Checklist of Requirements For Building Permit (Revised)
Checklist of Requirements For Building Permit (Revised)
2. Fire Department FSEC Application Form to be filled up at BFP Office Filled up at BFP Office
Clearance/ Endorsement from OBO (signed Application for building Permit) None
Fire Safety Evaluation Bill of Materials with LABOR COSTS
Clearance (FSEC) > must BE SIGNED & SEALED by the Engineer None and needs sign & seal
> 2 Original copies and 1 photocopy
Specifications (Detailed General or Technical)
> must BE SIGNED & SEALED by the Engineer Done but needs sign & seal
> 1 original copy
Sets of Plans – minimun of 4 sets (1 set original) Done but needs sign & seal
Photocopies of PRC ID
> Civil
> Architect None
> Electrical
> Plumber
> Mechanical
Building Owner’s Valid ID – 1 photocopy
*For Authorized Representative:
> 1 Authorization Letter/SPA/Secretary Certificate with General Information Sheet
(GIS) page 4
> 1 photocopy of Authorized Person’s ID
3. Application Forms & Bldg. Permit Application Form (5 copies) Get from OBO
Plans Electrical Permit Application Form (5 copies) Get from OBO
Plumbing Permit Application Form (5 copies) Get from OBO
Mechanical Permit Application Form (5 copies) Get from OBO
Electronics Permit Application Form (5 copies) Get from OBO
Set of Plans (5 sets)
a. Electrical Plans and specifications
b. Telecommunications plan (Electronics) Done but need to be signed and sealed by specific
c. Mechanical Plan engineers with attachment of updated PTR and PRC ID of
d. Construction Specifications (6 copies) signatory
e. Structural Analysis
f. Plumbing