, the load will be automatically
transferred to the conditioned line (inverter) without interruption.
In the absence of power supply to the direct and conditioned lines, the battery will
supply power to the loads through the inverter. During this phase, power will be
drawn from the battery and the battery charge will be reduced. Visible and audible
signals will alert the user to this operating state. The remaining autonomy time will
be calculated by a diagnostic algorithm.
When the quality and reliability of the direct line return within permitted limits, the
UPS will automatically start supplying the load from the direct line.
The UPS will be equipped with a bypass switch capable of transferring the load to
the bypass supply without interruption so as to enable the UPS to be switched off
and isolated for maintenance operations. The supply to the load will be maintained.
The controls for the electronic power supply modules will guarantee the following:
• A three-phase power supply which is ideal for the load
• Controlled battery recharging
• Minimum harmonic rejection to the upstream mains power supply (THDi<3%
at full load, THDi<7% in any other condition).
The UPS will feature a digital vector control based on a DSP (Digital Signal
Processor).
The special DSP algorithms must be designed to ensure rapid and flexible processing
of the detected data, allowing rapid generation of controlled variables. It must also be
possible to run the control for the electronic inverter devices in real time to:
• Improve short-circuit behavior (300% In for 10 ms, 150% In up to 5 s)
• Have a synchronised (precise phase) angle between UPS output and bypass
network, in the event of mains voltage distortion
• Highly flexible parallel operation.
Operation and control of the UPS should be provided through the use of micro-
processor-controlled logic. Indications, measurements and alarms, together with
battery autonomy, will be shown on a graphic liquid crystal display (LCD). The
procedures for start up, shutdown and manual transfer of the load to and from
bypass will be explained in clear step-by-step sequences on the LCD display.
Page 99
SHASHI PRABHU & ASSOCIATES
Measurements: this page holds the full set of measurements for each functional
block (rectifier, bypass, booster/charger, batteries, inverter and load).
Battery: displays the battery status/values including temperature, cell voltage,
capacity and run time as well as commands for allowing the user to configure
battery testing.
Tools: this page allows users to customize the settings of the LCD display and to
select the desired language, choosing between 15 languages.
5.1 Controls
The UPS will be provided with the following controls:
• Inverter start
• Inverter stop
• Reset faults
• Buzzer/mute alarm
•
5.2 Measurements
The UPS will provide the measurements (voltage, current and frequency) for every
single internal functional block and this information will be directly accessible on
the display, via the measurements button.
A voltage-free input will also be provided to disable the static switches and all power
converters (EPO) in case of emergency.
Programmable I/O contacts (at least 4 voltage-free outputs and 2 inputs).
6.0 TELEMONITORING
This section defines the requirements of the system for remote monitoring and
control from the Service Centre.
The system will guarantee single or parallel UPS surveillance, 24 hours a day for
Contractor Signature MCGM
Page 100
SHASHI PRABHU & ASSOCIATES
365 days a year by authorised technical personnel operating remotely. The system
will provide a detailed, preventive analysis of connected UPS, without any of the
disruption associated with an on-site visit.
Page 101
SHASHI PRABHU & ASSOCIATES
VENDOR
PARAMETERS UNIT SPECIFICATION
CONFIRMATION
Stability in dynamic conditions for 100% load step
(%) ±5%
variations
Load crest factor without derating 3:1
Output voltage distortion with 100% linear load (%) <1
Output voltage distortion with non-linear load as
(%) <3
specified by IEC/EN 62040-3
Output frequency stability in synchronization with
(%) ±1
mains (± 2 ± 3 ± 4 selectable)
Output frequency stability with internal clock (%) ±0.1
Frequency slew rate (Hz/sec) <1
Permitted overload:
for 10 minutes (%) 125
for 60 seconds (%) 150
Short circuit current:
300% In (ms) 10
150% In (s) 5
UPS characteristics
Maximum UPS cabinet dimensions WxHxD (mm)
Noise level measured @ 1 meter and @ 100% load
(dBA) 70 dba
according to ISO 3746
AC/AC efficiency – double conversion mode @
(%) 94.5
100% load(inbuilt K13 iso. Transformer)
Efficiency in digital interactive mode @ 100% load (%) 98
EMC compatibility as per EN 62040-2 Class C3
Degree of protection IP 20
Frame colour RAL 7021
The constructional and functional characteristics of UPS must be in line with the
state-of-the-art technology in this field.
The supplying company must be able to provide proof that it is ISO 9001-2000 and
ISO 14001 certified for design and manufacturing and for the provision of services.
The UPS will be guaranteed for one year during which time the Supplier will provide
technical assistance.
The offer must include:
Contractor Signature MCGM
Page 102
SHASHI PRABHU & ASSOCIATES
1.0 GENERAL
1.1 The lightning protection system shall be of the enhanced type which is designed to
attract lightning to a preferred point and safely convey the lightning energy to
ground with minimal risk of side flashing via a predetermined route.
Contractor Signature MCGM
Page 103
SHASHI PRABHU & ASSOCIATES
1.2 The complete lightning protection system will comprise the following key
components.
2.1 The advanced lightning rod shall be of a “Controlled Advanced Triggering” type and
will respond dynamically upon leader activity in the near area.
2.2 The advanced lightning rod shall be configured as a spheroid which is comprised of
separate electrically isolated panels surrounding an earthed central finial.
2.3 The insulation material used to electrically isolate the panels shall be comprised of
a base polymer which provides high ozone and UV resistance with a dielectric
strength of 24 – 38 KV/mm.
2.4 The external shape of the advanced lightning rod shall be such that it will limit the
development of sharp point corona discharge under static thunderstorm conditions.
2.5 The upper section of the central finial shall be rounded to provide a blunt surface.
2.6 The upper section of the central finial shall be rated to withstand 200KA.
2.7 An air gap shall be provided between the individual electrically isolated panels (4
panels) and the blunt configured tip of the central rod. Dome shapes and pointed
central rods will not be acceptable.
2.8 Arcing shall occur between the panel sections of the spheroid and the blunt
configured finial tip only upon the progression of a lightning leader.
2.9 The advanced lightning rod shall have no moving parts and will have no
dependence on external power supply or batteries. There should be no high
impedance static drain unit between the central rod and the panels.
2.10 Under a normal atmosphere all components of the advanced lightning terminal
shall be non corroding.
2.11 The advanced lightning rod shall be installed at a minimum of 10 metres from the
ground.
2.12 The advanced lightning rod shall be insulated from all surrounding points and
features of the structure being protected.
2.13 The advanced lightning rod shall not be installed in a corrosive environment unless
the manufacturers written approval has first been granted.
Page 104
SHASHI PRABHU & ASSOCIATES
2.14 The advanced lightning rod shall be installed as per the manufacturers
instructions.
2.15 The advanced lightning rod shall not be of the ESE type and all lightning terminals
claiming compliance to NF C17-102 shall not be considered suitable.
2.16 The advanced lightning rod shall have been tested to the following standard IEC
601:1989.
2.17 The lightning rod shall be shown to have withstood a minimum current impulse of
a 180kA 8/20 μs waveform as per the test standard IEC 60-1:1989.
3.1 The mounting pole used to support the lightning rod shall be a circular insulating
fibreglass tube at a minimum height of 2 metres. The pole will have an outside
diameter of 68mm.
3.2 The mounting pole and supports shall be securely fixed with brackets and guy
wires where required.
3.3 The downconductor shall pass through the centre of the insulating pole for the
entire length of the pole.
4.1 The high voltage shielded cable shall consist of a core filler, stranded copper
conductor, insulation material, outer copper conductor with external conductive
sheath.
4.2 The main copper conductor within the high voltage shielded cable shall have a
minimum cross sectional area of 50mm².
4.3 The outer diameter of the high voltage shielded cable shall be less than 38mm.
4.4 The high voltage shielded cable shall have a maximum inductance of 25 nH/m.
4.5 The main copper conductor shall allow for direct connection to the lightning rod
through the use of a compression lug.
4.6 The high voltage shielded cable shall be fixed to the structure through the use of
suitable saddles every two metres for the length of the cable route.
4.7 The high voltage shielded cable shall be installed as per manufacturers instructions
and shall not be subject to bends of less than 0.6 metres radius.
4.8 The high voltage shielded cable shall have been tested to the following standard IEC
60-1:1989.
Page 105
SHASHI PRABHU & ASSOCIATES
4.9 The high voltage shielded cable shall have been subjected and successfully
withstood a maximum voltage of 280kV in compliance to IEC test standard, IEC
600601, 2nd edition, 1989-11.
5.1 All systems shall be installed complete with the lightning strike recorder.
5.2 The lightning strike recorder shall contain a mechanical 6 digit display which will
register all lightning discharges with a sensitivity of 1500A 8/20 μs peak current
impulse.
5.3 The lightning strike recorder shall be housed in a IP 67 rated enclosure and will
operate without reliance on batteries or an external power source.
5.4 The lightning strike recorder shall be installed as per the manufacturers
instructions.
5.5 It shall be shown that the event recording device has been successfully tested under
test standard IEC 60-1:1989.
6.0 EARTHING
6.1 The earthing system shall incorporate the following individual components or a
combination of the following – 25 x 1mm flat copper tape buried to a depth of not
more than 800mm or by deep driven copper bonded steel core earth rods. All
components of the earthing system shall be electrically connected to the central
injection rod which is securely connected to the lower end of the high voltage
shielded cable.
6.2 The earthing system shall be installed so that the final impedance reading does not
exceed 10 Ohms unless otherwise stipulated by the lightning protection
manufacturer or consulting engineer.
6.3 It is recommended that the earthing system is bonded to all structural reinforcing
steel of the building, along with all connecting services.
6.4 The use of ground resistance improvement material shall be applied in order to
reduce the resistivity levels of the earthing system.
Page 106
SHASHI PRABHU & ASSOCIATES
1.1 General
1.1.1 Scope
Whether called for specifically or not, all accessories required for normal
operation of equipment are deemed to be considered as a part of the contractor’s
scope of supply. Hardware / fabricated supports required for mounting and
installation of the ATS is within the scope of work.
It is not the intent to specify completely herein, all details of design and
construction of the equipment. However, the equipment shall conform in all
respects to high standard of Engineering, design and workmanship and be
capable of performing in continuous commercial operation up to the
Manufacturer’s guarantees in a manner acceptable to the Engineer, who will
interpret the meaning of the drawings and specifications and shall be entitled to
reject any work or material which is not full accordance therewith.
The automatic transfer switches and controls shall conform to the requirements of:
IEEE Standard 446 - IEEE Recommended Practice for Emergency and Standby
Power Systems for Commercial and Industrial Applications
1.2 Products
Contractor Signature MCGM
Page 107
SHASHI PRABHU & ASSOCIATES
The transfer switch shall be electrically operated and mechanically held. The
electrical operator shall be a momentarily energized, single-solenoid mechanism.
Main operators which include overcurrent disconnect devices, linear motors or
gears shall not be acceptable. The switch shall be mechanically interlocked to
ensure only two possible positions, normal or emergency. The switch shall be rated
for AC-33A duty cycle for mixed load application as mentioned in IEC 60947-6-1.
All transfer switch sizes shall use only one type of main operator for ease of
maintenance and commodity of parts.
The switch shall be positively locked and unaffected by momentary outages, so that
contact pressure is maintained at a constant value and contact temperature rise is
minimized for maximum reliability and operating life.
All main contacts shall be silver composition. Switches rated 600 amperes and
above shall have segmented, blow-on construction for high withstand and close-on
capability and be protected by separate arcing contacts.
Inspection of all contacts shall be possible from the front of the switch without
disassembly of operating linkages and without disconnection of power conductors.
Switches rated 600 amps and higher shall have front removable and replaceable
contacts. All stationary and moveable contacts shall be replaceable without
removing power conductors and/or bus bars.
Where neutral conductors must be switched as shown on the plans, the AS shall be
provided with fully rated complete overlapping neutral transfer contacts. The
neutrals of the normal and emergency power sources shall be connected together
only during the transfer and retransfer operation and remain connected together
until power source contacts close on the source to which the transfer is being made.
The overlapping neutral contacts shall not overlap for a period greater than 100
milliseconds. Neutral switching contacts which do not overlap are not acceptable.
A single controller shall provide twelve selectable nominal voltages for maximum
application flexibility and minimal spare part requirements. Voltage sensing shall
be true RMS type and shall be accurate to 1% of nominal voltage. Frequency
Page 108
SHASHI PRABHU & ASSOCIATES
sensing shall be accurate to 0.2%. The panel shall be capable of operating over a
temperature range of -20 to +60 degrees C and storage from -55 to +85 degrees C.
1.3 Operation
A four line, 20 character LCD display and keypad shall be an integral part of the
controller for viewing all available data and setting desired operational parameters.
Operational parameters shall also be available for viewing and limited control
through the serial communications input port. The following parameters shall only
be adjustable via DIP switches on the controller:
Voltage and frequency on both the normal and emergency sources (as noted below)
shall be continuously monitored, with the following pickup, dropout and trip setting
capabilities (values shown as % of nominal unless otherwise specified):
Parameter Sources Dropout / Trip Pickup / Reset
Undervoltage N&E,3 70 to 98% 85 to 100%
Contractor Signature MCGM
Page 109
SHASHI PRABHU & ASSOCIATES
The controller shall be capable (when activated by the keypad or through the serial
port) of sensing the phase rotation of both the normal and emergency sources. The
source shall be considered unacceptable if the phase rotation is not the preferred
rotation selected (ABC or CBA).
Source status screens shall be provided for both normal & emergency to pro-vide
digital readout of voltage on all 3 phases, frequency, and phase rotation.
Two time delay modes (which are independently adjustable) shall be provided on re-
transfer to normal. One time delay shall be for actual normal power failures and
the other for the test mode function. The time delays shall be adjustable from 0 to
60 minutes. Time delay shall be automatically bypassed if the emergency source
fails and the normal source is acceptable.
A time delay shall be provided on shut down of engine generator for cool down,
adjustable from 0 to 60 minutes.
A time delay activated output signal shall also be provided to drive an external
relay(s) for selective load disconnect control. The controller shall have the ability to
activate an adjustable 0 to 5 minute time delay in any of the following modes:
The controller shall also include the following built-in time delays for optional
Closed Transition and Delayed Transition operation:
Contractor Signature MCGM
Page 110
SHASHI PRABHU & ASSOCIATES
All time delays shall be adjustable in 1 second increments, except the extended
parallel time, which shall be adjustable in .01 second increments.
All time delays shall be adjustable by using the LCD display and keypad or with a
remote device connected to the serial communications port.
A three position momentary-type test switch shall be provided for the test /
automatic / reset modes. The test position will simulate a normal source failure.
The reset position shall bypass the time delays on either transfer to emergency or
retransfer to normal.
A SPDT contact, rated 5 amps at 30 VDC, shall be provided for a low-voltage engine
start signal. The start signal shall prevent dry cranking of the engine by requiring
the generator set to reach proper output, and run for the duration of the cool down
setting, regardless of whether the normal source restores before the load is
transferred.
Auxiliary contacts, rated 10 amps, 250 VAC shall be provided consisting of one
contact, closed when the ATS is connected to the normal source and one contact
closed, when the ATS is connected to the emergency source.
LED indicating lights (16 mm industrial grade, type 12) shall be provided; one to
indicate when the ATS is connected to the normal source (green) and one to indicate
when the ATS is connected to the emergency source (red).
LED indicating lights (16 mm industrial grade, type 12) shall be provided and
energized by controller outputs. The lights shall provide true source availability of
the normal and emergency sources, as determined by the voltage sensing trip and
reset settings for each source.
The following features shall be built-in to the controller, but capable of being
activated through keypad programming or the serial port only when required
by the user:
Terminals shall be provided for a remote contact which opens to signal the ATS to
transfer to emergency and for remote contacts which open to inhibit transfer to
emergency and/or retransfer to normal. Both of these inhibit signals can be
activated through the keypad or serial port.
Contractor Signature MCGM
Page 111
SHASHI PRABHU & ASSOCIATES
An In phase monitor shall be provided in the controller. The monitor shall control
transfer so that motor load inrush currents do not exceed normal starting currents,
and shall not require external control of power sources. The in phase monitor shall
be specifically designed for and be the product of the ATS manufacturer.
The controller shall be capable of accepting a normally open contact that will allow
the transfer switch to function in a non-automatic mode using an external control
device.
The controller shall provide an internal engine exerciser. The engine exerciser shall
allow the user to program up to seven different exercise routines. For each routine,
the user shall be able to:
At the end of the specified duration the switch shall transfer the load back to normal
and run the generator for the specified cool down period. A 10-year life battery that
supplies power to the real time clock in the event of a power loss will maintain all
time and date information.
The controller LCD display shall include a “System Status” screen which shall be
readily accessible from any point in the menu by depressing the “ESC” key a
maximum of two times. This screen shall display a clear description of the active
operating sequence and switch position. For example,
Normal Failed
Load on Normal
TD Normal to Emerg
2min15s
Page 112
SHASHI PRABHU & ASSOCIATES
The controller shall contain a diagnostic screen for the purpose of detecting system
errors. This screen shall provide information on the status input signals to the
controller which may be preventing load transfer commands from being completed.
The controller shall have the ability to log data and to maintain the last 99 events,
even in the event of total power loss. The following events shall be time and date
stamped and maintained in a non-volatile memory:
1. Event Logging
1. Data and time and reason for transfer normal to emergency.
2. Data and time and reason for transfer emergency to normal.
3. Data and time and reason for engine start.
4. Data and time engine stopped.
5. Data and time emergency source available.
6. Data and time emergency source not available.
2. Statistical Data
1. Total number of transfers.
2. Total number of transfers due to source failure.
3. Total number of days controller is energized.
4. Total number of hours both normal and emergency sources are
available.
A full duplex RS485 interface & Ethernet TCP/IP RJ45 socket shall be installed in
the ATS controller to enable serial communications. The serial communications
shall be capable of a direct connect or multi-drop configured network. This module
shall allow for the seamless integration of existing or new communication transfer
devices through Modbus open protocol. The proprietary protocols are not
acceptable.
The ATS/BPS shall be rated to close on and withstand the available RMS
symmetrical short circuit current at the ATS/BPS terminals with the type of
overcurrent protection shown on the plans.
The ATS/BPS shall be UL-1008 and IEC-60947-6-1 complied & in accordance with
UL 1008 listing and be labeled in accordance with that standard's 1½ and 3 cycle,
Contractor Signature MCGM
Page 113
SHASHI PRABHU & ASSOCIATES
long-time ratings. ATS/BPS which are not tested and labeled with 1½ and 3 cycle
(any breaker) ratings and have series, or specific breaker ratings only, are not
acceptable.
The ATS rated 800A and above must be tested for 18/30 cycles short time
withstand capacity matching breaker fault level to enable use of ACB as a back up
protection device with short time delay setting for providing discrimination with the
downstream breakers.
9 BUSDUCT
Scope:
Whether called for specifically or not, all accessories required for normal
operation of equipment are deemed to be considered as a part of the contractor’s
scope of supply. Hardware / fabricated supports required for mounting and
installation of the busducts / rising mains is within the scope of work.
Page 114
SHASHI PRABHU & ASSOCIATES
It is not the intent to specify completely herein, all details of design and
construction of the equipment. However, the equipment shall conform in all
respects to high standard of Engineering, design and workmanship and be
capable of performing in continuous commercial operation up to the
Manufacturer’s guarantees in a manner acceptable to the Engineer, who will
interpret the meaning of the drawings and specifications and shall be entitled to
reject any work or material which is not full accordance therewith.
General
The size of the neutral bus bar shall 100% of the phase busbar.
Note: Before fabrication and installation of the bus duct is taken up, the layout of
the M.V. switchgear and transformer shall be got approved by Engineer and the bus
duct layout properly co-ordinated.
Standards
Rating details:
(I) Rated 3 Phase voltage: 415 volt, IP 54 Category
(II) Standard insulation withstand for one minute: 1000 v
(III) Rated frequency: 50 HZ
(IV) Asymmetrical short circuit current: 60 KA r.m.s.
(V) Maximum bubar operating temperature at full rated current above ambient:
55oC
(VI) Maximum ambient temperature: 500 C
(VII) Current rating: 3500 A TPN EC grade sleeved Cu busbars busduct.
(VIII) Rated impulse withstand voltage – 12 KV at 1000 V
9.1 Enclosures
9.1.1 Construction
The eclosure shall be made from 16 SWG GI / CRCA sheet steel powder coated to
shade RAL 7032 (or such other shade) or from extruded aluminium sheet. Busbars
would be in sandwich construction and the conductors shall be individually
insulated with four layers of insulating film. Inner layer shall be of glass MICA and
outer layer shall be of polyester material of Class F. Alternatively extrusion of class
Contractor Signature MCGM
Page 115
SHASHI PRABHU & ASSOCIATES
For installation as rising mains / vertical installation at each floor a set consisting
of 2 spring hangers shall be provided for fixing it on channels grouted in wall. At
the start of run hangers without springs may be used for the rigid support. In
addition horizontal supports shall be provided -2 nos per floor to hold busbars in
position. On rising mains on front face of the busbar trunking Tap Off points shall
be provided for inserting plug in boxes. No. of tap of points at each floor shall be as
per requirement given in BOQ / SLD; but min distance between tap off points shall
be kept around 500 mm. Each tap off opening closed by insulated shutters forming
part of BBT, when not occupied by plugin boxes. Neutral cross section shall be
same as phase cross section. Necessary vertical / horizontal bends / Tees / fire
barriers etc shall be provided as required by the layout.
Busbar trunking shall be rigidly fixed to the side walls or suspended from ceiling by
supports as per requirements detailed in the shop layout.
At the termination either on the transformer side / generator end / switchgear end,
busduct shall be provided with flange end / adaptor box / copper flexible
(preferably multisheath types) / phase change overs if required to connect busbars
of busduct to the busbars of switchgears / transformers / generator terminals.
Expansion units shall be installed after every 50 mtrs of uninterrupted run for
composite expansion of complete bus trunking run.
Integral Earth Bus of copper should be provided for entire length of the bus trunk.
Suitable copper links shall be provided at the joints of bus duct. Earth bus at the
point of wall entry should have suitable arrangement as approved by the purchaser.
Size of earth bus shall be as per IEC 60439.
These are required for rising Mains. Plug in boxes will be of draw out type. Contacts
will be of silver plated copper and spring loaded. Earth connection will be the first
to make and last to break during insertion and withdrawal. Plug in box will be
made from 1.6mm CRCA sheet steel powder coated or GI. Inside the plug in boxes
MCCB / ACB will be located as per requirements. The operating handle will be
interlocked with plug in box cover so that MCCB can be operated only with suitable
cover in closed position. If required the plug in box will be interlocked with bus bar
trunking so that it could be inserted or removed with the plug in box lid opened.
MCCB/ACB will be of 4 pole type unless otherwise specified in BOQ. Short circuit
breaking capacity of MCCB in PIB should preferably be same as short circuit with
stand for one second of bus bar trunking.
Contractor Signature MCGM
Page 116
SHASHI PRABHU & ASSOCIATES
The End feed unit will be manufactured from 1.6mm thick steel with powder
coating to shade RAL 7032 or of GI. Inside the End feed unit MCCB/ACB of
required rating and specification will be located. End feed units at top will be
connected to Bus bars of Rising Mains through solid connections. Terminals at the
bottom will be provided to accept cable connections as required. The operating
handle of MCCB/ACB will be interlocked so that the door can be opened only when
MCCB or ACB are in off position. The current rating of MCCB should correspond
with current rating of bus bar trunking and short circuit breaking capacity with one
second short circuit withstand of bus bar trunking.
9.4 Transposition:
Transposition of bus bars should be done preferably in ACB adaptor chamber. Cost
of adaptor chamber should be included in indoor bus duct. The tenderer should
indicate clearly for any extra prices if required, for adaptor chamber and the length
of adaptor chamber in that case should be indicated clearly. Terminal arrangement
of transformers will be furnished to the successful tenderer at a later date.
The tenderer must furnish complete data for the bus duct for calculating the net current
rating of bus duct.
9.6 Drawing:
Detailed layout and fabrication drawings showing the sizes of bus bars enclosure,
fixing, details, supports, bends, joints, wall entry assembly etc. shall be submitted
by the Contractor for approval of Engineer in charge/purchaser’s comments
/modifications suggested by; the Purchaser shall be incorporated by the Contractor.
Actual fabrication of the bus duct shall be carried out only after the approval
of the purchaser, with respect to actual physical location of main panel
incomer and transformer L.T. cable box for dimensions (i.e. cross checking of
dimensions and phase sequence shown in panel / transformer GA drawings)
Page 117
SHASHI PRABHU & ASSOCIATES
GENERAL :
The medium voltage cables shall be supplied, laid, connected, tested and
commissioned in accordance with the drawings, specifications, relevant Indian
Standards specifications, manufacturer’s instructions. The cables shall be delivered
at site in the original drums with manufacturer’s name, size and type clearly
written on the drums.
All cables shall be adequately protected against any risk of mechanical damage to
which they may be liable in normal conditions of handling during transportation,
loading, unloading etc.
The cable shall be supplied in single length i.e. without any intermediate joint or
cut unless specifically approved by the client.
The cable ends shall be suitably sealed against entry of moisture, dust, water etc.
with cable compound as per standard practice.
CONDUCTOR :
Uncoated, annealed copper of high conductivity, upto 4 mm2 size the conductor
shall be solid and above 4 mm2 the conductors shall be concentrically stranded as
per IEC : 228.
INSULATION :
CORE INDENTIFICATION :
ASSEMBLY :
Two, three or four insulated conductors shall be laid up, filled with non-hygroscopic
material and covered with an additional layer of thermoplastic material.
ARMOUR :
Contractor Signature MCGM
Page 118
SHASHI PRABHU & ASSOCIATES
Galvanised steel flat strip / round strips applied helically in single layers complete
with covering the assembly of cores.
For cable size upto 10 sq mm : Armour of 1.4 mm dia G.I. round wire
SHEATH :
Inner sheath shall be extruded type and shall be compatible with the insulation
provided for the cables.
Outer sheath shall be of an extruded type layer of suitable PVC material compatible
with the specified ambient temp. of 50oc and operating temperature of cables. The
sheath shall be resistant to water, ultra violet radiation, fungus, termite and rodent
attacks. The colour of outer sheath shall be black.
Sequential length marking along with size and other standard parameters shall be
required at every 1.0 mtr on the outer sheath.
Aluminium Conductor A
XLPE Insulation 2X
Steel round wire armour W
Steel flat strip armour F
Steel Double round wire armour WW
Steel Double flat strip armour FF
Non-magnetic (Al.) round wire armour Wa
Non-magnetic (Al.) flat strip armour Fa
PVC outer sheath Y
TESTING :
Finished cable tests at manufacturers works : The finished cables shall be tested at
manufacturer’s works for all the routine tests for all the length and size of cables to
be delivered at site and the certificate for the same shall be furnished to client. If
required the cables shall be tested in presence of the client’s representative.
Voltage test : Each core of cable shall be tested at room temperature at 3 KV A.C.
R.M.S. for duration of 5 minutes.
Conductor resistance test : The D.C. resistance of each conductor shall be
measured at room temperature and the results shall be corrected to 20oc to check
the compliance with the values specified in the Is 8130 – 1976.
Cable tests before and after laying cables at site :
Insulation resistance test between phases, phase to neutral and phase to earth.
Continuity test of all the phases, neutral and earth continuity conductor.
Contractor Signature MCGM
Page 119
SHASHI PRABHU & ASSOCIATES
All the tests shall be carried out in accordance with the relevant IS code of practise
and Indian Electricity Rules. The vendor shall provide necessary instruments,
equipments and labour for conducting the above tests and shall bear all the
expenses in connection with such tests. All tests shall be carried out in the
presence of client and the results shall be prescribed in forms and submitted.
CABLE MARKING :
The outer sheath shall be legibly embossed at every meter with following legend :
ELECTRIC CABLE : 1100 V, SIZE :___C X ____ MM2 with Manufacturers name,
year of manufacturing and ISI symbol.
After tests at manufacturer’s woks, both ends of the cables shall be sealed to
prevent the ingress of moisture during transportation and storage.
Cable shall be supplied in length of 500 mtrs or as required in non-returnable
drums of sufficiently sturdy construction.
Cables of more than 250 meters shall also be supplied in non-returnable drums.
The spindle hole shall be minimum 110 mm in diameter.
Each drum shall bear on the outside flange, legibly and indelibly in the Englist
literature, a distinguishing number, the manufacturer’s name and particulars of the
cable i.e. voltage grade, length, conductor size, cable type, insulation type, and
gross weight shall also be clearly visible. The direction for rolling shall be indicated
by an arrow. The drum flange shall also be marked with manufacturer’s name and
year of manufacturing etc.
CABLE TERMINATION:
Cable terminations shall be made with aluminium crimped type solder less lugs for
all aluminium cables and stud type terminals. For copper cables copper crimped
solder less lugs shall be used.
Crimping shall be done with the help of hydraulically operated crimping tool.
For joints where by cable is with aluminium conductor and busbars are aluminium,
bimetallic lugs shall be used with compound. CUPAL type of washers shall be used.
Crimping tool shall be used for crimping any size of cable.
CABLE GLANDS:
FERRULES:
Page 120
SHASHI PRABHU & ASSOCIATES
CABLE JOINTS:
Kit type joint shall be done and filled with insulating compound. The joint should
be for 1.1 KV grade insulation.
WORKMANSHIP
Cables shall be laid in the routes marked in the drawings. Where the route is not
marked, the Contractor shall mark it out on the drawings and also on the site and
obtain the approval of the CLIENT AND/OR ITS ARCHITECT before laying the cable.
Procurement of cables shall be on the basis of actual site measurements and the
quantities shown in the schedule of work shall be regarded as a guide only.
Cables shall be laid on walls, cable trays, inside shafts or trenches. Saddling or
support for the cable shall not be more than 500 mm apart. Plastic identification tags
shall be provided at every 30 m.
Cables shall be bent to a radius not less than 12 (twelve) times the overall diameter
of the cable or in accordance with the manufacturer's recommendations whichever is
higher.
In the case of cables buried directly in ground, the cable route shall be parallel or
perpendicular to roadways, walls etc unless marked on drawing by architect /
consultant. Cables shall be laid on an excavated, graded trench, over a sand or soft
earth cushion to provide protection against abrasion. Cables shall be protected with
brick or cement tiles on all the three sides as shown on drawings. Width of
excavated trenches shall be as per drawings. Back fill over buried cables shall be with a
minimum earth cover of 750 mm to 1000 mm. The cables shall be provided with cables
markers at every 10 meters and at all loop points.
All cables shall be full runs from panel to panel without any joints or splices.
Cables shall be identified at end termination indicating the feeder number and the
Panel/Distribution board from where it is being laid. Cable termination for
conductors up to 4 sq.mm. may be insertion type and all higher sizes shall have
compression type lugs. Cable termination shall have necessary brass glands. The end
termination shall be insulated with a minimum of six half-lapped layers of PVC tape.
Cable armouring shall be earthed at both ends.
In case of cables entering the buildings. It would be done duly only through pipes.
The pipes shall be laid in slant position, so that no rainwater may enter the
building. After the cables are tested the pipes shall be sealed with M. seal & then
tarpaulin, shall be wrapped around the cable for making the entry watertight.
Testing : MV cables shall be tested upon installation with a 500 V `Meggar and the
following readings established:
Continuity on all phases.
Insulation Resistance.
between conductors.
all conductors and ground.
Page 121
SHASHI PRABHU & ASSOCIATES
All test readings shall be recorded and shall form part of the completion
documentation.
Cable joints shall be done as per regular practice and check shall be carried out for
loose connections and leakages. Insulation cutting shall be done properly taking
care that no area of the conductor remains exposed. Crimping shall be done with the
help of hydraulic tool. Proper insulation tape shall be applied at the cable and lug joint.
client, his consultant and their authorized representative shall have the right to
inspect and test or get inspected and tested the goods at the works of the Seller or
its sub suppliers any time during manufacture and prior to dispatch and to inspect
within a reasonable time after arrival of goods at the ultimate destination and
during and after erection, testing and commissioning. The goods shall not be
deemed accepted until after the said inspection, testing and commissioning and
signing of the Acceptance Certificate. Failure to make any inspection of or payment
for or acceptance of goods shall in no way impair client right to reject non-
conforming goods or to avail itself of any other remedies to which client may be
entitled, notwithstanding client knowledge of the nonconformity, its substantiality
in the case of its discovery. In the event of failure of Seller to remove the rejected
goods within the time allowed, client shall have the right to dispose of the same at
the seller’s risk and cost. During the time the rejected goods lie with client awaiting
removal by the seller, they will so lie at the seller’s risk. All goods rejected by client
after receipt at the destination shall be removed by the seller within a reasonable
time allowed by client, not exceeding 30 (thirty) days at seller’s expense and risk.
