02.11.2022 Syb-07 Dor

The document reports on maintenance work performed on valves at the PGB GTR Dengkil Station, including leak testing, flushing, sealing, and grease fitting replacement on valves tagged ML209-1 through ML209-4. Crew members Ahmad Khairu Awang and Zulhelmiie Sabri used pumps and hand tools to service the valves from 08:30 to 19:00, addressing issues like leaks and replacing vent caps on the grease fittings.

Uploaded by

Mohd Shahir
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
38 views

02.11.2022 Syb-07 Dor

The document reports on maintenance work performed on valves at the PGB GTR Dengkil Station, including leak testing, flushing, sealing, and grease fitting replacement on valves tagged ML209-1 through ML209-4. Crew members Ahmad Khairu Awang and Zulhelmiie Sabri used pumps and hand tools to service the valves from 08:30 to 19:00, addressing issues like leaks and replacing vent caps on the grease fittings.

Uploaded by

Mohd Shahir
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 2

ESSEM CORPORATION SDN BHD

(ROC No: 126457-T)

DAILY SITE WORK REPORT


`

CLIENT : PETRONAS GAS BERHAD (PGB) JOB NO : EPBPM07160279


JOB DESCRIPTION : TO RECTIFY VALVE JAMMED AT ML404. LOCATION : PGB GTR, DENGKIL STATION
: TO PERFORM SEALING ACTIVITY OF PASSING VALVE AT ML260 & ML209A. (ML209/MLL209)
: TO PERFORM GREASE FITTING CHANGE OUT AT ML404, ML209A, ML210, ML404. TOTAL VALVE : -
i)
WORK DATE : 21.05.2017 EQUIPMENT : TYPE OF SERVICES :
WELLH
CREW : : AHMAD KHAIRU AWANG (TEAM LEADER) EAD :
1. 1 UNIT PUMP ESS751 (ESS/751/3002) + 10 MTR HOSE i) WELLHEAD : PREVENTIVE MAINTENANCE (PM)
CORRE
: ZULHELMIE SABRI (ENGINEER) 2. 1 UNIT PUMP ESSFM2 (ESS/FM2/3002) + 10 MTR HOSE : CORRECTIVE MAINTENANCE (CM)
CTIVE
3. 1 UNIT HAND TOOLBOX ii) PIPELINE
MAINTE : PREVENTIVE MAINTENANCE (PM)
NANCE : CORRECTIVE MAINTENANCE (CM)
TAG NO. MLL 209 : VL-209-1, 209-2, 209-3, 209-4 PRODUCT : (CM)
START DATE : 09.08.2016
1. 9 PAILS VALVE FLUSHING (VF)
MODEL SERCK AUDCO 2. 12 PAILS VALVE LUBRICANT (VL)
3. 2 PAILS VALVE REPAIR SEALANT (VRS) NO. OF DAY : 01
SCOPE OF WORK 1. PERFORM LEAK TEST, FUNCTIONAL TEST, FLUSHING, GREASING AND SEALING.
2. PERFORM CHANGE OUT GREASE FITTING.
3. PERFORM GEARBOX SERVICING.
TIME
ACTIVITY
START END
0830 Arrived at SARO for PTW application and pre-job discussion with PIC.
1000 PTW approved and mobilize to working station ML209.
1015 1100 Arrived at ML209 - Block Valve Station Dengkil.
1115 1145 Transferring equipment from vehicle to work site.
1200 1215 Conducted toolbox meeting among crew to brief on JHA, job scopes and safety precaution before start the maintenance job.
1230 Performed visual inspection and record condition and initial position all valves.
Performed visual inspection at site to ensure safe to start work.
1245 Received permission to utilize pipeline gas as source to operate pumps. Pipeline pressure is 350 bar (5,076psi).
1245 Setup pump ESS751 and ESSFM2 and performed function test. Both pumps found working in good condition.
Isolate by close the power gas valves connected to the valve before start the job.
1300 Start the valve maintenance job at MLL209. Record the valve details for reference.
1315 Conducted leak test for MLL209 (3pcs Plug Valve) start with Upstream, Downstream and Bypass and monitor for 15mins. No test at Blowdwon due to no available point for monitoring.
Found Upstream valve passing 10 psi per min while Downstream passing 10 psi per min. Bypass valve is holding 0 psi per min.
Started the flushing job for the valve. Connected flushing hose from ESSFM2 pump into grease fitting valve.
Secured the connection by installing whip check.
Open the inlet valve, regulate the incoming pressure to operate the pump.
Completed flushing Upstream, Downstream, Bypass and Blowdown valve.
Continue with injected sealant at Upstream and Downstream valve and lubricant for Bypass and Blowdown.
Disconnected flush hose and connect the grease hose to valves. Pressurize pump ESS751 by regulate the incoming pressure.
1530 Started the sealing job at Upstream and Downstream. Continue with greasing job at Bypass and Blowdown valve.
1530 1600 Break for Lunch
1615 Performed leak test after injected sealant at Upstream and Downstream.
Found Upstream and Downstream valve holding.
Start change out grease fittings for all valve at MLL209.
Completed replace grease fittings with vent cap type.
Unable to perform gearbox servicing due to different type of gearbox at MLL209.
Start flushing job at ML209 for all valves.
1900 Stop work due to time constraint.
Cross checked all the valves and pipeline condition. Return all valves into intial position.
1900 1930 Performed housekeeping before close the job for today. Separate the chemical waste and secure in the allocated bin.

