This document provides a cost estimate for a garage extension project. It lists 6 items of work required including earthworks, masonry works, steel works, painting works, and tinsmithry works. For each item, it specifies the materials and labor quantities in units like bags, pieces, and square meters. It calculates the unit price and total price for both materials and labor for each item. The total estimated cost for materials is 53,751, labor is 20,077.40, with a profit of 7,382.84, for a grand total estimated project cost of 81,211.24.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
29 views1 page

Extension Garage

This document provides a cost estimate for a garage extension project. It lists 6 items of work required including earthworks, masonry works, steel works, painting works, and tinsmithry works. For each item, it specifies the materials and labor quantities in units like bags, pieces, and square meters. It calculates the unit price and total price for both materials and labor for each item. The total estimated cost for materials is 53,751, labor is 20,077.40, with a profit of 7,382.84, for a grand total estimated project cost of 81,211.24.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 1

PROJECT: GARAGE EXTENSION OF TWO STOREY BUILDING

LOCATION:

UNIT PRICE TOTAL PRICE


ITEM NO. PARTICULARS QTY UNIT TOTAL ITEM PRICE
MATERIALS LABOR MATERIALS LABOR
1 GENERAL REQUIREMENTS
MOBILIZATION 1 LOT 1000 0 1000 1000

2 EARTHWORKS
EXCAVATION AND BACKFILL 1 LOT 1500 0 1500 1500

3 MASONRY WORKS
CHB LAYING
CHB 5" 244 PCS 14 5.6 3416 1366.4 4782.4
CEMENT 19 BAGS 250 100 4750 1900 6650
SAND 1.8 CU.M 1900 760 3420 1368 4788
10MM DIA DEFORMED BAR 17 PCS 155 62 2635 1054 3689
GI TIE WIRE NO.16 10 KGS 90 36 900 360 1260
PLASTERING
CEMENT 12 BAGS 250 100 3000 1200 4200
SAND 1.2 CU.M 1900 760 2280 912 3192

4 STEEL WORKS
TUBULAR 2"X4"X1.2MM 9 PCS 750 375 6750 3375 10125
WELDING ROD 7 KGS 100 50 700 350 1050
CONSUMABLES(HINGES, BODY FILLER ETC.) 1 LOT 3000 1500 3000 1500 4500

5 PAINTING WORKS 1 LOT 12420 12420 0 12420

6 TINSMITHRY WORKS
0.5MM GI RIBTYPE ROOFING 15 SQM 450 180 6750 2700 9450
PLAINSHEET 2 rolls 700 280 1400 560 1960
TUBULAR 2x2x1.2MM 3 PCS 550 220 1650 660 2310
STAINLESS GUTTER 1 PCS 680 272 680 272 952

TOTAL MATERIALS PRICE: 53751


TOTAL LABOR PRICE: 20077.4
PROFIT: 7382.84

GRAND TOTAL: 81211.24