The Seller will permit client Inspectors, Consultant and their authorized
representatives free access during normal working hours to his works, godown,
storage or loading spot etc. and will give them all necessary assistance to perform
their task including free use of all accessories, testing and control instruments. The
seller shall ensure that the same facilities are granted by his sub-suppliers.
Unless specifically stated to the contrary in the order, all expenses relevant to the
preparation and performance of testing, inspection and preparation of any test
reports or certificates shall be borne by the Seller EXCEPT for the salaries, fees,
Contractor Signature MCGM
Page 122
SHASHI PRABHU & ASSOCIATES
The sellers shall carry out tests related to performance tests as described in the
specifications and specified in the order. All such performance tests shall be at
supplier costs. Supplier shall also provide all the tests certificates and documents
as demanded by the Inspector for his satisfaction that the order has been executed
as per PO specifications. All such certificates, documents in original shall be
submitted to the Client before dispatch of material. The goods shall be dispatched
from suppliers shop only after written confirmation from clients / or its authorized
representative.
The contractor shall consider all cost towards inspection of goods by consultant /
EIC at factory / manufacturers works prior to shipping for 2 persons. (travelling
(Air / 1st AC) / stay etc complete)
Page 123
SHASHI PRABHU & ASSOCIATES
Lightning Protection:
This part of IEC 62305 provides the requirements for protection of a structure
against physical damage by means of a lightning protection system (LPS), and for
protection against injury to living beings due to touch and step voltages in the
vicinity of an LPS.
Lightning is one of the most devastating natural phenomena. There are many
discharges during lightning storms and some of them can even reach hundreds of
kilo amperes. The electrical discharges are a great hazard to people, animal,
buildings and electronic equipment’s. Until now, there is no device that can prevent
lightning formation or lightning strikes. However, it is possible to create a path
(divert) for the lightning discharge to the ground which will minimise the damage to
the environment through a well-designed Lightning Protection System (LPS). The
purpose of a lightning protection system is to protect buildings from direct lightning
strikes and possible fire or from the consequences of lightning currents (non-
igniting flash). If national regulations such as building regulations, special
regulations or special directives require lightning protection measures, they must
be implemented. If these regulations do not specify a class of LPS, a lightning
protection system which meets the requirements of class of LPS III according to IEC
62305-3 (EN 62305-3) is recommended as a minimum. In principle, a risk analysis,
which is described in the IEC 62305-2 (EN 62305-2) standard (see chapter 3.2.1),
should be performed for an overall assessment.
Page 124
SHASHI PRABHU & ASSOCIATES
An internal LPS prevents dangerous sparking within the structure using either
equipotential bonding or a separation distance (and hence electrical insulation)
between the external LPS components and other electrically conducting elements
internal to the structure.
Maximum value of rolling sphere radius, mesh size and protection angle
corresponding to the class of LPS
Protection Method
Class of LPS Rolling Sphere Mesh size Protection angle α
Radius r m Wm
I 20 5x5 As per figure below
II 30 10 x 10
III 45 15 x 15
IV 60 20 x 20
Page 125
SHASHI PRABHU & ASSOCIATES
Protection Class for the structure as per LPL (Lightning Protection Level)
Application LPL*
Computer Data Centres, Military Applications, Nuclear Power I
Stations, High raise Hotels/Hospitals, airports, essential services
such as telecom towers
EX-Zones in the industry and chemical sector, Low raise II
Hospitals & Hotels, fuel retail outlets, gas station, compressor
station etc.
Schools, Banks, Residential Buildings, Temple, Churches, III or
Mosques IV
Page 126
SHASHI PRABHU & ASSOCIATES
For Concrete / RCC Roof: The fixing of roof conductor holder with DMC insulator
min height of 50 mm 8 mm round at every 1 meter and The Holder can be fixed
with glue and screw.
For Metal shed.
If any structure like AC panel, Vent, ducts etc need to protect from Vertical Air
Terminal after calculation of separation distance.
Down Conductor:
In order to reduce the probability of damage due to lightning current flowing in the
LPS, the down-conductors shall be arranged in such a way that from the point of
strike to earth:
Typical value of the distance between down- conductor and between ring
conductors according to the class of LPS
Page 127
SHASHI PRABHU & ASSOCIATES
I 10
II 10
III 15
IV 20
For Concrete wall: The fixing of roof conductor holder with DMC insulator min
height of 50 mm 8 mm round at every 1 meter and The Holder can be fixed with
glue and screw.
For Metal shed.
Test Joint:
At the connection of the earth termination, a test joint should be fitted on each
down conductor,
except in the case of natural down-conductors combined with foundation earth
electrodes.
For measuring purposes, the joint shall be capable of being opened with the aid of a
tool. In
normal use it shall remain closed. The test joint shall be in IP 65 rated box and
copper bus bar of 25 x 3 x 150 mm.
Earthing arrangement:
An earthing system or grounding system connects specific parts of that installation
with the Earth's conductive surface for safety and functional purposes.
Type A arrangement:
This type of arrangement comprises horizontal or vertical earth electrodes installed
outside
the structure to be protected connected to each down-conductor. In type A
arrangements, the total number of earth electrodes shall be not less than two.
Type B arrangement
Page 128
SHASHI PRABHU & ASSOCIATES
Detailed planning and smooth execution of the project. Energy yield report
for the designed system showing month-wise energy yield and loss
diagram. Detailed engineering document consisting of layout, single line
diagram and component specifications.
The vendor to provide yield report (kWh/kWp) and loss diagram of the
proposed grid connected system being offered to Client
The Vendor to specify the space needed for installing the system.
Lowest space usage will be preferred.
The Vendor shall submit the technical offer complete in all respect and as
per the items of technical data sheet
Page 129
SHASHI PRABHU & ASSOCIATES
Page 130
SHASHI PRABHU & ASSOCIATES
Compatible Connectors at
both
input and output terminals.
Page 131
SHASHI PRABHU & ASSOCIATES
The PV modules convert the light reaching them into DC power. The
amount of power Solar PV Module produce is nearly proportional to the
intensity and the angle of the light reaching them. They are therefore
required to be positioned to take maximum advantage of available
sunlight within string constraints. Bidder will position the PV modules in
such a manner that the maximum power shall be obtained with the sun's
movements during the day.
The PV Modules shall be “PID Free” and the certification of the same shall
be submitted along with the modules by the supplier from a
Internationally Recognized certification agency for PID testing.
The PV Modules shall be “LID Free” and there shall not any effect of LID
on the modules in the first year of installation.
Page 132
SHASHI PRABHU & ASSOCIATES
Stabilized net output of the Solar PV Array for the Solar Power System
shall not be less than the Nominal design level for the System under
Standard Test Condition.
The panel shall have positive tolerance of Maximum output power and the
maximum voltage shall not exceed 1000V. The negative temperature
coefficient of power max shall be equal to or less than -0.3% per deg C
temperature.
Page 133
SHASHI PRABHU & ASSOCIATES
The PV module shall use lead wire with weatherproof connector for output
terminal.
Test report from any Indian Lab or agency Like NISE will be preferred.
16.5 JUNCTION BOXES (JBs):
Copper bus bars/terminal blocks housed in the junction box with suitable
termination thread
Conforming to IP65 standard and IEC 62208 Hinged door with EPDM
rubber gasket to prevent water entry. Single/double compression cable
glands shall be provided for cable connections and entry to the junction
boxes or panel. Provision of earthings with placement of 5 feet height or
above for ease of accessibility.
Page 134
SHASHI PRABHU & ASSOCIATES
Each Junction Box shall have High quality Suitable capacity Metal
Oxide Varistors (MOVs) / SPDs, suitable Reverse Blocking Diodes. The
Junction Boxes shall have suitable arrangement monitoring and
disconnection for each of the groups.
Suitable markings shall be provided on the bus bar for easy identification
and the cable ferrules must be fitted at the cable termination points for
identification
AC Distribution Panel Board (DPB) shall control the AC power from PCU/
inverter with necessary surge arrestors. Interconnection required from
ACDB to mains at LT Bus bar while in grid tied mode. All switches, circuit
breakers and connectors shall conform to IEC 60947, part I, II and III/
IS60947 part I, II and III.
All outdoor panels shall have protection of IP65 and conform to Indian
Electricity Act and rules (till last amendment).
All the 415 AC or 230 volts devices / equipment like bus support
insulators, circuit breakers, SPDs and VTs etc., mounted inside the
switchgear shall be suitable for continuous operation and satisfactory
performance under the supply voltage +/- 10 % Variation in supply
frequency
+/- 3 Hz
Page 135
SHASHI PRABHU & ASSOCIATES
Three phase PCU/ inverter shall be used with each power plant system
(10kW and/or above) PCU/inverter shall be capable of complete
automatic operation including wake-up, synchronization & shutdown.
The output of power factor of PCU inverter is suitable for all voltage ranges
or sink of reactive power, inverter shall have internal protection
arrangement against any sustainable fault in feeder line and against the
lightning on feeder.
Page 136
SHASHI PRABHU & ASSOCIATES
Page 137
SHASHI PRABHU & ASSOCIATES
Contractor Signature
MCGM
Page 138
NAME OF PROJECT: - PROPOSED MULTI-SPECIALITY BHANDUP
HOSPITAL AT LAND BEARING C.T.S.NO681A/88,681A/3,681A/4 OF
VILLAGE NAHUR IN S-WARD, BHANDUP MUMBAI
Page 139
SHASHI PRABHU & ASSOCIATES
INDEX
3. PUMPS
5. COOLING TOWER
9. VRV/VRF SYSTEM
17. INSULATIONS
Page 140
SHASHI PRABHU & ASSOCIATES
1 SPECIAL CONDITIONS OF CONTRACT
General
The scope of this section is to describe materials and systems for HVAC
installations of building which form together with the project documents,
a complete volume of work and quality description.
The work shall be carried out simultaneously with building work and
shall be continued till it is completed satisfactorily along with the
completion of essential portions of the building works. All installed HVAC
works shall be protected till the end by the HVAC contractor.
Scope of Work:
The general character and the scope of work to be carried out under this
contract are illustrated in the drawings, specifications. The Contractor
shall carryout and completes the said work under this contract in every
respect in conformity with the rules and regulations of the Local
Authority. The contractor shall furnish all labour, supply and install all
new materials, appliances, equipment necessary for the complete
provision and testing of the complete HVAC services installation as
specified herein and in accordance with relevant codes. This al so
includes any material, appliance, equipment not specifically mentioned
here in or noted on the drawings as being furnished or installed but
which are necessary and customary to make a complete installation. In
Page 141
SHASHI PRABHU & ASSOCIATES
general, the work to be performed under this contract shall comprise but
not limited to the following:
1. Air-conditioning works
2. Toilet Ventilation Works
3. Kitchen Ventilation Works
4. Smoke Extraction works
5. Pressurization works
6. Miscellaneous, unforeseen & client requirement’s Works
Before starting the work at site the contractor shall examine all
services drawings and report to client/ Consultant for discrepancies and
obtain clarifications. Any work done without regard for consultation with
other trades, shall be removed by the contractor without additional cost
to the Client.
Contractor shall temporarily cover & protect all fixtures & accessories,
equipment’s & open pipe/ Duct ends etc. It is the responsibility of the
Contractor to protect all the installed fixtures/ fittings and all
equipment’s until the time of testing, commissioning & handing over to
the Clients.
Page 142
SHASHI PRABHU & ASSOCIATES
Painting of all concealed and exposed pipes, equipment as specified
including weather proof treatment on exposed & treatment of buried pipe
work shall be part of this contract, even if it is implicitly/ explicitly not
specified.
All equipment shall be of the class most suitable for working under
the conditions specified and shall withstand the atmospheric conditions
without deterioration. All the material selection will be done for maximum
life span of the equipment’s and system.
The Contractor during the execution of the Works shall coordinate with
other Contractors, and other Agencies associated with the Project and
shall work in harmony with them without causing any hindrance or
obstruction or impeding the progress of their work in any way.
Since many other contractors and agencies will be engaged on site and
working simultaneously, the Contractor shall ensure at all times that
during the execution of his work or during the operations and movements
of equipment’s and supply vehicles and machinery, no dam age or injury
is caused to the work or property or personnel of other contractors and
agencies.
In case of any such loss or damage the Contractor shall take full
responsibility for same and shall bear all cost and expenses thereof. Also,
the Contractor shall be responsible and liable for all delays caused due to
such damage and or injury and for the consequences which the other
Contractors and Agencies may have to face or to which they may be
subjected to or be accountable for as a result of such delays.
Page 143
SHASHI PRABHU & ASSOCIATES
Safety of Materials:
The Contractor shall conduct all checks and carry out all tests and
obtain test certificates necessary to ascertain and ensure that the Client
supplied materials are in conformity with the requirements stipulated in
the Contract Documents. Should any of the Client supplied materials
obtained from any supplier not be in conformity with the requirements
stipulated in the Contract Documents then the Contractor shall not take
acceptance of such materials and he shall not incorporate them in the
Works unless so specifically authorized by the Construction Manager/
Consultants and it shall be the Contractor's responsibility to bring this
matter to the immediate attention of the Construction Manager/
Consultants and seek his instructions in respect of the disposal of such
materials. Should the Contractor fail to com ply with this procedure then
all costs and/or delays which are a result and consequence thereof shall
be to the account of the Contractor.
The contractor shall supply and install at his expense all secondary
materials and special fittings found necessary to overcome the
interference and to supply the modifications on the route of HVAC pipe
lines that are found necessary during the work, to the complete
satisfaction of the Construction Manager/Consultants.
Rating:
Page 144
SHASHI PRABHU & ASSOCIATES
That all items operate efficiently and quietly to meet the specified
requirements.
The contractor shall provide all necessary instruments and labour for
testing, shall make ad equate records of test procedures and readings,
shall repeat any tests requested by the Construction
Manager/Consultants and shall provide test certificates signed by a
properly authorized person. Such test shall be conducted on all materials
and equipment’s and on completed work as called for by the Construction
Manager/Consultants.
Shop Drawings:
Page 145
SHASHI PRABHU & ASSOCIATES
He shall prepare shop drawings incorporating the details given by
manufacturers for the items included in his contract and also Client
supplied items and any other items which need to be coordinated with
other contractors for interfacing.
Before starting the work, the contractor shall submit to the Construction
Manager/Consultants for his approval in the prescribed manner, the
shop/execution drawings for the entire installation.
Instruction/Maintenance Manual:
Page 146
SHASHI PRABHU & ASSOCIATES
Description of the project.
Operating instructions.
Manufacturers catalogues.
Drawings.
Completion Certificate:
Guarantee:
Staff:
The contractor shall employ competent fully licensed qualified, full time
HVAC engineers to direct the work of HVAC installation in accordance
with the drawings and specifications.
Page 147
SHASHI PRABHU & ASSOCIATES
The Contractor shall at his own cost provide for the protection and safety
of the persons working in the area, safety barriers around all openings in
every location and at the periphery and edges of all slabs, staircases and
stairwells, lift shafts, ducts etc., all to the approval and satisfaction of the
Construction Manager. However, contractor shall take appropriate safety
precautions suitable for specific locations/ situations and as instructed
by the Construction Managers.
The Contractor shall, in general, be fully responsible for all matters with
regard to every form of safety during construction and in connection with
the execution of the Works, and the Contractor shall take all necessary
precautions and provide at his cost everything necessary to ensure such
safety at all times. Should any accidents occur due to the Contractor's
failure to comply with such safety requirements and to take all other
safety measures necessary, the Contractor shall be fully responsible for
all such accidents and he shall bear and pay for all costs and damages in
connection therewith and as a consequence there of.
Disposal Of Rubbish From The Works And The Site And Provision Of
Safety Netting/Screens By Contractor:
The Contractor shall at all times keep the Works and the site in clean,
neat and tidy condition. All rubbish from the Works and the site shall be
collected and deposited in large bins provided on the site for such
purpose by the Contractor at his own cost. The rubbish from such bins
shall be regularly carted away by the Contractor to rubbish tips and
dump yards beyond the site.
At no time or stage shall any rubbish be thrown over the edges of slabs or
through any openings or shafts or ducts or stairwells.
The Contractor shall, at his own cost and to the approval and satisfaction
of the Construction Manager, provide safety netting/screens at the
periphery of all slabs and at all openings, shafts, ducts and stairwells
and/or canopies to prevent any rubbish or material falling over or into
such areas and endangering the safety of the persons working below.
Should the Contractor fail to provide such safety measures and to take
other necessary precautions in accidents that may occur, he shall bear
all costs and damages as decided by Construction Manager in connection
therewith and as a consequence there of.
Page 148
SHASHI PRABHU & ASSOCIATES
payment certificates in case of Contractor's persistent noncompliance
with provisions of this clause. Also the construction Manager is
empowered to employ another agency at Contractor's cost after one
week's notice to implement this Clause in case of Contractor's
noncompliance with provisions of this Clause.
In order to achieve the milestone and completion dates and to keep pace
with the approved construction programme, the Contractor shall be
permitted to carry out his work beyond the normal working hours or in
shifts. The Contractor shall be responsible for obtaining any necessary
permission from the relevant authorities that may be required for him to
carry out the work beyond the normal working hours or in shifts. Also,
the Contractor shall give prior notice to and make arrangements with the
Construction Manager for the supervision of work carried out beyond the
normal working hours or in shifts. The Contractor shall make his own
arrangements in respect of the provision of adequate lighting and any
other facilities that may be required for carrying out the work beyond the
normal working hours or in shifts. No extra payments shall be made to
the Contractor for or in connection with any such overtime or shift work.
The Contractor will not be required to bear the overtime expenses of the
Construction Manager in respect of the supervision of such overtime or
Page 149
SHASHI PRABHU & ASSOCIATES
shift work of the Contractor.
The period and time limit for Completion of the Works shall be as per
client’s requirement from the date of issue of Work Order to commence
works or handing over of site in respect of the award of Contract. This
time period shall be inclusive of the mobilization period and monsoon
period.
Reference Points:
Contractor shall provide permanent bench marks, flag tops and other
reference points for the proper execution of works and these shall be
preserved till the end of the work.
All such reference points shall be in relation to the levels and locations,
given in the architectural and HVAC drawing.
Reference Drawings:
The Contractor shall maintain one set of all drawings issued to him as
reference drawings. These shall not be used on Site. All important
drawings shall be mounted on boards and placed in racks indexed, no
Page 150
SHASHI PRABHU & ASSOCIATES
drawings shall be rolled.
All correction, deviations and changes made on the site shall be shown
on these reference drawings for final incorporation in the completion
drawings. All changes to be made shall be initialed by Engineer in Charge
or Architect.
Vendor shall prepare Shop Drawings with all details after checking the
feasibility at Site which shall be approved by the Consultants before
execution. No work will be carried out without approval of Shop drawing
by the Consultant.
Handing Over:
General Provisions
Description
The scope of works for all HVAC works and system comprises supply,
installation, testing and commissioning, handover, training, maintenance
as described or reasonably implied.
Shop drawings shall take into account actual measurement and setting
out dimensions/levels obtained and determined by the Contractor on
Page 151
SHASHI PRABHU & ASSOCIATES
site, actual equipment/material used, actual routing of services,
coordination with all installation, and site conditions/constraints.
Page 152
SHASHI PRABHU & ASSOCIATES
2 WATER COOLED SCREW CHILLER WITH VFD (AHRI Certified)
General
System Description
Quality assurance
Products
Equipment
General
Factory assembled, single piece, air cooled liquid chiller contained within
the unit cabinet shall be all factory wiring, piping, controls, refrigerant
charge (HFC – 134a), required prior to field startup.
Unit Cabinet
Page 153
SHASHI PRABHU & ASSOCIATES
Compressors
Unit shall have semi hermetic mono / twin screw, gear driven
compressors with internal muffler and check valve.
Each compressor shall be equipped with a discharge shutoff valve.
Capacity control shall be provided by pilot operated solenoid valve,
capable of reducing unit capacity to 20% of full load. Compressor shall
start in unloaded condition.
Motor cooling shall be provided by direct liquid injection and protected by
internal overload thermistor.
Lube oil system shall include pre filter and internal filter capable of
filtration to 3 microns.
Evaporator
Condenser
Coil shall be Water cooled with integral sub cooler and shall be
constructed of aluminium fins mechanically bonded to internally finned
copper tubes. The tubes are then cleaned, dehydrated and sealed.
Condenser tubes shall be leak tested and shall be pressure tested at
3400 kPa.
Refrigeration Circuits
Page 154
SHASHI PRABHU & ASSOCIATES
Controls
Provide a dual set point for the leaving chilled water temperature
activated by a remote contact closure signal.
Diagnostics
Safeties
Page 155
SHASHI PRABHU & ASSOCIATES
Low chilled water temperature.
Low oil pressure (per compressor).
Current imbalance.
Thermal overload.
High pressure.
Electrical overload.
Loss of phase.
Operating characteristics
Electrical characteristics
Unit electrical power supply shall enter the unit at one or two locations.
Unit shall operate on 3phase power supply without neutral.
Control voltage shall be supplied by a factory installed transformer.
Unit shall be supplied with factory installed electrical disconnect switch
/ circuit breaker.
Finishing
Page 156
SHASHI PRABHU & ASSOCIATES
Phase loss
Phase reversal
Phase imbalance
Ground fault
Shorted SCR
Current flow while stopped protection
Starter on
Run (up to voltage)
Phase correct
Over temperature fault
SCR gates energized
Ground fault
Current imbalance fault
Shorted SCR.
I²T fuses the solid state circuitry at 200,000 amp interrupting capacity.
Electrical requirements
The contractor shall supply and install main electrical power line,
disconnect switches, circuit breakers, electrical protection devices per
local code requirements and as indicated necessary by the chiller
manufacturer.
The contractor shall wire the water flow switches to the chiller control
circuit to ensure that chiller will not operate until flows are established &
maintained as per contractor’s / consultant’s specifications.
The contractor shall supply and install electrical wiring and devices
required to interface the chiller controls.
Contractor Signature MCGM
Page 157
SHASHI PRABHU & ASSOCIATES
Gauges shall be installed in the entering and leaving water lines of the
cooler and condenser.
HVAC contractor shall supply & install flow detection devices in chilled
water and condenser water piping. Switches shall make contact when
flow is established. Flow switches shall be installed in horizontal runs at
least 5 pipe diameters downstream from any bend or tee.
Insulation
Chilled water piping and cooler water boxes shall be installed by the
HVAC contractor.
Vibration isolation
Startup
After the above services have been performed, the same factory trained,
representative shall be available for a period of class room instruction
(not to exceed 4 hours) to instruct the chiller owner’s personnel in the
proper operation and maintenance of the chiller.
Page 158
SHASHI PRABHU & ASSOCIATES
basis and hourly basis.
Quality Assurance
Capacity& Efficiency:
Design Parameters:
Page 159
SHASHI PRABHU & ASSOCIATES
• Sound Pressure Level @ 1m - 85 db(A)
• Refrigerant - 134A
• Chiller Pr. drop - Not more than 32 feet
• Condenser pr. Drop - Not more than 25 feet
• Preferred Type of Compressor & motor & chiller: Semi hermetic
• Preferred Number of Compressors: One/Multi.
Note:
Ball Trape
The ball shall be mounted between two flanges - (BS Table 10 E) Grade B,
15 days 100 lbs capacity, at the outlet line of the condenser. The casing
shall be made from a MS material of IS2062 Grade B. The Ball trap shall
be galvanized & have epoxy based finished paint. The screen inside is
made from stainless steel SS304L perforated metal sheet.
The Ball Trap should have pressure drop of less than 800 mm of WC. The
body of the Ball trap shall be of size as nozzle or flange size or the
pipeline size in which Ball trap must be installed. For example, if the
pipeline size is 10 inches the Ball trap body should be of 10 inches. The
Ball Trap shall have Race Face Flange with gasket on only inner dial of
pipe and should not be on the entire flange dia to avoid leakage.
Ball Collector
The Ball shall be made of suitable size capable of storing all the sponge
balls required and should be made from MS material of IS2062 Grade B.
The Ball collector should be galvanized & have epoxy based finished
paint. The Ball Collector should have a sight glass for monitoring the
balls. Toughened glass should be used and should be mounted by Allen
key fasteners or SS nut bolt.
The skid should have pipe and flanges of MS material IS2062 Grade B
and should be galvanized. All welding of Skid shall be performed by
Argon weld. The Skid frame should be of MS material of same IS2062
grade B. The Skid valves should be of diaphragm type or equivalent with
all joints to be flanged and bolted. The valves used for injection and
collection from respective chillers shall be of actuator type with minimum
IP54 protection and less tan10s running time for open or close function
with NEMA –II protection. The valve should be suitable to work in high
humid environment up to 95% (Non-condensing) RH. All fasteners shall
Contractor Signature MCGM
Page 160
SHASHI PRABHU & ASSOCIATES
be of high-tension grade 9.8, 10.9, 12.9. Pumps shall be from reputed
makes like Grundfos/Xylem/Amstrong. Motorized Valves shall be from
reputed makes like Belimo/Siemens/Honeywell.
Control Panel
Control Panel should be PLC based with LCD depiction of injection and
collection cycle. The touch display should show system wise running
along with pump running and off condition. The alarms and faults shall
be indicated on the screen in case of any issue in operation. Display must
be Touch type, graphical presentation, and with multi-level security
passwords with defined functional authorities. The HMI shall be from
reputed makes like Delta/ABB/Honeywell.
The operation is based on the circulation of the sponge ball through the
condenser tube. The sponge ball must be pushed to the condenser inlet
in not more than 5 seconds by a high flow of water (min. 7L/S) which can
be produced by a high-pressure source at least 2bar higher than the
injection point at the condenser inlet. The source can be obtained by a
single water injection pump in water injection system. Water injection
system will be operated by a PLC controller which is pre-programmed to
execute the cleaning process in two consecutive steps. They are ball
injection cycle and ball collection cycle.
Step-01
PLC shall activate the cleaning process by detecting the on/off status of
the corresponding chiller (or condensing water isolating valve). If the
chiller is on, the PLC shall command the control valves to open to
manage the injection. The check valves shall be installed in the location
as shown on the scheme above and as close as possible to the collector to
ensure correct water flow direction during the injection cycle and the
collection cycle.
Step-02
The ejection cycle, the PLC shall command the injection control valve to
open for couple of seconds (the collection control valve kept closed in the
cycle) and then close. The water pressure from the pump shall be used to
push the water inside the injector to the collector and force all balls in
the collector to the condenser.
Step-03
The Cycle shall be completed until the ball passing through the
condenser where it should clean all the deposits on internal surface of
the tubes. After leaving condenser the balls shall be trapped inside the
ball trap unit.
Page 161
SHASHI PRABHU & ASSOCIATES
Step-04
After injection cycle is finished, the PLC shall command the collection
control valve to open for couple of seconds (the injection control valve
kept closed in the cycle) and then close. The negative pressure shall let
the ball return from the ball trap unit back to the collector where the
rinsing of the balls is carried out and then water is discharged to the
outlet header of Condenser which goes to cooling tower. The ball shall
wait in the collector until the next injection cycle. The time of the
collection cycle is normally pre-set at 27 minutes.
9. The total time of the whole cycle (injection and collection cycle) shall be
3 - 4 minutes.
Page 162
SHASHI PRABHU & ASSOCIATES
Page 163
SHASHI PRABHU & ASSOCIATES
# Total points for Chiller
Plant
Condenser Water
D
1 PumpsAuto/Manual
Pump DI DO AI AO SW Software Integration
2 (CWP) On/Off command
status
Pump signal
Software Integration
3 Pump run status signal
Software Integration
4 Pump trip status signal
Software Integration
Total points for signal
E# Condenser
Cooling Tower (CT)
1 Water Pumps
Fan Auto/Manual Software Integration
2 status
Fan On/Off Command signal
Software Integration
3 Fan Run status signal
Software Integration
4 Fan Trip status signal
Software Integration
5 CT inlet/outlet signal
NO/NC Relay
6 Isolation valve
CT inlet/outlet Command to
NO/NC Potential free
6
7 Open command
Isolation
Common valveCW Valve
contact from
TE-632AM-1+WZ Valve
8 Open/close
supply
Common status
CW 1000-5
TE-632AM-1+WZ
9 header
return
CT temperature
VFD command 1000-5
Software Integration
10 header
CT VFDTemperature
feedback signal
Software Integration
# Total points for Cooling signal
G Tower Diagnostic
Chiller
1 Points chilled liquid -
Leaving
2 setpoint
Motor current limit -
3 setpoint chilled liquid -
Leaving
3
4 Temperature
Entering chilled liquid -
4
5 Temperature
Leaving condenser
6 liquid - condenser
Entering
5
6
7 Temperature
liquid -
Evaporator pressure
8 Temperature
Condenser pressure
9 Oil – low differential
12 pressure
Motor FLA current
0
13 Discharge pressure
14 Operating hours
15 Unit safety fault code
16 Unit cycling fault code
17 Operation code
18 Evaporator – low
19 pressure – low-
Evaporator
20 pressure – –
Evaporator
21 smart freeze–orhigh
transducer
Condenser
22 leaving liquid
pressure
Condenser probe
– pressure
23 transducer–out
Discharge lowof range
24 temperature
Oil – high temperature
25 Oil – low differential
pressure
Contractor Signature MCGM
Page 164
SHASHI PRABHU & ASSOCIATES
26 Oil – clogged filter
27 Motor controller – loss
28 of
Oilcurrent
– high pressure
29 Oil – separator – low
30 level
Leaving chilled liquid –
31 low
Motor controller – loss
32 temperature
of
Syscurrent
Oil Temperature
33 Sys Oil Pressure
34 Sys Oil Filter Pressure
35 Slide Valve Position
36 Sys Discharge Temp
37 SYS.EVAPORATOR
38 SATURATION
SYS.EVAPORATOR SUB
39 TEMPERATURE
SYS.CONDENSER
40 SATURATION
EVAPORATOR
41 TEMPERATURE
REFRIGERANT
EVAPORATOR SMALL
41
42 TEMPERATURE
CONDENSER SMALL
42
43 DIFFERENCE
TEMPERATURE
SYS. START TIMES
DIFFERENCE
Total diagnostic points
Page 165
SHASHI PRABHU & ASSOCIATES
3 PUMPS SYSTEM
GENERAL
The various items of the water circulating system shall be complete in all
respects and comply with the specification given below. The total sound
intensity with all fans in operation shall not practically exceed 60 DB at a
distance of 50 meters.
PUMP SETS
Pumps capacity shall be as per detail design requirement.
Scope:
General:
The pumps shall be single stage, close coupled, inline suction and
discharge ports of identical Diameter with top pullout design. Hence, the
rotating unit can be removed and serviced without disconnecting the
suction and discharge piping.
Features of Construction:
Page 166
SHASHI PRABHU & ASSOCIATES
Pump casing shall capable of withstanding 1.5 times the design pressure.
b.) Impeller:
The impeller shall be having cast bronze enclosed type with smooth
surface finish for minimum frictional loss. This ensures high Efficiency.
Impeller shall be keyed to the shaft and secured by impeller lock nut.
All impellers are dynamically balanced to ISO 19401: Grade G6.3. The
thrust balancing can be of Balancing holes or back vanes.
c.) Shaft:
Shaft run out shall be limited at the seal face and at the impeller to 0.05
mm. Shaft shall be provided with Mechanical seal as default fitment to
provide leak free operation.
The stuffing box cavity shall be sealed off at the pump shaft by an
internally or externally flushed Mechanical seal with carbon / Silicon
carbide face material, suitable for continuous operation up to140 Deg C.
f.) Bearings:
As radial and axial forces are absorbed by the fixed bearing in the motor
drive end, the pump requires no bearing. Bearing shall be effectively
sealed to prevent loss of lubricant or entry of dust or water.
Page 167
SHASHI PRABHU & ASSOCIATES
g.) Coupling:
The pump coupling should be of close coupled type with stub shaft.
h.) Motors:
Motor shall be a flange mounted, totally enclosed fan cooled motors with
main dimensions according to IEC standards. Electrical tolerances are to
IEC
60034. Motor shall be IE2motor for normal mode & fir mode equipment’s
with IE2 motor. Motor shall be to with IP 55 enclosure. The class of
insulation shall be F with temperature rise limited to Class B.
Each pump shall be provided with a name plate indicating the following
de tails:
k.) Vibration:
Page 168
SHASHI PRABHU & ASSOCIATES
Painting:
The equipment shall be thoroughly cleaned and greased. All rust sharp
edges and scales shall be removed. All external and exposed cast iron
parts of pumps have an epoxy based coating made in a cathodic electrode
position (CED) process which is high quality dip painting process and
which would prevent rusting and corrosion. The color code for the
finished product is NCS 9000/RAL 9005. The pump shaft shall not be
painted.
