This document is a bill of quantities for renovation works including flooring, ceiling, painting, electrical, toilet areas, doors, block work, counters, and ground works. It contains item descriptions, quantities, unit rates and prices for various renovation items totaling AED 119,945. The works include supply and installation of floor tiles, sandwich panels, gypsum ceilings, switches, sockets, lights, toilet fixtures, doors, partitions, kitchen counter, and excavation works. Payment will be made for mobilization, equipment, materials, and completion of the listed renovation items.

Uploaded by

Hm
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
36 views

Ali Villa Extention

This document is a bill of quantities for renovation works including flooring, ceiling, painting, electrical, toilet areas, doors, block work, counters, and ground works. It contains item descriptions, quantities, unit rates and prices for various renovation items totaling AED 119,945. The works include supply and installation of floor tiles, sandwich panels, gypsum ceilings, switches, sockets, lights, toilet fixtures, doors, partitions, kitchen counter, and excavation works. Payment will be made for mobilization, equipment, materials, and completion of the listed renovation items.

Uploaded by

Hm
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 1

UNIT AMOUNT

NO. DESCRIPTION QTY UNIT PRICE AED


1 PRELIMINARIES
1.1 PPE for workers, visitors and staff
1.2 Contractor's All Risk Insurance policy
Protection of existing finishes i.e. lift lobbies walls, floors, ceilings etc. during
1.3 fit out works.
1 Lsm ‐ 4,000
Mobilization / demobilization, transportation for the personnel, materials and
1.4 equipment's and site office / establishments.
1.5 Power hand tools and scaffoldings.
1.6 Approvals for the related authorities, feels not included
3 Flooring work
supply and Installation 60x 60 RAK cermic tille wiith approved sample andd
3.1 necessary fixing. 55 M2 90 4,950

4 Steel work
Supply and Installation of 50 mm thick sandwich panel with steel structure for
4.1 panel support and necessary fixing. 55 Lms 460 25,300
Waterproofing for roof and repairing works of installed sandwich panel of
4.2 exisiting works 55 Lms 65 3,575

5 Ceilling Work
Installation of 100 mm thick gypsum ceilling , composed of 12.5 mm REG
gypsum board on both sides, GI stud and track frame work, mineral rock wool
insulation , joint tape, joint compound with necessary primer and sanding ,
5.1 ready to receive paint finish (Quoted separately). 65 M2 85 5,525

6 Painting Work
Ceiling paint finishes to be applied 2 coat /primer as per specification,
6.1 complete as required as per specifications National paint 90 M2 25 2,250
Wall paint finishes to be applied 2 coat /primer as per specification, complete
6.2 as required as per specifications National paint 179 M2 25 4,475

6.3 Outside tetxure paint work with wall Acc National paint 49 M2 35 1,715
7 Electerical Work
Supply & Installation of 13A single socket with WP including all conduiting & 9 Nos 350 3,150
7.1 wiring Schneider brand
Supply & Installation of switch lights mounted including all conduiting & wiring 6 Nos 250 1,500
7.2 Schneider brand
7.3 Supply & fixing of 13W Down light Philips Lights 14 Nos 70 980

7.4 Supply & fixing of 1d DB for home 1 Nos 4500 4,500


8 Toilet Area
supply and apply 60 x 60 vinyl faced washable ceiling tiles for bathrooms
ceiling white color with all suspension system and all required accessories.
8.1 Brand: USG‐Boral. 9 M2 80 800
Removal & cart away of existing ceiling is included RAK Brand

8.2 Supply & installation of mirror for toilet, Size (3m*1.6m). RAK Brand 2 Nos 100 200
8.4 Supply & apply Pedestal Sink with all accissories RAK Brand 3 Nos 550 1,650
8.5 Supply and installation of mixers from Rak for vanity counter 3 Nos 250 750
Supply & installation of new W/c from RAK included all accessories & flush
8.6 fittings.Remove & cart away of existing WC . 3 Nos 700 2,100

8.7 Supply & installation of new Shattaf from RAK 3 Nos 30 90


8.8 Supply & installation of new angle valves from RAK 9 Nos 35 350
8.9 Supply & installation of window exhaust fan. Local Brand 2 Nos 200 400

10 Doors work

10.1 supply & installation of wodden door closer & handle with lockand all Acc 8 NOS 1800 14,400
12 Block work
12.1 supply and instullation block work for internal and external partition 135 M2 120 16,200
12.1 supply and instullation plaster work for internal and external wall 149 M2 45 6,705
13 Counter for kitchen
13.1 counter top for kitchen granite 7 Lms 650 4,550
14 Escavastion & ground work
14.1 Back fill 10 mm inder the ground level 55 M2 25 1,375
14.2 Screed work 89 M2 95 8,455

(AED): One Hundred Fifty Six Thousand only Grand Total 119,945