1-Hydrostatic Test Procedure
1-Hydrostatic Test Procedure
2018
PROCEDURE Revision : 0
Page : 1/2
1. PURPOSE
The purpose of this procedure is provide a guideline to carry out the hydrostatic test to
check soundness of welds of the equipment.
Water that is used in test, test pump, blind flanges, pressure indicator.
The test scheme shall have suitable connections, necessary valve and calibrated pressure
gauge.
3. REFERENCE CODE
EN 13445-5
EN 14015
API 650
AD 2000-Merkblatt HP 30
4. PERSONAL
The personnel shall be competent and have thorough knowledge in performing this method
5. PROCEDURE
If test will done under pressure; pressure test operation is done as the procedure written below.
The problems which are seen during operation are proceeded as article “7th Reaction Plan”.
• Water quality and the percentage of the salt are detected and those are controlled whether is
harmful or not for the material.
• During test, necessary precautions are taken for the equipment that can be deformed. If it is
necessary, special case is prepared under the equipment.
• To take in and out the water, necessary valves should be assembled. To take in the air which
is stored on the top of the equipment a ½” spherical valve should be assembled.
• After the air is taken out, as the top valve is closed, the equipment is controlled by sight and if
there is any leakage, it should be repaired.
• If the above situation is happened, the manager of the production is informed about the
situation and test continues with the control of the manager of the production
• The pressure is adjusted as the document. The duration of the test should have min 1 hour.
HYDROSTATIC TEST Date : 15.05.2018
PROCEDURE Revision : 0
Page : 2/2
• The pressure change is checked in every 10 minutes, if any pressure change is not detected
on the manometers, this means the pressure test is accomplished.
If test will done with unpressured water; test operation is done as the procedure written
below. The problems which are seen during operation are proceeded as article “7th Reaction
Plan”.
• Water quality and the percentage of the salt are detected and those are controlled whether is
harmful or not for the material.
• During test, necessary precautions are taken for the equipment that can be deformed. If it is
necessary, special case is prepared under the equipment.
• The equipment is controlled by sight and if there is any leakage, it should be repaired
• If the above situation is happened, the manager of the production is informed about the
situation and test continues with the control of the manager of the production
Testing is made done according to project ITP which refers to EN 13445-5, EN 14015, API 650,
ASME SEC VIII, AD 2000-Merkblatt HP 30 standards.
6. CONTROL
Control written below is applied by the operator who is done the pressure test operation.
If any problem is detected after the control, as the article “7th Reaction plan” written in
instruction is proceeded.
Welded Part Eye Control: All the weld seams are controlled by sight and it is checked for if
there is any problem such as leakage.
7. REACTION PLAN
If test will done under pressure; during pressure test, if any leakage or deformation is detected,
the test is immediately stopped and the pressure is dropped by the operator.
Manager of the production is informed about the situation.
If test will done with unpressured water; during test, if any leakage or deformation is detected,
the test is immediately stopped and water is drained.
Manager of the production is informed about the situation.
HYDROSTATIC TEST Date : 15.05.2018
PROCEDURE Revision : 0
Page : 3/2
8. INSPECTION REPORT
9. ACCEPTANCE CRITERIA
The area under test is acceptable when no leaking and no deformation is observed.