1. Hydrostatic Testing
2. Performance Test (Single point / Duty point)
3. Dynamic balancing for pump impeller.
Tender Drawings:
Variable speed pump should provide stable and predictable flow rate over
a wide variation of head pressure including the following:
Page 169
SHASHI PRABHU & ASSOCIATES
Pump logic controller, adjustable frequency drives, sensor / transmitters
and related equipment shall be installed by the HVAC contractor as
shown on the drawing.
Low voltage (24V DC and 110V AC) wiring shall be installed by the BMS
contractor as shown on the field connection drawings and wiring
diagrams supplied with the pumping package.
COMPONENTS
The pump logic controller shall have an additional analog input for a flow
sensor. This input shall serve as the criteria for the end of curve
protection algorithm.
Page 170
SHASHI PRABHU & ASSOCIATES
• Soft touch membrane keypad switches.
The readout shall be two lines of forty 0.25” backlit LCD super twist
characters capable of displaying the following values:
The adjustable frequency drive (s) shall be pulse width modulation (PWM)
type, microprocessor controlled design.
The AFD including all factory installed options shall have CSA approval.
Page 171
SHASHI PRABHU & ASSOCIATES
The AFD shall be suitable for elevations to 3300 feet above sea level
without derating. Maximum operating ambient temperature shall not be
less than 104 degrees F.AFD shall be suitable for operation in
environments up to 95% non condensing humidity.
SENSOR/TRANSMITTERS:
SEQUENCE OF OPERATION
The system shall consist of a technologic pump logic controller, one duty
pump /AFD set; with duty standby pump selection, automatic
alternation and automatic transfer to the standby pump.
The pumping system shall start upon the closure of customer’s contact
when the pump logic controller Mode of Operation selector switch is in
the REMOTE position.
When the pump logic controller selector switch is in the LOCAL position,
the pumping system shall operate automatically. Sensor/transmitters
shall be provided as indicated on the plans.
The Technologic pump logic controller shall compare each signal to the
independent, engineer/user determined set points.
When all set points are satisfied by the process variable, the pump speed
shall remain constant at the optimum energy consumption level.
Page 172
SHASHI PRABHU & ASSOCIATES
the least satisfied zone.
As the worst case zone deviates from set point, the pump logic controller
shall send the appropriate analog signal to the AFD to speed up or slow
down the pump/motor.
The redundant variable speed system shall be started through the pump
logic controller.
In the event of failure to receive all zone process variable signals, the AFD
shall maintain 100% speed; reset shall be automatic upon correction of
the zone failure.
Pumps shall be single stage, end suction design with a foot mounted
volute to allow servicing of the impeller and bearing assembly without
disturbing piping connections.
Pump volute shall be class 30 cast iron with integrally cast pedestal
support feet. The impeller shall be cast bronze enclosed type, dynamically
balanced keyed to the shaft and secured by a locking cap screw.
The liquid cavity shall be sealed off at the pump shaft by an internally
flushed mechanical seal with ceramic seal seat and carbon seal ring,
suitable for continuous operation at 225o F.A. replaceable bronze shaft
sleeve shall completely cover the wetted area under the seal.
Page 173
SHASHI PRABHU & ASSOCIATES
Base plate shall be structural steel or fabricated steel channel with fully
enclosed sides and ends, and securely welded cross members. Grouting
area shall be fully opened. A flexible type, center drop put design coupler,
capable of absorbing torsional vibration shall be employed between the
pump and motor. Coupler shall be shielded by a coupler guard securely
fastened to the base.
Motor shall be energy efficient, totally enclosed fan cooled, class ‘F’
insulation and suitable for operation on AFD (only for secondary side).
Motor shall be specially designed for quite operation and its speed shall
not exceed 1450 RPM. The motor rating shall be such as to ensure non
over loading of the motor throughout its capacity range. Motor shall be
suitable for 415 ± 10% volts, 3 phase, 50 cycles AC power supply.
Suction Guides
Furnish and install on the suction of each pump Suction Guide, with Outlet
Flow Stabilizing Guide Vanes, removable Stainless-Steel Strainer and Fine
Mesh Start-up Strainer. Supply suction guide with Ductile Iron body, with
BSPT inlet and PN16 outlet connections. The mechanical contractor shall
inspect the strainer prior to activating the pump and, further, shall remove
the Fine Mesh Start-up Strainer after a short running period. (24 hours
maximum). Space shall be provided for removal of the Strainer and
connection of a Blow-down Valve.
Page 174
SHASHI PRABHU & ASSOCIATES
4 VARIABLE FREQUENCY DRIVES
The VFD and its options shall be factory mounted and tested as a single
unit under full load before dispatch.
The VFD shall be CE marked and conform to the European Union Electro
Magnetic Compatibility directive.
The VFD shall be UL listed for a short circuit current rating of 100 kA
and labeled with this rating.
The VFD shall convert incoming fixed frequency three phase AC power
into an adjustable frequency and voltage for controlling the speed of three
phase AC motors. The motor current shall closely approximate a sine
wave. Motor voltage shall be varied with frequency to maintain desired
motor magnetization current suitable for the driven load and to eliminate
the need for motor derating when properly sized, the VFD shall allow the
motor to produce full rated power at rated motor voltage, current, and
speed without using the motor's service factor. VFDs utilizing sine
weighted/coded modulation (with or without 3rd harmonic injection)
must provide data verifying that the motors will not draw more than full
load current during full load and full speed operation.
The VFD shall convert incoming fixed frequency three phase AC power
into an adjustable frequency and voltage for controlling the speed of three
phase AC motors. The motor current shall closely approximate a sine
wave. Motor voltage shall be varied with frequency to maintain desired
motor magnetization current suitable for the driven load and to eliminate
the need for motor derating.
When properly sized, the VFD shall allow the motor to produce full rated
Page 175
SHASHI PRABHU & ASSOCIATES
power at rated motor voltage, current, and speed without using the
motor's service factor. VFDs utilizing sine weighted/coded modulation
(with or without 3rd harmonic injection) must provide data verifying that
the motors will not draw more than full load current during full load and
full speed operation.
The VFD shall include an input full wave bridge rectifier and maintain a
fundamental (displacement) power factor near unity regardless of speed
or load.
The VFD’s full load output current rating shall meet or exceed the normal
rated currents of standard IEC induction motors. The VFD shall be able
to provide full rated output current continuously, 110% of rated current
for 60 seconds and 120% of rated torque for up to 0.5 second while
starting.
The VFD shall provide full motor torque at any selected frequency from
20 Hz to base speed while providing a variable torque V/Hz output at
reduced speed. This is to allow driving direct drive fans without high
speed derating or low speed excessive magnetization, as would occur if a
constant torque V/Hz curve was used at reduced speeds. Breakaway
current of 160% shall be available.
Page 176
SHASHI PRABHU & ASSOCIATES
The VFD must be able to produce full torque at low speed to operate
direct driven fans.
VFD shall minimize the audible motor noise through the used of an
adjustable carrier frequency. The carrier frequency shall be automatically
adjusted to optimize motor and VFD operation while reducing motor
noise. VFDs with fixed carrier frequency are not acceptable.
The VFD shall allow up to at least 100 meters of SWA (Single Wire
Armour) cable to be used between the FC and the motor and allow the
use of MICS (Mineral Insulated Copper Sheath) cable in the motor circuit
for fire locations.
Protect VFD from input phase loss. The VFD should be able to protect
itself from damage and indicate the phase loss condition. During an input
phase loss condition, the VFD shall be able to be programmed to either
trip off while displaying an alarm, issue a warning while running at
reduced output capacity, or issue a warning while running at full
commanded speed. This function is independent of which input power
phase is lost.
Protect from under voltage. The VFD shall provide full rated output with
an input voltage as low as 90% of the nominal. The VFD will continue to
operate with reduced output, without faulting, with an input voltage as
Page 177
SHASHI PRABHU & ASSOCIATES
low as 70% of the nominal voltage.
If the temperature of the VFD’s heat sink rises to 80°C, the VFD shall
automatically reduce its carrier frequency to reduce the heat sink
temperature. It shall also be possible to program the VFD so that it
reduces its output current limit value if the VFD’s temperature becomes
too high.
The VFD shall have temperature controlled cooling fan(s) for quiet
operation, minimized losses, and increased fan life. At low loads or low
ambient temperatures, the fan(s) may be off even when the VFD is
running.
The VFD shall store in memory the last 10 alarms. A description of the
alarm, and the date and time of the alarm shall be recorded.
when used with a pumping system, the VFD shall be able to detect
noflow situations, dry pump conditions, and operation off the end of the
pump curve. It shall be programmable to take appropriate protective
action when one of the above situations is detected.
Hand Off and Auto keys shall be provided on the control panel to start
and stop the VFD and determine the source of the speed reference. It
shall be possible to either disable these keys or passwords protect them
from undesired operation.
There shall be an “Info” key on the keypad. The Info key shall include
“online” context sensitive assistance for programming and
troubleshooting.
Page 178
SHASHI PRABHU & ASSOCIATES
All VFDs shall have the same customer interface. The keypad and display
shall be identical and interchangeable for all sizes of VFDs.
A red FAULT light, a yellow WARNING light and a green POWERON light
shall be provided. These indications shall be visible both on the keypad
and on the VFD when the keypad is removed.
A quick setup menu with factory preset typical HVAC parameters shall be
provided on the VFD.
A three feedback PID controller to control the speed of the VFD shall be
standard.
The VFD shall be able to apply individual scaling to each feedback signal.
For fan flow tracking applications, the VFD shall be able to calculate the
square root of any or all individual feedback signals so that a pressure
sensor can be used to measure air flow.
The VFD’s PID controller shall be able to actively adjust its set point
based on flow. This allows the VFD to compensate for a pressure
feedback sensor which is located near the output of the pump rather
than out in the controlled system.
The VFD shall have three additional PID controllers which can be used to
control damper and valve positions in the system and to provide set point
reset.
Page 179
SHASHI PRABHU & ASSOCIATES
VFD output power, VFD output energy, VFD temperature in degrees,
feedback signals in their own units, among others.
Programmable Sleep Mode shall be able to stop the VFD. When its output
frequency drops below set “sleep” level for a specified time, when an
external contact commands that the VFD go into Sleep Mode, or when the
VFD detects a noflow situation, the VFD may be programmed to stop.
When the VFD’s speed is being controlled by its PID controller, it shall be
possible to program a “wakeup” feedback value that will cause the VFD to
start. To avoid excessive starting and stopping of the driven equipment, it
shall be possible to program a minimum run time before sleep mode can
be initiated and a minimum sleep time for the VFD.
VFD shall be programmable to sense the loss of load. The VFD shall be
programmable to signal this condition via a keypad warning, relay output
and/or over the serial communications bus. To ensure against nuisance
indications, this feature must be based on motor torque, not current, and
must include a proof timer to keep brief periods of no load from falsely
triggering this indication.
Page 180
SHASHI PRABHU & ASSOCIATES
A programmable low pass filter for either or both of the analog inputs
must be included to compensate for noise.
The VFD shall provide front panel meter displays programmable to show
the value of each analog input signal for system setup and
troubleshooting,
It shall be possible to read the status of all analog and digital inputs of
the VFD through serial bus communications.
It shall be possible to command all digital and analog output through the
serial communication bus.
These modules shall use rigid connectors to plug into the VFD’s control
card.
Page 181
SHASHI PRABHU & ASSOCIATES
standards and conditions.
It shall be possible to use this to display the current date and time on the
VFD’s display.
The realtime clock shall be able to time and date stamp all faults
recorded in the VFD fault log.
The VFD shall be able to store load profile data to assist in analyzing the
system demand and energy consumption over time.
Modbus/ Bacnet/RTU
VFD shall have standard USB port for direct connection of Personal
Computer (PC) to the VFD. The manufacturer shall provide no charge PC
software to allow complete setup and access of the VFD and logs of VFD
operation through the USB port. It shall be possible to communicate to
the VFD through this USB port without interrupting VFD
communications to the building management system.
Page 182
SHASHI PRABHU & ASSOCIATES
interface to power the VFD’s control card. This is to allow the VFD to
continue to communicate to the building automation system even if
power to the VFD is lost.
PART 6: ADJUSTMENTS
The VFD shall have a manually adjustable carrier frequency that can be
adjusted in 0.5 kHz increments to allow the user to select the desired
operating characteristics. The VFD shall also be programmable to
automatically reduce its carrier frequency to avoid tripping due to
thermal loading.
Each setup shall have two programmable ramp up and ramp down times.
Acceleration and deceleration ramp times shall be adjustable over the
range from 1 to 3,600 seconds.
Each setup shall be programmable for a unique current limit value. If the
output current from the VFD reaches this value, any further attempt to
increase the current produced by the VFD will cause the VFD to reduce
its output frequency to reduce the load on the VFD. If desired, it shall be
possible to program a timer which will cause the VFD to trip off after a
programmed time period.
If the VFD trips on one of the following conditions, the VFD shall be
programmable for automatic or manual reset: external interlock, under
voltage, overvoltage, current limit, over temperature, and VFD overload.
Page 183
SHASHI PRABHU & ASSOCIATES
PART 8: SERVICE CONDITIONS
All power and control wiring shall be done from the bottom.
All optional features shall be functionally tested at the factory for proper
operation.
Page 184
SHASHI PRABHU & ASSOCIATES
5 COOLING TOWER
GENERAL DESCRIPTION
SCOPE OF WORK
The scope shall include development of a total system and design of their
sub-systems as per concepts and parameters given herein, providing
engineering drawings and data for approval by Customer / Consultants.
SCOPE
Page 185
SHASHI PRABHU & ASSOCIATES
TYPE
DESIGN:
Rating: The cooling tower shall be rated for the heat rejection capacity
specified in the tender specifications. All cooling towers shall be
certified by CTI (Cooling Tower Institute).
Range: The Cooling tower shall be designed to cool the requisite quantity
of water through 7.0-degree C or as specified in the tender specifications,
against the prevailing wet bulb temperature.
Wet Bulb approach: The cooling tower shall be selected for a wet bulb
approach of not more than 5.0-degree C.
Outlet temperature: The cold water temperature from the cooling tower
shall match the entering temperature for which the condenser selection is
Page 186
SHASHI PRABHU & ASSOCIATES
made.
Flow rate: The water flow rate through the cooling tower shall match that
through the condenser.
Multi cell design: The induced draft cooling tower shall be of one or
more cells.
Drive Motor: The fan motor shall be premium efficiency IE3 class, as per
IS 12615.
MATERIAL
STRUCTURE
SIDE CASING
The side casing shall be made of FRP with smooth surface for minimum
resistance to airflow. It should have sufficient structural strength to
withstand high wind velocity and vibrations. The casing shall be installed
in the fiberglass-reinforced basin. The tower supporting structure shall
be made out of hot dipped galvanized frame. The tower shall have FRP
panels reinforced with embedded steel frame.
AIR INTAKE
The air intake shall be from openings all along the circumference of the
casing near its base in case of circular shape. Air Intake shall be along
the sides in case of square or octagonal/ rectangular cooling tower. These
openings shall be covered with hot dip galvanized expanded metal mesh
screens.
✓ Bottom outlet
✓ Suction screen
✓ Drain outlet
✓ Over flow
✓ Make up water connection with ball valve & float valve
Page 187
SHASHI PRABHU & ASSOCIATES
✓ Equalizer connection where required
✓ Quick fill.
✓ The basin shall be watertight without the use of any fillets, paints
or sealing compounds
The basin shall have a holding capacity adequate for operation for at
least 30 minutes without addition of make-up water to the basin. The
construction should be such as to eliminate the danger of drawing air
into the pump when operating with minimum water in the basin.
Suitable provision shall be made in the tower for cable supports and for
fixing galvanized steel flats as earthing and lightning protection.
DISTRIBUTION SYSTEM
FILLINGS
The filling shall be of PVC. Thickness of PVC fills shall not be less than
0.2mm. Fillings shall be made of corrosion proof and rigid film in cross-
fluted design and arranged in square/rectangular form and shall be
elevated from floor of the cold-water basin to facilitate cleaning and easy
replacement. They shall be arranged in such a manner to ensure
negligible resistance to airflow and to eliminate backwater spots and
prevent fouling through scales that may form. In order to reduce carry
over losses through entrainment of moisture drops in air stream, PVC
drift eliminators shall be of high efficiency. Drift eliminators of PVC shall
be provided for maximum removal of entrained water droplets. The
spacers and tie rods used shall be of plastic material.
MECHANICAL EQUIPMENT
Fan shall be made of cast aluminum alloy and propeller type lightweight
rotor fitted with multiple aerofoil blades. The entire fan assembly shall be
statically balanced fan shall be direct driven by motor suitable for 415 ±
10% Volts, 3 phase, 50 cycle per second AC supply, TEAO, weather proof
construction (IP:56) designed to operate in humid air stream fan shall be
protected by fan guard and shall be easily accessible for inspection and
maintenance. A service ladder fabricated out of hot dipped galvanized
material shall be provided. The mechanical equipment assembly shall be
supported on a rugged steel base welded to tubular support for vibration
Page 188
SHASHI PRABHU & ASSOCIATES
free support. Fan shall be provided to prevent birds from nesting during
idling periods. All fans shall be direct driven with low RPM motor. The fan
drive shall be from a three phase induction motor of efficiency class IE3
as per IS 12615. The entire drive arrangement shall be designed for a
minimum noise and it shall be rigidly supported to the tower structure.
Tower from 175 TR onwards shall have twin fans with low RPM motors of
720/600 RPM suitable for low noise application. Maximum noise level
within One (1) meter of the source shall not exceed 75 dBA.
OTHER ACCESSORIES
INSTALLATION
Cooling tower shall be not less than 75cm above the ground/ floor level
unless otherwise stated in the tender specifications. 6mm neoprene pads
shall be placed between the tower and the girder for vibration isolation
whereas directed by the Engineer-in-charge. Guy-wires of suitable sized
shall be used to secure firmly to its base wherever necessary.
PAINTING
Page 189
SHASHI PRABHU & ASSOCIATES
ACCESSORIES
a) Cold-water basin common outlet header shall have pot strainer. The
strainer shall have handles for easy removal.
b) The cooling tower basin shall have automatic float valve with a stop valve
for continuous Make up water flow, quick fill arrangement with stop
valve, over flow and drain connections with stop valves.
c) A hot water bleed connection to drain line through a stop valve shall be
provided and shall be connected to drain line below the drain stop valve.
d) Hot dipped galvanized steel ladder made of 40mm x 40mm x 6mm HDG
angle sides and
e) 16mm HDG straps shall be provided for complete access to tower. The
ladder shall be bolted to tower on top and grouted in masonry at bottom
side.
h) All hardware used inside the cooling tower shall be of stainless steel. All
pipe
i) Connections shall be hot dipped galvanized and double flanged.
TESTING
Page 190
SHASHI PRABHU & ASSOCIATES
6 AIR HANDLING UNITS (AHUS)
GENERAL
The scope of this section comprises the supply, erection, testing and
commissioning of double construction air handling units, conforming to
these specifications and in accordance with requirements.
The air handling units shall be double skin construction, draw thru type
comprising of various sections such as pre-filter section, coil section and
fan section.
CAPACITY
CASING
Units shall have hinged quick opening access doors in the fan and filter
section. Access doors shall also be double skin type.
Page 191
SHASHI PRABHU & ASSOCIATES
insulation as per manufacturer standard.
AHU’s such as TFA units, AHU with mixing box having return air ducted
shall be provided with thermal break casing. Also these AHU’s shall be
provided with 43 + 2 mm thick panel.
FAN
EC Fan
Fans shall be backward curved Plenum plug fan with aero-foil design
blades so as to give maximum efficiency for given duty condition. In
case of Plug fan, the AHU will be certified by a reputed 3rd party
internationally acclaimed certifying body like Eurovent / AHRI, and
the entire Fan + Motor assembly will be balanced at supplier’s works
before dispatch. Fans driven by variable frequency drive shall be
backward inclined irrespective of static pressure value. Fans shall be
selected for minimum efficiency of 70%. Fan wheels shall be made
of MS epoxy coated/composite material in case of plug fans. Fan
array with multiple fans should be used for capacities more than
15000 CMH. Plug fans in fan array shall have individual VFDs for
Contractor Signature MCGM
Page 192
SHASHI PRABHU & ASSOCIATES
every motor fan set. Certified Computerized selection for AHU shall
be with fan selection and sound level spectrum. Complete AHU
sound level should be given in computerized selection sheet instead
of sound level of bare fan.
Motors shall be mounted inside the AHU casing on rigid frame/ slide
rails for alignment, and be totally enclosed, fan cooled, to be class `F’
insulation and shall have premium efficiency i.e. minimum IE-3.
Heavy duty anti-vibration mounts shall be provided for isolating the
unit casing. Fire retardant, waterproof silicone rubber impregnated
flexible connection shall be provided at the fan inlet/ discharge.
COOLING COILS
CHW Cooling coils shall have 12mm dia. (O.D) tubes minimum 0.5 mm
thick with sine wave aluminum fins firmly bonded to copper tubes
assembled in zinc coated steel frame. Face and surface areas shall be
such as to ensure rated capacity from each unit and such that the air
velocity across the coil shall be around 155 meters per minute. The coil
shall be pitched in the unit casing for proper drainage. Each coil shall be
factory-tested at 21 kg per sq. m air pressure underwater. Tubes shall be
mechanically expanded for minimum thermal contact resistance with fins.
Fin spacing shall be 4 - 5 fins per cm. No drop should be observed
indicating any leaks.
The depth of the coil shall be such as to suit the requirements, viz. re-
circulated air applications, or 100 % fresh air applications and the bypass
factor required shall be specified in the tender specifications. The coil shall
be 6 rows deep for normal/general area re-circulated air application and 8
rows deep for all critical/TFA and for outdoor air application, unless
otherwise specified in the tender specifications. In case of 8 rows deep coils,
it shall be made of 2x4 rows deep coils with a spacing of 200mm between
the two coils, access door and independent drain pan.
Each section of the coil shall be fitted with flow and return headers to feed
all the passes of the coil properly. The headers shall be of copper and shall
be complete with water in/out connections, vent plug on top and drain at
the bottom. The coil shall be designed to provide water velocity between 0.6
to 1.8 m/s in the tubes.
The fins shall be of aluminum. The minimum thickness of the fins shall be
0.15 mm nominal. The no. of fins shall not be less than 4.7 per cm length
Page 193
SHASHI PRABHU & ASSOCIATES
of coil. Fins may be of either spiral or plate type. The tubes shall be
mechanically expanded to ensure proper thermal contact between fins and
tubes. The fins shall be evenly spaced and upright. The fins bent during
installation shall be carefully realigned. For coastal areas fins shall be
phenolic coated for re-circulated and 100% F.A. application fins shall be
hydrophilic type.
The coil shall be suitable for use with the refrigerant specified or with water
as specified in schedule of quantities. Refrigerating coils shall be designed
for the maximum working pressure under the operating conditions. Water
coils shall be designed for a maximum working pressure of 10 kg./sq.cm.
Shut off and regulating valves at the inlet and outlet of water shall be
provided. In the case of DX coils, solenoid valve and expansion valves shall
be provided at the inlet of coil.
Each UVGI unit or fixture shall contain at least 2 lamps, to ensure UVC
rays penetrate deep into the rows of the Cooling Coil to enable bacteria
destruction in the inner rows of the Coil. Units or Fixtures with single lamp
is not acceptable due to its limited ability to penetrate into the depth of the
Cooling Coil.
Page 194
SHASHI PRABHU & ASSOCIATES
mounting cups, pre drilled vertical telescopic channels, screws, and
hardware shall be factory provided.
Each UVGI unit or fixture shall comprise at least two lamps, installed over
a properly profiled aluminum reflector. The reflector shall be mirror surface
specular reflectivity 86%. The enclosure shall be not less than 0.04 Inch (1
mm) thick Aluminum.
The lamps shall be high output type 425 mA each. Energy output of the
lamp measured 3'3"(1M) from the Lamp shall not be less than 144
μwpercm². The lamps shall be rated for useful lamp life not less than 9,000
hours.
The lamps shall not operate at wave length 180 nM or lower, to ensure no
uncontrolled ozone is put out by the lamps.
All electrical connections within the fixture shall be factory ready, ending
on terminals. All fixtures within an AHU shall be daisy looped at site. All
electrical cables shall be UL Listed. It shall be possible to connect all the
UV fixtures within an AHU easily and quickly with minimum labor time,
opening the terminal box alone, and without opening the fixtures.
The Ballast shall be electronic type, fully encapsulated, and confirm to the
following;
UL Listed (Class P, Type 1, Outdoor)
Tested and certified to comply with fire and smoke safety to UL 2043
Sound Rated A
Compliance to FCC Part 18 (Class A) for EMI and RFI (non-consumer limits)
ANSI Standard C62.41
Page 195
SHASHI PRABHU & ASSOCIATES
Facilitate environmentally safe disposal of broken lamp. Installation of
vertical telescopic support structure in AHU and mounting of UVGI
Fixtures to the frame shall be easy and quick using minimum labor hours.
All installation materials shall be factory supplied. No material shall be field
supplied, except one power input cable for each AHU and inter connect
cable between fixtures.
DRAIN PAN :
FILTER:
TYPES OF FILTERS:
Cleanable metallic viscous type filter made out of aluminium wire mesh or
of dry cleanable synthetic type minimum 50mm thick, shall be provided on
the suction side of AHU as standard equipment with the unit. These filters
shall have the efficiency of 90% down to 10 micron& 10micron particle size.
When these filters become loaded or full of dirt, it is removed from service
and replaced by another filter. The dirty filter can then be washed in a
cleaning solution in a tank, dried and then given a bath of viscous oil. Face
velocity across these filters shall not exceed 155 MPM.
These filters shall have greater efficiency of 99% down to 3-micron particle
size as per MERV-3 standard. When these filters become loaded or full of
Contractor Signature MCGM
Page 196
SHASHI PRABHU & ASSOCIATES
dirt, it is removed from service and replaced by another filter. The dirty
filter can then be washed in a cleaning solution in a tank, dried and then
given a bath of viscous oil. Face velocity across these filters shall not
exceed 155 MPM.
Page 197
SHASHI PRABHU & ASSOCIATES
ABSOLUTE (HEPA) FILTERS: (MVRV-17)
These filters shall have efficiency of 99.99% up-to 0.3-micron particle size
as per MERV-17 standard & are required for applications like operation
theatre, PE, AII, Combined isolation room etc. These are also provided in
the AHU after fan section or at terminal point and always must be backed
by fine filters & pre filters as per tender documents. These filter after they
become dirty, cannot be reused and have to be thrown away. Face velocity
across these filters shall not exceed 25-35 MPM. These filters shall be
separately measured & paid for.
The filter area shall be made up of panels of size convenient for handling.
The filter panels shall be held snugly within suitable aluminum framework
made out of minimum 1.6 mm aluminum sheet with sponge neoprene
gaskets by sliding the panels between the sliding channels so as to avoid
air leakage.
In order to indicate the condition of these filters while in operation, a
manometer shall be provided to indicate the pressure drop across the fine
filters and absolute filters.
Each fine and HEPA filter shall carry test certificate from manufacturer.
LIMITATIONS:
The air velocity across the cooing coil shall not exceed 155 MPM. The fan
outlet velocity shall not exceed 610MPM. (Subject to Fan Noise Level not
exceeding 75dBA at 2-meter distance from AHU/TFA etc.)
The air velocity across the filters shall not exceed 155MPM.
The cooling coils, special and standard filters, etc., shall all be housed in a
separate section of suitable size and length. The inspection doors shall
have double synthetic rubber seals doors and locking arrangements. The
gaps between filter frames and housing shall have synthetic rubber
packing, to eliminate any air leakage. All filter frames shall be epoxy
painted. The flat filter section shall be suitable for mounting filters
vertically.
Page 198
SHASHI PRABHU & ASSOCIATES
FRESH AIR INTAKES:
VIBRATION ISOLATORS:
Vibration isolators shall be provided with all air handling units. Vibration
isolators shall be cushy foot mounting type.
NOISE LEVEL:
For Floor mounted AHU: Not more than 75 dBA at 2 Mtr. Distance
For Ceiling suspended AHU: Not more than 55 db at 1 Mtr. Distance
ACCESSORIES:
Each air handling unit shall be complete with the following as part of AHU
price.
MIXING BOX
Page 199
SHASHI PRABHU & ASSOCIATES
DAMPER
ACCESSORIES
Each air handling unit shall be provided with manual air vent at high
point in the cooling coil and drain plug in the bottom of the coil.
ISOLATORS
SAFETY FEATURES
The Fan access door shall be equipped with micro switch inter locked
with fan motor to enable switching of the fan motor automatically in the
event of door opening.
The access door shall have further wire mesh screen as an added safety
feature bolted on the unit frame.
All the screw used for panel fixing shall be covered with PVC caps to
avoid human injury.
Fan & motor should be properly earthed.
Page 200
SHASHI PRABHU & ASSOCIATES
opposed blade louver type. Blades shall be made of extruded aluminum
construction and shall be rattle free. Dampers shall be similar to those
specified in “Air Distribution”. Fresh air fans and fresh air intakes shall
be as per the requirements of Schedule of Quantities.
PAINTING
PERFORMANCE DATA
Air handling unit shall be selected for the lowest operating noise level as
per ASHRAE standard (Sound and Vibration Control) of the equipment.
Fan performance rating and power consumption data, with operating
points clearly indicated shall be submitted and verified at the time of
testing and commissioning of the installation. Computerized selection
for air handling units shall be provided through 3rd party certified
software for all the Floor Mounted AHUs.
TESTING
LIMITATIONS
The air velocity across the coil shall not exceed 50mtr/minute. The fan
outlet velocity shall not exceed 600 mtr / minute.
SCOPE
TYPE
The fan coil unit shall be suitable for chilled water application,
Contractor Signature MCGM
Page 201
SHASHI PRABHU & ASSOCIATES
horizontal Powder coated type to be mounted within ceiling space. The
units shall have horizontal discharge and complete with chilled water
coil, one or more centrifugal fans and motors, synthetic cleanable pre-
filters, double skin insulated (CFC & HCFC FREE) condensate drain
pan. Horizontal fan coil units shall be provided with auxiliary secondary
condensate drain pan.
CAPACITY
The air moving and coil capacities shall be as shown on Drawings and
indicated in Schedule of Quantities.
CABINETS
INTERIOR CHASSIS
The interior chassis shall be constructed of not less than 16 gauge cold
rolled galvanized sheet steel bowdlerized and painted with approved
shade of powder coating finish. All ceiling suspended fan coil units shall
be securely mounted from the building structure with top panel set dead
level in both directions. In case of ceiling suspended horizontal units,
fan deck and cooling coil shall be easily removable from FCU without
lowering down of the FCU or disturbing the other installation.
FAN SECTION
COOLING COIL
Page 202
SHASHI PRABHU & ASSOCIATES
to 5 fins per cm. Tubes shall be mechanically/ hydraulically expanded
for minimum thermal contact resistance with fins. Air vent shall be
provided in headers at a level higher than coils. The cooling coil shall be
easily removable from backside of FCU without disturbing the other
installations. The copper tube or pipe should not be manufactured from
reprocessed or recycled copper. The coil circuit should be sized for
adequate water velocity but not exceeding 1.8 m/s. The air velocity
across the coil shall not exceed 155 m/min.
DRAIN PANS
MOTOR
Motor shall be 220 ± 6% volts, 50 cycle, single phase, six poles, shaded
pole type, rpm not exceeding 1000 at maximum airflow. Motor shall
have three speed windings and shall be factory wired to a terminal block
mounted within the fan section. Motors shall have extended shaft on
both sides.
SPEED CONTROL
A sturdy switch shall be provided with the unit complete with wiring, for
ON/OFF operation and with minimum three speed control of the fan.
AIR FILTER
The filter shall be cleanable type 15mm thick with 90% efficiency down
to 10 micron of dry cleanable synthetic type AL. wire mesh and mounted
behind the pan in a filter plenum of GI sheet.
WATER CONNECTIONS
The water lines shall be finally connected to the coil of the fan coil unit,
by at least 300mm long, type `L‘ seamless solid drawn copper tubing,
with flare fittings and connections.
Contractor Signature MCGM
Page 203
SHASHI PRABHU & ASSOCIATES
PAINTING
CONTROLS
PERFORMANCE DATA
Fan coil units shall be selected for the lowest operating noise level
having standard sound level rating of NC 30 at low speed and NC 35 at
medium / high speed. Fan performance rating and power consumption
data, with operating points clearly indicated, shall be submitted by the
Contractor and verified at the time of testing and commissioning of the
installation.
TESTING
Cooling capacity of various fan coil unit models shall be computed from
the measurements of airflow and dry and wet bulb temperatures of
entering and leaving the coil. Flow measurements shall be by
anemometer and temperature measurements by accurately calibrated
mercury -in-glass thermometers. Computed ratings shall conform to the
specified capacities and quoted ratings. Power consumption shall be
computed from measurements of incoming voltage.
GENERAL
Page 204
SHASHI PRABHU & ASSOCIATES
vendor.
