Q3510-00-SCIFCMI-45000013161317-Z-Z01-0018 Rev0 - Code C
Q3510-00-SCIFCMI-45000013161317-Z-Z01-0018 Rev0 - Code C
P.O. No.
GRADE DATE CHK APPD
A. APPROVED WITHOUT COMMENTS.
HSE:
- The risk assessment is not appropriate (risks are B.
REVISE AND RESUBMIT, WORK MAY PROCEED, SUBJECT TO
INCORPORATION OF CHANGES INDICATED.
not evaluated separately – list of risk with a list of REJECTED, TO BE REVISED AND RESUBMITED, WORK MAY
M.A / B.B
C. 03/02/2022 S.S / I.R /
control measures) NOT PROCEED.
N. F
O.M
- Lack of information regarding all scrubber "PERMISSION TO PROCEED DOES NOT CONSTITUTE ACCEPTANCE OF DESIGN DETAILS, CALCULATIONS, ANALYSIS, TEST METHODS
OR MATERIALS DEVELOPED OR SELECTED BY THE VENDOR/ CONTRACTOR, DOES NOT RELIEVE THE VENDOR/ CONTRACTOR FROM
equipment FULL COMPLIANCE WITH CONTRACTUAL OBLIGATIONS"
10
27/12/2021 Work Method Statement for Equipment (Scrubber Area 107DEF) S.HAMADANI M.SERNOU I.JAOUAD 0
REQUISITION REFERENCE :
Q3510-00-SCIFCMI-4500001316/1317-Z-Z01-0018
HELP
JESA DOCUMENT NUMBERING SYSTEM Project Nbre Code of Sub-Project Sender Code PO Discipline Code Doc Type Number Order / Rev
Please Refer to Annex Q, L & DC
Procedure . Shall you need help to fill-in
this cover page, please contact JESA
Example (Trigram is unique to each contractor) Q3510 00 SCIFCMI 4500001316/1317 Z Z01 18 00
Equipment Scrubber Area 107DEF
DOC. NO.:
TOTAL 14 S H E E T S (INCL. COVER)
WORK METHOD STATEMENT
Summary
I. Object: .......................................................................................................................................... 3
II. Resources: ................................................................................................................................... 3
a) Human resources: ................................................................................................... 3
b) Material resources: .................................................................................................. 3
III. Reference documents .................................................................................................................. 4
IV. Site Organization chart. ............................................................................................................... 5
VI. Sequences of pre-assembly and assembly. ................................................................................ 7
Seq 0: On-site transport and storage ................................................................................................... 7
Seq 1:Topographical Control ............................................................................................................... 7
Seq 2: Installation of equipment Tail Gas Scrubber Vaporizer AE05 ................................................... 8
VII. Scrubber building equipment location El 100.000:..................................................................... 9
VIII. Scrubber building equipment location El 103.410:................................................................... 10
IX. Scrubber building equipment location El 106.550.................................................................... 11
X. Scrubber building equipment location El 112.180.................................................................... 12
XI. Scrubber building equipment location El 115.600.................................................................... 13
XII. Scrubber building equipment location El 122.260.................................................................... 14
XIII. Annexes. ................................................................................................................................. 15
WORK METHOD STATEMENT
I. Object:
This document named as general method statement will describe the philosophy and the steps that the
Contractor will follow as part of the contract “NEW DAP PROJECT MECHANICAL CONSTRUCTION
of ISBL” with CONTRACT N° JESA-4500001316 / 4500001317-2020.
This general work method statement will describe the major points of the erection, control and preservation
of the elements of the scope that has been assigned to the Contractor, while respecting all the HSE, Quality
and erection procedure according to the industry good practices. This method statement will be a gathering of
many procedures that the Contractor will follow from the material reception, passing by the erection work,
then controls and acceptance until reaching the period of the pre-commissioning of each system. The
mechanical reception of each lot will be done in order to allow the commissioning to take place.