Summary :

Grease
No Valve Size Tag No. Brand Rating Activity Before After Product Open Close Note
Fitting
Leak Test 5 psi/min - - VF = 2 liter
Flushing - - VF Replaced VRS = 8 lbs
1 Upstream 12 VL-209-1 Audco 600 16 16 to Vent
Sealing - - VRS Cap type GF : 1/4" Vent Cap type.
Leak Test - 0 psi/min -

Leak Test 0 psi/min - - VF = 2 liter


Flushing - - VF Replaced VRS = 8 lbs
2 Downstream 12 VL-209-2 Audco 600 16 16 to Vent
Sealing - - VRS Cap type GF : 1/4" Vent Cap type.
Leak Test - 0 psi/min -

Leak Test 0 psi/min - - Replaced VF = 2 liter


3 Bypass 12 VL-209-3 Audco 600 Flushing - - VF 16 16 to Vent VL = 6 lbs
Greasing - - VL Cap type GF : 1/4" Vent Cap type.

Flushing - - VF Replaced VF = 2 liter


4 Blowdown 12 VL-209-4 Audco 600 Greasing - - VL 16 16 to Vent VL = 6 lbs
Cap type GF : 1/4" Vent Cap type.

PLAN FOR 1. CONTINUE VALVE MAINTENANCE AT ML209.


JOB STATUS ON GOING
TOMORROW 2. CONTINUE VALVE MAINTENANCE AT KICKER VALVE
1. ALL PRESSURE HOSE CONNECTION SECURED BY INSTALLING WHIP CHECK.
ACT / BOT
2. TOOLBOX MEETING CONDUCTED AMONG CREW BEFORE START ANY JOB.
ESSEM CLIENT
PREPARED BY : VERIFIED BY :
NAME : AHMAD KHAIRU AWANG NAME : M ZAHIN AKMAL A GHANI

SIGNATURE : SIGNATURE :

DESIGNATION : TEAM LEADER DESIGNATION : PGB GTR REP.


DATE : 09.08.2016 DATE : 09.08.2016
ESSEM CORPORATION SDN BHD
(ROC No: 126457-T)

DAILY SITE WORK REPORT


`

CLIENT : CARIGALI HESS OPERATING COMPANY SDN BHD JOB NO : ECSF20220472


JOB DESCRIPTION : PREVENTIVE MAINTENANCE CAMPAIGN FOR WELLHEAD AT CAKERAWALA PLATFORM. LOCATION : SYB

TOTAL STRING :

WORK DATE : 02.11.2022 EQUIPMENT : TYPE OF SERVICES :


CREW : : MOHD SHAHIR BIN HARON ESS/751/3011 :PNEUMATIC GREASING PUMP 751 i) i)
WELLHEAD
WELLHEAD : : PREVENTIVE MAINTENANCE (PM)
: MOHD SAKRI BIN ABDUL RAHMAN ESS/FM2/3004 :PNEUMATIC FLUSHING PUMP FM2 CORRECTIVE : CORRECTIVE MAINTENANCE (CM)
ESSEM-DPG-001 :DIGITAL PRESSURE GAUGE (5K) MAINTENANCE
ii) PIPELINE (CM) : PREVENTIVE MAINTENANCE (PM)
ESSEM-DPG-001 :DIGITAL PRESSURE GAUGE (10K) : CORRECTIVE MAINTENANCE (CM)
WELL NO.
SYB-07 S/N : 2011-06-0377N PRODUCT : START DATE : 18.10.2021
STRING DETAILS
FMC M120 PLUS 5 1/8 5000 PSI 1) VALVE FLUSHING (VF) : 10PAILS
STRING DETAILS 2) VALVE LUBRICANT (VL) : 51PAILS
3) GATE VALVE SEALANT (GVS2) : 19 PAILS
4) VALVE REPAIR SEALANT (VRS) : 1 PAILS
5) SUBZERO (SZLS2) : 6PAILS NO. OF DAY 16
TO PERFORM CDFT AND WHV GREASING ON WELL SYB-07
SCOPE OF WORK ( HWSP55773)