Page 205
SHASHI PRABHU & ASSOCIATES
CO SENSOR & DETECTORS
‘CO’ sensor shall be designed to detect Carbon Monoxide gas in the air.
The sensor should have high accuracy even at low concentration.
It should be suitable for installation in a parking lot, underground
basements, tunnels &underground spaces.
The model shall be compact in size and shall offer ease of installation.
The device should be a solid-state semi-conductor type sensor, high
sensitivity and selectivity to carbon monoxide and low sensitivity to
alcohol vapor.
Sensor should meet the minimum technical parameters as listed below:
Electrical
Power supply +16-
29VDCwithreversepolaritydiod
eprotection
Power 22mAmax.(0.5VA@+24VDC)
consumption
Analog signal Linear proportional4-
output 20Macurrentloop
Output load ≤500Ωfor current signal
Sensor Performance
Sensor element Electrochemical( Ge Based
type Diffusion)
Detected gas Carbon Monoxide(CO)
Measurement 0-300ppm
range
Accuracy ±3ppm
Resolution 0.5ppm
Repeatability < ±5%FS
t90Time ≤50seconds
Zero-point ±4ppm
variation
Zero/Gain <±0.4%FSsignal/month
calibration drift
Sensor Life Time >6 years(with recommended
calibration interval)
Page 206
SHASHI PRABHU & ASSOCIATES
25mm2tomax.2.5mm2
Mounting Wall mounting
Relative Gas Density 0.97(Air=1)
Mounting Height 1.5to1.8meter
Recommended Coverage 400m2to750m2,ideal
Area condition assumed
Dimensions(sensor 38mm(L)xM25mountingdia
cartridge only) meter
Weight(sensor cartridge 30g
only)
Sensor Cartridge PolycarbonateIP65
Optional Housings F:ABS,IP44,UL94:V0,weight
Specifications: :0.1KgD:Polycarbonate,
IP65, UL94:V2,
weight:0.15KgK:DHousingw
ith DuctKit,weight:0.1Kg
• EMC Directives2014/30/EU
• CE
• IP65/66 (EN60529 / DINVED–0470-1)
• Impact Resistant IK08 (DINEEN5012/VDE0470seg.100
• UL508 / CSA Certified C22.2 No.94.1-07-Enclosure for Electrical
Equipment
• UL50 / CSA22.2 Certified Enclosure for Electrical Equipment
Page 207
SHASHI PRABHU & ASSOCIATES
CO2 SENSORS & DETECTORS
TECHNICALSPECIFICATION:
PHYSICALSPECIFICATIONS:
Page 208
SHASHI PRABHU & ASSOCIATES
EXPANSION TANK AND AIR SEPERATOR:
Pressurized Cold water expansion tank (PN16) suitable for total volume of
water in Cold water circuits along with necessary accessories such as
pressurization unit etc. in order to keep Cold water system under (+)
pressure and to prevent entrapment of pressure and to prevent entrapment
of air in the system. The system shall also include a fully automatic
pressurization unit with 2 pumps (1 Working + 1 Standby) with IP56
protection giving 2 CMH flow rate @ 25m with pressure switch/transmitter,
flow meter, interconnecting piping, wiring & control panel completely
assembled on skid with all necessary valves & manifolds. The tank shall be
pre-charged steel expansion tank with replaceable heavy duty butyl rubber
bladder. The tank shall have a system connection with isolation valve,
drain connections with ball valves and charging valve connection to
facilitate the onsite charging of the tank to meet system requirement. The
expansion tank shall have pressure gauges fitted with isolation valves and
high capacity auto air vents with isolation valves. The tank shall have
safety valve, 50 mm system connection and 20 mm drain and charging
valve connection to facilitate the onsite charging of the tank to meet system
requirement. The tank shall be fitted with lifting rings and a floor mounting
skirt for vertical installation. The tanks shall be coated with two coats of
anti-corrosive paint (LOW VOC). Two coats of lag coating (Anti-fungal &
vapour barrier -5590 standard). It shall be covered with Nitrile Rubber
thermal insulation (density 45-60 kg/m3, CFC/HCFC FREE) with
laminated one sided thick glass woven cloth with suitable adhesive. The
Adhesive used for shall be of low volatile organic compound. Two coats of
lag coating (Anti-fungal & vapour barrier -5590 standard).The contractor
shall submit calculations for total system volume and tank sizing
calculations and accordingly expansion tank capacity shall be finalized.
The contractor shall furnish material test certificates of various
components & performance test certificates carried out by manufacturer.
Page 209
SHASHI PRABHU & ASSOCIATES
RETURN AIR RISER:
The Return Air Risers shall be comprising 18 G GI epoxy painted risers with
EU filter, Powder coated Aluminum perforated sheet & damper. The riser
should be have internally coving with step in fixing arrangement for filter
and perforated sheet
Page 210
SHASHI PRABHU & ASSOCIATES
7 HYDRONIC CHILLED WATER CASSETTE UNITS
GENERAL
The Cassette units shall be ceiling hung type. Ceiling hung units shall
have 4 way directional air discharges. All units shall be complete with
chilled water coil, fins centrifugal fans and motor, cleanable fabric
filters, condensate drain pump, drain pan & grill.
CABINETS
DRAIN PAN
COOLING COIL
All cooling coils shall be standard three row staggered seamless copper
tube with aluminum fins. The coil shall be fitted with for connection
with MS pipes. Tubes shall be minimum 9 mm OD of required
thickness. Fin spacing shall be between 4 to 5 fins per cm. All bends
and joints shall be enclosed within insulated end sections of the base
unit for protection against sweating. Tubes shall be
mechanically/hydraulically expanded for minimum thermal contact
resistance with fins. The cooling coil shall be easily removable without
disturbing the other Installations. The coil circuit should be sized for
adequate water velocity but not exceeding 1.8 M/s. (6 F.P.S.). The fins
shall be uniformly bounded to the tubes by hydraulic expansion of the
tubes. The fins material shall be anticorrosive blue coted aluminum.
FANS
MOTOR
Page 211
SHASHI PRABHU & ASSOCIATES
INSTALLATION
Ceiling suspended units and units mounted within the ceiling mounting
shall be hung through rubber in shear vibration isolator suspenders.
ACCESSORIES
All Cassette coil units shall be equipped with copper piping connections.
In addition, the following accessories are required at coil units;
WATER CONNECTIONS
The water lines shall be finally connected to the coil of the fan coil unit,
by at least 300mm long, type L seamless solid drawn copper tubing with
flare fittings and connections.
Page 212
SHASHI PRABHU & ASSOCIATES
8 PRECISION AIR CONDITIONING UNITS FOR SERVER ROOM
SCOPE
The scope of this section comprises the supply, erection, testing and
commissioning of Precision Air Conditioning Units conforming to these
specifications and in accordance with the requirements of Drawings and
Schedule of Quantities.
TYPE
CAPACITY
The refrigeration capacity and air quantity for the unit shall be as shown
in Drawings and Schedule of Quantities. Manufacturer shall submit unit
capacity software selection as per tender design conditions.
CASING
Page 213
SHASHI PRABHU & ASSOCIATES
section shall be constructed of thick sheet steel all welded / bolted
construction, adequately reinforced with structural members and
provided with sufficient access panels for proper lubrication and
maintenance. Base panel shall be constructed of fabricated steel
structure provided with an under frame suitably braced. Drain pan shall
extend under coil and fan sections with drain connections.
Units shall have hinged, quick opening access door in the fan & coil
section and also in filter section where filters are not accessible from
outside. Access doors shall be double skin type.
Outdoor unit shall consist of condenser coil and propeller type fan for
air cooled unit.
The compressor shall be hermetic sealed type and suitable for operation
on Eco-friendly refrigerant HFC-410a/HFC-407c. The compressor shall
have dual pressure stat and an operating oil charge. The motor shall be
suction gas cooled and shall be sealed against dirt and moisture.
The motor shall be suitable for 415± 10% V, 50 Hz, 3 Phases AC supply.
The compressor shall be located in separate compartment isolated from
air stream to permit servicing without shutting down the system.
Compressor shall be installed on spring mounted floating platform /
rubber pads or manufacturers recommended approved mounting.
Suitable overload protection shall be provided in compressor. Isolating
valves shall be provided at suction & discharge. Compressor shall be
fitted with electrically operated oil heaters with built-in thermostats and
the heaters shall be automatically actuated when the compressor is
stopped. In built TIME DELAY shall be provided for restart of
compressor.
EVAPORATOR SECTION
Evaporator coil shall be of fin and tube type having hydrophilic coated
aluminium fins firmly bonded to copper tubes assembled in zinc coated
steel frame. Face and surface areas shall be such as to ensure rated
capacity from each unit and air velocity across each coil shall not exceed
Contractor Signature MCGM
Page 214
SHASHI PRABHU & ASSOCIATES
500 FPM. The coil shall be minimum 3 row deep for DX coil.
For dual feed unit, chilled water coil shall be provided in addition to DX
coil. Chilled water coil shall be minimum 4 rows deep. Coils shall be
pitched in the unit casing for proper drainage. Each coil shall be factory-
tested at 21 Kg. per sq.cm air pressure under water. Tube shall be
mechanically / hydraulically expanded for minimum thermal contract
resistance with fins. The number of fins per cm. shall be 4 to 5.
BLOWER SECTION
The unit shall be under floor / top discharge type and should be able to
deliver between 550-600 CFM per ton. Total external static pressure
shall be of minimum 5 mm of WG for top discharged units. Units with
top discharge shall be designed for required static pressure as per actual
ducting arrangement.
The units should be equipped with direct driven backward curved plug
fans with electronically commutated brushless motors suitable for 415 ±
10% V, 3 Phase, 50 Hz AC supply. The motor’s high efficiently should
make for less energy absorption, especially at partial loads and during
starting. The motor shall be of IP 54 grade. The fan shall be directly
coupled having a maximum speed of 1400 R.P.M. The fan speed shall be
controlled through microprocessor panel based on temperature &
humidity set points. Fan motor assembly shall be statically and
hydraulically balanced and designed for quite operation.
Page 215
SHASHI PRABHU & ASSOCIATES
from 30 % to 100% of its total capacity with help of microprocessor. The
humidifier shall be fully serviceable with replaceable electrodes. Waste
water shall be flushed from the humidifier by initiation of water supply
valve via U-trap. The microprocessor should be able to display the
current drawn and actual steam output in the microprocessor.
Heater should be of minimum two stages & heating circuit shall include
dual safety protection through loss of air and manual reset high
temperature controls.
FILTERS
Refrigerant piping and fittings within the unit shall be of copper and
valves shall be of brass / gunmetal construction. Piping thickness shall
be designed based on type of refrigerant and superheated gas pressure
at full load, corresponding to ambient dry bulb temperature of 45ºC.
Page 216
SHASHI PRABHU & ASSOCIATES
f. Liquid Line Solenoid Valve for interception of Liquid Refrigerant
All external pipe work shall be carried out with 18G refrigerant quality
copper tube and where bends are required; the same shall be completed
using either a proprietary bending tool or radius fittings.
The fan shall be selected for low speed quiet operation. The fan shall be
directly driven by a motor of speed not exceeding 1000 RPM and
constructed from sheet and cast aluminum. When compressor stops
condenser fan shall also stop after a suitable time delay.
ELECTRICAL SYSTEM
Page 217
SHASHI PRABHU & ASSOCIATES
c. Separate over load preventer for all individual components.
SAFETY CONTROLS
SAFETY INTERLOCKS
Operation of heaters & humidifier shall be possible only when blower fan
is in operation.
Condenser fan shall stop after a suitable time delay on Compressor’s
stopping.
MICROPROCESSOR CONTROLS
Page 218
SHASHI PRABHU & ASSOCIATES
l. Delay of General Alarm activation.
m. Alarm calibration.
PAINTING
Units shall be factory finished with durable alkyd spray enamel. Shop
coats of low VOC paint that have become marred during shipment or
erection shall be cleaned off with mineral spirits, then coated with
enamel paint to match the finish over the adjoining shop-painted
surface.
PERFORMANCE RATING
The unit shall be selected for the lowest operating noise level (65 dBA at
3m). Capacity rating and power consumption with operating points
clearly indicated shall be submitted with the tenders and verified at the
time of testing and commissioning of the installation. For site
verification of working of humidification / dehumidification systems, set
point RH shall be changed below / above (respectively) actual RH.
Similar procedure shall be adopted for temperature control system. Test
report shall indicated selected set point for RH and temperature and
achieved values of these process variables after humidification /
dehumidification cycles are activated.
Page 219
SHASHI PRABHU & ASSOCIATES
9 VARIABLE REFRIGERANT VOLUME/FLOW SYSTEM
SCOPE
The scope of this section comprises the supply, erection testing and
commissioning of 100 % inverter based Variable Refrigerant Flow
System with hermetically sealed Scroll/ Rotary Compressor conforming
to these specifications and in accordance with the requirements.
TYPE
Outdoor unit shall be suitable for mix match connection of all type of
indoor units.
The refrigerant piping between indoor units and outdoor unit shall be
extendable up to 165m actual piping length for outdoor unit with
maximum 50m level difference without any oil traps and total piping
length with 1000m.
Both indoor units and outdoor unit shall be factory assembled, tested
and filled with first charge of refrigerant before delivering at site.
OUTDOOR UNIT
Page 220
SHASHI PRABHU & ASSOCIATES
All outdoor units above 8 HP shall have minimum two scroll/ rotary
compressors and be able to operate even in case one of compressor is
out of order.
In case of outdoor units above 14HP, the outdoor unit shall have at least
2 inverter compressors so that the operation is not disrupted with
failure of any compressor.
All outdoor units must be equipped with night time quite operation
function which results in less sound level in night time operations of the
outdoors. The nighttime quiet operation shall be with three modes
automatic, manual and combined mode.
The noise level shall not be more than 68 dB (A) at normal operation,
measured horizontally 1m away and 1.5m above ground level.
The outdoor unit shall be modular in design and should be allowed for
side by side installation.
The unit shall be provided with its own microprocessor control panel.
The outdoor units shall be complete with safety devices namely –high/
low pressure switch, fan driver overload protector, over current relay,
inverter overload protector.
The oil mechanism shall be capable of oil film control by high thrust
mechanism.
The heat transfer circuit should perform super cooling before the
expansion process in the indoor units.
The outdoor unit’s side panel and outer panel shall be alloyed hot dip
zinc coated steel plate with powder polyester resin coating on the inner
and outer surfaces in the thickness of 32 micron.
The outdoor unit’s bottom frame shall be hot dip aluminum; zinc and
silicone coated steel plate.
The outdoor unit should be fitted with low noise, aero spiral and aero
asymmetrical design fan with multiple speed DC motor. The fan shall be
coated with styrene acrylonitrile res in(glass fiber filled) The fan shall be
covered with aero smooth grille which shall be three dimensional,
integrated, soft woven steel covered with plastic coating. The fan
protective net shall be coated with weather resistant polypropylene
resin.
Contractor Signature MCGM
Page 221
SHASHI PRABHU & ASSOCIATES
INVERTER COMPRESSOR
The inverter shall be IGBT type for efficient and quiet operation.
All outdoor units shall have step less of capacity control to meet load
fluctuation and in door unit individual control. All parts of compressor
shall be sufficiently lubricated. Forced lubrication may also be
employed.
HEAT EXCHANGER
The unit shall be provided with necessary number of direct driven low
noise level propeller type fans arranged for vertical discharge. Each fan
shall have a safety guard.
REFRIGERANT CIRCUIT
The refrigerant circuit shall include liquid & gas shutoff valves and a
solenoid valve at con denser end.
SAFETY DEVICES
Page 222
SHASHI PRABHU & ASSOCIATES
OIL RECOVERY SYSTEM
INDOOR UNIT
GENERAL
Noise level should not be more than 42 db at high speed for Hiwall unit.
Noise level should not be more than 40 db at high speed for cassette.
Noise level should not be more than 45 db at high speed for Ductable
unit.
Unit shall have cleanable type filter fixed to an integrally molded plastic
frame. The filter shall be slide away type and neatly inserted.
Each indoor unit shall have computerized PID control for maintaining
design room temperature. Each unit shall be provided with
microprocessor thermostat for cooling and heating.
Each unit shall be with wired LCD type remote controller. The remote
controller shall memorize the latest malfunction code for easy
maintenance. The controller shall have self-diagnostic features for easy
Contractor Signature MCGM
Page 223
SHASHI PRABHU & ASSOCIATES
and quick maintenance and service. The controller shall be able to
change fan speed and angle of swing flat individually as per
requirement.
The unit shall be ceiling mounted type with four directional flow. The
unit shall include pre filter, fan section and DX-coil section. The housing
of the unit shall be powder coated Galvanized steel. The body shall be
light in weight and shall be able to suspend from four corners.
Unit shall have an external attractive panel for supply and return air.
Unit shall have four-way supply air grilles on sides and return air grille
in center.
Each unit shall have high lift drain pump, fresh air intake provision (if
necessary) Low gas detection system and very low operating sound.
All the indoor units regardless of their difference in capacity should have
same panel size for harmonious aesthetic point of view. The sound
absorbing thermal insulation material shall be polyurethane foam.
For connection with Dx-type AHU, necessary kit for connection to the
VRV/VRF based refrigerant circuit, expansion valve & dries,
thermostat etc. as required shall be provided
The unit shall be high wall mounted type. The unit shall include pre-
filters, fan section and DX coil section. The housing of the unit shall be
powder coated galvanized steel. The body shall be light in weight and
shall be able to suspend from four comers. The fan shall be aero
dynamically designed diffuser turbo fan type.
Unit shall have an external attractive panel for supply and return air.
REFRIGERANT PIPING
All refrigerant piping for the air conditioning system shall be constructed
from soft seamless upto 19.1mm and hard drawn seamless copper
refrigerant pipes for above 19.1mm with copper fittings and silver
soldered joints. The refrigerant piping arrangements shall be in
accordance with good practice within the air conditioning industry, and
are to include expansion valves, charging connections, suction line
insulation and all other items normally forming part of proper
refrigerant circuits.
All joints in copper piping shall be sweat joints using low temperature
brazing and or silver solder. Before joining any copper pipe or fittings, its
Contractor Signature MCGM
Page 224
SHASHI PRABHU & ASSOCIATES
interiors shall be thoroughly cleaned by passing a clean cloth via wire or
cable through its entire length. The piping shall be continuously kept
clean of dirt etc. while constructing the joints. Subsequently, it shall be
thoroughly blown out using nitrogen.
The air-conditioning system supplier shall design sizes and erect proper
interconnections of the complete refrigerant circuit.
The suction line pipe size and the liquid line pipe size shall be selected
according to the manufacturers specified outside diameter. All
refrigerant pipes shall be properly supported and anchored to the
building structure / cable tray using steel hangers, anchors, brackets
and supports which shall be fixed to the building structure by means of
inserts or expansion shields of adequate size and number to support the
load imposed thereon.
Vacuum drying of the system has to be carried out after passing of air
tightness test and will be carried out with a Vacuum Pump which can
bring the pressure below – 100.7 KPaG (755 mm Hg). During Vacuum
test, evacuation from both the liquid and gas piping must be carried out.
The system in a vacuum state below – 100.7 KPaG (755 mm Hg) shall be
left for atleast 4 hours and in case the gauge indicator does not rise the
test will be considered successful. If the gauge indicator rises, there may
be moisture remaining or a leak in the circuit.
Page 225
SHASHI PRABHU & ASSOCIATES
10 SPLIT TYPE AIR CONDITIONED UNITS:
SCOPE
The scope of this section comprise the design supply, erection, testing
and commissioning of air-cooled package units conforming to these
specifications and in accordance with the requirements.
TYPE
The total derating on all accounts will not exceed more than 10%.
CAPACITY
Page 226
SHASHI PRABHU & ASSOCIATES
CASING
Fan motor shall be TEFC suitable for 1/3 phase, 50 Hz ±3%, AC supply
and provided with necessary safety devices to withstand voltage
fluctuation from 160250 ( for single phase machines) and 340 V to 440V
(for 3 phase machines). Motor shall be provided with soft Starters of
required capacities. Motors shall be especially designed for quiet
operation and motor speed shall not exceed 1440 rpm. Drive to fan shall
be provided either directly or through belt drive with an adjustable
motor sheave. Belts shall be of the oil resistant type.
FAN
Fan wheels and housing shall be fabricated from minimum 18G sheet
steel. Fan wheels shall be of double width, double inlet forward curve,
multi speed, multi blade type enclosed in a housing with electrical
heating with strip heater and mounted on a common shaft. Fan
housings shall be made of deformed steel sheets with stream lined inlets
to ensure smooth air flow into the fans. Fan shaft bearing shall be
oil/grease lubricated. Bearing shall be mounted externally for servicing
without dismantling of the unit. All rotating parts shall be dynamically
balanced individually, and the complete assembly shall be statically and
dynamically balanced. Fan speed shall not exceed 1000 rpm and
maximum fan outlet velocity shall be 550 meters per minute.
COOLING COIL
Cooling coil shall be fin and tube type having aluminum fins firmly
bonded to copper tubes assembled in zinc coated steel frame. Face and
surface areas shall be such as to ensure rated capacity from each unit
and air velocity across each coil shall not exceed 150 meters per minute.
Contractor Signature MCGM
Page 227
SHASHI PRABHU & ASSOCIATES
The coil shall be pitched in the unit casing for proper drain age. Each
coil shall be factory tested at 21 kg. Per sq.cm. air pressure under water.
Tube shall be mechanically / hydraulically expanded for minimum
thermal contact resistance with fins. The no. of fins per cm. shall be 4 to
5.
VIBRATION ISOLATORS
The indoor and outdoor units shall be provided with vibration isolators.
PAINTING
Package units shall be factory finished with durable alkyd spray enamel.
Shop coats of paint that have become marred during shipment or
erection shall be cleaned off with mineral spirits, then coated with
enamel paint to match the finish over the adjoining shop painted surface.
PERFORMANCE RATING
The unit shall be selected for the lowest operating noise level. In all air
conditioned spaces noise level should not exceed NC35, 2m away from
face of supply air outlet. Capacity ratings and power consumption with
operating points clearly indicated shall be submitted with the tenders
and verified at the time of testing and commissioning of the installation.
TEMPERATURE CONTROLS
MISCELLANEOUS
Page 228
SHASHI PRABHU & ASSOCIATES
11 STP EXHAUST AIR TREATMENT (DEODORIZATION SYSTEM)
The system shall not require any replacement consumable except air
filter, and maintenance shall be minimum or near zero subject to timely
replacement of intake air filter to the unit.
The ozone generating corona and ozone wetted parts shall be confined in
a fully welded stainless steel enclosure to prevent ozone leaks. It shall be
provided with openable glass or plexi glass panel for inspection of corona
plates while the equipment is in operation. The outer enclosure of the
equipment shall be provided with lockable doors to provide easy access
to the glass inspection panel.
The corona chamber shall not have any trace of exhaust air while it
starts and operates. Necessary ROHS compliant and UL listed electrical
relay shall be provided to ensure this safety feature. The electrical
compartment shall be isolated from all other compartments, and rated
to NEMA 4X (IP 66). The transformer shall be electrical induction type,
UL listed. It shall not damage, burn, or elevate in temperature even if
short circuit occurs. Shall revert to normal operation upon removal of
short circuit. The transformer shall be fully encapsulated and housed in
metallic enclosure for safety against moisture and water impregnation.
High voltage cable shall be silicon insulated, ozone and corona resistant,
rated for 20 KV, and UL listed with UL flame test rating.
Page 229
SHASHI PRABHU & ASSOCIATES
d. UL listed switches such as DPST Main On Off Switch, Fan On
Off Switch, Indicating Lamps, and Terminal Block.
The system shall be rated for operation on 220/240 V, 1 Ph, 50/60 Hz &
supplied with Control Panel H2S Monitor, DLC Controller, and Ozone
Monitor Listed to UL 867A, for automatic modulation. The system shall
Delivers 0 – 10 VDC for BMS interface.
Page 230
SHASHI PRABHU & ASSOCIATES
12 VENTILATION FAN
GENERAL (FANS)
Fans shall be installed at staircase or lobby where fresh air intake is free
from any obstruction and shall be energized only by fire alarm system. Fan
shall be of Axial Flow Fan or DIDW Centrifugal Fan. Protective wire mesh
with MERV-7 fresh air filter at the suction of the fan is required.
For Smoke Extraction Fans where motor is in the air stream with
electrical/electronic temperature limit switch for motor protecting shall not
be used.
Anti-condensation heater is recommended to be installed for all
Pressurization and Smoke Spill Fans, and the control circuit shall be
arranged such the way that the heater is off when the starter is on and vice
versa. Heaters shall be wired from the respective local motor control panel
Page 231
SHASHI PRABHU & ASSOCIATES
or motor control console.
Fan should be of G-90 high grade galvanized steel or carbon steel with
epoxy coat.
If fan is open to atmosphere, Fans shall be with pure polyester powder
coating for minimum thickness of 60 microns.
IN-LINEFANS:
The fan shall be provided with ball bearings can be used in any mounting
position at maximum indicated temperature. The bearing lubricant shall be
suitable for a minimum ambient temperature of minus 150C (admissible for
a short time without reaching dew point at minus 300C). For applications at
maximum indicated ambient temperature life expectancy shall be 40000
hours minimum.
Motor shall be with minimum IE3 rating. Fan motor, fans shall be supplied
with built-in-thermal contact (TK) at the critical high temperature point (“B”
= 1300C. The thermal contact shall open and break the power supply to the
fan; Fan motors have insulation class “B” and protection class IP54. Motor
shall be suitable for external power supply 200~220V/50Hz/Single Phase
OR 415+10% v/50Hz/Three Phase.
Fan should be provided with factory made built in hanging clits bolted
firmly on fan body with the holes for installation.
Direction of rotation to be marked firmly on fan body.
All fan shall be electronic speed regulator & wiring with 3 pin plug top
Page 232
SHASHI PRABHU & ASSOCIATES
between fan & speed regulator for single phase fans. In case of 3-phase fan
with DOL starter panel & FRLS power cabling, earthing etc. between starter
panel & fan. The incoming power supply to speed regulator/ starter panel
shall be provided by electrical contractor.
Wire guard and bird-screen
PROPELLER FANS:
Propeller fans shall be direct driven, three or four blade type mounted on a
steel mounting plate with orifice ring.
Shaft shall be of steel accurately ground and shall not pass through first
critical speed through entire range of specified fan speed.
Page 233
SHASHI PRABHU & ASSOCIATES
Single-phase preventers for 3 phase fans.
3 pin plug top with power cable with earthling from fan motor to 3
pin socket shall be
Included in installation cost of fan.
Fans shall be licensed to bear the AMCA Air and Sound Certified Ratings
Seal. The test standard used shall be ANSI/AMCA 210-85, ANSI/ASHRAE
Standard 51-1985 “Laboratory Method of Testing Fans for Rating” and
AMCA 300 “Reverberant Room Method for Sound Testing of fans”.
To achieve the minimum and equal clearance between the blade tips and
casing, tube casing shall maintain its roundness by means of using one
piece of sheet metal with 90 edge flanging up.
Fan motor base support shall be properly secured (locked and sealed) to
the fan housing and be of adjustable type to have precise control of motor
shaft central position as well as running clearance between blade tips and
casing. Motor (KW/HP) shall be able to be changed or upgraded at site
without changing fan housing or ducting construction.
All hubs shall be cast Aluminum alloy (Grade LM2) unless for Smoke
Extractor Fans where high temperature (250C/2Hrs) air is expected then
Aluminum alloy or steel fan impeller blades are required. Otherwise
impeller blade material with Polypropylene (PP), Glass-reinforced
Polypropylene (PPG) and Glass-reinforced Polyamid (PAG), to provide self-
balancing, anti-static, anti-sparking characteristic is preferable.
Running clearance between blade tips and casing shall not exceed 1% of
the impeller diameter, and 2% for smoke spill high temperature fan where
mechanical expansion coefficient is different from normal ambient
temperature. Fan manufacturer shall provide the fan assembled with the
dame clearance between blade tips and casing of the tested prototype. Note
that the air performance and pressure loss are greatly affected by this
clearance.
Impellers shall be secured to the drive shaft by a key and keyway. Axial
location shall be provided by a collar or shoulder on the drive shaft together
with a retaining washer and screw fitted into a tapped hole at the end of
the shaft and locked in position. Blades shall be secured in place to the
Page 234
SHASHI PRABHU & ASSOCIATES
angle setting by setscrews, locking nuts or setting pins.
Fan motor shall be totally enclosed and external terminal box of at least
IP56 shall be provided.
Fan should be of G.S.S., the Steel sheet should be JFE Galva zinc
(Base metal cold rolled), JIS G3302, SGCC with Z22 (minimum coating
weight on both sides @ 220 g/m2) zinc coating & Zero Spangle, skin
passed, chromate and dry.
Fan shall be complete with motor, motor mount, direct driven and vibration
isolation type, suspension arrangement as per approved for construction
shop drawings. Fresh air fans shall be equipped with filters as specified in
schedule of quantity.
Rotor hub and blades shall be of cast aluminum, or cast steel construction.
Blades shall be die-formed aero foil shaped for maximum efficiency and
shall vary in twist and width from hub to tip to effect equal air distribution
Contractor Signature MCGM
Page 235
SHASHI PRABHU & ASSOCIATES
along the blade length. Fan blade mounting on the hub shall be statically
and dynamically balanced. Extended grease leads for external lubrication
shall be provided. The fan pitch control may be manually re-adjustable at
site, upon installation, for obtaining actual airflow values, as specified.
Starter for the motor shall be direct on line (D.O.L) for motors up to and
including 7.5 H.P. rating and automatic star-delta close transition type for
motors of higher ratings unless otherwise specified in the tender
specifications. Starters shall be rated for intermittent duty. Starting current
should not exceed two times the full load current.
The starter shall be mounted on the main electrical control panel/ unit
mounted/ self-mounted as specified.
The speed of fan shall not exceed 1000 RPM for fans with impeller diameter
above 450 mm, and 1450 RPM for fans with impeller diameter of 450 mm
and less.
Vibration Isolation
Base shall be provided for each fan. Base for both fan and motor shall be
built as an integral part and shall be mounted on a concrete foundation
through cushy foot vibration isolators. The concrete foundations shall be at
least 15 cm above the finished floor level and shall be further isolated from
the structural floor through 5 cm. Thick layers of sand all around, topped
with bitumen. In case ceiling hung fan within the ceiling shall be provided
Vibration Isolation Suspension (VIS) shall be provided in each of string.
CENTRIFUGAL FANS
Page 236
SHASHI PRABHU & ASSOCIATES
listed
Drive to fan shall be provided from 3 phase electric motor through belt with
adjustable motor sheave and belt guard. Belt shall be of the oil resistant
type. The number of belts shall be not less than two.
Motor shall be with minimum IE3 rating and TEFC type. Motor shall be of 3
phase squirrel-cage totally enclosed, fan cooled type. Motor and starter
shall be conform to IS: 1822 ―Motor starters of voltage not exceeding 1000
volts‖ and shall be air insulated and suitable for 415 volts, + 10%, 50 Hz., 3
phase AC supply. Enclosures shall have protection of IP 54.
Starter for the motor shall be direct on line (D.O.L) for motors up to and
including 7.5 H.P. rating and automatic star-delta close transition type for
motors of higher ratings unless otherwise specified in the tender
specifications. Starters shall be rated for intermittent duty. Starting current
should not exceed two times the full load current.
The starter shall be mounted on the main electrical control panel/ unit
mounted/ self-mounted as specified.
Page 237
SHASHI PRABHU & ASSOCIATES
The impellers of the fan or fan shall be of GI sheets, double inlet backward
curved centrifugal design, both statically and dynamically balanced. The
fan housing shall be of sturdy construction made from double skinned GSS
casing having 0.6mm pre-coated GI sheet outside and plain 0.6mm thick
GI sheet inside with 25 mm thick puff insulation with smooth air inlets.
The fan shall be mounted on properly aligned shaft and mounted on self-
aligning bearing blocks. The casing of the cab section shall be made of 16 G
(1.6mm) GI sheets suitably reinforced to provide rigidity. The frame work
shall either be folded G.I. sheets or of hot dipped galvanized iron.
Fresh air fans shall be equipped with filters as specified in schedule of
quantity
The fan section shall be complete with V belt drive, belt guard and motor
mounting base in case of Belt driven type.
Drive to fan shall be provided from 3 phase electric motor through belt with
adjustable motor sheave and belt guard. Belt shall be of the oil resistant
type. The number of belts shall be not less than two.
Starter for the motor shall be direct on line (D.O.L) for motors up to and
including 7.5 H.P. rating and automatic star-delta close transition type for
motors of higher ratings unless otherwise specified in the tender
specifications. Starters shall be rated for intermittent duty. Starting current
should not exceed two times the full load current.
The starter shall be mounted on the main electrical control panel/ unit
mounted/ self-mounted as specified.