In the following, this document will give a brief overview about the scope of work of the contractor, state the
references and documents used in order to prepare this general work method statement, project management
organization and responsibilities, the procedure of communication between the Contractor and the client, the
temporary site facilities and utilities and the work procedures without letting of site the quality and HSE
procedure that will accompany the work all along the project.
II. Resources:
a) Human Resources:
The pre-assembly and assembly work will be carried out by teams composed of:
• Site manager
• Technician preparer
• Topographic surveyor
• Team leader
• HSE animator
• Boilermakers
• Welders
• Helps
• Quality controller
WORK METHOD STATEMENT
b) Human Material:
According to this statement method, the material resources to complete the work:
In Order to prepare this granulator method statement, we used the following documents as references:
• Annexes:
▪ Annexe A
▪ Annexe B
▪ Annexe G
▪ Annexe X
▪ Annexe Z
S. MEKKAOUI
P.M.
J. FARKOUCH Z. TIANE Y.
I. JAOUAD A. ABBAD
ELKHALOUKI
HSE Manager QA/QC Manager Lead P.E. P.C.M. Admin
Y. H.
H. BENOUFIR D. WAHID
MOHAMMADI ELMAJNAOUI
Field Engineer Material Manager Scheduler D.C.C.
M. SERNOU
C.M.
Work
Foremen
preparators
o Ensure workers assigned to projects are qualified and competent for their own trade.
o Ensure that all necessary preparation is done prior to the commencement of the work.
o Follow-up of construction progress.
o Set-up construction dashboard.
Mechanical Engineer:
Construction Manager:
Quality Manager:
Rigging Supervisor:
o Rigging supervisor works to coordinate, supervise, and operate machinery such as a crane. Your
duties in this career include working to inspect machinery and erect rigging equipment and cables.
Your responsibilities focus on supervising the riggers and other specialists. You ensure the crew
follows correct safety procedures while they lift, hoist, or install equipment or materials. You may
also be responsible for the budget and the schedule for each project. At various points throughout
the day or project, you must report activities and progress to project supervisors.
1. Example of sequence of assembly works for equipment Tail Gas Scrubber Vaporizer AE05.
o Grouting.
WORK METHOD STATEMENT
o All mechanical equipment must be mounted according to the plans provided by JESA (updated
revision), and according to the logical sequences of the mounting.
o Gear must be placed according to access and site clutter.
o In the first step we will start to install the steel structure Level1 using a mobile crane depending on
the weight and current condition on site.
o In the second step we will start to install the mechanical equipment mentioned int the location plan
below.
o During handling, two nacelles must be used for assembly work.
WORK METHOD STATEMENT
o All mechanical equipment must be mounted according to the plans provided by JESA (updated
revision), and according to the logical sequences of the mounting.
o Gear must be placed according to access and site clutter.
o In the first step we will start to install the steel structure Level 3 using a mobile crane depending on
the weight and current condition on site.
o In the second step we will start to install the mechanical equipment mentioned int the location plan
below.
o During handling, two nacelles must be used for assembly work.
o All mechanical equipment must be mounted according to the plans provided by JESA (updated
revision), and according to the logical sequences of the mounting.
o Gear must be placed according to access and site clutter.
o In the first step we will start to install the steel structure Level 4 using a mobile crane depending on
the weight and current condition on site.
o In the second step we will start to install the mechanical equipment mentioned int the location plan
below.
o During handling, two nacelles must be used for assembly work.
WORK METHOD STATEMENT
The scope of work of Contractor 1 is only to install the equipment listed above, apart from the chimney
that we have to install and weld the parts of the following equipment:
Following the contract, the Tail Gaz will be delivered on 12 parts and the stack on 2 parts. Depending on
the time of delivery and cranes availability, we have two options:
- Option 1: Erect and weld the 12 parts of tail gaz then apply rubber lining while assembling the 2
parts of the Stack and rubber lining it at the floor then erect. See example of lifting plan on the
annexes below.
