Lecture 9
Lecture 9
A
1 2 A B
3 days
Network is more compact and clearer. Network is more complex and require maintenance and analysis.
Better suited for small projects planning Better suited for large projects planning
Project Time Management
Building a Project Network Diagram (AOA/AON):
Project Time Management
Network Planning Techniques:
Critical Path Method (CPM):
Developed to coordinate maintenance in the chemical industry (1957).
Uses two-time approach, a normal time and a crash time, for each activity.
A deterministic technique: aims to find the exact date of completing the entire project.
Results are more specific (tasks duration is determined).
Program Evaluation & Review Technique (PERT):
Developed to manage the Polaris missile project (Us navy-1958).
Three times for each activity (optimistic, pessimistic and most likely times) are
combined.
A probabilistic technique: aims to find the probability of the entire project being
completed by a given date.
Results are less specific (tasks duration is probabilistic).
Project Time Management
PERT/CPM:
Are used to plan the schedules of a project individual activities.
Can graphically display the precedence relationships & sequence of activities.
Can determine the earliest/latest start and finish for each activity, and the entire project
completion time.
Identify critical activities that cannot be delayed without delaying the project.
Estimate the amount of slack time for non-critical activities
Can determine at a given date, if the project is on schedule, behind schedule, or a head of the
schedule.
Can determine at a given date, if the money spent is equal to, less than, or greater than the
budget.
Can determine if there are enough resources to finish the project on time.
Can determine the best way to finish the project in a shorter time (if possible) , with the least
cost? (crash analysis).
Project Time Management
Example: ELSEWEDY ELECTRIC is bringing a new cable to the market . The planning engineer has
identified 11 activities necessary for the production process. Develop an AON for the project.
Immediate Duration
Activity Description
Predecessor (weeks)
A Develop cable specifications None 4
B Design manufacturing process A 6
C Source & purchase materials A 3
D Source & purchase tooling & equipment B 6
E Receive & install tooling & equipment D 14
F Receive materials C 5
G Pilot production run E&F 2
H Evaluate product design G 2
I Evaluate process performance G 3
J Write documentation report H&I 4
K Transition to manufacturing J 2
Project Time Management
CPM
B D E H
(6) (6) (14) (2)
A G J K
(4) (2) (4) (2)
C F I
(3) (5) (3)
Project Time Management
CPM
A typical beta distribution is shown below, note that it has definite end points
The expected time for finishing each activity is a weighted average
Project Time Management
optimistic + 4 most likely + pessimisti𝑐𝑐
Exp. time =
6
Optimistic Most likely Pessimistic Expected
Activity
time time time time
A 2 4 6 4
B 3 7 10 6.83
C 2 3 5 3.17
D 4 7 9 6.83
E 12 16 20 16
F 2 5 8 5
G 2 2 2 2
H 2 3 4 3
I 2 3 5 3.17
J 2 4 6 4
K 2 2 2 2
Project Time Management
PERT
B D E
(6.83) (6.83) (16) H (3)
K
A (4) G (2) J (4)
(2)
C F I
(3.17) (5) (3.17)
Project Time Management
PERT
Estimated Path Durations:
ES = 4 ES = 7.17 ES = 35.66
EF = 7.17 EF = 12.17 EF = 38.83
LF = 28.66 LF = 33.66
LS = 25.49 LS = 28.66
S = 21.49 S = 21.49
Project Time Management
Gantt Chart at the Earliest Possible Start Dates
Project Time Management
Gantt Chart at the Latest Possible Start Dates
Project Time Management
Estimating the Probability of Completion Dates
Using probabilistic time estimates offers the advantage of predicting the probability of
project completion dates.
We have already calculated the expected time for each activity by making three-time
estimates. p−o
σ =
2
2
6
Now we need to calculate the variance for each activity.
The variance of the beta probability distribution is:
where: p=pessimistic activity time estimate
o=optimistic activity time estimate
Project Time Management
Project Activity Variance
Activity Optimistic Most Likely Pessimistic Variance
A 2 4 6 0.44
B 3 7 10 1.36
C 2 3 5 0.25
D 4 7 9 0.69
E 12 16 20 1.78
F 2 5 8 1.00
G 2 2 2 0.00
H 2 3 4 0.11
I 2 3 5 0.25
J 2 4 6 0.44
K 2 2 2 0.00
Project Time Management
ΣVariances of Each Path
2 A,B,D,E,G,I,J,K 4.96
3 A,C,F,G,H,J,K 2.24
4 A,C,F,G,I,J,K 2.38
Project Time Management
Calculating the Probability of Completing the Project in Less Than a Specified Time
When you know:
The expected completion time.
Its variance.
You can calculate the probability of completing the project in “X” weeks
with the following formula:
specified time − path expected time DT − EFP
z= =
path standard time σP 2