Page 238
SHASHI PRABHU & ASSOCIATES
galvanized iron.
The fan section shall be complete with brushless EC motor mounting base.
Drive to fan shall be provided from 3 phase electric motor through direct
drive type complete with Brushless EC motor.
The Fan speed must be 100% adjustable with the potentiometer placed in
the connection box. Fan should be send Analogue input with terminals in
the terminal box to control the fan with 0-10V input signal. Models are
suitable for mounting in any orientation and operation within ambient air
temperatures between -20ºC up to +40ºC
Starter for the motor shall be direct on line (D.O.L) for motors up to and
including 7.5 H.P. rating and automatic star-delta close transition type for
motors of higher ratings unless otherwise specified in the tender
specifications. Starters shall be rated for intermittent duty. Starting current
should not exceed two times the full load current.
The starter shall be mounted on the main electrical control panel/ unit
mounted/ self-mounted as specified.
Page 239
SHASHI PRABHU & ASSOCIATES
13 DRY SCRUBBER UNIT
GENERAL:
The scrubber shall be made to take care of the kitchen exhaust which
shall comprise mainly of Black soot; unburnt oil and odour of roasted
food from tandoor etc. Care will be taken to handle high volume of gases
and P/V (Pollutants / Volumetric flow rate) ratio less than 0.001 means
size of particulate matter which is reason for foul smell.
TECHNICAL PARAMETERS:
The unit shall provide efficiency of 90% or better for single pass base on
ASHRAE test method at flow rates of 800 – 1300 CFM per module
(supported by sample test report by a US laboratory).Multiple units can
be joined together for increased volume. The system shall be suitable to
connect to fan section with average velocity of 500 FPM across air
cleaner. The unit shall be CE-certified.
EQUIPMENT SPECIFICATIONS:
UNIT HOUSING:
BLOWER SECTION:
Page 240
SHASHI PRABHU & ASSOCIATES
constructed and rated based on delivery against the rated static
pressure with the media and filters in place. The fan will be of riveted
construction and made with GI sheet of required thickness. The fan
wheel will be of the multi blade type and mounted on two self-aligning
pillow block bearings of the requisite size. The fan shall be run with the
help of “V” Groove drives as per the re-commendation of the drive
supplier. The blower housing will of the Pittsburg joint construction and
the drive will be provided by a motor of adequate capacity. The motor
plate will be constructed out of 12 G MS or heavier metal with slotted
holes, which permit belt adjustment in both the directions. The outlet
velocity of the blowers will be kept low.
BASE CONSTRUCTION:
FINISH:
The electronic air cleaner shall be the two stage dual voltage plate type
cells, rated at not less than 90% efficiency as per the ASHRAE test
standards for dry particulate (supported by sample test report by a US
laboratory). The collection cells shall be in Single Pass arrangement to
provide for maximum collection efficiency.
Page 241
SHASHI PRABHU & ASSOCIATES
ionizer ground electrodes shall be 0.090-inch-thick aluminum. Both
repelling and collector plates shall be 0.020-inch-thick aluminum, 9.125
inch deep in direction of airflow and rigidly retained in place with
tubular spacers and tie rods. Spacing between plates shall be no less
than 0.175 inch. Ionizing electrodes shall be 24-gauge stainless steel
spiked design, ionization wires are not acceptable, rigidly supported
both vertically and laterally. High voltage support insulators shall be of
self-glazing Cordierite ceramic with all surfaces, including center hole,
glazed to enhance dielectric strength and retard tracking. Insulators
shall be mounted out of the airstream, to reduce contaminant buildup.
All high voltage electrical connections within each tier of cells, shall be
between cells and automatically made when cells are installed. All
electrical connections between unit tiers and high voltage connections
between power packs and cells shall be located on the access door end
of the cabinet and manually connected for ease of service.
POWER SUPPLIES:
SYSTEM CONTROLS:
Programmable Logic Controller (PLC) shall be housed in a NEMA12 type
enclosure. Controller shall be shipped for remote mounting and must be
installed indoors or other means of weather protection provided if
installed. Terminals shall be provided to inter connect the system fan
and shall sequence the detergent wash, soak, rinse fan force dry and
return to operation cycle. All sequence times shall be factory set. Control
initiation shall be semiautomatic, push button initiated, or fully
automatic by time clock, with semi-automatic push button override.
Contractor Signature MCGM
Page 242
SHASHI PRABHU & ASSOCIATES
The control cabinet shall be furnished with a factory installed and wired
7day initiator clock with battery backup.
The pressure drop shall not exceed the following (inches H2O):
ESP Section 0.14” Metal Mesh prefilter or after filter 0.10”. The ESP
section must have both an internal prefilter and an after filter, select
and add for each.
ADSORBER MODULE:
SAFETY FEATURES
Contractor Signature MCGM
Page 243
SHASHI PRABHU & ASSOCIATES
The fan access door shall be equipped with port hole window and micro
switch inter locked with fan motor to enable switching off the fan motor
automatically in the event of door opening.
The Access Door shall further have GI 8 SWG wire mesh screen as on
added safety feature bolted on to the unit frame.
PERFORMANCE DATA
The Air scrubber unit shall be selected for the lowest operating noise
level of the equipment. Fan performance rating and power consumption
data, with operation points clearly indicating shall be submitted and
verified at the time of testing commissioning of the installation.
Page 244
SHASHI PRABHU & ASSOCIATES
14 TWO-STAGE EVAPORATIVE COOLING UNIT FOR KITCHEN
FRESH AIR
SCOPE
The scope of this section comprises the supply, erection, testing and
commissioning of two stage evaporative direct/indirect cooling unit for
use in kitchen fresh/make-up air.
Evaporative coolers are cooling systems that use only water and a
blower to circulate air. In the system, warm, dry air is pulled through a
water-soaked pad. As the water evaporates, a cooling effect on the
surrounding air occurs. Evaporative coolers use only a fraction of the
energy of traditional air conditioning systems. Unfortunately, except for
in very dry climates, they may increase humidity to a level that makes
occupants uncomfortable. Two-stage evaporative coolers do not produce
humidity levels as high as that produced by traditional single-stage
evaporative coolers.
Features
Benefits
TYPE
Page 245
SHASHI PRABHU & ASSOCIATES
in BOQ in suitable horizontal configuration. As shown on drawings and
included in schedule of quantities.
CAPACITY
The evaporative unit capacity of the cooling and air quantity from the
blower fan and static pressure of blower fan shall be as laid down in the
tender documents. Where these parameters as calculated by the
tenderer exceed the specified values, the blower fan shall satisfy these
calculated values.
CASING:
Units shall have hinged or removable type quick opening access door in
the fan section and also in filter section where filters are not accessible
from outside. Access doors shall be double skin type. All the section of
air handling units should be accessible for easy maintenance.
Internal panels shall be fabricated so that there are no gaps between the
panel and frame work. Fabrication clearances shall be closed with
blank-off pieces or with sealant. Partitions shall be of sufficient
thickness to prevent deflection and vibration during unit operation.
Manufacturer shall provide suitable stiffening by means of box type
Contractor Signature MCGM
Page 246
SHASHI PRABHU & ASSOCIATES
members across the same.
Unit shall be with clean inside surfaces with beveled corners to the best
possible extent without crevices as may allow growth of algae / fungus.
In case on internal fittings such as dampers, the same shall be with
beveled edges and without sharp corners to prevent operator injury.
There shall be no screws projecting into unit or air stream. If the same is
unavoidable, the tips shall be fitted with rubber caps to prevent operator
injury.
Unit panels shall be factory fitted with pressure ports for DPT
installation. The number and size of these shall be confirmed in the unit
technical approval stage. In case opening is to be made in unit panel,
the same shall be with C-channel all around to prevent entry of PUF into
air stream. The channels shall be cut at 45 degrees at the corners to
avoid overlap. Material for the channel shall be same as that of internal
skin of unit.
Rubber grommets shall be provided at all entry points into unit such as
piping connection, cable entry etc. The same shall be double lip tight
fitting to prevent air leakage.
DAMPER:
Fan motors shall be energy efficient (IE-3) and shall be 415±10% volts,
50±5% cycles, three phases, totally enclosed fan-cooled class F, with IP-
55 protection. Motors shall be especially designed for quiet operation.
Belt driven backward cured DIDW fans shall be used for SA. Provision
for cable entry to the motor shall be made at the factory itself. Drilling of
holes at site shall not be acceptable. Limit switch arrangement along
Contractor Signature MCGM
Page 247
SHASHI PRABHU & ASSOCIATES
with wiring shall be provided, so that when access doors opens, fan
stops. Motor shall be epoxy painted.
Fans shall be belt drive backward curved DIDW fan with aerofoil design
blades for kitchen exhaust areas of floor mounted units. The entire fan
with casing will be certified by a reputed 3rd party internationally
acclaimed certifying body like Eurovent, or AHRI or AMCA, and the
entire Fan + Motor assembly will be balanced at supplier’s works before
dispatch. Fans drive shall be suitable for variable frequency drive shall
be backward inclined irrespective of static pressure value. Fans shall be
selected for minimum efficiency of 70%. MS epoxy coated in case of
backward curved DIDW fans. For DIDW Fan shaft shall be grounded
C40 carbon steel and supported in self-aligning Plummer block
operating less than 75% of first critical speed, grease lubricated
bearings. Fan wheels and pulleys shall be individually tested and
precision balanced dynamically. Fan motor assembly shall be statically
and dynamically balanced to G6.3 grade as per relevant ISO/AMCA
standard. Certified Computerized selection for unit shall be with fan
selection and sound level spectrum. Complete unit sound level should
be given in computerized selection sheet instead of sound level of bare
fan.
Motors shall be mounted inside the unit casing on rigid frame/ slide
rails for alignment, and be totally enclosed, fan cooled, to be class `F’
insulation.
Heavy duty anti-vibration mounts shall be provided for isolating the unit
casing. Fire retardant, waterproof silicone rubber impregnated flexible
connection shall be provided at the fan inlet/ discharge.
DRAIN PAN:
FILTER:
PRE-FILTERS (MERV-8) :
Contractor Signature MCGM
Page 248
SHASHI PRABHU & ASSOCIATES
Cleanable metallic viscous type filter made out of aluminium wire mesh
or of dry cleanable synthetic type minimum 50mm thick, shall be
provided on the suction side of AHU as standard equipment with the
unit. These filters shall have the efficiency of 90% down to 10 micron
particle size. When these filters become loaded or full of dirt, it is
removed from service and replaced by another filter. The dirty filter can
then be washed in a cleaning solution in a tank, dried and then given a
bath of viscous oil. Face velocity across these filters shall not exceed 155
MPM.
COOLING PAD:
The cooling pads shall be of honey comb design to provide extended and
sufficient wetted surface to give a water absorbing efficiency of at least
80% at an air velocity of 3.0 m/sec.
The cooling pads shall be made of either acetate paper or high impact
PVC. The cross section and depth shall be sufficient for specified
efficiency. The cooling pad section shall be of 16 G (1.6mm) G.I. sheet
similar to fan section. It shall be complete with galvanized supports for
mounting the pads and a water distribution through the uniform supply
of water over the entire surface.
The fresh air taken shall be cooled sensibly before mixing of water to the
air stream. This is the first heat exchanger in an IDEC unit. The
construction of it should be such that the air being sensibly cooled (i.e.
without adding water/air to it) should not get in contact with scavenging
air.
The heat exchanger shall have peak wet bulb efficiency of 80%. This
heat exchanger module shall be made of engineering polymer with a
cellulosic media thermally fused. The velocity within the heat exchanger
should not exceed 450 FPM(2.3 m/s) at any given cross section on heat
exchanger face area. These need to be stacked up modularly to required
air capacity. These heat exchanger modules shall facilitate a secondary
air passage without mixing with the primary air flow. The heat
exchanger shall be UL type tested.
Page 249
SHASHI PRABHU & ASSOCIATES
pads 90%.
Page 250
SHASHI PRABHU & ASSOCIATES
WATER SUMP:
The water sump below the pad section shall be of minimum 1mm SS
304. The tank shall be complete with makeup, overflow and drain
connections. A float valve shall be provided for makeup water line.
The pump set shall be of construction, with end suction and top
discharge with flanged connections, bronze impeller and casing all
mounted directly on a squirrel cage, drip proof induction motor of
suitable capacity. Distribution pumps (1W+1S) shall be provided for
both stages. Internal distribution piping of GI IS-1239 Class-C with
nozzles shall be included for efficient water distribution. Necessary
valves and strainer shall be provided for pumps.
Power for pumps, scavenger fan etc. shall be obtained from starter panel
along with internal power cabling.
MISCELLANEOUS:
VIBRATION ISOLATORS:
NOISE LEVEL:
For Floor mounted unit: Not more than 75 dBA at 2 Mtr. Distance
ACCESSORIES:
Each air handling unit shall be complete with the following as part of
Unit price.
PANITING:
Shop coats of low VOC paint that have become marred during shipment
or erection shall be cleaned off with mineral spirits, wire brushed and
Contractor Signature MCGM
Page 251
SHASHI PRABHU & ASSOCIATES
spot primed over the affected areas, then coated with paint to match the
finish over the adjoining shop painted surface.
INSTALLATION:
PERFORMANCE DATA:
Unit shall be selected for the lowest operating noise level of the
equipment. Fan performance rating and power consumption data with
operating points clearly indicated shall be submitted and verified at the
time of testing, commissioning of the installation. Computerized
selection for unit shall be provided through 3rd party certified software
for all the FMUs.
TESTING:
Page 252
SHASHI PRABHU & ASSOCIATES
15 PIPE WORK AND VALVE STATIONS
GENERAL
All piping work shall conform to quality standards & shall be carried out
as per specifications and details given here under:
PIPES
All pipes up to 150 mm diameter shall be M.S. E.R.W. tube (black steel)
heavy class as per I.S. 123979, part I with upto date amendments. Pipes
above 150 mm dia. shall be
M.S. E.R.W. tube (black steel) heavy class as per I.S. 3589 upto date
amendments.
Design Parameters
All bends in sizes up to and including 150mm dia, shall be ready made
of heavy duty, wrought steel of appropriate class.
All bends in sizes 200mm and larger dia shall be fabricated from pipes
of the same dia and thickness, with a minimum of 4 sections, and
having a minimum center line radius of 1.5 diameter of pipes.
All fittings such as branches reducers etc. in all sizes shall be fabricated
from pipes of the same dia and thickness, and its length should be at
least twice the dia of the pipe.
The branches shall be welded straight to the main line, without making
a separate fit ting.
Blank ends are to be formed with flanged joints and 6mm thick blank
between flange pair for 150mm and over in case where, a future
extension is to be made, otherwise blank end discs of 6mm thickness
Page 253
SHASHI PRABHU & ASSOCIATES
are to be welded on, with additional cross stiffeners from 50mm x 50mm
M.S. heavy angles, for sizes upto 350mm, all ends larger than 400mm
dia. shall have dished ends.
For Condenser pipe 4mm FRP quoting is required.
FLANGES
All flanges shall be of mild steel as per I.S. 6392/71 and shall be steel
slip on type, welded to the pipes, flanges thickness shall be to suit class
II, pressures.
Flanges may be tack welded into position, but all final welding shall be
done with joints dismounted, 3mm thick gaskets shall be used with all
flanged joints. The gaskets shall be fiber reinforced rubber as approved
by the department. Special adhesive com pound shall be used between
flanges of steam, air and gas lines.
Flanged pairs shall be used on all such equipment, which may require
to be isolated or removed for service e.g. pumps, refrigeration machines,
air handling units etc.
All threaded valves shall be provided with nipples and flanged pairs on
both sides to permit flange connections, for removal of valves from main
lines for re pair/replacement.
Flanges shall be of the same pressure rating as the fittings and valves in
each service category. Welding neck flanges or slip on flanges shall be
used with flanged valves, equipment, etc., on welded lines. All flanges
shall be drilled in conformance with pressure rating requirements and
shall be faced and spot faced. Welding flanges shall be of steel.
Flanged pair shall be provided at all such equipment which may require
isolation or removal for services e.g.; pumps, chiller, Air Handling units,
etc.
VALVES
BUTTERFLY VALVES
The butterfly valve shall consist of Cast Steel body preferably in two-
Page 254
SHASHI PRABHU & ASSOCIATES
piece construction.
The disc shall consist of disc pivot and driving stem shall be in one piece
centrally located.
The valve seat shall be of synthetic material suitable for water duty. It
should be field replaceable.
The disc should move in slide bearings on both ends with `O' ring to
prevent leakage.
The handle should have arrangement for locking in any set position.
Valves 200 mm dia size and above shall be worm gear operated.
The valve shall be design for pressure rating of 16 bar & tested for 1.5
times higher pressure for body & 1.1 time’s high for seat.
Material Specification –
Page 255
SHASHI PRABHU & ASSOCIATES
BALANCING VALVES
The test cocks shall be long enough to protrude out of pipe insulation.
5.1.4 The valve shall be design for pressure rating of 16 bar & tested
for 1.5 times higher pressure for body & 1.1 time’s high for seat.
Material Specification –
Page 256
SHASHI PRABHU & ASSOCIATES
Bonnet : 25mm n brass and 32 mm to 50mm in IS 318
LTB 2 (Gun Metal)Plug : IS 318 LTB 2 (Gun Metal) / Brass IS 319
Stem : IS 319 TypeI (Brass)
Temperature : 46 Degree C to 200 Degree C
Gland Nut : Brass
Hand Wheel : Nylon Gr. 66Pressure Test
Cocks : Brass
All valves shall be tested for flow vs. pressure drop within + 5% accuracy
and data be furnished as part of Test Certificate.
Dual Plate Check Valves (Wafer Type) with spring loaded as per API 594.
Inspection and testing conforms to API 598.
The detailed material of construction as given below: Style : Wafer
Design
Body : Cast Steel to ASTM A 216 Gr WCB
Plates : ASTM A 351 Gr. CF8M (SS316)
Plate Coating : Integrally
Body Lining : BunaN / Nitrile (Temp. Range 57 Deg. C to
120 Deg. C)
Hinge/Stop Pin : AISI SS316
Spring(s) : SS316
Retainer : Carbon Steel
Page 257
SHASHI PRABHU & ASSOCIATES
Body Bearing : AISI SS316
Plate Bearing : AISI SS316
Spring Bearing : AISI SS316
End Connection : ASTM A 16.5
Page 258
SHASHI PRABHU & ASSOCIATES
STRAINERS
The strainers shall either be pot type or Y type. Body shall be cast steel
for y strainer & mild steel for Pot type strainer, tested up to pressure
applicable for the butterfly valves.
The strainers shall have a perforated stainless steel sheet screen with 3
mm perforation and with a permanent magnet, to catch iron fillings. The
filtration area should not be less than 75 %.
Material of Construction:
POT Strainer
Y Strainer
Page 259
SHASHI PRABHU & ASSOCIATES
BALL VALVES:
All ball valves shall be forged brass body construction with chrome
plated with the pressure rating PN 16 as per schedule of quantity and
handle of stainless steel constructions & shall be covered with Plastic
material. End connections of ball valve to be screwed type & shall be
applicable for 15mm to 40mm in dia. The ball valve shall be coated with
two coats of zinc chromate paint (LOW VOC) for its antirust properties
and then shall be finally painted with epoxy paint of required colour
including all fittings like valves, flanges & unions. The valves used for
both HW and CHW application shall be covered with
insulation(CFC,HCFC FREE)/lag coating/glass cloth as specified in
schedule of quantity. The Adhesive used for shall be of low volatile
organic compound. Pressure testing of valves shall be done at
manufacturer’s works. The contractor shall furnish material test
certificates of various components of the valve & performance test
certificates carried out by manufacturer
The flexible joints should be factory tested for pressure & vacuum.
Before installation the proper selection of expansion joints as per the
pipe dia should be done.
Material Specification –
Page 260
SHASHI PRABHU & ASSOCIATES
The ball valve with strainer of nominal bores between 15mm and 40mm
shall be sup plied with 316 stainless steel screen.
JOINTING
Square cut plain ends will be welded for pipes upto and including
100mm dia.
All pipes 125mm dia or larger will be beveled by 35 deg for welding.
MISCELLANEOUS
All condensation drainage, including air handling unit and fan coil unit
shall be pitched in the direction of flow to ensure adequate drainage,
with an adequate trap seal to prevent leakage of air due to static
pressure developed by air conditioning units. Pitch, 20mm per meter
wherever possible, but not less than 10mm/ meter. Drains from other
equipment shall be pitched similarly without trap seal.
Provide valves and capped connections for all low points in piping
system, necessary or required for draining systems. Provide for all risers
isolating valves and drain valves to permit repairs without interfering
with the rest of the system.
Page 261
SHASHI PRABHU & ASSOCIATES
Pipe supports shall be adjustable for height and primer coated with rust
preventive paint and finish coated with gray paint, both as approved by
department spacing of pipe supports shall not be more than that of
specified below :
Extra supports shall be provided at the bends and at heavy fittings like
valves to avoid undue stresses on the pipes. Pipe hangers shall be fixed
on walls and ceiling by means of metallic approved dash fasteners.
Page 262
SHASHI PRABHU & ASSOCIATES
Where pipes are to be buried under ground, they should be coated with
one coat of bituminous paint without any extra charge. The top of the
pipes shall not be less than 75 cms. from the ground level. Where this is
not practical permission of department shall be obtained for burying the
pipes at lesser depth. The pipes shall be surrounded on all sides by sand
cushions of not less than 15 cms. After the pipes have been laid and top
sand cushions provided, the trench shall be refilled with the excavated
soil. Excess soil shall be removed from the site of work by the
contractor.
Hangers and supports shall be provided and installed for all piping and
tubing wherever indicated, required or otherwise specified. Wherever
necessary, additional hangers and supports shall be provided to prevent
vibration or excessive deflection of piping and tubing.
All hangers and supports shall be made of steel and painted as required.
Wood, wire or perforated strap iron shall not be used as permanent
hangers or supports.
SLEEVES
Where pipes pass through floors, provide galvanized steel pipe sleeves
50mm larger than outside diameter of pipe. Where pipes are insulated,
sleeves shall be large enough to provide ample clearance for insulation.
The center pipes shall be in the center of sleeves, and sleeves shall be
flush with the finished surface.
EXPANSION OR CONTRACTION
The contractor shall provide for expansion and contraction of all piping
Page 263
SHASHI PRABHU & ASSOCIATES
installed by the use of expansion loops.
Page 264
SHASHI PRABHU & ASSOCIATES
ARRANGEMENT AND ALIGNMENT OF PIPING
The stresses in pipe lines shall be guided and pipes shall be supported
in such a manner that pipe lines shall not creep, sag or buckle.
TESTING
After tests have been completed the system shall be drained and flushed
3 to 4 times and cleaned of all dust and foreign matter. All strainers,
valves and fittings shall be cleaned of all dirt, fillings and debris.
Page 265
SHASHI PRABHU & ASSOCIATES
All piping shall be tested to hydraulic test pressure of at least one and
half times the maximum operating pressure for a period of not less than
24 hours. All leaks and defects in the joints revealed during the testing
shall be rectified to the satisfaction of the Engineer in charge without
any extra cost. All the valves shall be tested to hydraulic test pressure of
at least one and half times the maximum design operating pressure.
All the piping systems shall be tested in the presence of the department
or his authorized representative. Advance notice of test dates shall be
given and all equipment’s, labour, materials required for inspection, and
repairs during the test shall be provided by the contractor. A test shall
be repeated till the entire systems are found satisfactory by the above
authority. The tests shall be carried out for a part of work if required by
department in order to avoid hindrance in the work of the insulation
contractor.
The contractor shall provide all labours and materials to make provision
for removing water and throwing it at the proper place during the testing
or/and after the testing to avoid damages to employer or other
contractor’s properties. Any damages caused by the contractor to the
employer or other contractors properties, shall be borne by the
contractor.
Flare fittings e.g. flare nuts, tees, elbows, reducers etc. shall all be of
brass.
DRAIN PIPING
The drain piping shall be medium class Hot dipped galvanized steel as
per IS 1239/1979 with up to date amendments.
Rigid PVC pipes may be used for drain pipe. (Option only for single story
building)
Page 266
SHASHI PRABHU & ASSOCIATES
The drain line shall be provided up to the nearest drain trap and pitched
towards the trap.
Drain lines shall be provided at all the lowest points in the system, as
well as at equipment, where leakage of water is likely to occur or to
remove condensate and water from pump glands.
The main drain pipe should be connected to the vertical drain pipe
through a Yjoint or Tjoint. A vent pipe should be installed at the top of
the vertical to improve the drain water flow. Vent pipe should be
provided with insect screen. Cost for these accessories is deemed to be
included in the rates quoted by the tenderer.
PAINTING
All pipes support, hangers, etc., shall be given two coats of red oxide
primer.
All pipes, which are not to be insulated, shall then be given two coats of
finish paint, of a type and colour, as approved by the Engineer in
Charge.
For AHUs:
Page 267
SHASHI PRABHU & ASSOCIATES
534 compliant, have 20 mm stroke and insulated.
The valve shall be coated with two coats of zinc chromate paint (LOW
VOC) for its anti-rust properties and then shall be finally painted with
epoxy paint of required colour including all fittings like valves, flanges &
unions. The valves used for both HW and CHW application shall be
covered with insulation (CFC,HCFC FREE)/lag coating/glass cloth as
specified in schedule of quantity. The Adhesive used for shall be of low
volatile organic compound.
In case BMS is provided in the building then, only the valve with
actuator shall be in the scope of HVAC vendor and rest of all control and
power wiring and sensors etc. shall be excluded from HVAC vendor
scope.
For FCUs:
2 way motorized shall be of on/off type valve and operated on 230 volts and
of PN rating as mentioned in schedule of quantity complete with motor
actuator of suitable torque & control power wiring from individual
thermostat of each FCU to each related actuator of 2 way valve with
controller & its related wiring. The valve should be IEC 534 compliant, have
20 mm stroke and insulated as suitable.
In case of BMS is provided in the building then only valve with actuator
shall be in the scope of HVAC vendor and rest of all control and power
wiring and sensors etc. shall be excluded from HVAC vendor scope.
Water pressure gauges 4"dia. made out of stainless steel SS-304 all
parts are made from copper alloy and stainless steel to prevent from
corrosion attack. Dial shall be in white colour and number shall be in
the black and red colour for the visibility, gauges shall have ‘A’ stainless
steel ‘U’ tube of 6mm dia. x 400mm in length both side threaded with
stainless steel nut, A pet cock along with SS syphon tubing shall be
provided at one end of tube for protecting gauge during testing of system
Flow Switches
Page 268
SHASHI PRABHU & ASSOCIATES
cooled condensing units for refrigeration load. The flow switch shall
prevent the compressor from starting unless the water flow is
established in condensing water lines, and chilled water flow is
established chilled water lines.
ULTRASONIC FLOW METER:
Water flow meters shall be Ultrasonic type of PN16 rating. Ultrasonic Inline
Flow Meter shall be suitable to be installed in Chilled Water Return line to
each chiller with necessary fittings and isolation valves etc. The valve shall
be suitable for integration with Chiller Plant Manager /Variable Primary
Pump Logic Controller. The precision of flow measurement shall not be
lower than +/- 2%.
The housing shall have IP 55 protection. Vendors shall have to get their
design/ selection approved by the Consultant, prior to the supply.
The exact ranges to be set shall be determined by the contractor at the time
of commissioning. It should be possible to ‘zero’ the flow meter without any
external instruments.
The stem shall be coated with two coats of zinc chromate paint (LOW VOC)
for its antirust properties and then shall be finally painted with epoxy paint
of required colour including all fittings like valves, flanges & unions. Also
the stem shall be covered with insulation (CFC & HCFC FREE)/lag
coating/glass cloth as specified in schedule of quantity. The Adhesive used
for shall be of low volatile organic compound.
The contractor shall furnish material test certificates of various
components of the valve & performance test certificates carried out by
manufacturer.
Page 269
SHASHI PRABHU & ASSOCIATES
media coming into the valve.
• The gearbox of the actuator should comprise of hardened
planetary gears. The gear drive mechanism should provide
efficient, smooth operation while allowing easy manual override at
any time.
• There should be a provision of hand wheel or lever to operate the
valve manually.
• There should be a provision of two stop screws for limiting the
manual operation of actuator.
• Valves & actuator should be supplied with IP54 protection rated
(for indoor application) and with IP67 protection rated actuators
(for outdoor application).
• Two position or open/closed actuators shall accept 24 V AC/DC or
230V AC power supply and should be UL listed. Butterfly isolation
and other valves, as specified in the sequence of operations, shall
be furnished with adjustable end switches to indicate open/closed
position or be hard wired to start/stop the associated pump or
chiller.
• The valve should have a square stem head for form fit attachment
of the Rotary actuator.
Page 270
SHASHI PRABHU & ASSOCIATES
Shaft Bushing : Glass Field Nylon
Page 271
SHASHI PRABHU & ASSOCIATES
16 AIR DISTRIBUTION WORKS
General
The work under this part shall consist of furnishing labour materials,
equipment and appliances as specified necessary and required to install
all sheet metal and other allied work to make the air conditioning
supply, ventilating, and exhaust system ready for operation as per
drawings.
Maximum Velocity
2500 FPM
The steel sheets shall be hot dip galvanized with coating of minimum
220 GSM of Zinc (Total coating on both sides)
All duct work, sheet metal thickness and fabrication unless otherwise
directed, shall strictly meet requirements as described SMACNA
standard for factory fabricated duct. The minimum thickness of
fabricated GSS duct shall be 24 G & for Al 22 G.
Raw Material
Page 272
SHASHI PRABHU & ASSOCIATES
Duct Connectors and Accessories
Fabrication Standards
All edges to be machine treated using lock formers, flanges and roller for
fuming up edges.
All transverse connectors shall be the 4bolt slipon flange system with
built in sealant if any to avoid any leakage additional sealant to be used.
The specific class of transverse connector and duct gauge for a given
duct dimensions will be up to 2” (500 pa) low pressure class. If required,
Specific ventilation duct may as per medium pressure class.
Duct Construction
Page 273
SHASHI PRABHU & ASSOCIATES
shall be airtight and at corners only, which shall be either Pittsburgh or
Snap Button Punch to ensure air tightness.
All nuts, bolts and washers shall be zinc plated steel. All rivets shall be
galvanized or shall be made of magnesium aluminum alloy.
MISCELLANEOUS
• All ducts above 450mm are to be cross broken to provide rigidity to the
ducts.
• All duct work joints are to be true right angle or approaching with all
sharp edges re moved.
• Each shoot from the duct, leading to a grille, shall be provided with an
air deflector to divert the air into the grills through the shoot.
Page 274
SHASHI PRABHU & ASSOCIATES
Engineer in Charge.
• All duct supports, flanges, hangers and damper boxes etc. shall be given
2 coats of red oxide paint before installation and one coat of aluminum
paint after the erection, at no extra cost.
• All the angle iron flanges to be connected to the G.S.S. ducts by rivets at
100mm centers.
• All the flanged joints, to have a 4mm thick felt packing stack to the
flanges with shellac varnish. The holes in the felt packing are to be
burnt through.
TRANSFORMATION
The exposed type duct shall be double skin type spiral round metal
ducts in low pressure range. The ducting shall comply with NFPA
90A1989, "Standard for the Installation of Air Conditioning and
Ventilating Systems”.
Page 275
SHASHI PRABHU & ASSOCIATES
Round Mitered Elbows: Solid welded and with metal thickness listed
below for pressure classes from minus 2 inches to plus 2 inches. The
entire duct shall be fabricated as per SMACNA standard.
Flat Oval Mitered Elbows: The elbows shall be solid welded and with the
same metal thickness as longitudinal seam flat oval duct. 90Degree,
2Piece, Mitered Elbows shall be used for supply systems, or exhaust
systems only where space restrictions do not permit the use of 1.5 bend
radius elbows. These will be fabricated with single thickness turning
vanes.
Round Elbows for duct sizes 8 Inches and Smaller shall be Die-formed
for 45 and 90degree elbows and pleated for 30, 60, and 90 degrees only.
Fabricated nonstandard bend angle con figurations or 1/2" diameter
(e.g. 31/2 and 41/2inch) elbows shall be with gored construction.
Round Elbows for sizes 9 Through 14 Inches shall be gored or pleated
elbows for 30, 45, 60, and 90 degrees, except where space restrictions
require a mitered elbow.
Page 276
SHASHI PRABHU & ASSOCIATES
Die Formed Elbows for Sizes through 8 Inches and All Pressures shall be
minimum 20 gauge with 2piece welded construction. Round Gored
Elbows shall be fabricated out of the gauges as specified for non-elbow
fittings above. For Flat Oval Elbows the gauges shall be same of the
longitudinal seam flat oval duct.