- Option 2: Erect and weld the 12 parts of tail gaz then erect and weld the 2 parts of the Stack. After
that, apply rubber lining of the Stack and rubber lining it then erect.
After we have more visibility about the above-mentioned inputs and fabrication drawing, a detailed WMS
of the Tail Gaz and Stack will be established and shared with JESA.
WORK METHOD STATEMENT
ANNEXES
WORK METHOD STATEMENT
Version :00
Date of application:
Page : 1/14
Residual
Significant Initial Risk Control Measures
Who or what? Risk
S/N Hazards and
Is at risk Risk Risk
Environmental Aspects S L R S L R
Level Level
Version :00
Date of application:
Page : 2/14
Version :00
Date of application:
Page : 3/14
Only 8 people (in turn) are authorized to use the open air canteen for lunch
while respecting the safety distance and standards of cleanliness and hygiene
The rest area will be disinfected before and after each use
Wash hands with soap and water before eating
Take news only from official sources
Call the SCIF doctor for help
Minimum distance of 2 m. will be respected between workers.
When communicating, use the phones or V.C as much as possible even if your
colleague is close to you.
Each workshop employee will receive their own toolbox
Each workshop employee must have their own toolbox and must be disinfected
before starting work and after finishing work
5 5 25 H We have limited the number of people on 20-seat buses to 8 people only, sitting
5 2 10 M
in a zigzag pattern.
The same buses will be used during this pandemic
The same nozzle drivers will be fixed, no change of driver or bus is allowed
On buses, sit in the same seat every day
Covid 19 coordinator must organize twice per shift visually check to employees
If you feel unwell, stay at home, isolate yourself and ask for help by phone from
the doctor.
If you have high body temperature, cough and body pain, isolate yourself and
call 141 or 08001004747
Phone application WIQAYTNA to be unloaded by all the employees
Code :
Version :00
Date of application:
Page : 4/14
Version :00
Date of application:
Page : 5/14
Version :00
Date of application:
Page : 6/14
Version :00
Date of application:
Page : 7/14
Version :00
Date of application:
Page : 8/14
Version :00
Date of application:
Page : 9/14
Version :00
Date of application:
Page : 10/14
Version :00
Date of application:
Page : 11/14
Version :00
Date of application:
Page : 12/14
Severity (S) Values: 1-5 Likelihood (L) Values: 1-5 Risk (R) = S x L
Risk Level: 1 – 4 = Low (L) 5 – 12 = Medium (M) 15 – 25: High (H)
Note: Use the HSE Risk Assessment Matrix (RAM) when determining the values of S and L
Code :
Version :00
Date of application:
Page : 13/14
LIKELIHOOD
CONSEQUENCE
1 2 3 4 5
Never heard
SEVERITY
Heard of in
of in Incident has Happens several Happens several
industry/
industry/ occurred in times per year in times per year in a
company
PEOPLE ASSETS ENVIRONMENT company industry/ company industry/ company location
Activity is
Activity is Activity is taking Activity is taking Activity is taking
taking place
taking place place frequently place regularly place continuously
occasionally
rarely
Property damage
Medical Treatment Causes minor damage, can be
2 between $5,000 2 (L) 4 (L) 6 (M) 8 (M) 10 (M)
Case rectified with minor resources
and $100,000
Version :00
Date of application:
Page : 14/14
Multiply the severity (1‐5) by the likelihood (1‐5) to ascertain the risk level.
Resulting action is detailed in table below.
1‐4 Record hazard, record risk ratings, recommend upgrades to risk control measures if the risk rating is not as low as
(Low) reasonably practicable
5‐12 Record hazard, record risk ratings, record the recommended risk control measure needed to reduce the risk rating
(Medium) below 4 or as low as reasonably practicable
15 – 25 Stop the activity immediately and seek further advice to reduce the risk rating below 4 or as low as reasonably
(High) practicable.