TIME
START END
At standby mode and transferred from CKP to via Alkafi Maryam
Depart from CKP to SYB
Arrived at SYB
06:00 08:30
Present Task assignment briefing with DPIC
Lived the permit
Consultation among crews and DPIC on site
Proceed to worksite area and preparation on tools and equipment.
Assist DPIC mechanical isolation for double block manifold,PWV controller at WCP and main vent line

Perform CDFT and WHV Greasing on well SYB-05


Well Type Status FTHP SITHP Prod.Header Void PCP ICP SCP CCP
Gas Flowing 357 545 319 0 68 - 45 12

Valve Summary :
VALVE BEFORE GREASING PRODUCTS AFTER GREASING CONDITION BRAND AND SAIZ VALVE TIME Opening and Closing Actuator
PWV
HOLDING 8psi/10min LUBRICATE HOLDING 0psi/10min Actuator : Good FMC M120 PLUS 5 1/8" - 5000 psi Time Opening:3sec Time Closing: 6sec
SV FAILED 545psi/10min LUB/SEALANT PASSED 300psi/10min Hand wheel : Good FMC M120 PLUS 5 1/8" - 5000 psi
HUMV
FAILED 280psi/10min LUBRICATE PASSED 70psi/10min Actuator : Good FMC M120 PLUS 5 1/8" - 5000 psi Time Opening: 3sec Time Closing: 2sec
LMV HOLDING 2psi/10min LUBRICATE HOLDING 0psi/10min Hand wheel : Good FMC M120 PLUS 5 1/8" - 5000 psi
KWV
FAILED 94psi/10min LUBRICATE HOLDING 18psi/10min Hand wheel : Good FMC M120 PLUS 2 1/16" - 5000 psi

Remark : Exercise surface valve 5 times / PWV stem protector glass broken & cap jammed close, Unable to service./Production drain unable to operate (jammed open and no handwheel)

Performed leak test TR-SCSSV control Line


Perform cycling test 13 times on Control Line TR-SCSSV
Pressurized CL to 5259psi. Start monitoring from 5259psi to 5182psi for 15min.
Observed pressure decrease :77psi/15min
Tested Result Passed - Within allowable leak rate for 15min
08:30 16:15 Blowing Gas : No
Hydraulic Return : 160
Flowtube Movement: Clear indication observed.
Remark:

Performed 1st Inflow Test on TR-SCSSV


Initial THP : 545psi.
Bleed off THP from 576psi to 78psi and monitor for 30min
Observed pressure increase :93psi/10min
Tested Result Failed - badly passing
Remark: No

Performed 2nd Inflow Test on TR-SCSSV


Initial THP : 545psi.
Bleed off THP from 545psi to 93psi and monitor for 30min
Observed pressure increase :5psi/30min
Tested Result Passed - within allowable leak rate
Remark: Performed cycling test 10 Times

Secured worksite area


Normalize well and handover to operation
Housekeeping and secured work area.
Close PTW.
Depart from SYB to CKP
16:15 17:00
Arrived at CKP
Update activity today to Wellhead team leader and WSS
20:00 21:00
Prepare JSA and apply PTW for tomorrow.
21:00 23:00 Prepare report & submission to engineer

DEMOB
PLAN FOR TOMORROW JOB STATUS COMPLETED

UCUA/Action Tracker/QHSE SHAHIR= Observation : well SYB-07 PWV stem protector glass broken & cap jammed close, /Action taken inform DPIC and WSS to next planning
Moment SAKRI:Observation :well SYB-07- Production drain unable to operate (jammed open and no handwheel)/Action taken inform DPIC and WSS to next planning
SAFETY MOMENT : SAKRI> :Talk about noise
ESSEM CARIGALI HESS
PREPARED BY : VERIFIED BY :
NAME : MOHD SHAHIR BIN HARON NAME : VIKNESWARAN

SIGNATURE : SIGNATURE :

DESIGNATION : TEAM LEADER DESIGNATION : WELL SERVICES SUPERVISOR


DATE : 02.11.2022 DATE : 02.11.2022