The ducts shall be Installed with the fewest possible joints. Fabricated
fittings for all changes in directions, changes in size and shape, and
connections shall be used. The couplings shall be secured tightly to duct
wall surface with projections into duct at connections shall be kept to a
minimum. Ducts shall be running, except as otherwise indicated,
vertically and horizon tally, parallel and perpendicular to building lines
and shall avoid diagonal runs. There shall be a clearance of 1 inch
where furring is shown for enclosure or concealment of ducts, plus
allowance for insulation thickness, if any.
The flat oval ducts shall be supported with support systems as indicated
in SMACNA "HVAC Duct Construction Standards", tables 41 through 43
and Figures 41 through 48. The support for horizontal ducts shall be
within 2' of each elbow and within 4' of each branch inter section.
Support for vertical ducts shall be at a maximum interval of 16' and at
each floor. All connections to and from the duct to the equipment, air
terminals and branches etc. shall be as recommended by SMACNA
"HVAC Duct Construction Standards", Figures 27 to 219.
TAKEOFF
All branch takeoff and collars shall be provided with turning vanes.
Straightening vanes shall be provided in the collars.
Butterfly Dampers shall be provided in the duct work for proper control
and balancing of air distribution. Dampers shall of louver type of robust
connection. Dampers shall have easily accessible operating mechanism.
The operating mechanism shall consist of links, levers and quadrants as
required for proper control and setting in a desired position. The
position of the handle of damper operating mechanism shall be clearly
visible and it shall indicate the position of the damper in the duct.
Dampers, splitters and their operating mechanism shall be fabricated of
GS sheets of two gauges heavier then duct piece having these fittings
and shall be easily accessible through suitable access doors in the
ducts.
Page 277
SHASHI PRABHU & ASSOCIATES
Dampers shall be installed in duct at all required locations such as
chutes, branches etc.
Page 278
SHASHI PRABHU & ASSOCIATES
INSTALLATIONS
• The duct work shall be varied in shape and position to fit actual
conditions at building site. All changes shall be subjected to the
approval of the Engineer In Charge. The con tractor shall verify all
measurements at site and shall notify the Engineer In Charge of
any difficulty in carrying out his work before fabrication.
• The flexible joints are to be not less than 75 mm and not more
than 200 mm between faces.
Page 279
SHASHI PRABHU & ASSOCIATES
flanges, collars on each side of wooden frame to make the duct
leak proof.
ACCESS PANEL
MISCELLANEOUS
• All duct work joints are to be true right angle or approaching with
all sharp edges re moved.
• All duct supports, flanges, hangers and damper boxes etc. shall be
given 2 coats of red oxide paint before installation and one coat of
aluminum paint after the erection, at no extra cost.
Page 280
SHASHI PRABHU & ASSOCIATES
• All the flanged joints, to have a 4mm thick felt packing stack to
the flanges. The holes in the felt packing are to be burnt through.
• The entire air distribution system shall be balance with the help of
an anemometer. The measured air quantities at fan discharge and
the various outlets should be within range of +5 %.
• At the junction of each branch duct with main duct and split of
main duct, volume dampers must be provided.
• Dampers shall be two gauges heavier than gauge of the large duct,
and shall be rigid in construction to the passage of air.
• The dampers for fresh air inlet shall additionally be provided with
fly mesh screen, on the outside, of 0.8mm thickness with fine
mesh spacing.
• The fire dampers shall be made from heavy gauge galvanized steel
in multi plate construction. The damper shall be provided with
Jam seal (compression type) on sites to prevent spread of smoke
Page 281
SHASHI PRABHU & ASSOCIATES
and fire. Dampers shall meet the requirements of the latest edition
of NFPA 90A, 92A, and 92B.
• Fire dampers shall be provided in supply air ducts and return air
duct (wherever provided), return air passage in the air handling
unit’s room and all floor crossings.
• Fire dampers shall be multi blade type. The blade remains in the
air stream in open position& shall allow maximum free area to
reduce pressure drop & noise in the air passage. The blade &
frame shall be constructed with minimum 1.6 mm thick
galvanized sheet & shall be factory fitted in a sleeve made out of
1.6 mm galvanized sheet of minimum 400 mm long. It shall be
complete with locking device, motorized actuator & control panel.
• All fire cum smoke damper shall be CBRI tested & certified for 90-
minute rating against flame penetration as per UL standard
5551995. Each damper shall be equipped with a factory installed
UL approved damper actuator.
• Each damper shall be provided with its own control panel. This
control panel shall be suited for spring return actuator & shall
have at least the following features:
Potential free contacts for AHU On / Off & remote alarm indication.
Accept signal from external smoke / fire detection system for tripping
the actuator.
Test & reset facility.
Page 282
SHASHI PRABHU & ASSOCIATES
Page 283
SHASHI PRABHU & ASSOCIATES
GRILLES
The supply and return air grilles shall be fabricated from aluminum
extruded sections. The supply air grilles shall have single louvers (which
shall be used for air conditioning) & ventilation grille shall be of double
louvers. The front horizontal louvers shall be of extruded section, fixed
type. The rear vertical louvers shall of aluminum sheet and adjustable
type. The return air grille shall have single horizontal extended section
fixed louvers. The grilles may or may not be with an outer frame.
DIFFUSERS
The diffusers shall be die formed for proper air diffusion & shall have
removable inner core.
VAQ Station
All the VAQ (Variable Air Quality) Station shall be Pressure Independent
type with Direct Digital Controls to regulate and monitor the primary air
flow rate between the scheduled minimum and maximum values to
achieve the specified comfort level and ventilation rates within
acceptable noise criteria.
The VAQ Station shall control air to provide desired zone temperature,
and required minimum volume of outdoor air for proper ventilation. The
controller shall measure the pressure, position of the damper blades,
and temperature of the air flowing through the damper.
The VAQ Station shall have an air measuring station with an ultralow
leak, high performance control damper similar to AMCA Class-II
leakage. The complete assembly shall be factory assembled and tested to
provide effective set point monitoring and adjustment. The unit shall
come standard with a pressure transducer, with the output signal
Page 284
SHASHI PRABHU & ASSOCIATES
proportional to CFM and factory fitted standalone DDC controller.
Construction
The casing shall be single skin made out of galvanized sheet steel with
acoustic lining from inside. Casing leakage rate shall be Similar to
AMCA class II leakage. All VAQ Station shall have rectangular duct
connection with 25 mm. flange connections at the outlet of the station.
Each VAQ Station shall be factory fitted with a multipoint, averaging air
flow sensor in the inlet of the terminal. This air flow sensor shall amplify
the air pressure signal linearly with an amplification factor of at least
3.0. The air flow sensor shall contain not less than 2x8 sensing points,
which shall be arranged in a perpendicular axis of sensing. The points
shall be arranged in such a way that they are located at the center of
equal areas not more than 150 mm apart. The signal shall be averaged
and measured from the center of the sensor. And the accuracy shall be
within 5% even with irregular duct approach.
The jet nozzle assembly is designed to cater high air volumes. These are
designed for the cooling application with side wall installation. Each
Page 285
SHASHI PRABHU & ASSOCIATES
nozzle shall be manually adjusted to supply air to the specific zone.
Each nozzle shall be manually adjusted in 30º vertically upwards and
30º vertically downwards. The set angle position shall be held by friction
held fixing as standard supply. The nozzle shall be fitted with mounting
plate which will allow each nozzle to rotate at 360º giving it wider air
discharge pattern.
The Multiple Jet Nozzle shall comply following material and performance
data
The jet nozzle shall be constructed from concentric steel tubes mounted
on steel face plate with angle flanged border made from extruded
aluminum sections compete with countered punched holes for screw
fixing.
The jet nozzle with mounting plate and shall throw at 25m distance.
The jet nozzle should be tested in ISO 9000 certified test lab with
international standards.
The acoustic data shall be as per ISO 5219 and ISO 3741.
SOUND ATTENUATORS
Insertion loss dB
900 mm long
atte 2 7 1 1 2 2 1 9
nuat 2 9 3 3 8
ors
Insertion loss dB
1500 mm long
atte 6 8 1 3 4 3 2 12
nuat 8 0 2 4 3
ors drop values of the silencers shall be indicated for each
The pressure
duty.
Page 286
SHASHI PRABHU & ASSOCIATES
Manufacturers shall submit a test certificate for acoustic and
aerodynamic performance of the attenuators. Attenuators shall be tested
in accordance with ACMA test methods/BS 4718 and insertion loss and
self-generated noise for each octave band and pressure drop shall be
stated in the schedule.
CO2 Sensor
Co2 sensor shall be Non dispersive infrared type shall have range of
02000 PPM with accuracy of + 30PPM. The warm up time shall be of 2
minutes and response time within 120 seconds. The sensor shall be
suitable for 24Vac or 24Vdc+20 %, 50 Hz power supply & supplied with
necessary step down transformer. The range of the sensor shall be
approx.100 sq.m. The protection class shall be IP30 & suitable for
operation at 050°C and 095 % RH range. The life of sensor should be
greater than 10 years.
VENTILATION LOUVERS
Ventilation air intake louvers for interior application shall be suitable for
high free area and low air flow resistance. The louvers for external wall
application shall be drainable type louvers combined with back draft
damper & bird mesh. The blades are inclined at 45°on a 40 mm blade
pitch to minimize water ingress. The lowest blade of the assembly shall
extend out slightly to facilitate disposal of rain water without falling in
door/wall on which it is mounted. All the louvers shall be made of
extruded aluminum construction.
DOCUMENTATION TO MEASUREMENTS
All duct pieces to have a part number, which should correspond to the
serial number, assigned to it in the measurement sheet. The above
system will ensure speedy and proper site measurement, verification
and approvals.
Page 287
SHASHI PRABHU & ASSOCIATES
After duct installation, a part of duct section (approximately 5% of total
ductwork) may be selected at random and tested for leakage. The
procedure for leak testing should be followed “HVAC Air Duct Leakage
Test Manual: (First Edition).
Page 288
SHASHI PRABHU & ASSOCIATES
17 INSULATION WORKS
General
The Insulation of chilled water piping, air handling unit’s rooms, ducting
etc., shall be carried out as per specifications given below:
Materials
SCOPE
Page 289
SHASHI PRABHU & ASSOCIATES
• RETURN AIR DUCT-13/19 mm thick insulation
Method of Application:
All Duct surfaces should be free of dust, grease, oil. To clean the duct, first
wipe with a clean cloth to remove dust particles. Then remove grease and
oil by applying a methylated spirit or acetone or equivalent special glue
cleaner and allow evaporating. Work within reasonable clean area to avoid
too much dust prior to carrying out insulation work. Measurement of
surface dimensions shall be taken properly to cut closed cell nitrile rubber
sheets to size with sufficient allowance in dimension. Cutting of nitrile
rubber sheets shall be done with adjustable blade to make 90º cut in
thickness of nitrile rubber sheet. Hacksaw or blades are not acceptable
tools for cutting the insulation.
Material for Duct Lining : 15 mm thick Class O open cell structured Nitrile rubber with 150
kg/m3 density (CFC/HCFC FREE).
Page 290
SHASHI PRABHU & ASSOCIATES
and minimum surface temperature of -200C
The material should conform to Class 1 rating for surface spread of Flame
in accordance to BS 476 Part 7 & UL 94 (HBF, HF 1 & HF 2) in accordance
to UL 94, 1996.
The insulation should pass Air Erosion Resistance Test in accordance to
ASTM Standard C 1071-05 (section 12.7).
Method of Application:
Duct surfaces shall be cleaned to remove all grease, oil, dirt, etc. prior to
carrying out insulation work. Measurement of surface dimensions shall be
taken properly to cut closed cell Elastomeric rubber sheets to size with
sufficient allowance in dimension insulating material sheet and then on to
the metal surface. Apply OEM supplied food grade adhesive (LOW VOC) on
duct surface and insulation sheet and when adhesive is tack dry,
insulating material sheet shall be placed in position and pressed firmly to
achieve a good bond. All longitudinal and transverse joints shall be sealed
by providing 6 mm thick 50 mm wide Nitrile rubber tape. The adhesive
shall be strictly as recommended by the manufacturer and should be of low
volatile organic compound. Acoustic insulation to be applied for both
supply & return air duct/PLENUM up to 3 mtr. in length from AHU.
Page 291
SHASHI PRABHU & ASSOCIATES
when tested to ASTM G21. Seal all joints with 75mm reinforced
aluminums foil tape.
EQUIPMENT INSULATION
The complete shell of the chiller as well as its two heads shall be factory
insulated.
The chilled water pumps shall be insulated with 38 mm thick closed cell
Nitrile rubber (class "O") insulation having minimum 32 kg/cum density
and cladded with aluminum sheets of
0.63 mm thickness and properly clamped to pump in two semicircular
sections.
The Expansion tank/ air separator shall be insulated with 75mm thick
T.F quality expended polystyrene of 20 kg/cum density & covered with a
layer of 120 gm/sqm polythene sheet (vapor barrier) and finally finished
with 26 G aluminum sheet.
PIPING INSULATION
Page 292
SHASHI PRABHU & ASSOCIATES
Chilled water piping shall be insulated with closed cell EPDM insulation
Class ‘O’ moulded pipe section having density between 40 to 60 Kg/m3.
The thermal conductivity should not exceed 0.035 W/mK at mean
temperature of 0°C. The insulation shall have fire performance such that
it passes Class 1 as per BS476 Part 7 for surface spread of flame as per
BS 476 and also pass Fire Propagation requirement as per BS476 Part 6
to meet the Class ‘O’ Fire category. Moisture Diffusion Resistance Factor
or ‘µ’ value should be greater than 7000.
Coastal Area
CHW Pipe Size Thickness
25 NB to 40 NB 32mm
50 NB to 150 NB 38mm
200 NB to 600 NB 44mm
Method of Application:
The insulation over the pipe work shall be finished with 7 mill glass
cloth. All expose pipes (terrace& in shaft) outside the building laid
above ground the finishing over the pipe insulation shall be finished
with 26 gauge aluminum cladding over a vapor barrier of 120
gm/sq.m polythene sheet with 50mm overlap and tied down with
lacing wire and complete with type 3 grade I roofing felt strip
applied by means of cold setting CPRX compound.
Page 293
SHASHI PRABHU & ASSOCIATES
MEASUREMENT OF INSULATION
Unless otherwise specified measurement for duct and pipe insulation for
the project shall be as per CMMRDA specification for HVAC Work.
Page 294
SHASHI PRABHU & ASSOCIATES
18 ELECTRICAL INSTALLATIONS
GENERAL
SCOPE
The scope of work covered under this section shall be inclusive but not
limited to followings, and everything necessary to complete the work
shall be provided by the contractor within the rates quoted by him for
the electrical package on turnkey basis.
All electrical panels including the main panel, local electrical panel
boards (EPB) and distribution boards whether indicated in the drawings
or not/ as required for proper functioning of the system.
All copper conductor armoured control cables from the final outlets up
to the main control console.
WIRING SYSTEM
All power wiring shall be carried out with 650/ 1100 volts grade PVC
insulated, armoured, overall, PVC sheathed aluminum conductor cables.
Cables shall be sized for starting current and by applying proper
derating factor. All control wiring shall be carried out by using 650/
1100 volts FRLS insulated copper conductor wires in wire trays or in
conduit. Minimum size of control wiring shall be 1.5 sq.mm. FRLS
insulated copper conductor wires. Minimum size of conductor for power
Page 295
SHASHI PRABHU & ASSOCIATES
wiring shall be 4 sq.mm. 650/1100 volts grade PVC insulated aluminum
conductor wires in conduit.
The Low Voltage Switchboard shall be with aluminium bus bars, indoor
type, free standing, with Plinth, floor mounting type, extensible on either
side.
SITE CONDITIONS:
STANDARDS:
The design, manufacture & testing of the various items are covered by
the following standards:
Page 296
SHASHI PRABHU & ASSOCIATES
IS 32311965 : Protective relays.
IS 31561965 : Voltage transformers.
IS 27051981 : Current transformers.
IS 12481968 : Elect. indicating instruments.
SPECIFICATIONS:
General
Page 297
SHASHI PRABHU & ASSOCIATES
same ingress protection of IP specified retained. Suitable pressure
relief devices shall be provided to minimize danger to operator
during internal fault conditions.
• The Main LV (above 800A rated) & external placed panel cubicles
shall have structural steel frame work. It is enclosed on all sides
and top by Cold Rolled sheet steel of minimum outer thickness of
2.5 mm.
• The LV panel shall have provision for top / bottom in coming and
bottom / top out going
• respectively to suit site conditions of cable entries.
Page 298
SHASHI PRABHU & ASSOCIATES
identified with Green color rings at regular intervals.
Switchboard Configuration
i. DESIGN CONSIDERATIONS
Page 299
SHASHI PRABHU & ASSOCIATES
• The electrical system for all main distribution boards shall be 415
/ 380V, 50 Hz 3phase and neutral, 4wire solidly earthed. The
main distribution boards shall be suitable for operating voltage up
to 690 V and Insulation voltage of 1000V.
Equipment Specifications
Page 300
SHASHI PRABHU & ASSOCIATES
other equipment’s shall be accessible / operable from the front of panel.
Where front access type is specified, the panel shall be designed
completely for front access only.
Outgoing section(s)
Page 301
SHASHI PRABHU & ASSOCIATES
Each panel shall have various fixed compartments with individual doors
for each compartment and each compartment shall accommodate the
following:
Air circuit breaker front face shall be accessible without opening the
door.
Opening of the front door shall give access to the circuit breaker for
rating adjustments etc.
Enclosure manufacturing
Page 302
SHASHI PRABHU & ASSOCIATES
Main distribution board enclosure shall be a branded catalogue product
from approved manufacturer. Enclosure shall be made out of electro
galvanized steel sheets conforming to international specification. AluZinc
coating shall be provided on the sheets, which shall prevent rust
formation during storage and handling for processing, in addition to
giving corrosion protection to the finished product. The sheets have a
fine surface finish, which gives good presentation to the painted
components of the enclosure.
Enclosure construction
Main distribution boards (above 800A rated) & external placed panel’s
enclosure shall be fabricated of minimum 2.5 outer body 2 mm internal
(including doors), thick electro galvanized sheet steel folded
construction. The enclosure shall be of simple and robust construction
designed for a variety of dimensions obtainable by means of
standardized basic elements. Main distribution board shall consist of
several enclosures of equal height and depth mounted side by side to
form a composite board of uniform assembly.
Page 303
SHASHI PRABHU & ASSOCIATES
one or more pieces between two sections depending on the depth of the
compartment. The lower part of structure shall be closed by means of
bolted plates that can be removed whenever the assembly of cable
glands is required. The switchgear components contained in sections
shall be installed on mounting plates. Each door panel shall be equipped
with integral key lock and the key shall be common for all such locks.
All door hinges to be of concealed type and it shall be possible to remove
the door panel whenever required. All doors, bold on cover, partitions,
mounting plates and metallic shrouds shall be effectively connected to
earth. Flexible earth wires shall be used for removable covers and
hinged doors.
Page 304
SHASHI PRABHU & ASSOCIATES
shall be made between the switching device terminal and the switching
device within its compartment by means of rigid barriers and partitions.
Page 305
SHASHI PRABHU & ASSOCIATES
Constructional Features
All doors and covers shall also be fully gasketed with metal based
neoprene gaskets to ensure proper compression of the gaskets. The
hinged door shall open a maxi mum of 1500. All hinged doors shall have
earth braid connected to the cubicle. Good quality door handles fitted
with toggles to operate rods to latch with suitable slots in both top and
bottom of switchboards shall be provided. Latching rods and associated
brackets shall be cadmium plated.
Each vertical section shall be provided with a rear/ side cable chamber
housing the cable end connections and power/control cable
terminations. There should be generous availability of space for ease of
installation and maintenance with adequate safety for working in one
vertical section without coming into contract with any liver parts.
Page 306
SHASHI PRABHU & ASSOCIATES
All panels and covers shall be properly fitted and square with the frame.
The holes in the panel shall be correctly positioned.
Switchboard Compartmentalization
Sheet steel hinged lockable doors for each separate compartment shall
be provided and duly interlocked with the breaker in "ON" and "OFF"
position.
Each switchgear cubicles shall be fitted with label in front and back
identifying the circuit, switchgear type, rating and duty. All operating
device shall be located in front of switchgear only. Minimum height from
floor level for any device mounted on panel cover shall be 250 mm.
Page 307
SHASHI PRABHU & ASSOCIATES
A horizontal wire way with screwed cover shall be provided at the top to
take inter connecting control wiring between vertical sections.
Spare Provision
Bus bars shall be insulted with heat shrink PVC sleeves of 1.1 kV grade
and bus bar joints provided with clip on shrouds.
Auxiliary buses for control power supply, space heater power supply or
any other specified service shall be provided. these buses shall be
insulated, adequately supported and sized to suit specific requirement.
The material for auxiliary supply bus will be electrolytic copper.
Page 308
SHASHI PRABHU & ASSOCIATES
The busbar system shall be designed as per the predefined guidelines
provided by the original manufacturer. The busbar system shall be type
tested by the manufacturer at reputed laboratory for short circuit with
stand capacity. The neutral and earth busbars shall also be type tested
for the short circuit withstand capacity. The fault level rating of the
busbar system shall be as per the drawings however the minimum short
circuit withstand capacity shall be 65/50KA RMS for 1second. Neutral
busbar shall be able to withstand a thermal stress of atleast 50%,
corresponding to the main phase busbar rated short circuit withstand
capacity.
The dimensioning of the busbar system shall be as per the rated current
of the main switching device, the short circuit current, the maximum
rated permissible temperature at permanent operation and the ambient
temperature around the busbars. The selection of busbars shall be
supported by calculations and recommendations from the original
manufacturer.
The neutral busbar shall run along with the phase busbars and shall
outgoing switching devices neutral connection terminal shall be provided
with in the switching de vice compartment.
Page 309
SHASHI PRABHU & ASSOCIATES
Switchboard Interconnection
All connection and tap offs shall be through adequately sized connectors
appropriate for fault level at location. This shall include tap off to feeders
and instrument/control transformers. Alternatively, current limiters of
approved make and type shall be used.
For unit ratings up to 100 amps, FRLS PVC insulated copper conductor
wires of adequate size to carry full load current shall be used. The
terminations of such interconnections shall be crimped. Solid
connections shall be used for all rating of 100 amps and above.
Air Circuit Breakers shall be provided in fully draw out cubicles, unless
otherwise stated. These cubicles shall be such that draw out is possible
without disconnection of the wires and cables.
The power and control circuits shall have self-aligning and self-isolating
contacts. The fixed and moving contacts shall be easily accessible for
operation and maintenance. Mechanical interlocks shall be provided on
the draw out cubicles to ensure safety and compliance to relevant
Standards. The MCCB's shall be provided in fixed type cubicles.
Instrument Accommodation
Page 310
SHASHI PRABHU & ASSOCIATES
Wiring
All wiring for relays and meters shall be with FRLS PVC insulated copper
conductor wires. The wiring shall be coded and labelled with approved
ferrules for identification. The minimum size of copper conductor control
wires shall be 2.5 sq. mm. Wiring shall be terminated with ferrules on
terminal block. CTs shall be provided with shorting facilities
Cable Terminations
The cable terminations for the MCCB's shall be brought out to the rear
in the case of rear access switchboards or in the cable compartment in
the case of front access Switchboards.
Removable gland plates shall be provided for power and control cables.
The gland plates shall be 3 mm thick and for single core cables shall be
of nonmagnetic material.
Space Heaters
Ventilation Fans
Page 311
SHASHI PRABHU & ASSOCIATES
cubical volume for effective heat dissipation etc. in order to restrict
temperature rise to within the required limit.
Page 312
SHASHI PRABHU & ASSOCIATES
Earthing
Continuous internal copper earth bus sized for prospective fault current
to be provided with arrangement for connecting to station earth at two
points. Hinged doors / frames to be connected to earth through
adequately sized flexible braids.
All other requirements by the local Authority that are imposed in course
of execution of the work, particularly those listed below shall be
provided.
Danger Signs
Rubber floor mats will be provided all around the panels as per IS
156522007 amended up to date.
A dry chemical type fire extinguisher of 9 kg capacity with approved
label
Framed single line diagram with minimum A1 size
First Aid Demonstration sign.
CPRI TESTING
Switchboard configurations offered shall be CPRI tested. Copies of the
CPRI test certificates shall be submitted with the tender.
TESTING AT WORKS
Copies of type test carried out at ACB/MCCB manufacturers works and
routine tests carried out at the switchboard fabricators shop shall be
furnished along with the delivery of the switchboards. Client reserves
the right to get the switchboard inspected by their representative at
fabricators works prior to dispatch to site to witness the routine tests
Type Test
Page 313
SHASHI PRABHU & ASSOCIATES
The main distribution board and the components as applicable shall be
type tested in accordance with the IEC standards to verify the specified
fault level withstand capacity from a reputed and approved type testing
laboratory and certified by an competent authority.
Routine test
The panel assembler shall perform the routine test and provide the test
certificates as de fined in IEC standards. The routine test shall include
but not limited to the following:
Inspection of the assembly including inspection of wiring and electrical
operational test (IEC Clause 8.3.1);
Dielectric test & Insulation resistance test (IEC Clause 8.3.2 & 8.3.4);
Checking of protective measures and of the electrical continuity of the
protective circuits (IEC Clause 8.3.3)
Functional test as per the approved test procedure.
INSTALLATION
TESTING AT SITE
Page 314
SHASHI PRABHU & ASSOCIATES
evidence of dam age/cracks in any components.
Physical checking and inspections of Inter panel wiring
Checking free movement of ACBs/MCCBs/SFUs
Checking of operation of breakers
Insulation tests of bus bar supports and control wiring etc. with 1.1 kV
megger.
Primary & secondary injection tests of relays and CTs.
Checking of Interlocking function.
General Points
The ACB shall conform to IS/IEC 609472. The ACBs shall be type tested
& certified for compliance to standards. All ACBs shall have “CE”
Marking
All ACBs shall have Icu=Ics=Icw for 1 Second with Combined Test
Sequence Certification from Independent Testing Approved Authorities
CPRI/ERDA/ASTA/KEMA.
All ACBs shall have Rated Impulse withstand voltage of the main circuit
of not less than 12kV (Uimp) & Rated Insulation Voltage of not less than
1000 V.
Neutral Pole shall be of 100% Current Rating as Phase pole (In case of 4
Pole ACBs). However, in case where 3 Pole ACBs with O/L, S/C, E/F
(Inbuilt E/F mandatory in all ACBs) are specified, vendor to provide
Neutral CT from ACB manufacturer.
All ACBs shall be provided with Door Interlock and Racking Interlock.
One shall not be allowed to open the panel door without ensuring that
the ACB is in “ISOLATED” position
All ACBs shall have provision of removing Arc Chutes without use of any
tool thus facilitating quick inspection of electrical contacts.
All ACBs equipped with Shunt Release shall have the operating voltage
range from 10% Unto 110% Un to ensure intentional tripping even at
high voltage drops during short circuit.
Page 315
SHASHI PRABHU & ASSOCIATES
All ACBs shall have their Electrical Life with maintenance = Mechanical
Life. Minimum no. of operational life shall be as follows:
All ACBs shall have protection against O/L, S/C & E/F and shall
provide indication of cause of tripping for individual faults.
All Electrical Draw Out breakers shall have inbuilt electrical anti
pumping
All ACBs shall provide at least last 5 trip data history & last 10 event
history for analysis
All ACBs shall have 2 storable sets of LSIG protection settings to provide
adequate protection against loads varying as per time (E.g. Day Time –
different protection parameter set and night time – different protection
parameter set) & source changeover from Transformer to DG.
All ACBs shall have Double Short Circuit Selectivity and the same shall
be with Adjustable Time Delay.
All Incomer ACB releases shall have LED Display showing all Power
Parameters & Harmonic Metering (I, Imax, %loading, Iavg, V, Freq, PF,
W, VAr, VA, Wh, VArh, Vah, MD Active, MD Reactive, MD Apparent,
Temperature in each Phase Deg C, %THD). They shall also give ad
additional protection against Undercurrent, Current Unbalance, Under
Voltage, Over voltage, Under frequency, Over frequency, Reverse Power,
Lead/Lag PF, MD Exceed, Wrong Phase sequence, Breaker Failure.
All Outgoing ACB releases shall have LED Display for all Current
Parameters
All Main Incomer ACBs shall have inbuilt Temperature rise protection
for protection against abnormal temperature rise at ACB terminals.
The ACB shall confirm to the requirements of IEC 609472 & 3 (FOR
Page 316
SHASHI PRABHU & ASSOCIATES
SWITCH DISCONNEC TION) / relevant local standards and shall be type
tested & certified for compliance to standards from–authorized/ any
accredited international lab. The circuit breaker shall be suit able for
service voltage 690, 3 Phase 50 Hz supply system. Air Circuit Breakers
shall be with moulded housing flush front, draw out type and shall be
provided with a trip free manual operating mechanism or in accordance
with requirements with mechanical "ON" "OFF" “TRIP” indications.
CRADLE
Page 317
SHASHI PRABHU & ASSOCIATES
arrangement of the circuit breaker on the cradle.
Test Position: Main Isolating contacts are isolated but control contacts
are still engaged.
Isolated Position: Both main isolating and control contacts are isolated.
There shall be provision for locking the breaker in any or all of the first
three positions. The following safety features shall be incorporated:
Withdrawal or engagement of Circuit breaker shall not be possible
unless it is in open condition.
All Switchgear module front covers shall have provision for locking.
PROTECTIONS
The release shall sample the current at the rate of 16 times per cycle to
monitor the actual load current waveform flowing in the system and
shall monitor the true RMS value of the load current. It shall take into
account the effect of harmonics also.
Page 318
SHASHI PRABHU & ASSOCIATES
Thermal Memory
When the breaker shall reclose after tripping on overload, then the
thermal stresses caused by the overload if not dissipated completely,
shall get stored in the memory of the release and this thermal memory
shall ensure reduced tripping time in case of subsequent over loads.
Realistic Hot/Cold curves shall take into account the integrated heating
effects to offer closer protection to the system.
Trip Indication
Self powered
The release shall draw its power from the main breaker CTs (hog slay
type) and shall require no external power supply for its operation.
Page 319
SHASHI PRABHU & ASSOCIATES
breakers.
This type of release should be equipped with data logger and information
about last20 trips including cause of trip, value of interrupted current
with date and real time stamping, should be stored in the memory with
this type of release.
Metering Function –
Phase/ Neutral/ Ground Currents Voltage and power
Power Factor
Frequency & Peak Factor
Energy (Active, Reactive, Apparent)
Page 320
SHASHI PRABHU & ASSOCIATES
Under Voltage & over Voltage (Timing & trip) Reverse Power Protection
(Timing & Trip)
Under Frequency & Over Frequency (Timing & Trip)
Maintenance Data
SAFETY FEATURES
It shall be possible to bolt the draw out frame not only in connected
position but also in TEST and DISCONNECTED position to prevent
dislocation due to vibration and shocks.
The insulation material used shall conform to Glow wire test as per
IEC60695.
Page 321
SHASHI PRABHU & ASSOCIATES
The ACB shall provide in built electrical and mechanical antidumping.
The MCCB should be current limiting type with trip time of less than 10
milli sec under short circuit conditions. The MCCB should be either 3 or
4 poles as specified in report, specs. & as per detail design. MCCB shall
comply with the requirements of the relevant standards IEC 609472 and
should have test certificates for Breaking capacities (Ics=Icu=100%) from
independent test authorities of or any accredited international lab.
The breaking capacity of MCCB shall be as per detail design. The rated
service breaking capacity (Ics) should be equal to rated ultimate
breaking capacities (Icu). MCCBs for mo tor application should be
selected in line with Type2 Coordination as per IEC 609472 . The
breaker as supplied with ROM should meet IP54 degree of protection.
For Motor application, motor duty type MCCBs shall be selected with
reference to Type 2 coordination chart provided by the manufacturer.
a) All MCCBs shall have Phase Barriers & Extended Rotary
Operating Handles with door interlocks.
All MCCBs shall have Aux Contact (For On Off Indication), Trip Alarm
Contact (For Trip Indication) and Shunt / UVR Release as specified
The MCCB shall employ maintenance free minimum let through energies
and capable of achieving discrimination up to the full short circuit
capacity of the downstream MCCB. The manufacturer shall provide
both the discrimination tables and let through energy curves for all.
It shall be responsibility of Panel builder & OEM to carry out the
discrimination study at the time of drawing approval.
Page 322
SHASHI PRABHU & ASSOCIATES
Protection Functions
Testing
Original test certificate of the MCCB as per IEC 609471 &2 shall be
furnished.
Interlocking
The MCCB shall be current limiting type and comprise of quick make –
Break switching mechanism. Microprocessor MCCBs shall be capable of
defined variable over load adjustment.
All MCCB with microprocessor based release unit, the protection shall
be adjustable Overload, Short circuit and earth fault protection with
time delay.
The trip command shall override all other commands.
Page 323
SHASHI PRABHU & ASSOCIATES
be suitable for isolation conforming to standard IEC 609472 and shall
have a rated impulse withstand voltage (U imp) of 6 kV. The motor
circuit breakers shall be designed to be mounted vertically or
horizontally without derating.
Power supply shall be from the top or from the bottom. In order to
ensure maximum safety, the contacts shall be isolated from other
functions such as the operating mechanism, casing, releases,
auxiliaries, etc, by high performance thermoplastic chambers. The
operating mechanism of the motor circuit breakers must have snap
action opening and closing with free tripping of the control devices. All
the poles shall close, open, and trip simultaneously. The motor circuit
breakers shall accept a padlocking device in the “isolated” position.
CONTROL WIRING:
Page 324
SHASHI PRABHU & ASSOCIATES
stranded PVC insulated FRLS copper wires. These shall be black in color
for AC and grey in color for DC. The C.T. connections shall be done
using 2.5 sq.mm. Multi stranded PVC insulated copper wires of red
color.
INTERMODULE WIRING:
The control wiring between modules located in the same vertical section
shall be connected at the respective terminal blocks/ terminals. These
shall be routed through the cable duct in PVC wire channels. Inter
connections between adjacent cubicle in the same shipping sections
shall be done in a similar way.
CURRENT TRANSORMERS:
FUSES
All fuses shall be of the HRC cartridge type, conforming to IS: 2208
mounted on plugin type of fuse bases having a prospective current
rating of not less than 50 KA. Fuses shall be provided with visible
operation indicators to show that they have operated. Insulated fuse
pulling handle shall be supplied with each control panel.
Control and instrument switches shall be of the rotary type and shall be
provided with properly designated plate. Control switches shall have
momentary contacts spring return to centre with pistol grip handle.
Instrument and selector switches shall have stay put contacts.
PUSH BUTTONS
All push buttons shall be of push to actuate type having 2 `NO' and 2
Page 325
SHASHI PRABHU & ASSOCIATES
`NC' self reset contacts. They shall be provided with designation plates,
engraved with their functions. Push button contacts shall be rated for
10 amps at 415V A.C. and 0.6 Amp. Inductive breaking at 220V D.C.
DRAWINGS
The contractor shall provide the following drawings for approval to the
department before commencement of supply/ fabrication.
ROTARY SWITCHES
Switches upto 60amps shall be rotary type with compact and robust
construction, build up from one or more stacks with contacts and a
positioning mechanism with stop as required. The terminals shall be
shrouded with insulation to prevent accidental contact with live parts.
Rotary switches shall be backed up with moulded type HRC fuse fittings
of appropriate rating.
SELECTOR SWITCH
STARTERS
Direct on line starters shall be provided for motors upto 7.5 HP. Star
Delta type starters shall be provided for motors of 10.0 HP and above
capacity.
Starters contactors shall have 3 main and 3 auxiliary contacts and shall
be air break type suitable for making and breaking contact at minimum
power factor of 0.38. `For design con side ration of contactors, the
starting current of connected motor shall be assumed to be 6 times the
full load current of the motor in case of direct online starters, and 3
times the full load current of the motor in case of star delta/Reduced
Voltage Starters.
Main and auxiliary contacts shall be silver or silver alloy. The insulation
for contactor coils shall be of class "B". Operating coils of contactors
shall be suitable for 220/415 ± 10% volts AC, 50 cycles supply system.
The contactors shall drop out when voltage drops to 80% of the rated
voltage. The housing of the contactors shall be heat resistant and having
Page 326
SHASHI PRABHU & ASSOCIATES
high impact strength. Each starter shall have thermal overload
protection on all three phases and also single phasing preventing relay.
Single phase preventers shall be provided on all the three phase motor
starters and shall be in conformity with relevant ISI standards. Single
phase preventers shall act when the supply voltage drops down to 90%
of the rated voltage or on failure of one or more phases.
Time delay relays shall be adjustable type with time delay adjustment
from 0180 seconds and shall have one set of auxiliary contacts for
indicating lamp connection.
TOGGLE SWITCH
Push button stations shall be provided for manual starting and stopping
of motors/equipment as called for, `RED' and `GREEN' colour push
buttons shall be provided for `starting' and `stopping' operations. `Start'
or stop indicating flaps shall be provided for push buttons. Push
buttons shall be suitable for panel mounting and accessible from front
without opening door, dock lever shall be provided for `Stop' push
button. One set of normally open and one set of normally closed
contacts shall be provided in push button stations. The push buttons
contacts shall be suitable for 15 amps current capacity.
All Cabling, Wiring & Conduits work shall be done for wiring as per
Electrical Specification part of this tender. All Fire case fans & AHU’s &
other equipment’s shall strictly be supplied with Fire survival
MICC/MICA cables on GI/SS cable trays as detailed out in the electrical
Page 327
SHASHI PRABHU & ASSOCIATES
part of tender specifications.
Cable Laying
Cable Sizes
DRAWINGS
Shop drawings for control panel sand wiring of equipment showing the
route of conduit/cable shall be submitted by the contractor for approval
of purchasers before starting the fabrication of panel and starting the
work. On completion, four sets of completion/"As installed" drawings
incorporating all details like, conduit routes, number of wires in conduit,
location of panels, switches, junction/pull and cable route etc. shall be
furnished by the Con tractor.
PAINTING
TESTING
Page 328
SHASHI PRABHU & ASSOCIATES
Before commissioning of the equipment, the entire electrical installation
shall be tested in accordance with code of Practice IS:7321963 (Revised)
and test report furnished by a qualified and authorized person.
MISCELLANEOUS
The branch lines from the main panel to each equipment shall be
separated and should not cross other lines.
All exposed switch board panels, conduits; hangers etc. shall be given 2
coats of suitable paint of approved colour, when all work has been
completed.
Page 329
SHASHI PRABHU & ASSOCIATES
19 TESTS AT SITE & FACTORY
GENERAL
The contractor must perform all inspection and tests of the system as a
whole and of components individually as required, under the
supervision of the
Page 330
SHASHI PRABHU & ASSOCIATES
AIR HANDLING UNITS
BLOWERS
COILS
• Pneumatic test.
FILTERS
VALVES
MOTORS
Visual examination.
• Pressure testing of pipe fittings used for the refrigerant and water
services.
Page 331
SHASHI PRABHU & ASSOCIATES
functioning of controls of refrigerant systems and other circuits of air
conditioning plant.
PIPING SYSTEM
• After tests have been completed, the system shall be drained and
cleaned of all dust and foreign matter. All strainers, valves and
fittings shall be cleaned of all dirt, fit tings, and debris.
WATER PIPING
All water piping shall be tested and proven tight under hydrostatic
pressure of 1 1/2 times the design pressure unless stated otherwise in
the specifications. Prescribed pressure shall be maintained for four
hours.
DUCT WORK
• All branches and outlets shall be tested for air quantity, and the
total of the air quantities shall be within plus five percent (5%) of
fan capacity.
Page 332
SHASHI PRABHU & ASSOCIATES
Page 333
SHASHI PRABHU & ASSOCIATES
BALANCING AND ADJUSTMENT
All air handling ventilation equipment, duct work and outlets shall be
adjusted and balanced to deliver the specified air quantities indicated, at
each inlet and outlet, on the drawings. If these air quantities cannot be
delivered without exceeding the speed range available horse power, the
department shall be notified before proceeding with the balancing of air
distribution system.
ELECTRICAL EQUIPMENT
PERFORMANCE TESTS
• Differential pressure readings across each filter, fan and coil, and
through each pump.
Page 334
SHASHI PRABHU & ASSOCIATES
building.
MISCELLANEOUS
• The above tests are mentioned herein for general guidance and
information only but not by way of limitation to the provisions of
conditions of contract and specification.
• The contractor shall supply the skilled staff and all necessary
instruments and carry out any test of any kind on a piece of
equipment, apparatus, part of system or on a complete system if the
purchaser requests such a test for determining specified or
guaranteed data as given in the specification or on the drawings.
• The contractor must inform the department when such tests are to
be made, giving sufficient notice, in order that the purchaser or his
nominated representative maybe present.
• Complete records of all tests must be kept and 3 copies of these and
location drawings must be furnished to the department.
• The contractor may be required to repeat the test as required, should
the ambient conditions at the time not given, in the opinion of the
purchaser, sufficient and suit able indication of the effect and
performance of the installation as a whole or of any part, as required.
Page 335
SHASHI PRABHU & ASSOCIATES
its representative, the manufacturers test certificates (for all
acceptance test) for inspection of material and witnessing the various
tests at the factory as carried out by the manufacturer have to be
submitted along with the supply of equipment’s. This must be
witnessed by a representative of the contractor.
NOTES:
A. TEST INSTRUMENTS
CAPACITY COMPUTATIONS
1. AIRHANDLING UNITS
The capacity shall be computed from the water temperature and water
flow measurements. A tolerance of ± 5% from the A/T value shall be
acceptable in the capacity to computed. Air quantity shall be measured
in the supply duct and checked with the quantity specified in the A/T. A
tolerance of ±10% in the air quantity shall be acceptable. The enthalpy
difference of air entering and leaving the coil shall be computed from air
temperature. The capacity of TFA/HR Units shall be computed 75% both
sensible and latent.
Page 336
SHASHI PRABHU & ASSOCIATES
20 DETAILS OF TESTS TO BE CARRIED OUT AT SITE
− Date/Day/Time
− Temp. DB/WB °C
− RH %
CHILLER
Chiller Make/Model N
Water flow rate LP
a
Water temp. entering °C
M
m
Water temp. leaving °C
e/
Water pressure entering m
N
Water pressure leaving m
o.
Refrigerant Suction Temp. °C
m
H
Refrigerant Suction Pressure m
H
G
Capacity specified K
m
G
Capacity stipulated at 100% K
ca
H
load on the compressor ca
l/
G
Capacity specified K
l/
hr
COMPRESSOR ca
hr
.
Compressor Make/Model l/
.N
Speed hr
R
a
Refrigerant suction pressure .K
P
m
Refrigerant discharge pressure K
g/
M
e/
Refrigerant discharge temp. °C
G
S
N
Oil pressure K
/
q.
o.
Capacity specified T
g/
S
c
Capacity stipulated at various loading T
R.
S
q.
m
steps R.
q.
c
COMPRESSOR MOTOR c
m
m
Motor make/Model N
.
Speed R
a
Voltage V
P
m
Motor rating K
M
ol
e/
Current at 100% load A
W
ts
N
Current down at various loading steps. A
m
o.
m
ps
CONDENSER ps
Condenser Make/Model N
Refrigerant condensing pressure a
K
Refrigerant condensing temp. °C
g/
m
Air entring temperature °C
S
e/
q.
N
c
o.
Contractor Signature m MCGM
.
Page 337
SHASHI PRABHU & ASSOCIATES
PUMPS
(Pressure to be tested of existing pumps
after installation of gauges for
performance)
Pumps Make/Model Nam
Impeller diameter mm
e/No
Speed RPM
.
Water pressure entering Kg/S
Water pressure leaving Kg/S
q.cm.
Motor rating KW
q.cm.
Motor current at full load Amp
Motor voltage at full load Volts
s
Water flow rate (specified) LPM
Water flow rate (computed) LPM
Page 338
SHASHI PRABHU & ASSOCIATES
FAN Make/Model/Type Na
Fan speed RP
me
Fan Motor rating (specified) K
/N
M
Fan Motor current drawn A
W
o.
Line voltage Vol
mp
Fan capacity (specified Air qty.) CF
ts
Fan capacity (computed Air qty.) CF
M
M
DRY SCRUBBER
Make of dry scrubber & fan
Type of fan
Page 339
SHASHI PRABHU & ASSOCIATES
Date :
Day :
Time :
Room Temperature AM/PM
− Dry Bulb °C
− Wet Bulb °C
Ambient Temperature
− Dry Bulb °C
− Wet Bulb °C
Page 340
SHASHI PRABHU & ASSOCIATES
21 MODE OF MEASUREMENTS
UNIT PRICES
The unit price of the various items shall include the following:
The contractor's unit price shall also include all taxes, duties, octrois,
works contract tax etc. as applicable.
Page 341
SHASHI PRABHU & ASSOCIATES
• The unit duct price shall include all the duct hangers and
supports, exposing of concrete reinforcement for supports and
making good of the same as well as any materials and labour
required to complete the duct frame.
GRILLES/DIFFUSERS
PIPE
• All pipes shall be measured in linear meter (to the nearest cm)
along the axis of the pipes and rates shall be inclusive of all
fittings e.g. tees, bends, reducers, elbows etc. Deduction shall be
made for valves in the line.
Page 342
SHASHI PRABHU & ASSOCIATES
• Flexible connections, wherever required or specified shall be
measured as part of straight length of same diameter, with no
additional allowance being made for providing the same.
• The length of the pipe for the purpose of payment will be taken
through the center line of the pipe and all fittings (e.g. tees,
bends, reducers, elbows, etc.) as through the fittings are also
resumed to be pipe lengths. Nothing extra whatsoever will be paid
for over and above for the fittings. For valves and flanges, section
3.2 below app lies.
• All gun metal (gate & globe) valves shall include two Nos. of
flanges and two numbers 150mm long MS nipples, with one side
threaded matching one of the valves,
• and other welded to the M.S. slip on flange. Rate shall also
include the necessary number of bolts, nuts and washers, 3 mm
thick insertion gasket of required temp. grade and all items
specified in the specifications.
STRUCTURAL SUPPORTS
Page 343
SHASHI PRABHU & ASSOCIATES
INSULATION
The measurement for vessels, piping, and ducts shall be made over the
bare un insulated surface area of the metal.
PIPES
DUCTS
VESSELS
The area of standard dished and flat ends of vessels shall be the square
of the diameter of the uninsulated body of the shell. Areas for other
shapes shall be the actual calculated area. There shall be no deduction
or additions for nozzles, handles ribs, dampers, expansion joints etc. All
projections on vessels or tanks shall be measured separately as
pipe/duct.
ACCESSORIES INSULATION
Page 344
SHASHI PRABHU & ASSOCIATES
vapour proofing and finishing materials as well as additional
labour and material required for fixing the insulation.
Page 345
NAME OF PROJECT: - PROPOSED MULTI-SPECIALITY BHANDUP
HOSPITAL AT LAND BEARING C.T.S.NO681A/88,681A/3,681A/4 OF
VILLAGE NAHUR IN S-WARD, BHANDUP MUMBAI
Page 346
SHASHI PRABHU & ASSOCIATES
OVERVIEW:
Shop Drawings:
The contractor shall prepare and submit to the Construction
Manager/Consultants for his approval six (6) sets of detailed layout drawings
of all ELVequipment’s and piping layouts.
Before starting the work, the contractor shall submit to the Construction
Manager/Consultants for his approval in the prescribed manner, the
shop/execution drawings for the entire installation.
Page 347
SHASHI PRABHU & ASSOCIATES
Operating instructions.
Manufacturers catalogues
Drawings.
Completion Certificate:
On completion of the ELVinstallation a certificate shall be furnished by the
contractor countersigned by the licensed supervisor, under whose direct
supervision the installation was carried out. This certificate shall be in the
prescribed form as required by the local supply authority. The contractor
shall be responsible for getting the ELVinstallation inspected and approved
by the local concerned authorities and for obtaining the necessary clearance
certificates from the authorities.
Page 348
SHASHI PRABHU & ASSOCIATES
Guarantee:
At the close of the work and before issuance of final certificate of completion
by the Construction Manager/ Consultants, the contractor shall furnish
written guarantee Indemnifying the Client against defective materials and
workmanship for a period of one year after completion. The contractor shall
hold himself fully responsible for reinstallation or replacement, free of cost
to Client, the following:
Any defective work or material supplied by the Contractor.
Staff:
The contractor shall employ competent fully licensed qualified, full time
ELVengineers to direct the work of ELVinstallation in accordance with the
drawings and specifications.
The engineers shall be available at all times at site to receive instructions
from the Construction Manager., in the day to day activities throughout the
duration of contract. The engineer shall correlate the progress of the work
in conjunction with all the relevant requirement of the supply authority.
Safety Barriers and Construction Safety:
The Contractor shall at his own cost provide for the protection and safety of
the persons working in the area, safety barriers around all openings in
every location and at the periphery and edges of all slabs, staircases and
stairwells, lift shafts, ducts etc., all to the approval and satisfaction of the
Construction Manager. However, contractor shall take appropriate safety
precautions suitable for specific locations/ situations and as instructed by
the Construction Managers.
The Contractor shall, in general, be fully responsible for all matters with
regard to every form of safety during construction and in connection with
the execution of the Works, and the Contractor shall take all necessary
precautions and provide at his cost everything necessary to ensure such
safety at all times. Should any accidents occur due to the Contractor's
failure to comply with such safety requirements and to take all other safety
measures necessary, the Contractor shall be fully responsible for all such
Page 349
SHASHI PRABHU & ASSOCIATES
accidents and he shall bear and pay for all costs and damages in
connection therewith and as a consequence there of.
Disposal Of Rubbish From The Works And The Site And Provision Of
Safety Netting/Screens By Contractor:
The Contractor shall at all times keep the Works and the site in clean, neat
and tidy condition. All rubbish from the Works and the site shall be
collected and deposited in large bins provided on the site for such purpose
by the Contractor at his own cost. The rubbish from such bins shall be
regularly carted away by the Contractor to rubbish tips and dump yards
beyond the site.
At no time or stage shall any rubbish be thrown over the edges of slabs or
through any openings or shafts or ducts or stairwells.
The Contractor shall, at his own cost and to the approval and satisfaction of
the Construction Manager, provide safety netting/screens at the periphery
of all slabs and at all openings, shafts, ducts and stairwells and/or
canopies to prevent any rubbish or material falling over or into such areas
and endangering the safety of the persons working below. Should the
Contractor fail to provide such safety measures and to take other necessary
precautions in accidents that may occur, he shall bear all costs and
damages as decided by Construction Manager in connection therewith and
as a consequence there of.
The Construction Manager shall have powers to withhold amounts from
payment certificates in case of Contractor's persistent noncompliance with
provisions of this clause. Also the construction Manager is empowered to
employ another agency at Contractor's cost after one week's notice to
implement this Clause in case of Contractor's noncompliance with
provisions of this Clause.
Space For Contractor's Construction Yard, Stores Etc.:
The Client shall provide adequate storage/office space to the contractor for
his use. The space has to be maintained/constructed by the contractor as
per his usage requirements.
All spaces allotted to the contractor, as described above shall be vacated
and all structures removed from site at any time as and when required and
directed by the relevant authorities or by the Client, unconditionally and
without any reservation. The authorities or the Client will not be obliged to
give any reason for such removal. Upon receiving instructions to vacate the
space, the contractor shall immediately remove all his structures, materials,
Contractor Signature MCGM
Page 350
SHASHI PRABHU & ASSOCIATES
etc., from the spaces and clear and cleanup the site to the satisfaction of
the Construction Manager.
It shall be the specific responsibility of the Contractor to safeguard the site
and ensure that no illegal encroachments are made by outside elements
within the area allotted to the Con tractor. Upon completion of the work or
earlier as required by Client/Authorities, the Con tractor shall vacate the
land totally without any reservations. Necessary Bond to this effect on a
stamp paper shall be signed by the contractor in a prescribed form.
The Performance Bond and/or guarantees towards retention amount
furnished by the Con tractor shall not be released until the spaces allotted
to the contractor are fully vacated and handed over to the Client as per the
instructions of the Client.
Carrying Out Work Beyond Normal Working Hours Or In Shifts
In order to achieve the milestone and completion dates and to keep pace
with the approved construction programme, the Contractor shall be
permitted to carry out his work beyond the normal working hours or in
shifts. The Contractor shall be responsible for obtaining any necessary
permission from the relevant authorities that may be required for him to
carry out the work beyond the normal working hours or in shifts. Also, the
Contractor shall give prior notice to and make arrangements with the
Construction Manager for the supervision of work carried out beyond the
normal working hours or in shifts. The Contractor shall make his own
arrangements in respect of the provision of adequate lighting and any other
facilities that may be required for carrying out the work beyond the normal
working hours or in shifts. No extra payments shall be made to the
Contractor for or in connection with any such overtime or shift work. The
Contractor will not be required to bear the overtime expenses of the
Construction Manager in respect of the supervision of such overtime or shift
work of the Contractor.
Period And Time Limit For Completion Of Works:
The period and time limit for Completion of the Works shall be as per
client’s requirement from the date of issue of Work Order to commence
works or handing over of site in respect of the award of Contract. This time
period shall be inclusive of the mobilization period and monsoon period.
Professional Integrity And Team Spirit:
It is the intent of the Client, Architect and Construction Manager that this
project will be executed in a spirit of team and full professional integrity.
Page 351
SHASHI PRABHU & ASSOCIATES
Before procurement, Contractor will discuss with Client for preferred makes.
Reference Points:
Contractor shall provide permanent bench marks, flag tops and other
reference points for the proper execution of works and these shall be
preserved till the end of the work.
All such reference points shall be in relation to the levels and locations, given
in the architectural and ELVdrawing.
Reference Drawings:
The Contractor shall maintain one set of all drawings issued to him as
reference drawings. These shall not be used on Site. All important drawings
shall be mounted on boards and placed in racks indexed, no drawings shall
be rolled.
All correction, deviations and changes made on the site shall be shown on
these reference drawings for final incorporation in the completion drawings.
All changes to be made shall be initialed by Engineer in Charge or Architect.
Vendor shall prepare Shop Drawings with all details after checking the
feasibility at Site which shall be approved by the Consultants before
execution. No work will be carried out without approval of Shop drawing by
the Consultant.
Contractor Signature MCGM
Page 352
SHASHI PRABHU & ASSOCIATES
Handing Over:
Contractor will be responsible for following:
Entire System shall be commissioned and tested as per design parameter is
coordination with Client & consultant.
OBJECTIVES:
Networking Systems:
To achieve highly available and consistence network for various equipment to
communicate and seamlessly store or retrieve the data as and when required.
Telecommunication Systems:
To provide a stable and reliable Telephone / Communication network to the
users of the organization or campus within or outside the campus.
Page 353
SHASHI PRABHU & ASSOCIATES
General:
➢ The ELV System (Structure Cabling System, Enterprise Networking Systems,
Telecommunication Systems, Audio Visual Systems, Fire Alarm & Detection
Systems, Public Addressing Systems, Access Control Systems, Video
Surveillance Systems) shall be seamlessly integrated.
➢ The rates quoted by bidder shall include such costs to ensure compatibility
and seamless integration.
➢ The OEM should submit the authorization letter covering below mentioned
points, before commencing the work by the Bidder:
o OEM should confirm that the items quoted by the bidder are in
production and would be serviceable for at least Seven Years.
o OEM should confirm that the quoted items are not obsolete products.
o OEM should confirm that the quoted items are produced within One
Year before the date of Supply.
➢ Structure Cabling shall be design, built and installed as per the best practices
of Structure Cabling System, using all the components (Copper and Fiber)
from a single OEM for the assurance of consistent performance. The structure
cabling system shall be serve as a highway for transport of Data, Voice
Telephony and Video traffic over a common network throughout the network.
➢ Structure Cabling System designed such as 10G backbone OFC network with
ring topology for redundancy and network endpoint / host should be
connected on 1G Copper network.
➢ Two separate network to be designed for Hospital Premises and College
Premises, however it should be integrated with each other at Core Level.
➢ Two separate network to be designed as (i) Data (Wired & Wireless),
communication System, Telepresence & Collaboration System and Audio
Visual Systems, (ii) Utilities like IP Based Video Surveillance, Access Control
System, Public Addressing System, Fire Alarm & Detection System and
Integrated Building Management System.
➢ Installation, identification and termination of cables between information
outlets and network rack shall be considered as a part of bidder’s work.
Page 354
SHASHI PRABHU & ASSOCIATES
➢ Cabling utilized for Voice and Data Nodes shall originate from Network Racks
and terminated at Information Outlets at Wall.
➢ All cables and IOs shall be identified at both the ends (IO & Rackside) with
appropriate ferruling.
➢ All balanced twisted pair cables laying and termination shall comply and be
tested as per TIA/EIA 568-B series standard for Cat5, Cat5E and Cat6
installations.
➢ UTP Cabling system conforming to ANSI/TIA/EIA 568-B series and ISO/IEC
11801 2nd edition, EN-50173-1.
➢ The bidder carrying out the SITC work shall make the system entirely
operational for its intended use, by addition of components specific to its
make/model even if not specifically mentioned in the BOQ.
➢ It shall be the responsibility of the installer and OEM to ensure that the
Passive Components of structured cabling system will be free from
manufacturing defects in material and workmanship under normal and
proper use.
➢ The site should be duly certified by OEM for a period of 20 years from the
date of installation or issuance of the registration certificate, whichever is
earlier.
➢ 20-year systems performance guarantee by the OEM along with actual test
results conducted at site such as attenuation, return loss, NEXT & ACR.
Permanent link shall be tested for minimum guaranteed performance as per
standards at 500 MHZ operation as minimum.
➢ The final branch connections with single cables in conduit & the maximum
no. of cables in each conduit shall be as per given in below table:
Page 355
SHASHI PRABHU & ASSOCIATES
➢ The SITC job includes Supply, installation, testing and commissioning of UTP
Cat6 cables in existing conduit either on flooring / wall / ceiling / slab etc.
➢ The bidder has to furnish working drawings and commence work after
approval of end user or consultant. The successful bidder has to submit as-
built drawings.
➢ The structure cabling system should support various applications but not
limited to Voice, Video and ISDN Applications, Ethernet Applications,
IEEE802.3af PoE and IEEE802.3at PoE+, Fiber Channel Applications,
IEEE802.11a/b/g/n/ac Wireless LAN Applications, DSL Applications,
Various Audio & Video Streaming Applications.
➢ The structure cabling system as per the references and standards but not
limited to TIA/EIA, International Electro-technical Commission (IEC),
European Committee for Electro-technical Standardization (CENELEC),
National Fire Protection Association (NFPA), UL Listed.
➢ The structure cabling system compliant channels will meet or exceed the
guaranteed channel performance as per relevant standards in the structure
cabling system performance specifications in effect at the time of installation.
Page 356
SHASHI PRABHU & ASSOCIATES
Page 357
SHASHI PRABHU & ASSOCIATES
5. Face Plates
a. Standard and As per Above (1.a)
Compliance
b. No. of Ports One, Two, Four Ports
c. Material ABS / UL 94 V-0, Color: White
6. Patch Panels
a. Standard and As per Above (1.a)
Compliance
b. Height 1U – 1.75”
c. No. of Ports 24 Ports, Fully Loaded with Key Stone
Jack.
d. Port Type Individual Key Stone Type or 6 Port
Modular. Blank Inserts for un-used
ports.
e. Panel Fully Powder Coated, Pencil Grey Color.
f. Termination TIA/EIA 568 A & B.
Type
g. Performance NEXT, PS NEXT, FEXT, Attenuation,
Return-Loss
h. Approval UL Listed.
Page 358
SHASHI PRABHU & ASSOCIATES
Page 359
SHASHI PRABHU & ASSOCIATES
Page 360
SHASHI PRABHU & ASSOCIATES
Page 361
SHASHI PRABHU & ASSOCIATES
Page 362
SHASHI PRABHU & ASSOCIATES
Page 363
SHASHI PRABHU & ASSOCIATES
Page 364
SHASHI PRABHU & ASSOCIATES
Page 365
SHASHI PRABHU & ASSOCIATES
Page 366
SHASHI PRABHU & ASSOCIATES
Page 367
SHASHI PRABHU & ASSOCIATES
Page 368
SHASHI PRABHU & ASSOCIATES
Page 369
SHASHI PRABHU & ASSOCIATES
Page 370
SHASHI PRABHU & ASSOCIATES
Page 371
SHASHI PRABHU & ASSOCIATES
Page 372
SHASHI PRABHU & ASSOCIATES
Page 373
SHASHI PRABHU & ASSOCIATES
2.3 24 Port Access PoE+ Switch with 4 10G Uplink – Layer 2 (Type - 3):
Sr. Specification Compliance
No. Yes / No
Hardware Architecture:
1. Switch should have Stackable Architecture to provide Scalable
network.
2. Switch should be stackable switch at least eight switch should be
stack with a minimum stacking bandwidth of 160 Gbps.
3. Switch should have Resilient Stacking Architecture.
4. Manageable 24 Port PoE+ Giga Switch. Number of Ports: 24 x
10/100/1000 Mbps PoE+ and additional 4 x 10G SFP+ Ports.
5. Switch should have 802.3at PoE+ Ports, 30W per port or higher.
Page 374
SHASHI PRABHU & ASSOCIATES
6. Switch should have 370W PoE budget from day one and should
support 740W PoE budget, if required.
7. Switch should have switching capacity of 128 Gbps and 288 Gbps with
stacking or more.
8. Switch should have Redundant Power Supply Slot.
9. Switch should have non-blocking wire-speed architecture.
10. Switch port should support IEEE 802.3 10Base-T, IEEE 802.3u
100Base-Tx Fast Ethernet, IEEE 802.3ab 1000Base-T Gigabit
Ethernet, 802.3ae 10 GbE, IEEE 802.3x Flow Control for Full Duplex
Mode, Auto negotiation, IEEE802.1X Authentication.
11. Switch should be architected to support real time applications like
voice, video, data by having distributed architecture.
Requirement per Switch:
12. Minimum 24 interfaces of 10/100/1000 base-TX PoE+ and 04
interfaces of 10G SFP+.
13. Switch should support IEEE 802.3az Energy Efficient Ethernet.
14. Switch should have at least 4GB DRAM and 4GB Flash or higher.
15. Switch should support LED indication for System Status, per port
integrity, Activity, Disabled, Link Speed, etc.
Performance:
16. Switch should have non-blocking switching backplane of 128 Gbps.
17. Switch should have forwarding rate of minimum 95 Mpps on 64 Byte
Packet.
18. Switch should support 32K or more MAC Addresses.
19. Switch should support up to 512 static MAC entries and should
support auto-learning MAC addresses with enable / disable function.
20. Switch should support Hibernation Mode.
21. Switch should support EtherChannel Technology across different
members of stack.
22. Switch should support Power Redundancy and Fan Redundancy.
23. Switch should support Switched Port Analyzer (SPAN) & Enhanced
SPAN.
24. Switch should have SYSLOG capabilities to enable system logging.
25. Switch should support to NTP Client.
26. Switch should support logging banner for console.
27. Switch should support Spanning Tree Protocol per VLAN.
28. Switch should have functionality to add new features like IOS /
Firmware upgrades.
29. MTBF should be 420000 hours or more.
L2 Features:
30. Switch should support 9K Jumbo frames.
31. Switch should support Loop Back detection.
32. Switch should support Dynamic VLAN.
33. Switch should support HW based Source Learning, should support
voice VLAN.
34. Switch should support IEEE 802.1Q Tagged VLAN – Port based VLANs
and VLAN Stacking.
35. Switch should support for at least 1K Active VLAN’s.
Contractor Signature MCGM
Page 375
SHASHI PRABHU & ASSOCIATES
Page 376
SHASHI PRABHU & ASSOCIATES
2.4 24 Port Access Switch with 4 10G Uplink – Layer 2 (Type - 4):
Sr. Specification Compliance
No. Yes / No
Hardware Architecture:
1. Switch should have Stackable Architecture to provide Scalable
network.
2. Switch should be stackable switch at least eight switch should be
stack with a minimum stacking bandwidth of 160 Gbps.
3. Switch should have Resilient Stacking Architecture.
4. Manageable 24 Port Giga Switch. Number of Ports: 24 x 10/100/1000
Mbps and additional 4 x 10G SFP+ Ports.
5. Switch should have switching capacity of 128 Gbps and 288 Gbps with
stacking or more.
6. Switch should have Redundant Power Supply Slot.
7. Switch should have non-blocking wire-speed architecture.
Page 377
SHASHI PRABHU & ASSOCIATES
Page 378
SHASHI PRABHU & ASSOCIATES
38. Switch should support IPV4 and IPv6: MLD V1/V2 awareness.
39. Switch should support Link Aggregation based on 802.3ad across the
switches
40. Switch should support latency < 4µ seconds.
41. Switch should support IPv4 and IPv6 Features.
Quality of Service:
42. Switch should support QoS based on 802.1p Priority - 8 hardware
queues per port.
43. Switch should support Ingress Policing and Egress Shaping.
44. Switch should support 802.1p / ToS / DiffServ marking and mapping.
45. Switch should support CoS based on 802.1p priority, VLAN, MAC
Address, Ether type, IP address, DSCP, Protocol type, TCP/UDP Port
Number, DSCP of IPv6 Traffic Class and IPv6 flow label.
46. Switch should support SRR / WRR / CIR and SP.
Security:
47. Switch should support Broadcast / Multicast / Unicast Storm Control.
48. Switch should support DHCP Snooping
49. Switch should support Dynamic ARP Inspection.
50. Switch should support IP Source Guard.
51. Switch should support SSH for IPv4 and IPv6.
52. Switch should support SSL for IPv4 and IPv6.
53. Switch should support IP-MAC port binding.
54. Switch should support 802.1x Authentication on all ports.
55. Switch should support 802.1x with Guest VLAN allows guests without
802.1x client to have limited network access on the guest VLAN.
56. Switch should support RADIUS and TACACS + authentication for
switch access.
57. Switch should support scanning of network attacks based on
behavioral analysis.
58. Switch should support Port Mirroring, Remote Port Mirroring and
Policy-based Mirroring.
59. Switch should support Standard and extended ACLs on all ports.
60. Switch should support system event logging.
61. Switch should support real time multi-port statistics.
62. Switch should support MAC / IP Address Finder.
63. Device and Port Grouping for Navigation and Policy Management.
64. The Switch should be able to discover the neighbouring device of the
same vendor giving the details about the platform, IP Address, Link
connected through etc, thus helping in troubleshooting connectivity
problems.
Physical/Environmental:
65. AC Input: 100 to 240 VAC, 50/60 Hz internal
66. Operating Temperature: 0 to 45 °C
67. Certifications: CE, FCC, VCCI, UL, EN, IEC, RoHS.
Management:
68. Switch should support management using CLI, Telnet and GUI using
Web interface.
69. Switch should support IPv6 Neighbor Discovery.
Contractor Signature MCGM
Page 379
SHASHI PRABHU & ASSOCIATES
70. Switch should support SNMP V1, V2, V3, SNMP Traps and RMON.
71. Switch should support ICMPv6 and IPv4/v6 Dual Stack.
72. Switch should support LLDP and LLDP-MED.
73. Switch should support FTP / TFTP for upgrading the Operating
System.
Licensing:
74. Switch should support a licensing mechanism which will enable the
client to port the license to the new switch when client want to replace
the existing switch.
75. Switch should support new updates and upgrades along with new
features with that licensing mechanism.
76. Switch should support L3 Features like advanced IP unicast routing,
OSPFv3, EIGRPv6, IS-ISv4 with backward compatibility.
77. Switch should support Software Defined Network (SDN) from Day One,
If any license required should be included.
78. Offered Product must have OEM Support Contract for 1 Years with
8x5xNBD.
79. OEM Service Contract paper to be submitted after Installation.
OEM Criteria:
80. OEM should be Leaders in Gartner Magic Quadrant for Wired and
Wireless, atleast for Last 3 Years.
81. Offered Product Should not be End of Sale for atleast 5 Years.
Page 380
SHASHI PRABHU & ASSOCIATES
Page 381
SHASHI PRABHU & ASSOCIATES
Page 382
SHASHI PRABHU & ASSOCIATES
Page 383
SHASHI PRABHU & ASSOCIATES
Page 384
SHASHI PRABHU & ASSOCIATES
Page 385
SHASHI PRABHU & ASSOCIATES
Page 386
SHASHI PRABHU & ASSOCIATES
Page 387
SHASHI PRABHU & ASSOCIATES
Page 388
SHASHI PRABHU & ASSOCIATES
Page 389
SHASHI PRABHU & ASSOCIATES
Page 390
SHASHI PRABHU & ASSOCIATES
3. Telecommunication System:-
Page 391
SHASHI PRABHU & ASSOCIATES
Page 392
SHASHI PRABHU & ASSOCIATES
Page 393
SHASHI PRABHU & ASSOCIATES
l. Call retrieve
m. Calling line identification restriction
n. Call waiting
o. class of service
p. Hot Line
q. Do not Disturb
r. Do Not Disturb override
s. Call Hold
t. Call Transfer
u. Internal Music On Hold
v. External Music on Hold Support
w. Last Number Redial
x. Save Number Redial
y. Instrument locking for preventing
outgoing calls
z. One Number service.-Through this
feature it should be possible to have the
same number for internal extension and
Mobile Number. Through this feature both
internal extension and Mobile number will
ring simultaneously and once the call is
picked up from either of the devices the
ringing on the other device stops. This
requires integration of PRI Lines with
DOT/MTNL. This feature may also be termed
as parallel ringing.
IM and Presence The solution must be able to support point-
29.
to-point and multi-party messaging
It must support ability to send Multimedia
30.
(Text, voice, video and photo) messages
between users
It must have ability to store messages
31.
centrally and be able to deliver them when
users connect. Senders should be able to
send to offline receivers and messages
should be able to be delivered on demand.
The centrally stored messages should
provide secure access through encryption
between servers and endpoints. Also data
should be available only through secured
logins
Conversation persistency should be
32.
maintained so that users can view and
participate in active conversations from
multiple messaging applications, until they
leave the conversation
It must support notification events for all
33.
new messages
Page 394
SHASHI PRABHU & ASSOCIATES
Page 395
SHASHI PRABHU & ASSOCIATES
Page 396
SHASHI PRABHU & ASSOCIATES
Page 397
SHASHI PRABHU & ASSOCIATES
66 Environmental Conditions:
a. Operational temperature: 0 to 40
Degree C.
b. Storage -20 degree C to +65 degree C
c. Humidity 10% to 90% without
condensation
67 The exchange cabinet should field
replaceable RAM, flash, DSPs, PSUs, fan
tray, and main board module for enhanced
reliability
68 VoIP Network support and call details for Voice
Management over IP
69 Call detail records including current active
calls and call history for at least one month.
70 VoIP quality- Latency, Jitter, packet loss for
each call and get historical reports and trend
charts.
71 VoIP Traffic analysis-Monitor a mix of VoIP
and other network traffic proactively to
understand the network, preferably the
bandwidth and capacity bottlenecks of
different applications.
72 It should be possible to centrally take packet
captures for in and out of any IP endpoint to
help troubleshoot audio quality issues.
73 It should be possible to trace route to detect
DSCP markings to ensure end-to-end
markings are provisioned
74 It should be possible to access the IP phone
interface with live screen capture for taking
remote control of the phone for faster
resolution. It should also be possible to
simulate multiple calls from one end node to
another
Page 398
SHASHI PRABHU & ASSOCIATES
No. of Lines-1
1.
Incoming & Outgoing Call memory Storage
2.
Flash Programmable
3.
LCD Contrast adjustable
4.
Min 16 Digit Single Line Display
5.
Two Way Speaker supported
6.
Page 399
SHASHI PRABHU & ASSOCIATES
Port
4 Should have Antivirus throughput of 6 Gbps or higher
5 Should have IPS throughput of 8 Gbps or higher
6 Should have 2 Flexi Port Slots
7 Should have VPN throughput of 4Gbps or higher
8 Should have 3 Nos. USB 3.0 and 1 Nos. HDMI Port
9 Should have firewall throughput of 40Gbps or higher
10 Should have option of external power supply
11 Should have integrated inbuilt SSD hard disk for firewall
log storage
12 Should have 3 years OEM support from day 1 to upgrade
firmware, virus database, etc
Page 400
SHASHI PRABHU & ASSOCIATES
Page 401
SHASHI PRABHU & ASSOCIATES
➢ All Fire Alarm Panels need to be connected with each other in active form.
➢ An graphical software need to be install at Chief Fire Alarm Officer / Fire
Officer office to enable them to observe all Fire Alarm Panels from a single
point of location.
➢ Isolators need to be placed after approved device count as per NFPA
standards.
Page 402
SHASHI PRABHU & ASSOCIATES
Page 403
SHASHI PRABHU & ASSOCIATES
11 Operational instructions or
manual for use by building
personnel, including Name and
phone number of service
representative
12 Maintenance instructions as
required for use by building
personnel.
13 Copy of approved shop drawings.
Page 404
SHASHI PRABHU & ASSOCIATES
Page 405
SHASHI PRABHU & ASSOCIATES
Page 406
SHASHI PRABHU & ASSOCIATES
Page 407
SHASHI PRABHU & ASSOCIATES
Page 408
SHASHI PRABHU & ASSOCIATES
Page 409
SHASHI PRABHU & ASSOCIATES
Page 410
SHASHI PRABHU & ASSOCIATES
47 An automatic announcement or
tone evacuation signal shall be
capable of interruption by the
operation of the local system
microphone to give voice
evacuation instructions
overriding the preprogrammed
sequences
Page 411
SHASHI PRABHU & ASSOCIATES
54 Activation of stairwell
pressurization fans, smoke purge
and damper control shall be as
required
55 Supervisory Condition
a. Display the origin of the
supervisory condition
report at the fire alarm
control panel graphic/ 600
character LCD display
b. Activate supervisory
audible and dedicated
visual signal
c. Audible signals shall be
silenced from the control
panel by the supervisory
acknowledge switch
d. Record within system
history the initiating device
and time of occurrence of
the event
e. Print to the system printer
(where required) the
supervisory condition.
56 Trouble Condition
a. Display at the Fire alarm
control panel graphic/600
character LCD display, the
origin of the trouble
condition report.
b. Activate trouble audible
and visual signals at the
control panel and as
indicated on the drawings.
c. Audible signals shall be
silenced from the fire alarm
control panel by a trouble
Contractor Signature MCGM
Page 412
SHASHI PRABHU & ASSOCIATES
acknowledge switch
d. Trouble conditions that
have been restored to
normal shall be
automatically removed
from the trouble display
queue and nor require
operator intervention.
e. Record within system
history, the occurrence of
the event, the time of
occurrence and the device
initiating the event.
f. Print to the system printer
(where required) the trouble
condition
Page 413
SHASHI PRABHU & ASSOCIATES
Page 414
SHASHI PRABHU & ASSOCIATES
Page 415
SHASHI PRABHU & ASSOCIATES
Page 416
SHASHI PRABHU & ASSOCIATES
(Optional)
Page 417
SHASHI PRABHU & ASSOCIATES
Page 418
SHASHI PRABHU & ASSOCIATES
Page 419
SHASHI PRABHU & ASSOCIATES
Page 420
SHASHI PRABHU & ASSOCIATES
Page 421
SHASHI PRABHU & ASSOCIATES
Page 422
SHASHI PRABHU & ASSOCIATES
Page 423
SHASHI PRABHU & ASSOCIATES
Page 424
SHASHI PRABHU & ASSOCIATES
Page 425
SHASHI PRABHU & ASSOCIATES
23 1 x internal speaker
Page 426
SHASHI PRABHU & ASSOCIATES
Page 427
SHASHI PRABHU & ASSOCIATES
Page 428
SHASHI PRABHU & ASSOCIATES
Page 429
SHASHI PRABHU & ASSOCIATES
Page 430
SHASHI PRABHU & ASSOCIATES
Page 431
SHASHI PRABHU & ASSOCIATES
5.10 Software:
Page 432
SHASHI PRABHU & ASSOCIATES
Page 433
SHASHI PRABHU & ASSOCIATES
Detection(
LFD)
Page 434
SHASHI PRABHU & ASSOCIATES
7. Operating
7 - 10 °C to + 50 °C
Temperatures
8. Humidity
8 5% to 95% RH Non-Condensing
9. Certifications
9 CE and RoHS
Page 435
SHASHI PRABHU & ASSOCIATES
Page 436
SHASHI PRABHU & ASSOCIATES
Page 437
SHASHI PRABHU & ASSOCIATES
Page 438
SHASHI PRABHU & ASSOCIATES
up to 10 digits
32.Shall allow multiple cards, mobile access credentials or
finger print enrollment per cardholder.
33.Shall allow multiple cards per cardholder. Every card can be
assigned with 32 Access Levels
34.Upon editing card information, the updated information shall
be sent automatically to the appropriate access control
panel, when hardwired, with no other user intervention
35.Shall provide a card “Trace” function. The Trace function
shall allow normal access control, but will provide a tracking
alarm at the system monitor
36.Shall provide the ability to store digital images of cardholder
or other digital images such as property or family members
37.Integrated biometric enrollment functions shall be managed
directly inside the ACS UI without the need to use a 3rd
party software
38.Integrated assignment/managing/enrollment of mobile
access credentials shall be accomplished inside the ACS UI
without the need to external or 3rd party portals or software
39.ACS shall have a separate Alarm Monitoring screen, which
shall display alarms in real time, incoming alarms shall
display in the upper pane according to priority and time.
Once an alarm is received by Alarm monitor it should pop up
the alarm window and continuous to beep the sound until it
is acknowledged or operator can silence the beeper for 60
seconds without acknowledging the alarm, this feature can
be enabled or disabled as per requirement for every client
station
40.Shall provide color and icon shapes for each specific alarm
point action of “Alarm”, “Normal”, “Trouble”, and “Shunted”
41.Shall provide the ability to access the default floor plan
graphic for any active alarm point by a right click option
42.ACS shall have a capability to force the operator to enter an
acknowledge message while processing an alarm and it shall
be possible to print or export these reports for later analysis
if required
43.Shall provide the ability to access the default floor plan
graphic for any active alarm point by a right click option
44.ACS shall have a provision that allows acknowledge alarms
to be automatically cleared
45.Shall provide a mode of system operation that does not allow
the operator to clear an alarm before prior to it being
restored to normal
46.Floor Plan: Shall provide the ability to import floor plan
Page 439
SHASHI PRABHU & ASSOCIATES
Page 440
SHASHI PRABHU & ASSOCIATES
Page 441
SHASHI PRABHU & ASSOCIATES
Page 442
SHASHI PRABHU & ASSOCIATES
these API
Page 443
SHASHI PRABHU & ASSOCIATES
Page 444
SHASHI PRABHU & ASSOCIATES
Page 445
SHASHI PRABHU & ASSOCIATES
Page 446
SHASHI PRABHU & ASSOCIATES
Page 447
SHASHI PRABHU & ASSOCIATES
Page 448
SHASHI PRABHU & ASSOCIATES
Page 449
SHASHI PRABHU & ASSOCIATES
Page 450
SHASHI PRABHU & ASSOCIATES
Page 451
SHASHI PRABHU & ASSOCIATES
Page 452
SHASHI PRABHU & ASSOCIATES
Page 453
SHASHI PRABHU & ASSOCIATES
Page 454
SHASHI PRABHU & ASSOCIATES
Page 455
SHASHI PRABHU & ASSOCIATES
Page 456
SHASHI PRABHU & ASSOCIATES
· Option to add/edit/delete
Recorders, Cameras, Monitors,
Keyboard, Site, Workstation,
Partition and Event group.
· Associate cameras to a
recorder or switcher and map to a
site, partition or event group.
· Add monitor to a site,
partition, event group or keyboard. It
shall provide an option to add a
digital monitor and associate it with
a workstation with provision to
configure a digital monitor with a
default salvo and startup in full
screen.
· Support of bulk event
association to enable/disable and
adjust events for recorders and
inputs in bulk.
· System Macro Configuration:
Option to add/edit/delete macros.
Option to restore macros. Execute
button option to trigger selected
macros provides mechanism for
testing written macros.
Should support Audio / Video
recording.
Continuous, scheduled, manual,
event and alarm-based recording. All
modes shall be disabled and enabled
using scheduled configuration.
Different recording speeds (fps) and
resolution for each recording mode
for each camera shall be possible.
8 Recording Software Should support ANR
(Automatic Network replenishment)
Feature where camera should
Record to Camera SD card during it
gets disconnects from Storage. Once
connection is established recording
in SD card can be replenished
automatically to storage.
The Recording System, once
configured, shall run independently
Page 457
SHASHI PRABHU & ASSOCIATES
Page 458
SHASHI PRABHU & ASSOCIATES
Page 459
SHASHI PRABHU & ASSOCIATES
Page 460
SHASHI PRABHU & ASSOCIATES
Page 461
SHASHI PRABHU & ASSOCIATES
Page 462
SHASHI PRABHU & ASSOCIATES
· Maps navigation
with site / building / floorplan
hierarchy
· Easy configuration:
Drag and drop a camera on to a
floorplan
· Provision to Zoom
In or Zoom Out the map
· Camera alarm
indication and alarm status (latest
10) on map
· Analyze the alarms
and playback the associated video
· Perform PTZ and
preset actions on relevant cameras
· Instant Playback
with easy forward/reverse
enhanced with calendar selection
· Undock Popup
View: Drag freely across map to
avoid overlapping / covering other
icons and views
· Full Screen View of
Cameras to capture details of HD
video
· Enhanced password security –
non-recoverable passwords,
enforcing complex passwords,
password expiry, and no default
passwords.
· Secured firewall
configuration.
· Secured Web client – enabled
21 Cyber Security
HTTPS and TLS 1.2, and protection
from CSRF and XSS attacks.
· Restricted folder and Registry
access to operators.
· Secured Assemblies – Digital
signing.
· Secure communication with
Cameras using TLS 1.2
It shall be possible to get reports on
22 Report past events by querying the
databases.
Contractor Signature MCGM
Page 463
SHASHI PRABHU & ASSOCIATES
Page 464
SHASHI PRABHU & ASSOCIATES
Page 465
SHASHI PRABHU & ASSOCIATES
16 CE/EN, FCC, UL
Regulatory
Page 466
SHASHI PRABHU & ASSOCIATES
7.8 Client PC
Page 467
SHASHI PRABHU & ASSOCIATES
Page 468
SHASHI PRABHU & ASSOCIATES
Page 469
SHASHI PRABHU & ASSOCIATES
19 Output 84 ± 3dB
S.P.L.
20 Touch Touch feature should be seamlessly
Technology build-in the display and NO overlay is
Deployment allowed
21 Touch Advanced IR
Sensor
22 Surface Anti-Glare & Anti-Finger Print Glass
material of
touch
surface
23 Protection 3M antigalre
24 Haze 2%~5%
25 Touch
Screen Nano Pen (>3mm width) included or
Writing Finger
Tools
26 TOUCH
Response ≤4ms or better
time
27 Positioning
±1mm or better
Accuracy
28 Transmissio
5M
n Range
29 Transparenc >88% or better
y
30 Surface H7 or More than H7
Hardness
31 Glass 4 mm
thickness
32 HID Support Must have a provision to connect with
any external sources
33 Touch Must have a touch capability of
Points in MINIMUM 20 points
Windows
34 Touch Must have a touch capability of
Points in MINIMUM 10 points
Embedded
OS
35 Writing Tool Shall use with Nano Pen (>3mm width)
included or Finger
36 Scan Speed 133Hz or better
37 Communica inbuilt - USB-A type
tion
Interface
38 Requiremen For the purpose of ease access the
t of Front display must have the following ports in
Page 470
SHASHI PRABHU & ASSOCIATES
access ports the front side and must have flip cover to
with flip close when not in use
39 Minimum 1 x HDMI(1.4 , 4K@30Hz):- To connect
required with any resources
Input ports 1 x Exclusive USB1 for Touch :- To
at Front side connect with any resources and operate
of the 2 x Exclusive USB for Media Play
display function:- To directly view the contents
from USB 1x
Microphone(3.5mm):-To connect any
external microphone
40 Minimum HDMIx1(2.0,4K@60Hz) + USB for Touch
Requiremen Port 1 while using HDMI port
t of AV HDMIx2 (2.0,4K@60Hz)+ USB for Touch
Inputs at Port 2 while using HDMI port
rear side DPx1 (4K@60Hz)+ USB for Touch Port 3
while using Display port
VGAx1 (1920x1080@60Hz) + USB for
Touch Port 4 while using VGA port
41 Minimum HDMIx1(4K@60Hz)- Transmit the signal
requirement to other display with equipment with
of AV High definition
Outputs at 3.5mm Line out x 1
rear side DC Out (5V 2A) x1
SPDIF out x 1
42 Minimum USB 2.0 x2 : - To directly view the
Requiremen contents from USB
ts for other RS232 x1 :- Device Controlled by any
ports at rear third party controller
side RJ45 x1 :- Input port of Local area
network
RJ45 x1 :- Output port of Local area
network
USB 3.0 x1 :- To connect external USB
camera
OPS Slot (4K@60Hz):- To connect OPS PC
for windows function
43 Multimedia Support all major types of multi-media
File Formats files
Supported
44 GUI -The display must have GUI for ease
Graphic access of resources, functions and
User shortcuts. This GUI shall be any
Interface proprietary OS but must be computable
with Android coding.
45 Discussion Build-in white board ( seamless writing)
/ White with inbuilt browser
Board
Page 471
SHASHI PRABHU & ASSOCIATES
Page 472
SHASHI PRABHU & ASSOCIATES
Page 473
SHASHI PRABHU & ASSOCIATES
65 Total In-
48GB ( Inbuilt TF Card slot support max
built
64GB) or higher
Memeory
66 Android
8.0.0 or higher
Version
67 Android
4K
resolution
68 Working
AC 100-240V, 50/60Hz
Voltage
69 Power
Consumptio Maximum ≤450W Standby Mode ≤0.5W
n
70 Storage
-15℃~55℃/20~90%RH(Non
Temperatur
coagulation)
e/Humidity
71 Working
Temperatur 0℃-40℃/20~80%RH(Non coagulation)
e/Humidity
72 Mounting Display must have facility to mount on
Capabilities floor stand or wall brackets
73 Self Must self shutdown during abnormal
shutdown temperature
74 Inbuilt Soft The touch interactive display must have
features inbuilt onboard writing software. Thus,
this software shall has the capability to
write some thing on the display and store
in on-board system even WITHOUT any
PC/Laptop/External device
75 The display must have the facility of send
the written contents by mail, take
printout and transfer to pen drive as well
76 This software which is embedded in the
On-Board system shall have capability to
write(Annotate) on top the contents that
are shown from Pen drive direct /
External PC / Any such sources
77 External Touch interactive display shall also be
software supplied with specialised software which
shall be installed in PC/Laptop. This
software should have features of different
writing capabilities like Pen, Highlighter,
laser pen, geometric pen, text pen and so
on. The software shall also have features
of Screen record, screen capture, import
files, export files and saving the content
in different versions and so on.
78 Inbuilt The touch interactive diplay mush have
Internet inbuilt WiFi (2.4G/5G). So that the
access presenter shall visit the internet to
Contractor Signature MCGM
Page 474
SHASHI PRABHU & ASSOCIATES
Sr. Compliance
Description
No.
Device system should be standard based with separate camera system
1. and HD audio video Interfaces with all required Cables and
Accessories.
Device Should support 30 fps & 60fps (frames per second) with
2.
1080p resolution from day one.
Device Should have Ability to send and receive two live simultaneous
3. video sources in a single call, so that the image from the main camera
and PC or document camera can be seen simultaneously.
4. Device Should support H.239 and BFCP protocols
Device must have the ability to pair mobile devices such as Tablet and
Smartphones based on iOS or Android platforms so that these devices
can be used for:
5.
1) View the Presentation that is being shown in the VC call.
2) Add and disconnect call.
3) Take snapshot of the Presentation being shown
Device must have the ability to pair with laptop for sending content
without any wires to the VC system. In case this feature is not
6.
available natively, then additional components can be provided to
achieve this.
Device Should have at least One FHD video Input to in the form of
7. HDMI/HDCI/3G SDI to connect FDH cameras with full functionalities
as mentioned in the camera specifications.
Device Should have Should have HDMI/DVI (Digital Video Interface)
input to connect PC / Laptop directly to the Video conferencing system
and display resolutions 1080P/HD 720P along with PC Audio
Device Must have 2 HDMI inputs support formats up to maximum
8.
UHD (3840 x 2160) at 30 fps, including HD1080p60.
Device Should support the ability to view and share presentations at
9.
a resolution of 3840 × 2160 (4K)
Device must have the ability to pair with laptop for sending content
10.
without any wires to the VC system
Device Should have at least 2 no.'s of HDMI output to connect Full
11. High Definition display devices such as plasma and projectors for both
Video and Content.(Dual Monitor Support)
12. Device should support Call Swapping.
Page 475
SHASHI PRABHU & ASSOCIATES
Page 476
SHASHI PRABHU & ASSOCIATES
Sr. Compliance
Description
No.
Page 477
SHASHI PRABHU & ASSOCIATES
Proposed Solution should have Video IVR with visual cues for a more
7.
intuitive join experience.
Desktop, Mobile and Browser Apps --
Click-to-join from invitations.
Enter meeting number for ad-hoc join.
8.
Use your computer or a telephone for audio.
Or, have the cloud call your SIP based video system for full audio,
video, content share experience.
Proposed Solution should have following features In-meeting controls
using Dual-Tone Multi-Frequency (DTMF) controls, Mute and unmute
self , Mute and unmute all (host), Lock/unlock meeting (host), Record
meeting (host), Change own video layout,
SIP video systems require at least one of the following capabilities:
RFC 2833 RTP Payload Type, In-band DTMF audio tones, Key Press
9. Markup Language (KPML),
H.323 video systems require at least one of the following capabilities:
H.245 User Input Indicator, RFC 2833 RTP Payload Type, In-band
DTMF audio tones, Users on video systems that cannot negotiate
DTMF will only be able to join a meeting after the host starts it
Recording status indicator
Audio line mute state change prompts.
Proposed Solution should have Desktop, Mobile and Browser
Applications with Following features - Full participant list, Recording
status indicator, Meeting lock status indicator, Mute/unmute audio of
10.
participants (host), Expel participant from meeting (host),
Lock/unlock meeting (host), Record meeting (host), Transfer host role
to another participant (host).
Proposed Solution should support Min. Main video at up to 720p at
11. 30 frames per second (fps), Content sharing up to 1920x1200 at 3 fps,
Video Aspect Ratios - 16:9 widescreen, 4:3 standard.
Proposed Solution should support Video Codec - H.261, H.263,
12. H.263+, H.264 AVC, H.263 (CIF) or H.264 UC (720p/30) for Skype for
Business and Lync clients.
Proposed Solution should support Audio for Video Systems - G.711
13. (m-law and a-law), MPEG-4 AAC-LD, Opus, G.722, G.728, G.722.1,
G.729 (with and without Annex B), MPEG-4 AAC-LC (TIP calls only).
Proposed Solution should support Audio Codec for Applications –
14.
Opus, Internet Low Bitrate Codec (iLBC), G.722.
Proposed Solution should support Audio Access Methods for
Applications - Call-in (dial into the meeting), Call-back (meeting calls
15.
you) and video call-back, VoIP (use your computer microphone and
speakers or your smartphone data connection).
Proposed Solution should support Advanced Encryption Standard
(AES) 128-bit encryption, Signaling protocol support: SIP, SIP
16. Transport Layer Security (TLSv1.2), Binary Floor Control Protocol
(BFCP), Content share (dual video) protocol support: BFCP for SIP
Video Systems.
Proposed Solution should support ITU-T H.323 standards-based
17.
video systems, AES 128-bit encryption, Signaling protocol support:
Contractor Signature MCGM
Page 478
SHASHI PRABHU & ASSOCIATES
Page 479
SHASHI PRABHU & ASSOCIATES
SENSITIVITY
7 DFMD should have multi-zone capability with uniform sensitivity in all
zones
ZONES: -
8 Not less than eight real horizontal detection zones, covering full height of
the
equipment
9 CALIBRATION: -
DFMD shall have inbuilt feature of both manual and automatic calibration
SECURITY: -
i) There should be provision to secure the access to the control unit
10 by a password protected alpha numeric keypad
ii) DFMD should reset itself within 3 sec after alarm condition
iii) Unit should have traffic and alarm counter. The equipment
should work in bidirectional mode
OTHER FEATURES: -
11 i) High discrimination between small masses and personal metallic objects
ii) Automatic synchronization for DFMDs located close to each
other up to a distance of one feet side by side
STATIC METAL COMPENSATION: -
DFMD installed closed to fixed sheet or pieces of metal which form part of
12 the building or its fittings. The DFMD should compensate for the presence
of such metal and its performance should not be degraded by the presence
of metal as stated
above
HEALTH AND SAFETY: -
i) Magnetic field should be harmless to magnetic media,
electronic devices and should be film safe, (Supplier shall submit
test certificates from national / international accredited lab)
13 ii) Operation of DFMD shall not be affected by infrared, ultraviolet,
electromagnetic or RF radiation. Offered equipment shall comply
with CE or equivalent safety/ immunity standard (Supplier shall
submit test certificates from national / international accredited
lab)
iii) DFMD should be harmless to pacemaker and pregnant woman
(Supplier shall submit test certificates from national /
international accredited lab as per ICNIRP
guidelines)
INTERFERENCE REJECTION: -
i) Interference, which is ‘mains-borne’ or radiated by an external
source, should not cause the DFMD to raise the alarm spuriously. It
14 should be possible to use equipment such as radio, portable
telephone, walkie-talkie sets, X-ray monitors etc. at a distance of
Page 480
SHASHI PRABHU & ASSOCIATES
S. No.
Parameter Specifications
1 Dimensions
Length Maximum 500mm
Probe Maximum 120mm
width
Body width Maximum 65mm
2 Weight Maximum 500gms
3 Power source Alkaline battery 3 volt (1.5x2) volt, should run
minimum 550 hrs on 10% detection rate
4 Battery To be provided against damage due to reverse
protection polarity
a) Single LED based audio and visual multiple
5 Indication indication for-
i. SWITCH ON
ii. METAL DETECTION
iii. LOW BATTERY INDICATION
6 Operation Single push button operation
Page 481
SHASHI PRABHU & ASSOCIATES
Page 482
SHASHI PRABHU & ASSOCIATES
2.18. Video display – 17’’ or better LCD Monitor SVGA High resolution, low
radiation, flicker free, resolution at least 1280 x 1024, 24-bit colour real time
processing.
2.19. The machine should have features of Multi-energy X-ray imaging facility where
materials of different atomic numbers will be displayed in different colours to
distinguish between organic and inorganic materials. With this method to distinguish
high density organic materials including explosives. Machine should have variable
colour or materials stripping to facilitate the operator to monitor images of organic
materials for closure scrutiny. All suspicious items (Explosives, High density, material
narcotics) should be displayed in one mode and that should be online.
2.20. Radiation safety: - The machine must comply with requirements of health and
safety regulations with regard to mechanical electrical and radiation hazards. Before
installation of the machine, the supplier/ manufacturer should furnish relevant
certificate from Atomic Energy Regulatory Board of India regarding radiation safety.
The company manufacturing the equipment should have ISO certification for
manufacturing and servicing of X-Ray Screening machines.
2.21. Film Safety: - Guaranteed safety for high-speed films upto ISO1600. The
machines should be film safe. In other works, photographic films must not be
damaged due to x-ray examination.
2.22. Machine should be properly sealed from all sides for pest proof. Dust proof cover
is to be provided for covering when system is not in use.
2.23. Facility of variable contrast must be incorporated to allow enhancement of
lighter and darker portion of the image.
2.24. The machine should be so designed that the software enhancement can be easily
implemented to take care of new technique in image processing and pattern
recognition.
2.25. Full diagnostic built in test facility. All models should have software controlled
diagnosis report facility and system should give printout if printer is connected
2.26. All software features of the machine should be online and password protected.
2.27. Machine should be capable of recalling 15 or more previous images
2.28. It should have the capability of archiving 2000 or more images with date & time
stamp.
2.29. Control desk with security housing and locking provision should be available.
The operator
personal identification number can be entered the keyboard along with generation of
log.
2.30. Facility of image enhancement should be available
2.31. All models should have online recording facility and images can be recorded in
CD R/W or/and USB and should be able to view images so recorded on stand-alone
PC.
2.32. Lead impregnated safety screen should be available at either ends of the tunnel.
This should be covered by relevant AERB certificate. Idle rollers to be provided at
either ends of the tunnel to facilitate the placing of baggage at input and output
2.33. All software features should be controlled from key board of machine only.
Keyboard function should be user friendly. To enable/ disable the software features
system should not be rebooted.
2.34. If the machine fails to penetrate a particular item then an alarm video and audio
both should be generated to notify the operator.
Page 483
SHASHI PRABHU & ASSOCIATES
2.35. The threat Image projection (TIP) system software to be incorporated in all X-ray
BIS operation as
per details given in Cl No 4.
2.36. Copy of all software including X-Ray Software with recovery CD must be
provided.
2.37. Operational Training- Operating staff has to be provided free training.
2.38. Operating & service manual shall be provided with each machine.
2.39. Other Features:
a) Edge & variable edge enhancement
b) Inverse Video
c) Set up time not more that 10 minutes
d) Pseudo colour
e) Date & Time Display
2.40. Minimum Computer configuration:
a) CPU: Should be able to deliver the output to meet the specifications
mentioned as above.
b) Hard Disk Drive: 320 GB 7200 rpm serial ATA HDD or Better
c) Mouse: Optical
d) Ports: 6 USB Ports (with at least 2 in Front, 1 serial Port, 1 Parallel port, 1
PS/2 Keyboard and 1PS2 Mouse Port, audio ports for microphone and
headphone in front
e) CD R/RW Drive: DVD Writer
f) Networking Facility: 10/100/1000 on board integrated Network port with
remote booting facility, remote system installation, remote wakeup, out of band
management using any standard management software
2.41. UPS: 3 KVA online with backup time of 30 minutes.
Page 484
SHASHI PRABHU & ASSOCIATES
Page 485